Professional Documents
Culture Documents
_____
0A Internal Issue
Cod. modulo : MDT.GG.QUA.0004 Fg. 01/Rev. 3.96 Cod.file: File dati: 462717286.doc
This document is the property of Saipem who will safeguard its right according to the civil and penal provision of law.
AFAM – RIVERS STATE GOVERNMENT
OPEN CYCLE POWER PLANT Job Number UNIT
032083 00
INDEX
_______________________________
Table of Content
1 INTRODUCTION 10
1.1 FOREWORD 10
1.2 GLOSSARY OF TERMS USED AND UNITS USED 12
1 DESIGN BASIS 14
1.1 FUNCTION OF THE FIRE PROTECTION SYSTEMS 14
1.2 FEEDSTOCK CHARACTERISTICS 14
1.3 BATTERY LIMIT CONDITIONS 15
1.4 EFFLUENTS 15
1.5 MATERIAL BALANCE 16
1.6 UTILITIES REQUIREMENTS 16
1.7 CHEMICALS 16
2 PROCESS DESCRIPTION 17
2.1 REFERENCES 17
2.2 DETAILED PROCESS DESCRIPTION 18
2.3 ELEMENTS OF PROCESS CONTROL PHILOSOPHY 20
5 NORMAL OPERATION 31
5.1 OPERATING VARIABLES 31
5.2 SPECIFIC OPERATIONS 32
5.3 PERFORMANCE MONITORING 33
5.4 CORROSION CONTROL AND MONITORING 33
6 NORMAL SHUTDOWN 34
6.1 GENERAL 34
6.2 UNIT 50 SHUTDOWN 34
_______________________________
7 EMERGENCY SHUTDOWN 38
7.1 GENERAL 38
7.2 UTILITIES FAILURE 38
8 SAFETY 39
8.1 GENERAL 39
8.2 LISTING OF SAFETY EQUIPMENT 39
8.3 FIRE AND GAS DETECTION 40
10 DRAWINGS 42
10.1 PIPING AND INSTRUMENTATION DIAGRAMS 42
10.2 PLOT PLAN 42
10.3 FIRE AND SAFETY LAYOUT DRAWINGS 42
10.4 OVERALL FIREWATER RINGMAIN DRAWINGS 42
10.5 LOGIC DIAGRAM 42
10.6 VENDOR INFORMATION 42
1 DESIGN BASIS 43
1.1 GENERAL 43
1.2 FEEDSTOCK CHARACTERISTICS 43
1.3 PRODUCT SPECIFICATION 44
1.4 EFFLUENTS 45
1.5 MATERIAL BALANCE 45
1.6 UTILITY REQUIREMENTS 45
1.7 CHEMICALS 46
2 PROCESS DESCRIPTION 47
2.1 GENERAL 47
2.2 DETAILED PROCESS DESCRIPTION 48
2.3 ELEMENTS OF PROCESS CONTROL PHILOSOPHY 49
_______________________________
5 NORMAL OPERATION 59
5.1 OPERATING VARIABLES 59
5.2 SPECIFIC OPERATIONS 59
5.3 PERFORMANCE MONITORING 59
5.4 CORROSION CONTROL AND MONITORING 60
6 NORMAL SHUTDOWN 61
6.1 GENERAL 61
6.2 UNIT 60 SHUTDOWN 61
7 EMERGENCY SHUTDOWN 63
7.1 GENERAL 63
7.2 UTILITIES FAILURE 63
8 SAFETY 64
8.1 GENERAL 64
8.2 LISTING OF SAFETY EQUIPMENT 64
8.3 CHLORINE (Cl2) INFORMATION 65
10 DRAWINGS 68
10.1 PIPING AND INSTRUMENTATION DIAGRAMS 68
10.2 PLOT PLAN 68
10.3 FIRE AND SAFETY LAYOUT DRAWINGS 68
10.4 LOGIC DIAGRAM 68
1 DESIGN BASIS 69
1.1 GENERAL 69
1.2 FEEDSTOCK CHARACTERISTICS 69
1.3 MATERIAL BALANCE 70
1.4 EFFLUENTS 70
1.5 UTILITY REQUIREMENTS 70
1.6 CHEMICALS 70
_______________________________
2 PROCESS DESCRIPTION 71
2.1 GENERAL 71
2.2 DETAILED PROCESS DESCRIPTION 71
2.3 ELEMENTS OF PROCESS CONTROL PHILOSOPHY 72
5 NORMAL OPERATION 82
5.1 OPERATING VARIABLES 82
5.2 CORROSION CONTROL AND MONITORING 84
6 NORMAL SHUTDOWN 85
6.1 GENERAL 85
6.2 SHUTDOWN OF INDIVIDUAL EQUIPMENT ITEMS 85
7 EMERGENCY SHUTDOWN 87
7.1 GENERAL 87
7.2 UTILITIES FAILURE 87
8 SAFETY 88
8.1 GENERAL 88
8.2 LISTING OF SAFETY EQUIPMENT 88
8.3 SAFETY PRECAUTIONS FOR AIR COMPRESSORS 89
8.4 SAFETY PRECAUTIONS FOR AIR DRYERS 93
10 DRAWINGS 97
10.1 1 PIPING AND INSTRUMENTATION DIAGRAMS 97
10.2 2 PLOT PLANS 97
10.3 3 LOGIC DIAGRAM 97
10.4 4 FIRE AND SAFETY LAYOUT DRAWINGS 97
_______________________________
1 DESIGN BASIS 98
1.1 GENERAL 98
1.2 UNIT CAPACITY 98
1.3 DESIGN CONDITIONS 98
1.4 MATERIALS 99
1.5 MATERIAL BALANCE 99
1.6 UTILITY REQUIREMENTS 101
5 SAFETY 107
5.1 GENERAL 107
5.2 LISTING OF SAFETY EQUIPMENT 107
7 DRAWINGS 109
7.1 PIPING AND INSTRUMENTATION DIAGRAMS 109
7.2 PLOT PLAN 109
7.3 LAYOUT DRAWINGS 109
_______________________________
8 SAFETY 142
8.1 GENERAL 142
8.2 RISK LIST, RISK MITIGATION AND
COUNTERMEASURES 142
_______________________________
10 DRAWINGS 147
10.1 PIPING AND INSTRUMENTATION DIAGRAMS 147
10.2 PLOT PLAN 147
10.3 LAYOUT DRAWINGS 147
_______________________________
1 INTRODUCTION
1.1 FOREWORD
The information contained in this operating manual provides a basis for the safe startup, normal
operation, normal shutdown and emergency shutdown of the Utilities & Process System
(Balance of Plant BOP) at the AFAM Project facilities.
This document should be considered as a guide, and SCNL retains the right to modify these
procedures as a function of actual conditions encountered in the field during the pre-
commissioning, commissioning and startup of the plant.
This operating manual gives the process philosophy and describes the initial startup, normal
operation, shutdown and emergency procedures for the BOP. This volume, of necessity,
contains some of the process information since such information must be readily available for
the operating group. The instructions given herein are intended primarily for the use of foreman
and supervisors. They should serve as a basis for the preparation of detailed instructions to be
given to the operators by their foremen and supervisory personnel.
This volume describes the commissioning and operation of the entire unit as a convenient
reference for AFAM OCPP to ensure BOP operates at optimum conditions.
The procedures described in this manual should be considered as operating guides and may
have to be adapted at site. It is the prime responsibility of those in charge of the plant to interpret
the instructions, where necessary, to suit the conditions prevailing at any time and to take into
account local conditions during the preparation and commissioning of the BOP Unit.
It is essential that all personnel in charge of operating the plant read the whole of the operating
instructions and any related engineering manuals before commencing to start up any part of the
unit.
In general, the operating personnel will learn the proper operating procedures by actually
performing the necessary manual operations. Adequate training time must be provided for
extended drills covering all specific operations of both normal and emergency nature during
initial dry runs.
Operators should have their jobs and responsibilities clearly outlined and defined for them. They
should not be given the responsibility to start-up the plant by themselves even after a temporary
emergency shutdown, but should in such case call upon the technical supervisor in charge for
guidance and instructions. During all start-ups, it is recommended that a responsible technical
supervisor, who thoroughly understands the process and the plant in all its chemical and
mechanical aspects, be present. Since this will be less likely during and emergency shutdown,
the operators must be especially well schooled in the emergency shutdown procedures.
In order to cover all disciplines that operations personnel may require, the operating manual has
been issued as follows:
_______________________________
· Design criteria, giving the basic data are indicated in chapter 1, whereas BOP process
descriptions are included in chapter 2.
· All general and particular procedures concerning Unit preparation for initial and normal
operation are described in chapters 3 to 8.
· Finally, equipment specifications and data sheets, enclosed in chapter 9 give all design
information. Relevant drawings are enclosed in chapter 10 for reference purposes.
To facilitate the preparation for start-up and the coordination between the procedures for start-
up, normal operation and shutdown, the procedures have been separated as far as possible.
This will allow independent activities, and limit the possible bottlenecks and interference.
_______________________________
_______________________________
Surface m²
Volume m³
Temperature °C
Length k, m, mm
Mass kg, To
Concentrations
* gas %vol, %mol, ppmw, ppmv
* liquid %wt, ppmw, ppmv
Pipe sizes, nominal inches
Electrical power kW
Viscosity cSt or cP
Density kg/m³
Time s, h
_______________________________
The Fire Protection Systems installed as part of AFAM-OCPP Project have been provided to cater for
the firewater demands of the process and utility units. The fire water system shall be designed to meet
the design fire water demand as calculated by assuming one major fire in the plant.
The system include one firewater storage tank 50-T-001, two firewater main pumps
50-P-001/ 002, two jockey pumps 50-P-003 A/B, firewater main ring with hydrants and monitors and
deluge system.
The firewater pumps philosophy is 1 x 100% on emergency situation. In particular the design fire water
demand is supplied by electric motor driven pump (50-P-001) which is theprimary fire water source;
100% stand-by shall be provided by diesel engine driven pump (50-P-002) for redundancy.
The jockey pumps have been designed on a 1 x 100% operating basis. One pump operates
continuously on minimum flow recycle in order to ensure that fire water network will be maintained under
pressure
1.2 FEEDSTOCK CHARACTERISTICS
The following sections detail the capacity of the equipment and the characteristics of the firewater.
1.2.1 Unit Capacity
The following fire protection equipment has been installed as part of AFAM-OCPP Project:
Firewater Storage Tank, 50-T-001
Dimensions: 10.5 m ID x 9.15 m high.
Nominal Capacity: 780 m³
Operating Capacity: 600 m³
The firewater storage is sufficient to allow for two (2) hours continuous operation at maximum water
rate required of 300 m³/h.
Firewater Pumps 50-P-001/ 002
One of the Firewater Pumps 50-P-001 has an electric motor driver, the other 50-P-002 is driven by a
diesel engine.
The Firewater Pump electrically driven:
Pump Capacity: 300m³/h
Head: 83 m
Driver Power: 110 kW
The Firewater Pump diesel engine:
Pump Capacity:300m³/h
_______________________________
The make-up water to the firewater Storage Tanks is supplied from potable water distribution system or
by water tankers.
1.3 BATTERY LIMIT CONDITIONS
The fire water system shall be designed to meet the design fire water demand as calculated by
assuming one major fire in the plant.
Fire water demand shall be calculated by summing the following:
a) Either of the following, whichever is larger:
(a.1) the largest fixed fire suppression system demand.
(a.2) any fixed fire suppression system demands that could reasonably be expected to operate
simultaneously during a single event.
b) Water demand for two (2) hose streams (60 m3/h per hose stream).
Based on the above figures, the design fire water demand is set at 300 m3/h as resulted in
Fire Scenario 1:
1.4 EFFLUENTS
There may be periodic draining of pump casing and piping to grade. This water will be allowed to soak
away, since there is no open drain provided on the unit.
_______________________________
Reference documents:
50-ZA-E-85580 Fire Water Network Calculation Report.
50-ZA-E-85585 Water Spray System Calculation Report.
1.6 UTILITIES REQUIREMENTS
The utilities required by the Unit 50 are instrument air and electric power.
1.7 CHEMICALS
The firewater tanks will periodically be manually shock dosed with a biocide to inhibit the growth of any
algae which may cause blockages and affect the operation of the firewater system.
_______________________________
2 PROCESS DESCRIPTION
2.1 REFERENCES
The basic engineering documents related to the design of the Fire Protection Systems, Unit-50, are
listed hereafter:
- 50-ZA-E-85580 Fire Water Network Calculation Report.
- 50-ZA-E-85585 Water Spray System Calculation Report.
- 50-MA-E-85590 Fire Water Storage Tank 50-T-001 Data Sheet.
- 50-MA-E-85595 Fire Water Jockey Pumps 50-P-003 A/B Data Sheet.
- 50-MA-E-85600 Fire Water Main/Stand-by Pumps 50-P-001/002 Data Sheet
- 50-MA-E-85605 Level Valve Data Sheet.
- 50-MA-E-85610 Instrumentation Data Sheet.
- 50-ZA-E-85615 Fire Fighting Equipment Supply Specification.
- 50-GD-B-85660 Fire Water Storage and Main Pumps P&ID.
- 50-GD-B-85661 Fire Water Jockey Pumps P&ID.
- 50-GD-B-85665 Fire Water Pumps Controller and Remote Signalizations P&ID.
- 50-GD-B-85670 Fire Water Network Distribution P&ID.
- 50-GD-B-85675 Fire Fighting Equipment Installation Details P&ID.
- 50-GD-B-85680 Deluge Valves Installation Detail P&ID.
- 50-GD-B-85685 Water Spray System Distribution P&ID.
- 50-GD-B-85700 Fire Fighting Protection System Plot Plan.
_______________________________
Fire water is stored in a new dedicated above ground carbon steel tank 50-T-001 having 600 cubic
meters capacity to allow for two (2) hours continuous operation at design fire water demand.
The fire water tank is connected to service/potable water system located on site and is equipped with
local and remote level control for automatic make-up with service/potable water. In addition to the
above, a dedicated line is provided to guarantee the fire water storage tank refilling by road tanker.
50-T-001 operates with the water level being controlled by level controller 50-LIC-050, which maintains
the level in the tank at 7900 mm. Local level indication is also provided. 50-LAL-052 and 50-LALL-051
are also provided, with a set point of 4500 mm/ 2800mm to maintain the minimum necessary firewater
stock and to avoid firewater tank to be empty and damage the pumps.
The design fire water demand shall be supplied by electric motor driven pump which is the primary fire
water source; 100% stand-by shall be provided by diesel engine driven pump for redundancy.
All electric and diesel pumps have the same capacity set to 300 m3/h being this last the design fire
water demand.
In compliance with the above, the following shall be provided:
-No. one (1) – horizontal centrifugal pump 50-P-001 - electric motor driven – rated for 300 m3/h at 8
bar(g) discharge pressure serving as main fire pump unit. This pump can be operated either
automatically or manually, to this purpose it shall be provided with a dedicated local controller and shall
be powered by normal network.
-No. one (1) – horizontal centrifugal pump 50-P-002 - diesel engine driven – rated for 300 m3/h at 8
bar(g) discharge pressure serving as fire pump stand-by unit. This pump can be operated either
automatically or manually, to this purpose it shall be provided with a dedicated local controller. Diesel
engine shall be provided with a diesel oil fuel tank having a capacity calculated as per NFPA 20
requirements.
The fire water network will be maintained under pressure by means of suitable jockey pumps one of
them always running serving as main unit, the other serving as stand by unit and to be started on
request.
In compliance with the above, the following shall be provided:
-No. two (2) – horizontal centrifugal pumps 50-P-003 A/B - electric motor driven – each one rated for 15
m3/h at 8 bar g discharge pressure, one of them serving as jockey pumps main unit, the other serving
as jockey pump stand-by unit.
These pumps can be operated only manually; a double jockey pump controller is provided.
Jockey pump main unit will be powered by emergency power, the stand-by will be powered by normal
network.
Electric motor driven main and jockey pumps, controller and signals shall be generally in compliance
with NFPA 20 latest edition, but need not listed.
Diesel engine driven pump, fuel system, controller, and signals shall be generally in compliance with
NFPA 20 latest edition, but need not be listed.
_______________________________
As per NFPA 20 all fire water pumps shall supply not less than 150 percent of rated capacity at not less
than 65 percent of total rated head and the total shut-off shall not exceed 140 percent of total rated
head. To avoid firewater pumps and jockey pumps overheating in case of no or low flow operation, each
pump shall be fitted with minimum recirculation valve 3/4”.
The system provides for the following starting of both main and jockey pumps.
Electric motor driven main pump can be started as follows:
· Automatically upon low pressure in the fire water network;
· Manually locally at the pump controllers by start push button;
· Manually remotely from control room by push button.
· Electric motor driven main pump can be stopped manually only at pumps controller by push button.
Diesel engine driven stand-by pump can be started as follows:
· Automatically upon low pressure in the fire water network;
· Manually locally at the pump controllers by start push button;
· Manually remotely from control room by push button.
· Diesel engine driven stand-by pump can be stopped manually only at pumps controller by push button
Electric motor driven Jockey pumps can be started as follows:
· Manually in CR from the OS.
· Jockey pumps can be stopped manually only at pumps controller by push button.
The jockey pumps 50-P-003A/B maintains the firewater main ring pressure at 8 bar g while there is no
firewater demand. When the firewater demand exceeds the capacity of the Jockey Pump, the main ring
pressure will fall and, when it reaches 6 bar g, a sequential start of the firewater pumps is initiated. Refer
to section 3.2 for more detail.
Dedicated deluge systems have been provided to protect the following items of equipment:
· Step-up transformer 10-TRM
· Auxiliary transformer 10-TRU
· Common services transformer 00-TRS
2.2.2 Other Fire Fighting Facilities
In addition to the dedicated firefighting facilities, hydrants, and monitors have been provided around the
periphery of the process and utility units and at strategic locations within the units.
Carbon Dioxide (CO2) Extinguishing System
A total flooding, gaseous, carbon dioxide fire suppression system shall be provided to protect the
following rotating equipment:
· Gas turbine (thermal block / enclosures and exhaust end bearing tunnel).
· Emergency diesel generator (acoustic protective enclosures).
Carbon dioxide extinguishing system shall be automatically activated by means of fire detection and
shall be designed and installed in compliance with NFPA 12 requirements
_______________________________
2.3.1 General
50-T-001 operate with the water level being controlled by level controller 50-LIC-050, which maintains
the levels in the tank at 7900 mm. Local level indication is also provided. 50-LAL-052 and 50-LALL-051
are also provided, with a set point of 4500 mm/ 2800mm to maintain the minimum necessary firewater
stock and to avoid firewater tank to be empty and damage the pumps. Each firewater/ jockey pump is
provided with a dedicated minimum flow valve and spillback line.
2.3.2 Firewater main ring pressure control
In normal operation status (fire water flow less than 15 m3/h - one jockey pump capacity) the fire water
network is maintained under pressure at a required target value by one jockey pump 50-P-003 A or 50-
P-003 B. In emergency operations status (fire water flow in excess to 15 m3/h, one jockey pump
capacity), the pressure in the system will decrease and when will drop down to 6 bar the pressure
transmitters PT-050 and PT-051 will automatically activate the starting sequence which provide for:
· To start immediately the electric motor driven main pump 50-P-001.
· To start the stand-by diesel engine driven fire water pump 50-P-002 if fire water pressure does not reach
8 bar in 20 seconds after main electric motor driven fire water pump 50-P-001 starts (pump failure).
The failure of the main pump to start will not prevent subsequent starting of the stand-by pump.
Suitable manual selector HS-050 located in control room allow the selection of the stand-by pump 50-P-
002 as first pump to start in the case of main pump 50-P-001 is out of service.
_______________________________
3.1 GENERAL
Prior to initial startup, all pre-commissioning activities must have been completed and the unit must be
ready for operation.
Pre-commissioning covers those activities required to bring the unit to a "ready for startup" condition
following construction. In general, it consists of inspection, checking and testing operations required to
ensure that all components of the unit are properly installed and mechanically complete. The most
important requirement is that the unit can be started up in a controlled, efficient and safe manner.
This pre-commissioning phase is usually performed by the construction forces in close co-ordination
with the operations/commissioning team.
For this purpose, checking sheets (or "mechanical guides") will be issued and filled out on site in close
co-operation between construction and the commissioning team.
Full details of pre-commissioning activities with regard to inspection of equipment items, general checks,
hydrostatic testing, instrumentation functional testing, electrical motor run-in, line and vessel cleaning,
etc., are outside the scope of this document.
Details of the initial startup and commissioning of the Fire Protection Systems are detailed in this
chapter. Operating parameters and adjustments, shutdown and emergency situations are detailed in
Chapters 5 to 7.
The information and procedures described hereafter concern the preliminary operations for the first
startup of a new unit. Procedures are slightly adapted for normal and subsequent start up, as indicated
in Chapter 4.
3.2 PREPARATION PRIOR TO INITIAL OPERATION
It is assumed that all the pre-commissioning/maintenance activities are completed and that the unit has
reached a "ready for startup" status.
Most of the following pre-start up items are routine and are briefly presented as reminders only, as they
refer to pre-commissioning activities.
Ensure that the following requirements are satisfied:
¨ All safety equipment is in place and is fully operable.
¨ All pipe work has been pressure tested and cleaned.
¨ All equipment has been pressure tested, inspected, cleaned, drained and dried.
¨ All equipment is at ambient conditions and full of air (except where otherwise specified).
¨ Chemicals, if required, are available.
¨ Test equipment and special tools, if any, and facilities for their operation are available.
¨ All rotating equipment and their associated drivers have been aligned, run in and lubricated, as required,
following the manufacturers' recommended procedures.
¨ Temporary strainers must be installed where specified and their locations properly recorded for future
reference.
¨ Instrument air is available and commissioned to all instruments. (Refer to section 2.1).
_______________________________
¨ Electrical power systems have been checked out and commissioned. It is available to all electric drivers
and all instrument boards.
¨ All instruments have been calibrated, loops checked and commissioned. All sensing elements which
were removed from pipe work prior to hydro testing have been reinstalled.
¨ All the CS data links are operational.
¨ Emergency shutdown systems are fully operational and if possible, a dry run has been performed.
¨ All safety relief valves have been tested and are in service. All block valves around relief valves are
locked in the correct position.
¨ All blinds, if any, which were installed in the lines during hydro testing have been removed and replaced
with their relevant spacers.
¨ All utilities have been commissioned, lined up and are ready for use at the unit battery limit.
It is the prime responsibility of those in charge of the plant to ensure that all operations are carried out
satisfactorily.
3.2.1 Preparation of Utilities
3.2.1.1 Instrument Air
This section details the necessary steps to ensure the proper commissioning of the instrument air
system.
The instrument air supply to Unit 50 is provided from the existing distribution system. Instrument air is
used as the motive gas to operate control valves.
It is assumed that the instrument air system is pressurized with dry instrument air up to the Unit 50
battery limit. It is also assumed that all pre-commissioning activities have been carried out, and that the
instrument air system for Unit 50 is under a slight positive pressure of dry air.
The instrument air system will be commissioned in the following way:
· Ensure Unit 50 battery limit valve is closed.
· Close all instrument air regulator valves.
· Open the Unit 50 battery limit valve and pressurize the instrument air header to normal instrument air
pressure.
· Open the air regulator valves to supply air to the control valves.
The instrument air to Unit 50 is now commissioned.
_______________________________
_______________________________
During this operation, check if LLL/ LL level indications are cleared and HH/ HHH level indications will
be activated and LV-050 will close in AUTO mode.
3.3.2.1 Dosing the Firewater with Biocide
The firewater in firewater tank must be dosed with Biocide to prevent the growth of algae.
3.3.3 Commissioning of Jockey Pumps 50-P-003A/B
· Open the flange and remove the “Y” type suction strainers.
Open 50-V-19 and 50-V-20 suction line isolation valves and flush the suction lines.
After visual inspection satisfactory, stop flushing, close back the isolation valves and reinstall the
strainers.
· Open 50-V-19 and 50-V-20 suction line isolation valves for 50-P-003A/B. This will allow the casing of the
pump to fill with water. Lock open the valves.
· Open fully 50-V-23 and 50-V-24, ¾”minimum recycles flow for 50-P-003A/B.
Pumps are ready to be commissioned.
· Ensure the power supply is available and press the green "START" pushbutton located on the local
pumps control panel. Observe the running of the pump, and when running smoothly leave the pump
running at full rate for 3 hours. Record the parameters.
· The pump can be stopped at the local panel by pushing the red "STOP/RESET" pushbutton located on
the local pump control panel.
With the test run complete and the pump stopped the system can be lined up for normal operation.
3.3.4 Commissioning of Firewater Pumps, 50-P-001/002
For the initial start up of the Firewater Pumps 50-P-001/002, the test line will be used. Before this can be
done, however, the minimum flow spillback line must be commissioned to ensure the pump is fully
protected against low flows.
The procedure for starting the pumps and commissioning the minimum flow spillback line is as follows:
· Open 50-V-10 and 50-V-11, suction line isolation valves for 50-P-001/ 002.
This will allow the casing of the pump to fill with water.
_______________________________
· Open 1” vent valves upstream 50-V-12 and 50-V-13 and make sure the pumps are vented properly.
Close the vent valves.
· Open 50-V-18, 50-T-001 test line, and car seal.
· Open fully 50-V-16 and 50-V-17, minimum recycle flow for 50-P-001 and 50-P-002.
Pumps are ready to be commissioned.
· Ensure the power supply is available and press the green "START" pushbutton located on the local
pump control panel of 50-P-001. Observe the running of the pump, and when running smoothly the test
line can be opened.
· Open gradually up to fully open 50-V-14 and 50-V-15, the pump test line isolation valves for 50-P-001/
002. Leave the pump running at full rate for 3 hours and record the parameters.
· After three hours of running at full rate the pump can be stopped at the local panel by
pushing the red "STOP/RESET" pushbutton located on the local pump control panel.
With the test run complete and the pump stopped the system can be lined up for normal operation:
· Close 50-V-14 and 50-V-15 the pump test line isolation valves for 50-P-001/ 002 and car seal.
3.3.5 Commissioning of Firewater Main Ring
· Restart 50-P-003A on minimum flow.
· Open gradually up to fully open 50-V-21 the jockey pump firewater main ring isolation valve. Lock open
the valve. Leave the pump running at full rate to allow the firewater main ring to be pressurized. Ensure
the main ring is properly vented by opening of hydrants and monitors.
· Restart 50-P-001 on minimum flow.
· Open gradually up to fully open 50-V-12 pump firewater main ring isolation valve. Lock open the valve.
· When firewater main ring is considered properly pressurized and vented the pomp can be stopped and
considered on stand-by.
· Check the automatic starting sequence by giving false signal to PT-050/051. After satisfactory
completion of the test, commissioning of main and jockey fire water pumps and firewater main ring is
completed.
3.4 FIREWATER DELUGE SKIDS
Consider that firewater Main ring is fully operational and lines upstream deluge skids are properly
flushed.
The Firewater Deluge Skids are specialized items of equipment and so all operators must be fully
familiar with the information contained in the Vendor I.O.M.M. before attempting any set up or
maintenance of the skids.
The vendor manual contains a comprehensive commissioning and testing schedule which should be
referred to and followed before lining up the firewater deluge skids, but which falls outside the scope of
this manual.
_______________________________
With the valves in the above positions, the Firewater Deluge Skids are ready to be commissioned as
follows:
Ensure instrument air pressure is available to the skid.
Open the battery limit isolation valves in the primary and secondary firewater supply lines.
The Firewater Deluge Skids are now on-line.
_______________________________
4.1 GENERAL
The procedures and instructions laid out in this chapter are to be used to start up
Unit 50 following a shutdown. The shutdown may have been routine as part of normal operation,
turnaround or maintenance.
The recommended start-up procedure is presented in section 3.0.
The following start up procedures are recommended, with the understanding that the judgment of the
operators should dictate which of these steps are required, and in what order, based on the nature of
the preceding shutdown. The initial start-up instructions presented in Chapter 3 should be referred to for
specific details.
4.2 PRE-START UP CONDITIONS
Prior to restarting Unit 50 it is the prime responsibility of those in charge of operations to ensure that the
following criteria have been satisfied:
After a shutdown for turnaround and maintenance, start up orders have to be initiated after ensuring that
all requirements relating to plant acceptance and readiness for restart have been fulfilled. After an
unplanned shutdown the unit must be checked over to ensure that the unit is ready and safe to operate
and that the cause of the shutdown has been rectified.
The restart must be performed in accordance with all RSG-OCPP safety regulations and standing
instructions.
The following shall be assumed for the purpose of the start up procedures in this chapter:
All utility systems are commissioned and available as required to the units.
All instruments and control systems have been checked and are functional.
4.3 NORMAL AND SUBSEQUENT START-UP PROCEDURE
Unit 50 is designed such that it should never have to shut down. There are two firewater pumps, each
with 100% capacity, so that one can be isolated for maintenance while the other provides protection to
the plant. During shutdowns of other units, the Firewater supply must be maintained.
The following sections detail the normal start up of each of the items of equipment connected with Unit
50 after either maintenance or an incident requiring the activation of Unit 50.
4.3.1 Firewater Storage Tank 50-T-001
If 50-T-001 is shut down for maintenance and drained it must first be refilled before being brought back
on-line.
Maintenance on 50-T-001 should only be carried out during periods when all other units are shutdown
and Plant is ready for major overhaul. More information on the shut down and isolation of the Firewater
Storage Tank is contained in Chapter 6 of this manual.
_______________________________
_______________________________
_______________________________
The following tables contain the current controller set points, alarm set points and trip settings for the
instrumentation on Unit 50. The tables contain information for the instrumentation shown on P&IDs only.
4.4.1 UNIT 50 CONTROLLER SET POINTS AND ALARMS
_______________________________
5 NORMAL OPERATION
During the everyday running of the plant, Unit 50 will only "operate" if there is a fire somewhere on the
plant.
5.1.1 Control Philosophy
The function of the Fire Protection System is to meet the firewater requirements of the process and
utility units.
Unit 50 is controlled remotely from the control room or locally using local start/stop panels.
_______________________________
_______________________________
_______________________________
6 NORMAL SHUTDOWN
6.1 GENERAL
A normal shutdown is either a scheduled shutdown or one that is carried out in an orderly manner for
reasons other than emergencies or process trips. The extent of the work to be carried out during the
shutdown will dictate whether a full shutdown of all equipment is necessary.
The actions to be taken prior to a shutdown are dependent upon which equipment items are being taken
out of service and the expected duration of the shutdown.
During a shutdown all equipment must be properly isolated.
A normal shutdown is a scheduled operation and therefore should be carried out in coordination with all
other units, especially as firewater is vital to the safety and operation of the rest of the plant.
While shutdown procedures are being carried out it is the prime responsibility of those in charge of
operations to ensure that all requirements of RSG-OCPP safety regulations and standing operating
procedures are adhered to.
The instructions in this chapter form a basis for developing detailed step-by-step "standing operating
procedures" for the shutdown of Unit 50.
6.2 UNIT 50 SHUTDOWN
Unit 50 is designed such that it should never have to shut down. Firewater tank can be isolated and
maintenance/cleaning carried out on it only when the rest of the plant is shutdown.
There are two firewater pumps, each with 100% capacity, so that one can be isolated for maintenance
while the other provides protection to the plant.
During shutdowns of other units, the firewater supply must be maintained so that all fire hydrants,
monitors and hose reels are fully operational.
The shutdown of equipment following a fire is outlined in section 2.2 of this chapter.
If a complete shutdown of Unit 50 is required, it should be carried out by systematically shutting down
and isolating the individual items that form Unit 50.
The shutdown and isolation of individual items of equipment is outlined in section 2.1 of this chapter.
_______________________________
_______________________________
_______________________________
_______________________________
7 EMERGENCY SHUTDOWN
7.1 GENERAL
This chapter describes the philosophy and implementation of the safeguarding systems installed on
Unit-50.
In the following sections consideration is given to a range of emergency scenarios.
7.1.1 Safety Interlock System Philosophy
There is no ESD system for Unit 73.
7.2 UTILITIES FAILURE
The following procedure provides the basis for the operation of Unit 50 after the failure of utility systems.
7.2.1 Electrical Power Failure - Machinery and Control System
With regard to the power supply to machinery the following measures have been incorporated into the
power system design in order to mitigate potential problems associated with partial power failure:
One of the firewater pumps, 50-P-001, has an electric motor driver, the other
50-P-002 is driven by a diesel engine.
Jockey pumps 50-P-003A/B are fed from emergency diesel generator.
7.2.2 Instrument Air
The firewater system contain only one air actuated control valve LV-050 and the action is fail close.
Firewater supply to the hydrants, monitors, hose reels and deluge will be maintained and will continue to
operate as normal.
_______________________________
8 SAFETY
8.1 GENERAL
This chapter contains information on the safety systems installed on Unit 50 for protection from plant
fires and gas leaks.
Also discussed is the nature of the hydrocarbon materials handled by other units on the plant, and
safety precautions.
Unit 50 is an inherently safe unit. It is however part of a plant which handles hazardous materials, and
so sections of this chapter may not be specifically applicable to Unit 50, but are provided to give an
overall safety view of the units nearby and the rest of the plant.
8.1.1 Operator Training
Almost all hydrocarbons and chemicals can be dangerous if not properly handled. Therefore, the
operators should be thoroughly acquainted with the hazardous properties of all materials in use and
should be properly drilled in the correct procedures for handling these materials.
All operators should familiarize themselves with the location and use of fire fighting equipment:
hydrants, hose reels, extinguishers, and of safety equipment: safety showers, eye baths, breathing
apparatus and all other safety equipment installed on the units.
In addition the operators should be thoroughly familiar with basic first aid measures and should be able
to take appropriate action in case of an incident.
Periodic practice drills, and more specifically fire fighting drills should be carried out in order to instruct
the operators in the hazards involved and the proper emergency action required so as ensuring the
maximum protection both for personnel and equipment.
8.1.2 Fire and Explosion Hazards
Unit 50 does not handle hydrocarbons and as such does not pose a serious fire and explosion threat.
There are, however, hydrocarbon processing units nearby which do pose a serious threat and so
information on the fire and explosion hazards are contained in this section for reference.
8.1.2.1 General
All hydrocarbons involve a fire and explosion hazard. The most hazardous liquid petroleum products are
those having a flash point below 55°C: crude oil, condensate, etc. Light hydrocarbon liquids at ambient
conditions can produce vapors which are heavier than air and form an explosive mixture with air.
Therefore special attention should be given to any operation where that risk occurs such as draining or
venting pump casings or vessels, and during sampling operations.
Any leak must be repaired as soon as possible and preventative measures taken immediately (water
spray, steam or nitrogen hoses, sand on liquid pools, etc.).
In addition to the fire and explosion hazards, the operators must also be thoroughly acquainted with the
hazard of Nitrogen that is very dangerous since it is an asphyxiate. However, nitrogen is often
overlooked as a hazardous substance since it is the main constituent of air. For this reason the dangers
of nitrogen must be emphasized and the operators instructed in the procedures and precautions to be
taken before entering a vessel previously inserted.
_______________________________
8.2.1 General
Unit 50 is provided with a limited range of fire fighting equipment which is designed to be used to deal
with unit fire incidents only. Refer to section 2.2, below.
Before attempting to tackle a unit fire, of any magnitude, the operators must be aware of the nature of
the fire. It is essential that they are familiar with the capabilities and limitations of any particular piece of
fire fighting equipment (e.g. water must not be used on an electrical fire; burning liquid spills should be
tackled with foam, not water).
The first action to be performed on discovery of a unit or a plant fire, (regardless of size), is to raise the
alarm. In this way adequate support in the form of trained fire fighting personnel and mobile fire fighting
equipment will be rapidly mobilized to assist in dealing with the fire. Then, should the incident escalate,
personnel and equipment are already on the scene and prepared.
Operating personnel shall not endanger themselves while attempting to deal with a fire. While small
scale fires can be tackled with hand held extinguishers or steam lances, major fires should be dealt with
from a distance using deluge systems, firewater monitors and fire hoses.
The operators should familiarize themselves with the location and the details of operation of all fire
fighting equipment.
It is the responsibility of the safety officer to periodically check the fire fighting and safety equipment to
ensure that all systems are in full working order. Any items which are noted as being faulty, non-
functional or missing should be immediately reported to the safety officer.
8.2.2 Fire Fighting Equipment
The existing fire hydrant and additional portable dry chemical powder fire extinguishers located close to
the pumps are considered adequate to combat any possible fires.
8.3 FIRE AND GAS DETECTION
Fire and Gas Detection Systems shall include the following inputs:
• smoke and heat addressable point-type detectors (inside shelters)
• flame detectors (in plant areas);
• MCPs activation;
• field thermo-sensitive cables in pair;
• hydrocarbon (CH4) gas detectors;
and outputs
• HVAC systems shut-down;
• audible and visual alarm devices (inside/outside shelters and in plant areas);
• clean agent (FM200) discharge system activation (if applicable);
• active firefighting systems activation in plant areas;
The process plant Fire and Gas Detection System shall be provided with sufficient and
reliable detectors to ensure personnel warning and allow immediate response to minimize damage from
any emergency situation.
_______________________________
9.1 DATASHEETS
_______________________________
10 DRAWINGS
10.1.1 UNIT 50
Enclosed in this section are the following P&IDs:
50-T-001 AND 50-P-001/002 50-GD-B-85660
50-P-003A/B 50-GD-B-85661
10.1.2 BERMAD Deluge Skid Package
Refer to P&ID 50-GD-B-85680
10.2 PLOT PLAN
Enclosed in this section are the following Fire and Safety Layout Drawings:
INSTRUMENTS AND F&G EQUIPMENT LOCATION LAYOUT 00-SB-A-57504
10.4 OVERALL FIREWATER RINGMAIN DRAWINGS
Enclosed in this section are the operating instructions for the Firewater Pump.
AUDOLI E BERTOLA 50-MA-E-98240
_______________________________
1.1 GENERAL
_______________________________
The following Service and Potable Water quality have been used for the design of the System:
SERVICE/ POTABLE
PARAMETER UNITS WATERDESIGN ANALYSIS
ANIONS
CHLORIDE mg/l Cl- 31.47
BICARBONATE mg/l HCO3- 10.47
NITRATE mg/l NO3- 0.65
PHOSPHATE mg/l PO4-- 0.95
CARBONATE mg/l CO3-- 0.02
TOTAL ANIONS mg/l CaCO3 43.56
CATIONS
CALCIUM mg/l Ca++ 19
SODIUM mg/l Na+ 23.02
ZINC mg/l Zn++ 0.612
AMMONIUM mg/l NH4+ 0.881
IRON (Bivalent) mg/l Fe++ 0.054
TOTAL CATIONS mg/l CaCO3 43.56
OTHERS
pH VALUE - 7.15
TOTAL SUSPENDEDSOLIDS mg/l 0.2
OPER. TEMPERATURE °C 31
DES. TEMPERATURE °C 70
CONDUCTIVITY@25°C μS/cm 98
Moreover, a maximum free chlorine concentration of 2 ppm is prevised for Service and potable water
distribution loop.
1.4 EFFLUENTS
_______________________________
General input design data used for tank and pump sizing are shown below:
Continuous users
· Number of operators in the Plant: 8
· Water consumption per person per day 400 litres
· Average Potable Water for human consumption: 3.2 m3/d
Intermittent users
· Number of safety showers/ hose contemporary in service: 2
· Flow rate required for one safety shower or one hose: 6.8 m3/h
· Gas Turbine Compressor Washing System
· Natural Gas Water Bath Heater
· Secondary Cooling Water Make-up
60-T-003:
· Tank hold-up: 4 days
· Required Tank working Volume: 14 m3
· Selected Tank nominal Volume: 26.7 m3
60-P-002 A/B:
· Required Pump flow rate: 20.4 m3/h
· Selected Pump flow rate: 25 m3/h (See note below)
· Head at rated capacity: 63 m
· BHP: 6.5 kW
Note: Selected pump flow rate takes into account the water consumption for: continuous users, two
contemporary operating safety shower / hose and the biggest intermittent user between the Gas Turbine
Compressor Washing System, Natural Gas Water Bath Heater and Secondary Cooling Water Make-up.
Pumps 60-P-002 A/B are under Emergency Diesel Generator (95-PK-007) backup power to guarantee
Service/ Potable Water supply also during a total power failure scenario.
The following Utilities and interfaces must be available for a proper operation of the Service and Potable
Water System:
a) Electric power for pumps/ Eletrochlorination/ dosage package operation
b) Instrument air for instrumentation operation.
c) Service Air hose for maintenance operations.
d) Service / Potable Water for hypochlorite solution dilution into 60-PK-004 hypochlorite storage tank and
for hose connection.
1.7 CHEMICALS
The chemical used on Unit 60 is the chlorine used by the chlorination package.
_______________________________
_______________________________
2 PROCESS DESCRIPTION
2.1 GENERAL
2.1.1 References
The basic engineering documents related to the design of the Service and Potable Water System Unit
60 are listed hereafter:
60-GD-B-86552 P&ID – Service and Potable Water System
60-MA-E-86100 Process Data Sheet for Service and Potable Water Pump
60-RA-E-86101 Process Data Sheet for Service and Potable Water Tank
60-PA-E-86109 Duty Specification for Sodium Hypochlorite Dosing Package-
00-ZA-E-86925 Utility Systems Cause & Effect Matrix
These documents are enclosed in Chapters 9 and 10 of this manual.
It is recommended that the relevant P&IDs to be studied in conjunction with this chapter.
_______________________________
_______________________________
Unit 60 is controlled remotely via a CS control panel in the main control room. There are also local
emergency STOP push buttons for the Potable Water Pumps
The level in the tanks is maintained by 60-LI-061 (Tank level is not maintained by any controller related
to this transmitter; this level will provide several alarms (HH, H, L) on the CS Operator Stations in
control room) which has high and low alarms set at 4240 mm and 2100 mm respectively. 60-LT-062 is
used to detect the low low liquid level at 700mm which will cause the running potable water pump to trip.
This liquid level must be exceeded before the pumps can be started.
2.3.1 Pressure Control
60-PIC-061/ 60-PV-061:
a) Function: 60-PIC-061 guarantees a suitable minimum pressure at the furthest point of potable water
distribution ring. The pressure value to be considered as set value for the controller is 3.5 bar measured
upstream valve 60-PV-061.
b) Action: When the pressure falls below the 60-PIC-061 set point, the associated pressure control valve
60-PV-061 tends to close to increase the pressure into the closed distribution loop. Vice versa when the
pressure rises over the set point of 60-PIC-061, the associated pressure control valve 60-PV-061 tends
to open to decrease the pressure into the closed distribution loop.
Should the controller either set in “BAD” by the logic or the related transmitter overridden by the suitable
MOS, then the controller will be set in manual and the set point will follow the controller output (PV
tracking). Due to the above, when the operator will set the controller in “Auto” mode, this will be “bump
less” for the control valve.
60-CS-01:
a) Function: The main pump selected by means of the suitable hand switch 60-HSMS-62 will be manual
started by the operator. 60-CS-01 starts the stand-by pump at low pressure and stops the stand by
pump at high pressure.
The HP and LP values are CS alarms through the 60-PI-062 (LP set value 4 bar,
HP set value 6 bar). Hand switch 60-HSMS-062 is provided to select main/ stand-by pump between the
two pumps 60-P-002 A/B.
The measured pressure value from 60-PT-062 and the main/ stand-by selection from 60-HSMS-062 are
the inputs to 60-PY-062. The resulting output value from
60-PY-062 is then sent to 60-CS-01.
b) Action: when the pressure falls below LP set point, 60-CS-01 starts the stand-by pump. Vice versa,
when the pressure rises above HP set point logic 60-CS-01 stops the stand-by pump.
_______________________________
_______________________________
3.1 GENERAL
Prior to initial startup, all pre-commissioning activities must have been completed and the unit must be
ready for operation.
Pre-commissioning covers those activities required to bring the unit to a "ready for startup" condition
following construction. In general, it consists of inspection, checking and testing operations required to
ensure that all components of the unit are properly installed and mechanically complete. The most
important requirement is that the unit can be started up in a controlled, efficient and safe manner.
This pre-commissioning phase is usually performed by the construction forces in close co-ordination
with the operations/commissioning team.
For this purpose, checking sheets (or "mechanical guides") will be issued and filled out on site in close
co-operation between construction and the commissioning team.
Full details of pre-commissioning activities with regard to inspection of equipment items, general checks,
hydrostatic testing, instrumentation functional testing, electrical motor run-in, line and vessel cleaning,
etc., are outside the scope of this document.
Details of the initial startup and commissioning of the Service and Potable System are detailed in this
chapter. Operating parameters and adjustments, shutdown and emergency situations are detailed in
Chapters 5 to 7.
The information and procedures described hereafter concern the preliminary operations for the first
startup of a new unit. Procedures are slightly adapted for normal and subsequent start up, as indicated
in Chapter 4.
3.2 PREPARATION PRIOR TO INITIAL OPERATION
It is assumed that all the pre-commissioning/maintenance activities are completed and that the unit has
reached a "ready for startup" status.
Most of the following pre-start up items are routine and are briefly presented as reminders only, as they
refer to precommissioning activities.
Ensure that the following requirements are satisfied:
¨ All safety equipment is in place and is fully operable.
¨ All pipework has been pressure tested and cleaned.
¨ All equipment has been pressure tested, inspected, cleaned, drained and dried.
¨ All equipment is at ambient conditions.
¨ Chemicals are available.
¨ Test equipment and special tools, if any, and facilities for their operation are available.
¨ All rotating equipment and their associated drivers have been aligned, run in and lubricated, as required,
following the manufacturers' recommended procedures.
¨ Temporary strainers must be installed where specified and their locations properly recorded for future
reference.
¨ Instrument air is available and commissioned to all instruments.
_______________________________
¨ Electrical power systems have been checked out and commissioned. It is available to all electric drivers
and all instrument boards.
¨ All instruments have been calibrated, loops checked and commissioned. All sensing elements which
were removed from pipework prior to hydro testing have been reinstalled.
¨ All the DCS data links are operational.
¨ Emergency shutdown systems are fully operational and if possible, a dry run has been performed.
¨ All safety relief valves have been tested and are in service. All block valves around relief valves are
locked in the correct position.
¨ All blinds, if any, which were installed in the lines during hydro testing have been removed and replaced
with their relevant spacers.
¨ All utilities have been commissioned, lined up and are ready for use at the unit battery limit.
It is the prime responsibility of those in charge of the plant to ensure that all operations are carried out
satisfactorily.
3.3 SERVICE AND POTABLE WATER TANK AND PUMPS STARTUP
3.3.1 Valve Positions Prior to Start Up
All valves should be in this position as shown on P&ID 60-GD-B-86552
Valve Number Location/Line Position
60-V-01 60-T-003 Inlet Isolation Valve. Closed
3”-60-PW-002
60-V-02 60-T-003 Inlet Isolation Valve. Closed
2”-60-PW-003
60-V-03 60-T-003 By pass PV- 061 Closed
2”-60-PW-003
60-V-04 60-T-003 Provision for water filling from tanker Open
3”-60-PW-004
60-V-05 60-T-003 Open Drain Closed
3”-60-PW-013
60-V-06 60-T-003 Tank Outlet Isolation Valve. Closed
4”-60-PW-005
60-V-07 60-P-002A Suction Line Isolation Valve. Closed
4”-60-PW-006
60-V-08 60-P-002B Suction Line Isolation Valve. Closed
4”-60-PW-005
60-V-09 60-P-002A Discharge Line Isolation Valve. Closed
3”-60-PW-008
60-V-10 60-P-002B Discharge Line Isolation Valve. Closed
3”-60-PW-008
60-V-11 60-PK-004 Dilution Water Line Closed
1/2”-60-PW-042
60-V-12 60-PK-004 Chlorine Outlet Line Closed
1/2”-60-CH-003
Note: the battery limits of all the users are closed.
_______________________________
_______________________________
Take in consideration that AT- 061/ AT-062 are on line and set point for residual Cl 2 is input by DCS.
Ensure the water level into the 60-T-003 is at the normal range. Top up if necessary.
Ensure that water make-up valve V-11 and sodium hypochlorite outlet valve V-12 are open at the
chemical skid.
With the water flowing around the minimum flow spillback loop, the Chlorination Package can now be
commissioned using the procedure outlined in this chapter.
· Verify the arriving tension to the panel cabinet: 400V+N 50Hz.
· Make sure that the selector switch SA1 is on the position “0” (Pict.1).
· Close all the ball valves of pvc lines: V1.V2, V3, V4, V5, V6.
· Put in action the general switch QS on the position “ON”. The presence of tension is indicated by the
warning light “HLL” (pict.1).
· Push the button “START PLANT” (SBS) (Pict.1). After few seconds the warning lights VERY LOW
LEVEL (HL1)“ for the very low level and LOW LEVEL (HL2) for the low level of chlorine inside the tank
will be activated (pict.1).
· Prepare the water-chlorine solution by pouring at first 50 liters of hypochlorite and 200 liters of water. It
is possible to pour water using the valve V5 (pict.4). Pour water before putting the sodium hypochlorite.
When the chlorination unit and the whole system of water distribution are at speed, it will be possible to
optimize the percentage of chlorine and water in order to obtain an accurate metering and a time as
long as possible before charging the chlorine tank again. After pouring water and, afterwards, chlorine,
the alarm of very low level is turned off.
· Open slowly the valve “V1”permitting the chlorine to flow to the metering pump (pict.5).
· Open the valve “V4” to activate the damping sack (pict.6).
· Slightly open the valve “V2” (pict.7) in order to eliminate the air.
· Activate the metering pump by positioning the selector switch “SELECTOR PUMP” (SA1) on 1 (pict.1);
the pump is activated and as soon as the air inside the pump body and piping is eliminated, close the
valve “V2” (pict.7) and deactivate the metering pump with the selector switch “SA1”.
_______________________________
· Open the valve V3 (pict.8) and start up the metering pump with the selector switch SA1. During the first
hours of operation the metering pump will inject chlorine at the maximum of its flow rate, and after this,
by means of the processed signal of water flow rate to be chlorinated and residual chlorine, the pump
will decrease the metering in order to keep the quantity of free chlorine measured in the potable water
near the set value (maximum value required = 2 ppm free chlorine).
Level Setting;
Levels are already set as follow:
Low Level 40% (to send signal ON-OFF)
Very Low Level 20% (to send signal ON-OFF and stops the metering pump)
Metering Pump Setting;
The metering pump setting is set as follow:
Stroke adjustment signal: 20 mA = MAXIMUM DOSAGE
Stroke adjustment signal: 4 mA = MINIMUM DOSAGE
Once the tank is full, the level alarms are deactivated. As the chlorine level goes below the low level
threshold, the warning light “LOW LEVEL” is activated (pict.1). In this case a digital free contact is
available on the panel, which can be used in case of external alarm.
· As the chlorine level goes below the very low level threshold, the warning light VERY LOW LEVEL is
activated (pict.1) and the metering pump is stopped. Also in this case a digital free contact is available
on the panel, which can be used in case of external alarm.
· Should a failure of the metering pump occur, will be indicated by the warning lamp THERMIC BLOCK
(HLR) (pict1). As for the pump failure, a digital free contact is available on the panel, which can be used
in case of external alarm.
· If a black-out of power occurs during the normal functioning, the chlorination skid remains deactivated.
In order to reactivate the whole system, it is necessary to push the button of “START PLANT” (SBS)
(Pict.1).
Operatively;
The minimum and maximum flow rate indicated (0,133 mc/h – 25 mc/h) and the value of maximum
residual chlorine (2 ppm) modify automatically the metering regulation of the metering pump.
3.5 FINAL PREPARATIONS
Ensure that any high point vents and low point drains previously opened are now closed.
· Ensure that flow controller 60-PIC-061 is in "AUTOMATIC" with a set point of
3.5 bar.
· Ensure the water level into the 60-T-003 is at the normal range. Top up if necessary.
· Ensure that the Residual Chlorine Analyzer has a set point of max 2 ppm Cl 2 and the Chlorination
Package Skid is fully operational.
Once the Service and Potable Water Network has been flushed and the residual chlorine concentration
at all the battery limit drain valves is at desired range, Potable Water users can now begin to fill and
flush their systems, as required.
_______________________________
4.1 GENERAL
The procedures and instructions laid out in this chapter are to be used to start up
Unit 60 following a shutdown. The shutdown may have been routine as part of normal operation,
turnaround or maintenance.
The recommended start-up procedure is presented in section 3.0.
The following start up procedures are recommended, with the understanding that the judgment of the
operators should dictate which of these steps are required, and in what order, based on the nature of
the preceding shutdown. The initial start-up instructions presented in Chapter 3 should be referred to for
specific details.
4.2 PRE-START UP CONDITIONS
Prior to restarting Unit 60 it is the prime responsibility of those in charge of operations to ensure that the
following criteria have been satisfied:
After a shutdown for turnaround and maintenance, start up orders have to be initiated after ensuring that
all requirements relating to plant acceptance and readiness for restart have been fulfilled.
After an unplanned shutdown the unit must be checked over to ensure that the unit is ready and safe to
operate and that the cause of the shutdown has been rectified.
The restart must be performed in accordance with all RSG-OCPP safety regulations and standing
instructions.
The following shall be assumed for the purpose of the start up procedures in this chapter:
All utility systems are commissioned and available as required to the units.
All instruments and control systems have been checked and are functional.
4.3 NORMAL AND SUBSEQUENT START UP PROCEDURE
Unit 60 is designed such that it should never have to shut down. There are two service and potable
pumps, each with 100% capacity, so that one can be isolated for maintenance while the other is on line.
During shutdowns of other units, the service water supply must be maintained so that all Safety
Showers and Eyebaths etc. are available and fully functional.
The following sections detail the normal start up of each of the items of equipment connected with Unit
60 after either maintenance or an incident requiring the activation of Unit 60.
4.3.1 Lining Up Service and Potable Water Tank 60-T-003
If 60-T-003 is shut down for maintenance and drained it must first be refilled before being brought back
on-line.
_______________________________
Maintenance on Service and Potable Water Tank 60-T-003 should only be carried out during periods
when all other units are shutdown and Plant is ready for major overhaul. More information on the shut
down and isolation of the Service and Potable Water Tank is contained in Chapter 6 of this manual.
The procedure is identically with the one described in chapter 3.3.2
· Provide a water tanker and fill it with chlorinated water from potable water skid situated in Afam Base (It
is not mandatory to have a chlorinated water because the water will be eventually chlorinated from 60-
PK-004.)
· Start discharging the water tanker using the filling line of Service and Potable Water Tank 60-T-003
Depending on water tank capacity and availability of treated/ chlorinated water, the filling of 60-T-003 will
take approximately 2 days.
· Open 60-V-06 the Tank Outlet Isolation Valve and car seal.
60-T-003 is now full and ready to be used.
During this operation, check if LL/ L level indications are cleared and H/ HH level indications will be
activated.
4.3.2 Lining Up Service and Potable Water Pumps 60-P-002A/B
Consider Pump A was under maintenance and Pump B is running in normal conditions.
· Open fully 60-V-07 and 60-V-09 suction and discharge line isolation valves for
60-P-002A.
This will allow the casing of the pump to fill with water. Lock open the valves.
· Ensure the power supply is available and press the "START" command located in control room.
Observe the running of the pump and when running smoothly, pump B can be stopped.
· The pump can be stopped at the local panel by pushing the red "STOP" emergency pushbutton or from
control room.
4.3.3 Lining Up of Chlorination Package 60-PK-004
Consider level in hypochlorite tank is on normal range and no L/LL alarm is activated.
· Open slowly the valve “V1”permitting the chlorine to flow to the metering pump (pict.5).
· Open the valve “V4” to activate the damping sack (pict.6).
· Slightly open the valve “V2” (pict.7) in order to eliminate the air.
· Activate the metering pump by positioning the selector switch “SELECTOR PUMP” (SA1) on 1 (pict.1);
the pump is activated and as soon as the air inside the pump body and piping is eliminated, close the
valve “V2” (pict.7) and deactivate the metering pump with the selector switch “SA1”.
· Open the valve V3 (pict.8) and start up the metering pump with the selector switch SA1. During the first
hours of operation the metering pump will inject chlorine at the maximum of its flow rate, and after this,
by means of the processed signal of water flow rate to be chlorinated and residual chlorine, the pump
will decrease the metering in order to keep the quantity of free chlorine measured in the potable water
near the set value (maximum value required = 2 ppm free chlorine).
4.4 CONTROLLER SET POINTS, ALARMS AND TRIP SETTINGS
_______________________________
The following tables contain the current controller set points, alarm set points and trip settings for the
instrumentation on Unit 60. The tables contain information for the instrumentation shown on P&IDs only.
_______________________________
_______________________________
5 NORMAL OPERATION
Ensure that all safety procedures concerned with the handling of Sodium Hypochlorite are being taken.
5.3 PERFORMANCE MONITORING
The two potable water pumps are designed so that one will be running at any one time, with one on
standby.
Operators should endeavor to give the pumps equal running times by logging the running times for each
pump. Pump changeovers should not be used purely for maintenance purposes, but also to avoid
leaving one pump standing for any great length of time. This may result in damage to bearings and
other parts of the pump.
_______________________________
_______________________________
6 NORMAL SHUTDOWN
6.1 GENERAL
A normal shutdown is either a scheduled shutdown or one that is carried out in an orderly manner for
reasons other than emergencies or process trips. The extent of the work to be carried out during the
shutdown will dictate whether a full shutdown of all equipment is necessary.
The actions to be taken prior to a shutdown are dependent upon which equipment items are being taken
out of service and the expected duration of the shutdown.
During a shutdown all equipment must be properly isolated.
A normal shutdown is a scheduled operation and therefore should be carried out in coordination with all
other units, especially as firewater is vital to the safety and operation of the rest of the plant.
While shutdown procedures are being carried out it is the prime responsibility of those in charge of
operations to ensure that all requirements of RSG-OCPP safety regulations and standing operating
procedures are adhered to.
The instructions in this chapter form a basis for developing detailed step-by-step "standing operating
procedures" for the shutdown of Unit 60.
6.2 UNIT 60 SHUTDOWN
Unit 60 is designed such that it should never have to shut down. There are two service and potable
pumps, each with 100% capacity, so that one can be isolated for maintenance while the other is on line.
During shutdowns of other units, the service water supply must be maintained so that all Safety
Showers and Eyebaths etc. are available and fully functional.
If a complete shutdown of Unit 60 is required, it should be carried out by systematically shutting down
and isolating the individual items that form Unit 60.
The shutdown and isolation of individual items of equipment is outlined in section 2.1 of this chapter.
6.2.1 Item Shutdown and Isolation
_______________________________
_______________________________
7 EMERGENCY SHUTDOWN
7.1 GENERAL
This chapter describes the philosophy and implementation of the safeguarding systems installed on Unit
60.
In the following sections consideration is given to a range of emergency scenarios.
7.1.1 Safety Interlock System Philosophy
There is a safety interlock system implemented in the DCS as follows:
If the level in Service and Potable Water Tank 60-T-003 falls below 700 mm as measured by 60-LT-062,
then this will cause the running Potable Water Pump(s) to trip and will inhibit any attempt to re-start any
of the pumps until the level in the tanks has risen.
For Sodium Hypochlorite Skid the pump stops in case of alarm of LL chlorine level, detected by the level
controller.
The level controller indicates the two levels on the panel, both L and LL, an ON-OFF contact is present
for each indication.
7.2 UTILITIES FAILURE
The following procedure provides the basis for the operation of Unit 60 after the failure of utility systems.
7.2.1 Electrical Power Failure - Machinery and Control System
With regard to the power supply to machinery the following measures have been incorporated into the
power system design in order to mitigate potential problems associated with partial power failure:
Both service and potable water pumps are fed from emergency diesel generator.
7.2.2 Instrument Air
The firewater system contain only one air actuated control valve PV-061 and the action is fail open.
Potable and service water to the users will be maintained and will continue to operate as
normal
_______________________________
8 SAFETY
8.1 GENERAL
This chapter contains information on the safety systems installed on Unit 60 for protection from plant
fires and gas leaks.
Also discussed is the nature of the hydrocarbon materials handled by other units on the plant, and
safety precautions.
Unit 60 is an inherently safe unit. It is however part of a plant which handles hazardous materials, and
so sections of this chapter may not be specifically applicable to Unit 60, but are provided to give an
overall safety view of the units nearby and the rest of the plant.
8.1.1 Operator Training
Almost all hydrocarbons and chemicals can be dangerous if not properly handled. Therefore, the
operators should be thoroughly acquainted with the hazardous properties of all materials in use and
should be properly drilled in the correct procedures for handling these materials.
All operators should familiarize themselves with the location and use of fire fighting equipment:
hydrants, hose reels, extinguishers, and of safety equipment: safety showers, eye baths, breathing
apparatus and all other safety equipment installed on the units.
In addition the operators should be thoroughly familiar with basic first aid measures and should be able
to take appropriate action in case of an incident.
Periodic practice drills, and more specifically fire fighting drills should be carried out in order to instruct
the operators in the hazards involved and the proper emergency action required so as ensuring the
maximum protection both for personnel and equipment.
8.1.2 Fire and Explosion Hazards
Unit 60 does not handle hydrocarbons and as such does not pose a serious fire and explosion threat.
There are, however, hydrocarbon processing units nearby which do pose a serious threat and so
information on the fire and explosion hazards are contained in this section for reference
8.2 LISTING OF SAFETY EQUIPMENT
8.2.1 General
Unit 60 is provided with a limited range of fire fighting equipment which is designed to be used to deal
with unit fire incidents only. Refer to section 2.2, below.
Before attempting to tackle a unit fire, of any magnitude, the operators must be aware of the nature of
the fire. It is essential that they are familiar with the capabilities and limitations of any particular piece of
fire fighting equipment (e.g. water must not be used on an electrical fire; burning liquid spills should be
tackled with foam, not water).
The first action to be performed on discovery of a unit or a plant fire, (regardless of size), is to raise the
alarm. In this way adequate support in the form of trained fire fighting personnel and mobile fire fighting
equipment will be rapidly mobilized to assist in dealing with the fire. Then, should the incident escalate,
personnel and equipment are already on the scene and prepared.
_______________________________
Operating personnel shall not endanger themselves while attempting to deal with a fire. While small
scale fires can be tackled with hand held extinguishers or steam lances, major fires should be dealt with
from a distance using deluge systems, firewater monitors and fire hoses.
The operators should familiarize themselves with the location and the details of operation of all fire
fighting equipment.
It is the responsibility of the safety officer to periodically check the fire fighting and safety equipment to
ensure that all systems are in full working order. Any items which are noted as being faulty, non-
functional or missing should be immediately reported to the safety officer.
8.2.2 Fire Fighting Equipment
The existing fire hydrant and additional portable dry chemical powder fire extinguishers located close to
the pumps are considered adequate to combat any possible fires.
8.2.3 Safety (Personal Protection) Equipment
In Unit 60 the following types of safety equipment are provided to protect operating personnel during the
execution of their duties:
¨ Eye Baths
An eyebath/face wash unit is provided as part of the Chlorination Package and is located at the
Chlorination skid.
¨ Safety Signs
Throughout Unit 60 numerous safety signs are provided to assist the operators. They describe
various hazards, the location of firefighting equipment, the location of safety equipment and
provide mandatory safety instructions ("wear ear defenders", etc.).
During the makeup of hypochlorite tank, operators must ensure they are wearing impervious gloves, a
facemask, and protective coveralls. These items of equipment are not provided locally, and so the
operator must carry them onto the unit.
8.3 CHLORINE (Cl2) INFORMATION
This section contains information about the physical properties and hazardous properties of chlorine.
Also included is information on the toxic nature of the gas, physiological effects of exposure and first aid
procedures to effect recovery from chlorine poisoning.
The procedures outlined in the following pages are offered as a guide only. Adherence to RSG-OCPP
standing operating procedures for the handling of chlorine and chlorine bearing materials shall be
adhered to at all times and take precedence over this manual.
Physical Properties
* Normal Physical State: Gaseous
* Color: Greenish yellow
* Boiling Point: -34°C
* Melting Point: -101°C
* Molecular Weight: 71
* Specific Gravity (Air = 1): 2.45
_______________________________
_______________________________
9.1 DATASHEETS
_______________________________
10 DRAWINGS
_______________________________
1.1 GENERAL
_______________________________
Total Instrument
UNIT Air/Service Air
Consumption
Nm3/h
00-Common Items 2
30-Stack System Unit 24
50-Fire fighting System Unit 2
60-Service and Potable water System Unit 15
70-Fuel Gas System Unit 17
80-Service & Instrument Air System Unit 8
1.4 EFFLUENTS
Sour water is drained from the plant air receiver using an automatic drain valve into an open drain .
1.5 UTILITY REQUIREMENTS
_______________________________
2 PROCESS DESCRIPTION
2.1 GENERAL
Instrument and Service Air will be provided by means of 2X100% electrical motor driven air
compressors (one operating and one stand-by) and sent to a Wet Air Receiver.
From the Wet Air Receiver part of the compressed air will be treated through a dryer package to
produce Instrument Air and the remaining part will be used as Service Air.
The System is a whole package composed of the following main items:
80-PK-005 A/B – Air Compressors Package
80-V-001 – Wet Air Receiver
80-PK-006 A/B – Instrument Air Dryer
_______________________________
The changeover of the dryers can be controlled manually using the local control panel or automatically
using either a timer or the dew point analyzer in the outlet from the dryers to initiate a changeover.
2.3 ELEMENTS OF PROCESS CONTROL PHILOSOPHY
Function: 80-CS-02 receives an input signal from the pressure transmitter 80-PT-085 located on
instrument air supply header. The outputs signals from 80-CS-02 are:
· The indication to DCS through the 80-PI-085 which is provided of three LP alarm sets. The three LP
alarms sets are for the values of 7.8 bar g (LP alarm),
7.5 bar g (LLP alarm) and 7 bar g (LLLP alarm).
· The signal for the automatic start of the stand-by compressor on low pressure value of 7 bar g (LLLP
alarm value for 80-PI-085).
Action: 80-CS-02 action is the automatic start of the stand-by compressor on low pressure value of 7
bar g.
In particular, the output signal from 80-CS-02 is sent to the hand switch
80-HSMS-085 and from 80-HSMS-085 to the hand switches 80-HSHL-580 (compressor A) and 80-
HSHL-581 (compressor B).
The hand switch 80-HSMS-085 is a main/ stand-by selector, while hand switches
80-HSHL-580/1 are automatic/ manual selectors provided to bypass the automatic start-up of the stand-
by compressor (the 80-CS-02 action).
It is mandatory that the automatic start of the stand-by compressor on low pressure value of 7 bar g
shall override the hand switches 80-HSHL-580/1.
Moreover, both compressors are provided of the following status signals to DCS:
· Local/ remote status signals with 80-XSLR-580 (compressor A) and
80-XSLR-581 (compressor B).
· Running/ stopped status signals with 80-XSHL-580 (compressor A) and
80-XSHL-581 (compressor B).
· Automatic operation status signals with 80-XSAM-580 (compressor A) and
80-XSAM-581 (compressor B).
· General warning status signals with 80-XSAL-580 (compressor A) and
80-XSAL-581(compressor B).
· General shutdown status signals with 80-XSTR-580 (compressor A) and
80-XSTR-581 (compressor B).
· Compressor loaded status signals with 80-XSHD-580 (compressor A) and
80-XSHD-581 (compressor B).
Should the pressure in the Instrument air header fall to the low set pressure of 6.8 bar g, PT-081 will be
activated and will close UV-081 and isolate the plant air header, thus conserving the remaining air for
the instrument air supply
Air to be dried prior to distribution through the Instrument Air system is taken from the outlet of 80-V-001
and fed to the Instrument Air Dryer Package 80-PK-006.
Each dryer unit is provided with a local control panel. The air dryers switching can be done MAN or
AUTO mode. AUTO mode is controlled by a digital timer with a standard setting of 168 hours.
The dryer is equipped with a Pressure Dew Point sensor (PDP sensor), extending the drying time. The
regeneration time is still timer controlled.
_______________________________
The PDP sensor constantly measures the pressure dew point (PDP) of the air leaving the drying tower.
As long as the PDP temperature is below the set point (-40 °C or -70 °C), the drying tower will keep on
drying, until the PDP temperature exceeds the set point. On that moment the regenerated tower will
start drying the compressed air and the other tower will be regenerated.
As long as the PDP temperature is below the set point, regeneration of the non-drying tower is stopped
after the preset time interval of the timer has elapsed. As a result, reduction of purge air is achieved.
_______________________________
3.1 GENERAL
Prior to initial startup, all pre-commissioning activities must have been completed and the unit must be
ready for operation.
Pre-commissioning covers those activities required to bring the unit to a "ready for startup" condition
following construction. In general, it consists of inspection, checking and testing operations required to
ensure that all components of the unit are properly installed and mechanically complete. The most
important requirement is that the unit can be started up in a controlled, efficient and safe manner.
This pre-commissioning phase is usually performed by the construction forces in close co-ordination
with the operations/commissioning team.
For this purpose, checking sheets (or "mechanical guides") will be issued and filled out on site in close
co-operation between construction and the commissioning team.
A summary of pre-commissioning activities and a checklist to be completed before unit initial operation
are included in Section 2 of this chapter.
Full details of pre-commissioning activities with regard to inspection of equipment items, general checks,
hydrostatic testing, instrumentation functional testing, electrical motor run-in, line and vessel cleaning,
etc., are outside the scope of this document.
Details of the initial startup and commissioning of the Instrument and Plant Air system are detailed in
sections 3 of this chapter. Operating parameters, adjustments, shutdown and emergency situations are
detailed in Chapters 5 to 7.
The information and procedures described hereafter concern the preliminary operations for the first
startup of a new unit. Procedures are slightly adapted for Normal and Subsequent Start Up, as indicated
in Chapter 4 of this manual.
3.2 PREPARATION PRIOR TO INITIAL OPERATION
It is assumed that all the pre-commissioning/maintenance activities are completed and that the unit has
reached a "ready for startup" status.
Most of the following pre-start up items are routine and are briefly presented as reminders only, as they
refer to pre-commissioning activities.
Ensure that the following requirements are satisfied:
* All firewater systems are pressurized and ready for operation. All firefighting equipment is in place,
operational and has been functionally tested.
* All safety equipment is in place and is fully operable.
* All pipework has undergone pressure testing, cleaning and/or air blowing.
* All equipment has been pressure tested, inspected, cleaned, drained and dried.
* All equipment is at ambient conditions and full of air.
* Chemicals, if required, are available.
* Test equipment and special tools, if any, and facilities for their operation are available.
_______________________________
* All rotating equipment and their associated drivers have been aligned, run in and lubricated, as required,
following the manufacturers' recommended procedures.
* Electrical power systems have been checked out and commissioned. It is available to all electric drivers
and all instrument boards.
* All instruments have been calibrated, loops checked and commissioned. All sensing elements which
were removed from pipework prior to hydro testing have been reinstalled.
* All the DCS data links are operational.
* Emergency shutdown systems are fully operational and if possible, a dry run has been performed.
* All safety relief valves have been tested and are in service. All block valves around relief valves are
locked in the correct position.
* All blinds, if any, which were installed in the lines during hydro testing have been removed and replaced
with their relevant spacers.
* All continuous drainer inlet valves are open and all other vents and drains are closed.
It is the prime responsibility of those in charge of the plant to ensure that all operations are carried out
satisfactorily.
_______________________________
_______________________________
* Inspect the liquid level in wet air receiver 80-V-001 and manually drain the vessel if necessary.
* Ensure all continuous drains are open.
* Ensure the set point of the pressure Controller for air compressors is set at 8.5 bar g and that the
controller is in ""REMOTE".
* Ensure 80-V-01 and 80-V-02 compressors outlet isolation valves are open.
* Wet air receiver bypass valve V-04 to be closed and V-03 to be open.
Utility air header isolation valves V-05 and V-09 to be open.
* Ensure 80-V-06 and 80-V-07 air dryer inlet valves are open and 80-V-08 air dryer outlet valve is open.
Unit 80 is now running and generating Instrument and Plant Air to all its users.
_______________________________
4.1 GENERAL
The procedures and instructions laid out in this chapter are to be used to start Unit 80 following a
shutdown. The shutdown may have been routine as part of normal operation, turnaround or
maintenance etc., or as a result of an ESD.
None of the preceding reasons for shutdown will necessitate as time consuming a pre-start procedure
as that performed prior to initial startup, as described in chapter 3.
A reasonable degree of experience will enable the operators to carry out a number of the previously
described operations in parallel.
The recommended start up procedure is presented in section 3
The following start up procedures are recommended with the understanding that the judgment of the
operators should dictate which of these steps are required and in what order, based on the nature of the
preceding shutdown. The initial startup instructions presented in chapter 3 should be referred to for
specific details.
4.2 PRE-START UP CONDITIONS
Prior to restarting Unit 80 it is the prime responsibility of those in charge of operations to ensure that the
following criteria have been satisfied:
* After a shutdown for turnaround and maintenance, startup orders have to be initiated after ensuring that
all requirements relating to plant acceptance and readiness for restart have been fulfilled.
* After an ESD or any unplanned shutdown the unit must be checked over to ensure that the unit is ready
and safe to operate and that the cause of the shutdown has been rectified.
* The restart must be performed in accordance with all SCNL/ RSG OCPP safety regulations and
standing instructions.
The following shall be assumed for the purpose of the startup procedures in this chapter:
* All utility systems (hydrocarbon and non-hydrocarbon) are commissioned and available as required to
the units.
* All instruments and control systems have been checked and are functional.
Note: Before starting the unit, ensure that all continuous drains are open.
4.2.1 Air Compressor Package 80-PK-005A/B
The pre-start check for the compressor and lube oil system should be carried out as described in
section 3.3.1 of Chapter 3 of this manual.
4.2.2 Air Dryer Package 80-PK-006A/B
The pre-start check for the air dryers should be carried out as described in section 3.4.1 of Chapter 3 of
this manual.
_______________________________
Following a complete shutdown of Unit 80 it should be re-started in the manner outlined in section 3.3 of
Chapter 3 of this manual.
_______________________________
The following tables contain the current controller set points, alarm set points and trip settings for the
instrumentation on Unit 80.
4.4.1 Unit 80 Controller Set Points and Alarms
The table contains information for the instrumentation shown on P&ID only.
Refer to P&ID 80-GD-B-86554
Controller Alarm Tag No. Range / Set Point Transmitter Function
80-PT-085 8 bar g Monitors the Instrument Air
pressure to distribution
80-PAL-085 7.8 bar g
80-PALL-085 7.5 bar g
80-PALLL-085 7 bar g Auto start of stand by compressor
80-PT-081 8 bar g Controls the Plant Air to
distribution.
67-PAL-3002 6.8 bar g Close control valve UV-081 to
service air header.
Compressor Package 80-PK-005A/B Controllers and Alarms
Factory setting
Motor running time in star sec 10
Load delay time (star-delta) sec 10
Number of motor starts starts/day 240
Minimum stop time sec 20
Programmed stop time sec 3
Power recovery time (ARAVF) sec 15
Restart delay sec 3
Communication time-out sec 20
Unloading pressure bar g 9
Loading pressure bar g 8
Oil pressure (shut-down warning level) bar g 1.3
Oil pressure (shut-down level) bar g 1.2
Delay at start, oil pressure sec 15
Delay at signal, oil pressure sec 6
Compressor element 1 outlet temperature (shut-down warning level) ˚C 225
Compressor element 1 outlet temperature (shut-down level) ˚C 235
Compressor element 2 outlet temperature (shut-down warning level) ˚C 225
Compressor element 2 outlet temperature (shut-down level) ˚C 235
Compressor element 2 inlet temperature (shut-down warning level) ˚C 65
Compressor element 2 inlet temperature (shut-down level) ˚C 70
Oil temperature (shut-down warning level) ˚C 65
Oil temperature (shut-down level) ˚C 70
Service warning level for DP air filter mbar 44
Delay at signal, DP air filter sec 60
_______________________________
_______________________________
5 NORMAL OPERATION
_______________________________
_______________________________
· Automatic operation
Local selector: AUTO position
The air dryers switching is controlled by a digital timer, with a standard setting of 168 hours (variable
locally by the operator).
Both the air dryers must have the on/off switch S1 in position 1 "ON"
1. dryer 80-PK-006A running
2. dryer 80-PK-006B freeze - see note 4
3. inlet valve EVP-006A open
4. inlet valve EVP-006B closed
switching after 168 hours by means of the digital timer
5. dryer 80-PK-006B running
6. inlet valve EVP-006B open
7. inlet valve EVP-006A closed with 20 seconds delay
8. dryer 80-PK-006A freeze
Notes:
(1) For maintenance activities read the general recommendation and safety precautions according to
Chapter 7.1 of the Instruction Manual of the air dryer CD35.
(2) The inlet valves EVP-006A/B are normally open and controlled by means of solenoid valves EV-006A/B
normally closed - the minimum pressure required to operate the inlet valves is 4 bar.
(3) Refer to AIR DRYER ELECTRICAL SCHEMATIC DIAGRAM
(4) "Freeze" the drying cycle: the dryer won't switch towers stopping purge air flow - no loss of compressed
air. For further detail see the Instruction Book of the air dryer CD35
5.2 CORROSION CONTROL AND MONITORING
No corrosion is expected within the unit, and all vessels and pipework are provided with an appropriate
corrosion allowance.
Areas where corrosion is most likely to occur are in the liquid drains from the vessels, and at low point
drains in the pipework. During annual shutdowns these areas may be visually or ultrasonically
inspected.
_______________________________
6 NORMAL SHUTDOWN
6.1 GENERAL
A normal shutdown is either a scheduled shutdown or one that is carried out in an orderly manner for
reasons other than emergencies or process trips. The extent of the work to be carried out during the
shutdown will dictate whether a full shutdown of all equipment is necessary.
The actions to be taken prior to a shutdown are dependent upon which equipment items are being taken
out of service and the expected duration of the shutdown.
During a shutdown all equipment must be properly isolated.
For shutdowns of duration longer than a few days it is recommended that the equipment be completely
drained and steamed out as required.
A normal shutdown is a scheduled operation and therefore should be carried out in coordination with all
other units, especially as instrument air is vital to the operation of the rest of the plant.
While shutdown procedures are being carried out it is the prime responsibility of those in charge of
operations to ensure that all requirements of SCNL-RSG OCPP safety regulations and standing
operating procedures are adhered to.
The instructions in this chapter form a basis for developing detailed step-by-step "standing operating
procedures" for the shutdown of Unit 80.
6.2 SHUTDOWN OF INDIVIDUAL EQUIPMENT ITEMS
6.2.1 General
Unit 80 is designed such that the whole unit should never need to be shut down, i.e. 100% redundancy
available. Both compressors are designed for 100% rated flow and there are two identical sets of dryers
also designed for 100% rated flow. Therefore Instrument and Plant Air supply should be uninterrupted
and available right through other unit shutdowns.
The instructions contained in the following section are guidelines for the safe and orderly shutdown of
individual items within Unit 80.
6.2.2 Shutdown and Isolation of one Instrument and Plant Air Compressor
Normal shutdown of one of the compressors will occur either for maintenance or for a routine
compressor changeover. The method of shutting down the compressor is the same for both cases and
is outlined below:
Note: Before shutting a compressor down ensure that the other compressor has been brought on-line
and is functioning satisfactorily using the procedure outlined in section 3.1 of Chapter 4 of this manual.
* Ensure the compressor is "UNLOADED" before shutting it down.
* Stop the compressor by pressing the red "COMPRESSOR STOP" button on the local control panel.
* Close the compressor discharge line block valve, isolating the compressor.
* Switch off the voltage.
_______________________________
If maintenance is to be carried out on the compressor then steps must be taken to positively isolate:
Disconnect the compressor from the mains.
Shut off and depressurize the part of the air net which is connected to the outlet valve.
Disconnect the compressor air outlet pipe from the air net.
Drain oil and condensate circuits.
Disconnect the compressor condensate piping from the condensate drain net.
6.2.3 Shutdown and Isolation of one Instrument Air Dryer Package
Normal shutdown of one of the dryer packages will occur either for maintenance reasons, changing the
filters and/or the desiccant, or for a routine dryer package changeover.
The procedure for changing over from one dryer package to the other is outlined in section 1.6 of
Chapter 5 of this manual.
If maintenance is to be carried out on the dryers, filters etc., then steps must be taken to positively
isolate the dryer package from the pressurized system.
_______________________________
7 EMERGENCY SHUTDOWN
7.1 GENERAL
This chapter describes the philosophy and implementation of the safeguarding systems installed on Unit
80.
In the following sections consideration is given to a range of emergency scenarios.
The following procedure provides the basis for the operation of Unit 80 after the failure of utility systems.
_______________________________
8 SAFETY
8.1 GENERAL
This chapter contains information on the safety systems installed on Unit 80 and within the Utility Area,
described by drawing 00-ZB-A-85080 and 50-GB-A-85700, for protection from plant fires and gas leaks.
8.1.1 Fire and Explosion Hazards
Unit 80 is considered a zone non-hazardous.
8.2 LISTING OF SAFETY EQUIPMENT
8.2.1 General
The Utility Area is provided with a range of firefighting equipment which can be used to deal with plant
fire incidents. Refer to section 2.2, below.
Before attempting to tackle a plant fire, of any magnitude, the operators must be aware of the nature of
the fire. It is essential that they are familiar with the capabilities and limitations of any particular piece of
firefighting equipment (e.g. water must not be used on an electrical fire; burning liquid spills should be
tackled with foam, not water).
Operating personnel shall not endanger themselves while attempting to deal with a fire. While small
scale fires can be tackled with hand held extinguishers, major fires should be dealt with from a distance
using deluge systems, firewater monitors and fire hoses.
The Utility Area is provided with a range of safety equipment to protect operating personnel during the
execution of potentially hazardous activities. These activities include: handling the water treatment
chemicals or changing the molecular sieve for air dryers.
The operators should familiarize themselves with the location and the details of operation of all
firefighting and safety equipment.
It is the responsibility of the safety officer to periodically check the firefighting and safety equipment to
ensure that all systems are in full working order. Any items which are noted as being faulty, non-
functional or missing should be immediately reported to the safety officer.
8.2.2 Fire Fighting Equipment
At the Unit 80 Area the following types of firefighting equipment are provided to protect the installed
equipment:
* Fire Hydrant
* Fire Extinguishers
Two different types of fire extinguisher are provided on the Utility Area, namely dry chemical powder,
and CO2. Each of these types is provided as either portable units, (9 kg dry chemical powder, 5 kg
CO2), or as wheeled units (75 kg dry chemical powder, 2 x 9 kg CO2 shelters).
_______________________________
_______________________________
_______________________________
_______________________________
_______________________________
_______________________________
_______________________________
_______________________________
_______________________________
9.1 DATASHEETS
_______________________________
10 DRAWINGS
Enclosed in this section is the following Fire and Gas Detection Layout Drawing:
00-ZB-A-85020
10.6 VENDOR INFORMATION
_______________________________
1.1 GENERAL
40-S-002
Working volume 13 m³
40-S-001
Working volume 166.55 m³
40-S-003
Working volume 8.14 m³
40-P-003
Rated flow 20 m³/h
Head at rated capacity 10 m
BHP 1 kW
Here below are reported the most significant data for the aim of this duty specification:
· Maximum ambient humidity: 83%
· Ambient temperature: min/ norm/ max 13/31/41 °C
· Maximum wind speed: 137 Km/h
· Maximum rainfall: 88 mm/h
.
_______________________________
1.4 MATERIALS
_______________________________
_______________________________
Two Service Water hose connections for discontinuous cleaning operations of the Sanitary Water Pit.
The following Utilities and interfaces must be available for a proper operation of the Trafo Oil Drainage
System:
· Electric power for discontinuous maintenance operations.
· Service water hose for sumps maintenance operations.
.
_______________________________
2 PROCESS DESCRIPTION
_______________________________
_______________________________
3.1 GENERAL
Prior to initial startup, all pre-commissioning activities must have been completed and the unit must be
ready for operation.
Pre-commissioning covers those activities required to bring the unit to a "ready for startup" condition
following construction. In general, it consists of inspection, checking and testing operations required to
ensure that all components of the unit are properly installed and mechanically complete. The most
important requirement is that the unit can be started up in a controlled, efficient and safe manner.
This pre-commissioning phase is usually performed by the construction forces in close co-ordination
with the operations/commissioning team.
For this purpose, checking sheets (or "mechanical guides") will be issued and filled out on site in close
co-operation between construction and the commissioning team.
Full details of pre-commissioning activities with regard to inspection of equipment items, general checks,
hydrostatic testing, instrumentation functional testing, electrical motor run-in, line and vessel cleaning,
etc., are outside the scope of this document.
The information and procedures described hereafter concern the preliminary operations for the first
startup of a new unit. Procedures are slightly adapted for normal and subsequent start up.
3.2 PREPARATION PRIOR TO INITIAL OPERATION
It is assumed that all the pre-commissioning activities are completed and that the unit has reached a
"ready for startup" status.
Most of the following pre-start up items are routine and are briefly presented as reminders only, as they
refer to pre-commissioning activities.
Ensure that the following requirements are satisfied:
¨ All safety equipment is in place and is fully operable.
¨ All pipe work has been pressure tested and cleaned.
¨ All equipment has been pressure tested, inspected, cleaned, drained and dried.
¨ All equipment is at ambient conditions.
¨ Electrical power systems have been checked out and commissioned. It is available to all electric drivers
and all instrument boards.
¨ All rotating equipment and their associated drivers have been aligned, run in and lubricated, as required,
following the manufacturers' recommended procedures.
¨ All instruments have been calibrated, loops checked and commissioned.
¨ All the DCS data links are operational.
¨ All utilities have been commissioned, lined up and are ready for use at the unit battery limit.
It is the prime responsibility of those in charge of the plant to ensure that all operations are carried out
satisfactorily.
_______________________________
· Start using water inside Control Room Toilet/ Shower. Check the arrival point N1 at the sanitary pit for
any possible blockage.
· Start building the level. For faster action, open the 1” valves used for flushing-fluidizing the pit bottom
solids.
· Check if alarms HLL and HHLL are activated and close 1” valves.
· Connect a hose and start to empty the sanitary pit using a vacuum truck.
· Check if alarms HHLL and HLL are cleared in control room.
At this stage, commissioning of Sanitary Sewer System can be considered completed.
3.4 TRM SUMP MANUAL SLUICE 40-SL-001
The gate sealing capacity should be checked prior commissioning of Trafo oil drainage system.
· Lower the gate to its fully closed position.
· Start building the level inside potentially oil water pit by using a hose connection from a water truck or
from the hydrant or from the service water system.
· Leakage allowed is 0.2 liters/sec/m.
If this requirement is fulfilled, proceed to the next step of commissioning operation.
3.5 TRAFO OIL DRAINAGE SYSTEM COMMISSIONING AND START UP
It is a good opportunity to correlate commissioning of Trafo oil drainage system with commissioning of
deluge system.
In this case the performance for deluge system can be monitored and in the same time this amount of
water will be used to build up the level inside the pit.
Check for any blockage at 12” pipes for sump 40-S-003 to sump 40-S-001.
After the LL level at 40-S-001 pit is cleared, observe the normal functionality for local level indication.
In this moment TRM Sump Pump 40-P-003 is ready for start up.
3.6 COMMISSIONING OF TRM SUMP PUMP 40-P-003
_______________________________
4 EMERGENCY SHUTDOWN
4.1 GENERAL
This chapter describes the philosophy and implementation of the safeguarding systems installed on Unit
40.
In the following sections consideration is given to a range of emergency scenarios.
4.1.1 Safety Interlock System Philosophy
There is no interlock system implemented.
4.2 UTILITIES FAILURE
The following procedure provides the basis for the operation of Unit 40 after the failure of utility systems.
4.2.1 Electrical Power Failure
There is no special measure to be taken in order to mitigate potential problems associated with partial
power failure.
4.2.2 Service and potable water
There is no special measure to be taken.
_______________________________
5 SAFETY
5.1 GENERAL
_______________________________
6.1 DATASHEETS
_______________________________
7 DRAWINGS
_______________________________
1.1 General
1.1.1 Scope
Present document represents the duty specification of Natural Gas fuel supply system for the new
Power Station to be realized in River State (Nigeria).
The Metering and reduction station will be installed to feed an Open Cycle Power Plant based on the
following main equipments:
· Gas Turbine Generator with its auxiliaries
· Balance of Plant
1.1.2 Integration of Unit 70 in the Overall Plant
The System will consist of the main sections listed here below, with piping, valves and all necessary
equipment for fuel conditioning before feeding the Natural Gas to the Gas Turbine fuel supply system:
· Gas heating section: Heating the gas, as required, to comply with the gas turbine superheat requirement
to preclude the deposition of hydrates in the pressure reducing valves (PRV).
Heating the fuel gas also insures that the gas turbine DLN combustion system will operate properly.
· Gas filtration section: Filtering the customer supplied fuel gas of entrained particulate matter that would
be deleterious to the satisfactory operation of the gas turbine.
· Gas flow measurement section: Metering Station
· Gas flow/pressure/temperature control section: Reduction Station to keep pressure at GT fuel supply
terminal point within the specified range.
This is a brief description of the design and operating guidelines for the aforementioned subsystems
performed to bring the fuel gas into compliance with GT manufacturer requirements at GT fuel gas
conditioning skid inlet battery limit.
As far as applicable to the subject of the present specification the following equipments are the typical
components of the fuel gas supply system, object of the present document:
· Filter Separators
· Fuel Gas Heaters
· Automatic Fuel Gas Shutoff Valve
· Pressure Reducing Valve (PRV) Stations
· Pressure Relief valves
· Automatic Fuel Gas Vent / Depressurizing valve
_______________________________
_______________________________
The Power plant Gas turbine and associated auxiliaries will be fed by Natural Gas, coming from the pipe
line by means of a flanged inlet header
(INLET SKID 70-ME-004).
Natural gas heating before pressure reducing shall be provided in order to compensate the temperature
drop associated to pressure reduction avoiding the dropping below the dew point of the gas and keeping
the gas temperature within the limits given by the gas turbine manufacturer (no hydrates and liquids
formation): this system shall ensure the minimum temperature of Gas Turbine fuel conditioning skid
battery limits for a stable operation of the GT combustors. However, the gas temperature shall be at
least kept so that no water shall condense from the atmosphere on the external surfaces of the gas line.
After the heating section, Natural Gas will be filtrated in order to separate the solid contaminants.
After filtration, natural gas is routed to the fiscal flow measurement section.
The gas chromatograph (GC) and auxiliaries will be installed downstream the metering section on a
suitable rack (Analyzer cabinet), properly designed and located close to the gas metering skid. The gas
chromatograph shall be specially designed for natural gas composition measurement and heating
value determination, and will consist of the following units as a package in the cabinet:
· Sampling system
· Analyzing unit
· Data converter
The HC Dew Point Analyzer and auxiliaries will be installed at the outlet of the station on a suitable rack
(Analyzer cabinet), properly designed and located close to the outlet skid.
Natural gas Pressure shall be reduced from pipe line pressure up to values suitable for GT feeding.
The gas turbine is equipped with automatic block and bleeds fast acting valves (supplied by GT
manufacturer) for stopping and depressurizing the downstream fuel supply piping up to combustors.
The Natural gas measuring and reduction station is mainly operated by system of automatic valves for
continuous operation and main process parameters are mounted by logical implemented in the control
system: operator action is required only to change the normal operation status or in case of abnormal
conditions which could cause trip activation or shutdown of the equipment.
_______________________________
1.4 UTILITIES
_______________________________
2 PROCESS DESCRIPTION
_______________________________
Burners of WBH will be fed by gas extracted from main run pipe downstream of the WBH and upstream
of the filtering and metering station by means of two (2) dedicated pressure filtering/reducing/metering
units (Fuel gas skid 70-ME-003 A/B).
Gas to burners shall be measured by an electronic volume conversion device
(FT, TT, PT), tagged 70-FQI-510.
During Start-Up, Natural Gas needs to be preheated by a dedicated electric startup heater (70-EH-
001), ON/OFF type complete with bypass line in order to guarantee fuel gas preheating during turbine
start-up and normal operation. During normal operative condition, the electrical heater is switched off,
so the supplier shall provide an heating system of fuel gas with tubing inside the hot water bath.
BMS shall carry out the gas temperature control by means of a temperature set point from Control
System that shall implement an algorithm (included in scope of supply) with temperature signals
coming from 3 Temperature Transmitters (2oo3 logic).
These transmitters shall be provided as loose items including thermowell and thermoelement and
complete with the equipment for piping connections (i.e. flange, nozzle and weldolet) at the outlet of the
gas reduction station for temperature control loop.
2.2 NATURAL GAS FILTRATION AND FLOW MEASUREMENT
After the heating section, Natural Gas will be filtrated in order to separate the solid contaminants.
Filtration will be achieved by means Nr. 2 Fiberglass Filtering units (one main and one stand by) 70-
MS-002 A/B, (2 parallel lines each designed for 100% of flow rate), skid mounted, with all required
piping, valves, instrumentation, metallic construction and fittings as required; plugging and/or fouling of
the running filter will be monitored by differential pressure measuring indicating instruments with
remote transmission of signal of high ΔP for alarming in Gas station control system.
2.2.1 Gas Filter Separators (70-MS-002 A/B)
Nr of units: 2 (1+1)
Capacity: 9.8 Kg /s
Design Press: 60 bar (g)
Design Temp: -10/+80°C
Filtration degree: 98% of solid particles larger ≥ 5 μm
100% of solid particles larger ≥ 10 μm
95% in weight of entrained liquid droplets
Clogging level of filters will be monitored by means of differential pressure indication both locally and
remotely, and a high ΔP alarm will be transmitted remotely.
Filters pressure drop shall not exceed 0.25 bar when new and clean at the design flow at minimum
inlet pressure.
Liquid hold up capacity shall not be less of 12 % of total gross volume of filter shell, liquid accumulation
shall not affect the gas passing part in order to avoid liquid entrainment.
_______________________________
_______________________________
Gas chromatograph will be interfaced via serial link RS 485 (Modbus protocol) with the metering
computers that provide its power supply.
The controller will have a built-in self-diagnostics with means of indicating and recording malfunction of
analyzer hardware and software to send to Control system in the control room. A HDM device (part of
GC) shall be fitted in the flow computer cabinet (70-MP-00).
2.2.4 Analysis unit: HC Dew Point Analyzer 70-AT-519
The HC Dew Point Analyzer and auxiliaries will be installed at the outlet of the station on a suitable
rack (Analyzer cabinet), properly designed and located close to the outlet skid.
The system will be fed by the metering computers and it will be directly interfaced via HW link to Control
System.
2.3 NATURAL GAS PRESSURE REDUCTION
Natural gas Pressure shall be reduced from pipe line pressure up to values suitable for GT feeding.
2.3.1 Pressure Reduction skid (70-ME-002 A/B)
The pressure reducing section consist of N°2 reducing lines, designed for total flow rate (100%), one in
working condition and the other in stand-by status. Each pressure reducing line consists mainly of two
pilot operated pressure reducing valve top-entry design; one is the main regulator and the other is used
as a monitor/slam shut valve. The operation of these both valves is fully pneumatic; internal high
pressure feed allows the operation of the pneumatic actuator, while the pressure signal coming from
downstream regulates the open position of the valve’s stem.
Each line shall be equipped with:
· One (1) pressure control valve.
· One (1) monitor control valve.
· One (1) fast acting slam shut off valve (built-in the same body of monitor regulator)
· Temperature transmitter for remote control with high / low natural gas temperature alarms.
· Pressure relief valve downstream the PRV sized in order to vent the gas leaking with control valve
closed.
· Piping, valves and fittings as required.
Each pressure reduction line of the main reducing stations, both main section and start-up section, is
equipped with one fast acting SLAM SHUT OFF VALVE (with limits switches) for isolation in case of
overpressure caused by gas leaking through the pressure reducing valves.
Main control valves will have the following features:
· body /trim material: see piping class, referring to P&ID.
· with limits switches.
· “Fail to open” piloted.
· embedded silencer.
· Monitor valves will have the following features:
· body /trim material: see piping class, referring to P&ID.
· “Fail to close” piloted.
· embedded silencer.
· limit switch for active monitor.
_______________________________
The active regulator normally assures pressure reduction to the setting value. To assure gas supply
continuity in case of failure of the active regulator a second regulator (the monitor regulator) is installed
in series with, and upstream of the active regulator. The monitor regulator is normally wide open as it is
set to regulate to a higher pressure. In the event of an accidental increase of outlet pressure (indicating
failure of the active regulator) the monitor regulator will take over as the main control valve.
During the normal operation, depending from the services one line is working while the other line is in
stand-by. Only in case of a failure of the monitor and main regulator of the operative line, the standby
line will be actives manual switch.
A self-operated overpressure shut off device (slam-shut) operates in the event the outlet pressure
exceeds acceptable a safe value and protects the equipment downstream of the pressure regulators
from over-pressure. The slam-shut devices acts on the pressure regulators and cause them to close
rapidly.
To minimize accidental intervention of the slam-shut device, a peak shaving pilot- operated pop
acting relief valve is installed on the outlet header of the station. This valve is designed to release
relatively small quantities of gas only.
Both pressure reducing lines is supplied with relevant blind disk to prevent any dangerous situation
during maintenance operation of the line.
Pressure setting of each pressure control valve is made in order to assure the operative range of
pressure for function of the gas turbine, according to pressure operative range requested by turbine
supplier.
Equipment has been positioned in order to withstand to fuel consumption as per attached GT load
curves:
· HTCT 682 273 Rev - Start on fuel gas with purging;
· HTCT 682 275 Rev - DE loading and shutdown fuel gas.
Note: typical reference curve, to be used for equipment design. HRSG purging is not applicable.
2.4 CONTROL PHILOSOPHY AND OPERATIONS DESCRIPTION
_______________________________
manipulate two or more final control elements, e.g. a split range control scheme, provision shall be
made that in manual mode the Operator can manipulate each final control element independently of the
others.
2.4.2 70-M-001A/B Burner installed in 70-E-001A/B Water Bath Heater
Natural gas temperature control at unit outlet is achieved controlling the water bath heaters 70-E-
001A/B (liquid bath) temperature. Control is achieved with two cascade controllers, controller TICA-521
(master) implemented within the control system regulating gas temperature at unit outlet and TICA-503
(slave) controlling the liquid bath temperature. Measured control variable is the gas temperature
downstream the pressure regulator section, set point temperature of outlet gas is adjusted by operator.
2.4.2.1 Gas Outlet Temperature
Gas outlet temperature is controlled by a master/slave control loop.
Process variable, gas temperature downstream the regulator section is measured prior entering gas
turbine section by three temperature elements. The temperatures measured are then processed by 2
out of 3 average logic by reverse acting PID controller TICA-521, the difference between the Operator
set point and the measured temperature produce a signal (4-20mA) to slave TICA-503.
2.4.2.2 Water bath heater liquid temperature
Water bath heat liquid temperature is controlled by a reverse acting controller TICA-503. TICA-503
controls the bath temperature measured by TT-503 modulating burner power through the servomotor
TY-503. Servomotor TY-503 is mechanically linked with the fuel burner main feed line control
valve TCV-503 and feed air control valve TCV-552 in order to maintain the correct air/fuel ratio while
regulating the burner power. TICA-503 controller set- point is a signal coming from TICA-521 (master)
implemented within the control system, setting the temperature set point as shown in figure 4.3.
Servomotor TY-503 is provided with two limit switches ZSL-503 and ZSH-503 in order to allow BMS to
check the functioning. 70-E-001 Water Bath Heaters are also provided with a safety temperature
switch TSHH-554 shutting off the burner when the temperature of 92°C is reached in the liquid bath.
2.4.3 70-EH-001- Gas Electric Start-up Heater
In order to feed the 70-E-001A/B Water Bath Heaters Burners a gas slipstream is taken downstream the
heating section to compensate the temperature drops caused by the Joule-Thomson effects in the 70-
ME-003A/B natural gas to heaters reducing skid pressure regulators. This condition cannot be satisfied
at start-up where condensates can occurs with the gas stream and heating can’t be achieved because
water bath heaters are not in operation. An electrical heater 70-EH-001 is provided to guarantee smooth
operation when heating up the liquid bath protecting the downstream section. Heater control is designed
to be in hot stand-by thus without needs of any operator intervention. Electric power is supplied to the
heater with an ON/OFF control implemented within the control system. The heater emergency shut
down logic based on high temperature set has been implemented in the ESD.
_______________________________
_______________________________
3.1 GENERAL
Prior to initial start-up, all pre-commissioning activities must have been completed and the unit must be
ready for operation.
Pre-commissioning covers those activities required to bring the unit to a "ready for start-up" condition
from the original as-constructed condition. In general, it consists of inspection, checking & testing
operations required to ensure that all components of the work are properly installed and are
mechanically complete. The most important requirement is that the unit can be started up in a
controlled, efficient and safe manner.
The pre-commissioning phase is usually performed by the construction forces in close coordination with
operations / commissioning team. For this purpose, checking sheets (or "mechanical guides") will be
issued and filled up on-site in close cooperation between construction and commissioning team.
A summary of pre-commissioning activities and a checklist to be completed before unit initial start-up
are included in section 2 of this chapter. Full details of pre-commissioning activities as regards to
inspection of equipment, general plant check, hydrostatic testing, instrument loop checks,
instrumentation functional tests, electrical motor run-in, line and vessel cleaning etc., are not in the
scope of this document and are a separate issue.
The information and procedures described hereafter concern the preliminary operations for start-up of a
new unit. Procedures are slightly adapted for normal and subsequent start-up, as indicated in chapter-4.
3.2 PREPARATION PRIOR TO INITIAL STARTUP
It is assumed that all the pre-commissioning activities are completed and that the unit has reached a
"ready for commissioning" status.
Most of the following prestart up items are routine and are briefly presented as reminders only, as they
refer to pre-commissioning activities.
Ensure that the following requirements are satisfied:
All firefighting equipment is in place, operational and has been functionally tested.
All safety equipment is in place and is fully operable.
All pipework has undergone pressure testing, cleaning and/or flushing and draining and drying.
· All equipment has been pressure tested, inspected, cleaned, drained and dried.
· The whole unit was satisfactorily air leak tested at the maximum available dry instrument air pressure.
The unit is under slight nitrogen pressure and the procedures detailed hereafter start from this step, to
be performed as part of commissioning and start up.
· Test equipment and special tools, if any, and facilities for their operation are available.
· Air blowers for the water bath heaters have been aligned, run in and lubricated as required, following the
manufacturer’s recommended procedures.
· Instrument air is available and commissioned to all instruments.
· Service and potable water is available at battery limit.
_______________________________
· Electrical power systems have been checked out and commissioned. It is available to electric drivers,
startup heater and all instrument boards.
· All instruments have been calibrated, loops checked and commissioned. All sensing elements which
were removed from pipework prior to hydro testing have been reinstalled.
· All the DCS data links are operational.
· Emergency shutdown systems are fully operational and if possible, a dry run has been performed.
· All safety relief valves have been tested and are in service. All block valves around relief valves are
locked in the correct position.
· All blinds, if any, which were installed during hydro testing have been removed and replaced with their
relevant spacers.
3.3 STARTUP METHODS
The system may be started up using two methods. In this section, both methods will be detailed, and the
criteria for selection of startup route will be explained.
The procedures described in this manual should be taken only as an operating guide and subject to
further development at site.
Refer to P&ID 70-SD-A-53301 sheet 1-4 and Alstom HTCT 124566 Fuel Gas Supply
Fuel gas coming from underground pipeline is available at @ 60 bar (g) at battery limit.
3.3.1 Unit 70 startup – System by System
This method will describe nitrogen displacement, pressurization and tightness test for each individual
system.
3.3.1.1 Inlet Skid 70-ME_004
Proceed as follows:
· Ensure all manual block valves and UV-501 is in close position.
· All the drains, vents, sample and nitrogen injection points are isolated.
· All instrumentation is lined up except PDIT 501.
· Start opening V-04 the battery limit inlet valve.
· If no leakage is observed, start opening 1” pressurization valves V-06/07.
· If no leakage is observed, start opening 6” valve V-05 and 1” pressurization valves V-08/09. Check if the
correct indications are shown for PI 601, PT 502, TT 501, TI 601, TI 602A/B and PI 602A/B.
· Line up PDIT 501 and if no alarm at CS, open UV 501.
· Close back the 1” pressurization valves V-06/07 and V-08/09.
_______________________________
Proceed as follows:
· Ensure all manual block valves are in close position.
· All the drains and vents are isolated.
· 1” by-pass valves for PSV 603 A/B are closed.
· All instrumentation is lined up.
· Start opening 1” pressurization valves V-13/14 and proceed for tightness test of FWB Heater 70-E-001A
fuel gas line. If no leakage observed proceed to open the main isolation valve V-10 and close 1” valves
V-13/14.
· Start opening 1” pressurization valves V-15/16 and proceed for tightness test of FWB Heater 70-E-001B
fuel gas line. If no leakage observed proceed to open the main isolation valve V-11 and close 1” valves
V-15/16.
· Check correct indication for TI 603A/B and TT 502A/B.
· Start opening 1” pressurization valves V-17/18 and check for leakage. When pressurization is
completed, start to open main isolation valves V-22 and V-23 and close 1” pressurization valves V-
17/18.
In order to start-up the unit, the Water Bath Heaters 70-E-001A/B must be filled with water using
provided manual ball valve for make-up water located at the top of the expansion tank. Operator must
begin to fill the vessel up to the normal liquid level pointed out in the level gauge LG-602. Proceed as
follows:
· Open the manual ball valve upstream the make-up water supply line, then open the
globe valve located aside the expansion tank; water will begin to fill the vessel.
· Proceed after a short time to open the drain valve at nozzle N5 to discharge the water from the
vessels in order to leave the vessel cleaned and free from dirty and rust/metal scales. When
the water going out from the drain valve look clean close the drain valve.
· Monitor the vessel filling using LG-602 level gauge, proceed to fill the vessel up to normal operating
liquid level half of the expansion tank (it can take time).
· Close the manual globe valve when the liquid level reaches the normal operating low level.
· Check the correct indication for TI-604, TT-503, LT501 and if LALL-502 is cleared.
_______________________________
Proceed as follows:
· Ensure all manual block valves are in close position.
· All the drains are isolated.
· 1” by-pass valves for PSV 608 A/B and PSV 609 A/B are closed.
· All instrumentation is lined up.
· Start opening 1” inlet valve V-19 and pressurize Start Up Electric Heater
70-EH-001. If no leakage observed proceed to open outlet isolation valve V-20.
· Crack open UV-53 inlet valve to dust filter 70-MS-003A and check for leakage and also check the
pressure downstream PCV 508A. If necessary adjust the pressure set point according to the
specification. Open fully V-56 and V-53.
· Crack open V-54 inlet valve to dust filter 70-MS-003B and check for leakage and also check the
pressure downstream PCV 508B. If necessary adjust the pressure set point according to the
specification. Open fully V-57 and V-54.
· Crack open V-58 and check the pressure downstream PCV 509A. If necessary adjust the pressure set
point according to the specification. Open fully V-58 and V-60.
· Crack open V-59 and check the pressure downstream PCV 509B. If necessary adjust the pressure set
point according to the specification. Close V-54, V-57 and V-59 and maintain only stream A on line.
· Open V-62 upstream manual valve to FQI 510 and if no leakage open downstream valve V-63.
· Open V-65, V-66, V-67 and V-68 and fuel gas is available up to pilot and burner lines.
At this stage, the fuel gas system may be considered ready for normal operations.
In any case, it will be necessary to vent all downstream fuel gas lines to consumers before a consistent
nitrogen-free fuel supply can be achieved.
· Ensure that 70-EH-001 is energized and the on/off control loop is operative.
· Push the main line heater e.g. 70-EH-001A Water Bath Heater start pushbutton
HS-504A1 from control room or HS-504A3 in the field local panel.
· The BMS will begin the ignition sequence lighting the burner.
· Wait until the liquid bath temperature is 85°C using TIC-503, the burner will stop automatically.
_______________________________
_______________________________
_______________________________
_______________________________
_______________________________
4.1 General
During the course of normal operations, it will be necessary to start up the plant after shutting down for
various reasons. After each maintenance turnaround, for example, the fuel gas systems will have to be
brought on line. The fuel gas system will also have to be restarted after a shutdown if the cause is a
mechanical/utilities malfunction.
The following normal startup sequence is recommended, although the judgment and experience of the
operators should be used to adapt these steps, if necessary, to suit the cause of the shutdown and
hence the prevailing startup conditions. It is at all times the responsibility of the shift supervisor to
ensure that the method used for startup is safe and efficient.
4.2 PRE STARTUP CONDITIONS
The exact condition of the system at startup will depend upon the nature of the shutdown of the system.
For the purposes of this manual, the following conditions have been assumed:
· The plant is mechanically complete.
· The natural gas system is oxygen free and under a slight positive fuel gas pressure.
· All the utilities/process lines outside the battery limit of the unit are fully commissioned and ready for
service:
· Natural gas lines upstream and downstream the package
· Water line header
· Utilities supply
· All other valves are in their normal operating positions.
· All temporary items installed in the system for shut-down reasons, i.e. temporary spectacle blinds, have
been removed.
4.3 START UP OF INDIVIDUAL EQUIPMENT ITEMS
_______________________________
_______________________________
70-MS-003A/B Filters are been installed in order to avoid dust coming inside the burner pressure
reducing fuel gas ramp that could interfere with the regulators operation.
Two spare identical lines have been provided for the 70-ME-003AB skid, one spare and the other in
standby, in order to allow maintenance and cartridges changeover without stopping the unit.
The need of cartridge changeover is matter of Operator choice and has to be done
periodically. It is difficult to foreseen the frequency of the filters change over, since it will depend on
many factors such as presence of solid particulate, hydrocarbons decomposition phenomena and so on.
It is recommended to record each change-over date so that the frequency of changeover can be
monitored for any problem detection.
Proceed as follows:
Switchover the line where maintenance have to be made to the spare one using manual isolation
valves. More precisely:
· Close both the spare line filter inlet and outlet isolation valve.
· Proceed to purge for a few minutes venting from the PSV-609 bypass line admitting a slipstream of gas
cracking opening the inlet isolation valve
· Close the PSV bypass vent line.
· Pressurize the skid to upstream pressure using inlet manual valve.
· Check in PI-608 and PI-609 that the required gas pressure is reached after the two regulators, more
precisely 5 bar (g) and 0.3 bar (g).
· Proceed to open the outlet isolation valve.
· Now both the filter skid are online
When the spare filter is online proceed to stop the main Filter.
4.4 STARTUP OF ENTIRE UNIT 70
The startup of Unit 70 will normally happen only after the entire plant was in shut down or major
overhaul was completed.
4.4.1 After major overhaul
Unit 70 will be restarted exactly as per chapter 3.3.2.
4.4.2 After pressing 70-HS-501 pushbutton
Unit 70 remains partially pressurized.
To restart the unit proceeds to close the main inlet valve V-05 at the Inlet Skid.
When PDIT-501 is at normal value, start opening the shutdown valve UV-501.
Start opening gradually the main valve V-05 till the pressure inside the system became normal.
Restart WBH if necessary.
4.4.3 After pressing 70-HS-600 pushbutton
Unit 70 will be restarted exactly as per chapter 3.3.2.
_______________________________
5 NORMAL OPERATION
5.1 GENERAL
The purpose of this section is to discuss the operation of the Natural Gas Metering and Reducing
Station. This will include the process variables which can affect the performances, the manual actions
which shall be done for a correct operation of the unit and the abnormal conditions which can occur
causing trip activation or even the complete shutdown of the Natural Gas Metering and Reducing
Station.
5.2 NORMAL OPERATION
Unit should be stable and does not need special advices however are suggested to monitor periodically
the gas supply condition in order to try to prevent any possible trip cause. Any possible upset is
monitored and alarmed to the operator in control room. Spare Train B guarantees the possibility of
continuous operation and allows easy maintenance operation on the Train A.
5.2.1 Manual Operations
_______________________________
Safe operation of the unit is managed by the Emergency Shutdown System of the unit (ESD).
Emergencies which occur into Natural Gas Metering and Reducing Station require immediate attention
and investigation to understand and act on the problem. Operator should carefully study in advance and
become familiar with the proper actions to be taken in such situations.
Automatic actions taken on emergency shutdown should protect the equipment from all dangerous
situations.
The overall protective system shall be based on the input (causes) and the output (effects) as
shown on relevant Cause & Effects Diagrams.
The water bath heater included into the Natural Gas Metering and Reducing Station shall be powered
off, and shut-down both locally in field and from GSCS by means of dedicated front panel push buttons
installed on the relevant BMS’s.
_______________________________
Here below the list of set point values for 0-100% controllers:
Tag No. Service Description Set By Unit
70-E-001-A/B Water Bath Heater TICA-521
TICA-503-A/B °C
Liquid Bath Temperature
Natural Gas Temperature Adjustable by the
TICA-521 °C
Downstream Outlet Skid 70-ME-005 operator
_______________________________
Here below the list of process alarms available on the operator station .
Low High
Tag No Service Description Low High Unit Trip
Low High
Pressure Upstream 70-ME-002 Reducing
PIT-515 - 40 60 - Bar(g) NO
Section
Pressure Downstream 70-ME-002 Reducing
PIT-518 A - - 30 - Bar(g) NO
Section PCV-517A
Temperature Downstream 70-ME-002 Reducing
TIT-518 A - - 70 - °C NO
Section PCV-517A
Pressure Downstream 70-ME-002 Reducing Bar
PIT-518 B - - 30 - NO
Section PCV-517B (g)
Temperature Downstream 70-ME-002 Reducing
TIT-518 B - - 70 - °C NO
Section PCV-517B
AT-519 Natural Gas Hydrocarbon Dew Point Temp. - - 30 - °C NO
TT-521-
Temp. Downstream 70-ME-005 Outlet Skid - 40 70 - °C NO
A/B/C 2over3
Liquid Bath Temperature Inside Water Bath
TSHH-554A - - - 92 °C YES
Heater 70-E-001A
Liquid Bath Temperature Inside Water Bath
TSHH-554B - - - 92 °C YES
Heater 70-E-001B
Liquid Bath Temperature Inside Water Bath
TT-503-A - 55 85 - °C NO
Heater 70-E-001A
Liquid Bath Temperature Inside Water Bath
TT-503-B - 55 85 - °C NO
Heater 70-E-001B
PdIT Pressure drop across ESD valve UV-501 - - 500 - Mbar NO
PT-502 Natural gas pressure at station inlet - 40 60 - Bar NO
TT-501 Natural gas temperature at station inlet - 0 40 - °C NO
TT-502A Natural gas temperature at WBH outlet - - 72 80 °C YES
TT-502A Natural gas temperature at WBH outlet - - 72 80 °C YES
TSHH-505 Startup electric heater element temperature - - - 380 °C YES
TSHH-505 Startup electric heater element temperature - - 360 - °C NO
Natural gas Temp. at startup electric heater
TT-507 - - - 80 °C YES
outlet
Natural gas temperature at startup electric
TT-506 - - 72 - °C NO
heater outlet
LSLL-502A Liquid level in WBH expansion tank - - - 20 % YES
LSLL-502B Liquid level in WBH expansion tank - - - 20 % YES
PdIT-512A Pressure drop across dust filters cartridges - - 500 - mbar NO
PdIT-512B Pressure drop across dust filters cartridges - - 500 - mbar NO
LSH-511A Liquid level inside dust filter cartridge bucket - - 100 - % YES
LSH-511A Liquid level inside dust filter cartridge bucket - - 100 - % YES
_______________________________
PCV-517A Pressure reduction section Line “A” Main Pressure Regulator 23.5 Bar g
PCV-517B Pressure reduction section Line “B” Main Pressure Regulator 23.5 Bar g
PCV-516A Pressure reduction section Line “A” Monitor Pressure Regulator 24.5 Bar g
PCV-516-B Pressure reduction section Line “B” Monitor Pressure Regulator 24.5 Bar g
_______________________________
6 NORMAL SHUTDOWN
6.1 GENERAL
This section is a guide to be followed during a shut-down of the unit which has been planned for
equipment inspection and maintenance.
Before initiating any planned shut-down, review all records to determine what inspections and repair
work must be accomplished during the shut-down. Prepare a shut-down schedule including plans for
maintenance activities in advance.
Co-ordinate the shutdown with the Operators of other units that could be affected by the shutdown.
Notify all interested parties in advance of the scheduled shut-down so that the shutdown can be well
planned so that its duration minimized.
When shutting down, steps should be taken to ensure the continued availability of utilities and purge
gases for as long as required.
The preparation of the equipment for maintenance is under plant Operators responsibility.
To guarantee safe operations, all the equipment and lines must be purged to safe location. When
purging operation of the unit has been completed, blind disks are to be installed on gaseous
hydrocarbons lines or at battery limit in order to isolate the Natural Gas Metering and Reducing Station
from the other units.
It is necessary to prepare a list of the blind disk installed, with the indication of their position. The blind
disc list will be continuously updated, under the responsibility of the Chief Operator.
All the work permits are to be signed by the Chief Operator, who will in verify advance that:
· All vessels interested to the maintenance operations are hydrocarbons free and are at
atmospheric pressure.
· All the connection are closed or blinded.
· All hot permits are already approved and duly signed by the competent authority.
Each equipment shall be completely purged with nitrogen prior to start-up, before and after equipment
maintenance to prevent dangerous hydrocarbon/air mixtures.
If maintenance to the regeneration system is carried out with the system on-line, then additional care is
required to ensure isolation from the live systems. Isolation procedures for safe maintenance are under
Operator responsibility.
During planned long term shutdown or off line periods, the unit should always be maintained at low
pressure – preferably with nitrogen - to prevent ingress of air.
The procedure for shutdown assumes that the plant is operating normally, no trips are activated, all
controllers are stable and all manual valves are positioned as per relevant P&ID.
Natural gas metering and reduction station does not need any special precaution for a normal
shutdown.
_______________________________
Gas heating section it is based on two (2) Natural gas water bath heaters design (n° 2 parallel lines
each designed for 100% of flow rate and 100% of the requested duty) and installed immediately
downstream of the inlet skid.
In order to shut down a unit, make sure that the stand-by one (WBH-001B) is running normally in
parallel with main one (WBH-001A).
Operator can turn off the water bath heater A using dedicated pushbutton HS-504A4 in field or HS-
504A2 in control room
· Close V-65 and V-67 fuel gas valves to pilot and main burner.
Maintain natural gas circulation through both water bath heaters until the water temperature TT-503A
goes below low alarm limit.
Proceed to isolate the natural gas circulation through heater A:
· Start closing main inlet valve V-10. This operation should be done very carefully to avoid any variation
on the fuel gas pressure/ flow downstream this unit.
· Close the outlet valve
The unit is now shutdown.
Depending on type of maintenance activities to be done the system can be
de-energized, depressurized, drained and isolated by spades.
Two spare skids have been provided for the station, one spare and the other in standby in order to allow
maintenance and cartridges changeover without stopping the unit.
The need of cartridge changeover is suggested by the high pressure drop across the filter in operation
as per PDIT-512 differential pressure indication (500 mbar should be considered as clogging warning
pressure drop).
When the spare filter is online proceed to stop the main Filter.
· Proceed to close the clogged filter 6” inlet and outlet manual valves.
· Vent the filter down to the atmospheric pressure using PSV 611 bypass vent line.
· After checking that the filter is depressurized to atmospheric pressure using local pressure gauge PI-
611, proceed to turn the spectacle blind on the vessel nozzle N1, N2 lines in order to positively isolate
the vessel from other pressure sources.
· Drain the filter.
· Once drained, open quick opening flanged head and proceed to replace the cartridges.
· Once the cartridges have been replaced, close the filter.
_______________________________
70-MS-003A/B Filters are been installed in order to avoid dust coming inside the burner pressure
reducing fuel gas ramp that could interfere with the regulators operation.
Two spare identical lines have been provided for the 70-ME-003AB skid, one spare and the other in
standby, in order to allow maintenance and cartridges changeover without stopping the unit.
The need of cartridge changeover is matter of Operator choice and has to be done
periodically. It is difficult to foreseen the frequency of the filters change over, since it will depend on
many factors such as presence of solid particulate, hydrocarbons decomposition phenomena and so on.
It is recommended to record each change-over date so that the frequency of changeover can be
monitored for any problem detection.
When the spare filter is online proceed to stop the main Filter.
· Proceed to close the clogged filter 1” inlet and outlet manual valves.
· Vent the filter to the atmosphere down to the atmospheric pressure using 1” by-pass valve for PSV
608A/B and also filter drain.
· Once drained, open the flanged head and proceed to replace the cartridge.
· Once the cartridges have been replaced, close the filter.
6.3 UNIT SHUTDOWN
The total shutdown of Unit 70 will normally only happen during planned maintenance outages, when the
entire plant is shut down.
6.3.1 Unit Depressurization
Unit depressurization can be achieved manually only after isolating the system upstream using the
dedicated isolation valve UV-501 provided with pushbutton both in field and in control room.
In order to isolate and blow down the unit Operator have to:
· Push the UV-501 activation button HS-501A or HS-501B or HS-501C.
· Close the manual ball 8” outlet isolation valve.
· Push the UV-600 activation button HS-600B or HS-600C, opening the blow down valve and discharging
all the unit capacity to the atmosphere.
Note: Operator may skip the second step of the procedure in order to depressurize also the
downstream equipment.
_______________________________
In case of short term stand-by, the Natural Gas Metering and Reducing Station can be left pressurized
but water bath heater burner system shall be stopped.
When inspecting or doing maintenance on equipment, be sure to ensure no ingress of contaminants
from all sources with a positive isolation, turning the relevant spectacle blind in close position.
6.4.2 Long Term Stand-By
If the system is shut-down for more than four weeks, additional precautions relevant to each individual
equipment shall be then considered.
In particular it is recommended attention to the following:
· Ensure that electrical and instrument enclosures are completely closed and the internals are maintained
dry. If necessary use silica gel bags but remember to remove them before restarting.
· Valves should be occasionally cycled (opened/closed).
It is then strongly recommended the following:
· Drain all vessels/equipment/piping.
· The unit when is not in use, it should be maintained at pressure (minimum 0.5 bar g) with an inert gas
(nitrogen) to prevent ingress of any contaminants from the atmosphere and avoid any possible
dangerous scenarios.
6.4.3 Unit Off-Line
If the system is shall be put off line, recommendations for long term standby should be
considered and additional precautions relevant to each individual equipment shall be then taken.
As per long term stand by guidelines, it is recommended attention to the following:
· Ensure that electrical and instrument enclosures are completely closed and the internals are maintained
dry. If necessary use silica gel bags but remember to remove them before restarting.
· Valves should be occasionally cycled (opened/closed).
It is then strongly recommended the following:
· Drain all vessels/equipment/piping.
· Depressurize and purge all plant equipment. Whenever the unit is not in use, it should be maintained at
pressure (minimum 0.5 bar g) with an inert gas (nitrogen) to prevent ingress of any contaminants from
the atmosphere and avoid any possible dangerous scenarios.
_______________________________
7 EMERGENCY SHUTDOWN
7.1 GENERAL
Unit can be shut down for emergency contingencies either by means of push buttons located both in
field, in control room and in GSCS or it can be shut down due to external causes by means of software
input from ESD.
Each Train and relevant Electrical Heater can be shut down for emergency contingencies by means of
push buttons located both in field and control room or, similarly, they can be shut down due to external
causes by means of software input from ESD.
7.2 UTILITIES SHUTDOWN
The Wet Air Receiver 80-V-001 has been designed to provide sufficient emergency air volume for 15
min plant operation at normal instrument air demand.
7.2.2 Potable Water
Gas Station Control Shelter and Startup Electrical Heater are connected to Emergency Power supply
system.
_______________________________
8 SAFETY
8.1 GENERAL
All plant personnel must comply with normal safety rules which generally cover the operation of oil and
gas/refinery plants.
Chief Operator must ensure that all safety rules are complied with in order to safeguard personnel life
and protect equipment from damage.
Fluid sampling shall be performed by authorized personnel with suitable equipment and tools.
Metal vessels shall be grounded during sampling operations to prevent dangerous electrostatic
accumulation. Protective gloves and glasses are necessary for samples above 60 °C or below 0 °C.
It shall be borne in mind that particular caution is always required owing to the presence of hydrogen
sulphide, as this gas is highly dangerous even in small concentrations.
All personnel employed in the plant shall be thoroughly acquainted with the dangers of H2S poisoning
and understand the emergency procedures in case of a toxic gas release. Therefore the personnel
should be equipped with portable H2S detectors.
_______________________________
_______________________________
All the equipments of the Natural Gas Metering and Reducing Station are protected from overpressure
by pressure safety valves. Safety interlocks have been provided to prevent possible overpressure to the
unit and downstream equipment due to mis-operation, abnormal plant conditions or external causes.
8.3.1 Overpressure Protection Description
Natural gas metering and reducing section is mainly composed of four sections with different design
conditions. Such sections are the following:
· High Pressure Section (design pressure: 60.0 bar g): This section includes the sections between the
Inlet Skid “70-ME-004” and the pressure reducing skid “70-ME-002” and lines between these
equipments and up to pressure reducing section.
· Medium Pressure Section (design pressure: 30.0 bar g): This section includes piping between the “70-
ME-002” skid outlet and the unit outlet comprehending the outlet skid “70-ME-005”
· Low Pressure Section (design pressure: 11.0 bar g) : This section includes piping downstream
PCV-508-A/B in the “70-ME-003” fuel gas burner reducing skid up to the water bath heaters burners.
This section also includes the instrument air connections and tubing.
· Atmospheric Section: Includes the Water Bath Heaters 70-E-001-A/B and connected instrumentation.
All these sections are connected one to each other therefore protection has been provided to avoid
possible overpressure of low pressure section due to fluid breakthrough from high pressure sections.
8.3.1.1 High Pressure Section Protection
Protection of Natural Gas Metering and Reducing Station high pressure section from upstream pressure
sources has been provided through PSV-101 at the inlet of the station, the safety shut valve UV-501 and
dedicated pressure safety valves.
8.3.1.2 Medium Pressure Section Protection
Natural Gas Metering and Reducing Station medium pressure section is connected upstream to high
pressure sources. Overpressure protection has been provided in the following way:
· PCV-516-A/B that closes in fail position and is also provided with an integrated slam shut device SSV-
516-A/B that automatically isolate the system from upstream section.
· Downstream lines are provided with PSV-618-A/B sized in order to relief eventual gas slips from the
closed slam shut valves.
8.3.1.3 Low Pressure Section Protection
Natural Gas Metering and Reducing Station low pressure section is connected upstream to high
pressure sources. Overpressure protection has been provided in the following way:
· PCV-508-AB are fail open devices thus the downstream line are provided with PSV-608-A/B sized in
order to relief the whole eventual gas capacity from the full open regulator, based on the valve
manufacturer data.
· PCV-509-A/B close in fail position and are also provided with an integrated slam shut device SSV-509-
A/B that automatically isolate the system from upstream section.
· Downstream lines are provided with PSV-609-A/B sized in order to relief eventual gas slips from the
closed slam shut valves.
8.3.2 Interlocks Protection Description
_______________________________
Interlock protections are associated with the possible process upsets conditions and external events
(such as external fire, gas leakage) to prevent system major damages and scenarios.
Warnings on all process variables are also provided to notify Operators possible malfunctions before trip
are activated.
Interlock protection is programmed and implemented into client ESD panel located in control shelter
whereas all warning and trip are repeated in Control Room. Refer to “Abnormal Conditions” paragraph
in chapter 5.3 “Normal Operation” for detailed description of interlock activation causes and actions.
8.3.2.1 Interlock Testing
All safety trip initiators and outputs shall be checked on a regular basis. No facility for online trip testing
has been provided and thus there are no trip defeat buttons.
It is recommended that the trip system would be checked for 'real' when it is required to stop operation
as an alternative to utilizing a shutdown push button/sequence. It is recommended to simulate the
output signal of each interlock transmitter and verify the correct function of each trip logic and
equipment/device. A different initiator should be checked in rotation.
Operator should keep record of trip system testing.
8.3.3 Manual Shutdown Description
Even if the unit has been provided with an automatic safety & trip system (ESD) which protects the
Natural Gas Metering and Reducing Station from possible damage due to process upset conditions, the
unit is also provided with safety pushbuttons, located either on client control room or in field and in
control shelter as follows:
· HS-505-A/B in control shelter and HS-504-A4 in field, both for the Heaters Emergency shutdown.
· HS-501-C pushbutton in field and HS-501-B in control room that close the UV-501 shutdown valve
isolating the unit and stopping the flow.
8.4 FIRE FIGHTING SYSTEM SELECTION
The above described extinguishing agents shall be applied to fire source and exposures by means of
both fixed and portable facilities as well as by means of fixed dedicated systems as below summarized:
· Fire hydrants;
· Fire water monitors;
· Portable and wheeled dry chemical powder fire extinguishers;
_______________________________
9 EQUIPMENT DATASHEET
9.1 DATASHEETS
_______________________________
10 DRAWINGS
_______________________________