SUBCON GUIDE
BASIC THINGS
TO KNOW
BEFORE
DOING THE
SMART QC
TASK
ISDP EHS CLOCK IN GUIDE
ISDP SMART QC ACTIVITY FLOW
PM/APM Will dispatch the DU ID of Subcon For Smart
QC Task
If all items are passed the RCC will update the subcon thru
whatsapp/viber. If not, RCC will advise the subcon to
reupload photos/rectify as per isdp remarks
ANY SMART QC TASK DISPATCHED THRU ISDP MOBILE IS SUBJECT FOR DELETION
Note:
➢ Only QC tasks dispatched from rollout plan will be accepted
➢ Subcon can ask support from RCC/PM/APM to dispatch their QC task
➢ Subcon should not dispatched their own QC task only EHS task is allowed
REASONS WHY SUBCON CANNOT SUBMIT THEIR TASK
INCOMPLETE UPLOAD/PHOTOS FOR VALID All valid items (items in subcon’s scope) should have an
ITEMS uploaded photo
UNMARKED “NA” IN DATA COLLECTION FOR All invalid items (items not in scope) should mark Na in
INVALID ITEMS data collection
NO “NA PHOTOS” FOR ITEMS WITH Must upload NA pictures for items with subitem which are
SUBITEM not scope of subcon (Combiner and RRU 1800)
MULTIPLE ACCOUNT USED IN ONE QC TASK Only one account should be used in one QC task
MULTIPLE PHONE USED IN ONE QC TASK Only one phone should be used in one QC task
2. Log in account
NOC/SUBCON GUIDE FOR LMT SCREENSHOTS AND FILE UPLOADING
3
NOC/SUBCON GUIDE FOR LMT SCREENSHOTS AND FILE UPLOADING
CLICK THE DU ID
6
NOC/SUBCON GUIDE FOR LMT SCREENSHOTS AND FILE UPLOADING
8
CLICK UPLOAD
10
11
TAKE PHOTO
GO TO
GALLERY
2
HOW TO USE ISDP DOODLE TOOL
4
CLICK THE TOOL YOU NEED TO USE
(DRAW/ENCIRCLE/INSERT TEXT/REDO/ERASE)
SAVE
5
PHOTOS WITH NA LONG/LAT AND DISTANCE WILL NOT BE ACCEPTED
LABELING GUIDE
CONNECTOR
CONNECTOR
READ AWAY TOWARDS
CORRECT WRONG
LABELING GUIDE
❑ RECTIFICATION OF LABELS SHOULD BE DONE IN ONE FULL TEXT NOT PART BY PART
CORRECT WRONG
LABELING GUIDE
X ELECTRICAL TAPE
WRONG CORRECT
HARDWARE
INSTALLATION
GUIDE
Scenario: If no RSL on site
Guide :
Upload clear and readable photo of
radio station license located at the
back of cabin door or rectifier door.
Output: RSL
Type: Photo
*if no RSL on site, take a photo of the back of the cabin door/rectifier (it is important that long/lat should be seen In the watermark)
INDOOR CABIN
Standard :
Upload 360 Degree indoor cabin
photo. Upload photo of indoor cabin
busbar.
Guide :
* Upload photo of Equipment room
where the BTS is located. Upload
photo of indoor busbar.
* Upload TSSR
* Enumerate scope and installed
materials
Type: Photo/text/file
Guide :
ACPDB photos need to show
readable photo of AC Circuit Breaker
Rating
Type: Photo
1 2
TMC/RACK INSTALLATION
Standard :
1. Upload photo of installed
Rack/Cabinet.
2. Upload photo of Rack/Cabinet
boltdown, grounding connection
from Rack/Cabinet to nearest bus
bar.
3. Picture of Level Meter taken on
top or side of Cabinet/Rack.
Guide :
Floor stand must be properly located
as per approved TSSR. Rack must be
properly grounded to nearest bus
bar. Rack base and ground fixed
expansion bolts installed firmly and
reliably bolt & nut installed in the
correct order.
Output: TMC/RACK
Type: Photo
TMC / RACK INCLINATION
3
3
Inclinometer is
accepted
Guide :
All the Plug-in units or modules must
properly secured and tightened. 1
Output: BBU OVERVIEW/SERIAL
NUMBER UBBP/UMPT/UPEU
Type: Photo
BBU Overview
Standard :
1. Take a clear front view and side by
side photos of the newly installed BBU.
2. Take a clear photo of CPRI cable
labels terminated in the BBU.
3.Take clear photo of BBU grounding 1 3
connection from BBU and bus bar.
4 .Labels direction should be read away
from the connector.
ROUTED IN THE
5. Take clear photo of installed CABLE HANGER
equipment's serial number.
Guide :
BBU is properly installed in the cabinet
or TX rack. BBU Boards are properly
placed in their corresponding slot as 1 3
per Configuration Standard. BBU must
be properly grounded. If the BBU is
installed in an existing transmission
rack, BBU grounding can be connected
SERIAL NUMBER
to the racks body provided that the
rack is grounded properly as well,
otherwise, BBU grounding must be
directly connected to the busbar using
the 16mm2 cable size.
Output: BBU
2 5
Type: Photo
*CPRI installed should be properly groomed and routed/inserted in the cable hanger. NOTE:
* BBU module shall be properly labeled. ➢ if reused bbu for item 1, need to identify cpri under project using isdp doodle tool
*Unused sub-modules or PIU slots shall be covered with dummy plates/ panels. ➢ if reused bbu no need to upload item 3 and 5
CABLE LAYOUT STANDARD FROM SMART
DC Circuit Breaker Tapping point FORMAT FOR DC CABLE LABEL:
DCDU + DCDU NUMBER 1 NEGATIVE 1 POSITIVE
Standard :
1. Upload photos of DC cable
termination to CB.
2. Take a clear photo of DC cable
labeling.
3. Upload readable photo of rectifier
voltage display for every QC task.
SHOELUGS &
4. Upload readable photo of rectifier SHRINKABLE TUBE
load current display for every QC
task.
Guide :
Prior to the installation and
termination of the DC cables, check
the current rating of the proposed CB 3 4
based on the approved TSSR. The
termination of the DC cables must
tightened properly. The terminated
DC cables must installed with shoe
lug and shrinkable tube and proper
labels. Installed DC cable labels
should be at this format:
DCDU + DCDU NUMBER.
Type: Photo
NOTE:
*YELLOW LABEL/FLAG LABELS ARE ALLOWED FOR LABELING
Regardless if there was dcdu power cable
*DC CABLE TERMINATION MUST HAVE SHOE LUGS/SHRIKNKABLE TUBE
*DC cables terminated between DCDU/ DCPDB and Rectifier DCPDB shall be used with proper lugs and sleeve shall be covered with terminated, there should always be an upload in
shrinkable tube rectifier current and voltage display
DCDU Overview
FORMAT FOR DCDU POWER CABLE LABEL:
Standard : RECTIFIER BRAND + RECTIFIER NUMBER + CB NUMBER
1. Take a clear front view and side by side
photos of the newly installed DCDU.
1 1
2. Take a clear photo of RRU power cable
labels terminated in the DCDU and end to
end grounding of dcdu.
3. Take clear photos of voltmeter reading
for input voltage measurement and
ammeter reading for input current
measurement for new and used existing
DCDU.
4. Labels direction should be read away
from the connector.
5. Take clear photo of installed equipment's
serial number.
1
Guide :
DCDU is properly installed in the cabinet or
TX rack with correct body label fixed in 2 2
DCDU terminal cover. DCDU must be
properly grounded. If the DCDU are
installed in an existing transmission rack,
DCDU grounding can be connected to the
racks body provided that the rack is 2
grounded properly as well, otherwise,
DCDU grounding must be directly
connected to the busbar using the 16mm2
cable size. DCDU power cable labels should
be at format: RECTIFIER BRAND + RECTIFIER
NUMBER + CB NUMBER.
Type: Photo
5 SERIAL NUMBER 3 3
Guide :
All signal cable connections are
properly patched in its assigned Port
(electrical or optical) with
corresponding label. Make sure to
provide Spiral Conduit for TX Fiber
Cable.
Type: Photo
Guide :
GPS Antenna need to be installed in
the approved proposed location.
Free from obstruction. Make sure to
waterproof the connection to the
antenna side. Fix the cable properly
using cable clamp and provide drip
loop for the cable before entering
the porthole.
Type: Photo
1 GPS ANTENNA 1 GPS SUPPRESSOR 1 GPS SUPPRESSOR
WEATHERPROOFED
MUST BE PROPERLY
LABELED GROUNDING AT
SUPPRESSOR SIDE
LABEL
1 GPS SUPPRESSOR
SERIAL NUMBER
GROUNDING AT
BUSBAR SIDE
Jumper Cable Route
PROPERLY
SECURED
Standard :
Guide :
Jumper cable should be properly
groomed, not obstructing other
equipment/cable, and should not
violate the bending radius. Jumper
cable should be properly labeled. MINUMUM
Jumper cable should be secured in BENDING RADIUS
AMB/Tower Leg to avoid cable DRIP LOOP
SHOULD BE
swaying due to strong wind. OBSERVED
Standard :
Guide :
Jumper-Feeder connector should be
properly weatherproofed based on 2 CORRECT
TERMINATION
standard weatherproofing and SHOULD BE IN THE
should be properly labeled. Feeder HOLE NEAR THE
CABLE
grounding kit should be
weatherproofed and terminated to
busbar
• FEEDER AND JUMPER CABLE CONNECTORS SHALL BE SEALED WITH– 2 LAYERS OF ELECTRICAL TAPE,
FOLLOWED BY 3 LAYERS OF RUBBER TAPE AND 3 LAYERS OF ELECTRICAL TAPE. COMPLETE THE
SEALING BY USING CABLE TIE TO SEAL BOTH ENDS OF THE TAPE
• OVERLAPPING GROUNDING TERMINATION IS NOT ALLOWED
Cable Management
CABLESUBITEM:
ON EQUIPMENT
CABLE ON EQUIPMENTPORTHOLE
PORTHOLE
1 WITH CABLE
1
Standard : GLAND
Guide :
Power and Signal Cables are properly
routed in the cabinet/rack Power and
Signal Cables should not cross each
other nor be routed in only one side
of the cabinet/rack. Feeder, CPRI and
1 1
RRU DC Power cable must be OUTDOOR CABINET CABLE ENTRY
properly installed in the ladder with
its clips in the same direction at
regular interval of 1m apart. SEALED
Type: Photo/Video
NOTE:
➢ FOR VIDEO MINIMUM IS 20 SECONDS
NOTE:
*PORTHOLE MUST HAVE CABLE GLANDS AND PROPERLY SEALED ➢ SUBCON MUST ALWAYS IDENTIFY PORTHOLE USED USING ISDP DOOLE TOOL
CABLE FIXING
SUBITEM: CABLE FIXING
2 2 2 2
IF OUTDOOR TYPE,
POWER CABLE AND POWER CABLE
CPRI SECURED WITH SHOULD BE SECURED
CABLE CLIPS WITH LTC FROM
CABINET TO
RECTIFIER
NOTE:
➢ SUBCON MUST ALWAYS IDENTIFY CABLES UNDER PROJECT USING ISDP DOOLE TOOL (FROM BBU/DCDU TO
PORTHOLE INDOOR AND FROM HORIZONTAL LADDER TO VERTICAL)
EXCESS CPRI LOOPING
SUBITEM: EXCESS CPRI LOOPING
Guide :
Combiner are properly and securely
installed in its approved location
BODY LABEL
based on TSSR. Apply waterproofing PROPERLY SERIAL NUMBER
on jumper connectors terminated to WEATHERPROOFED AND
it when installed outside. Combiners LABELED (OUTPUT)
should always have body labels.
Type: Photo
• COMBINER MUST BE SECURED/FIXED WITH METAL STRAP
• COMBINER MUST BE PROPERLY LABELED ACCORDING TO BAND AND SECTOR
• ALL CONNECTORS TERMINATION SHALL BE PROPERLY WEATHERPROOFED FIX WITH METAL STRAP
COMBINER LABELING
HIGHBAND LOWBAND
Bandpass Filter (850/900) 1 PORTS WERE PROPERLY
2
WEATHERPROOFED AND
LABELED FIX WITH METAL STRAP
Standard :
1. Take photo of all the filters
installed (Indoor/Outdoor) showing
proper waterproofing and cable
labels.
2. Labels direction should be read
away from the connector.
3. Take clear photo of installed
equipment's serial number.
Guide : 1
Filters are properly and securely
BODY LABEL SERIAL NUMBER
installed. Apply waterproofing on
jumper connectors terminated to it
when installed outside. Filters should
always have body labels. Only L850
and GU900 requires Filters.
Type: Photo
ZOOMED OUT PHOTO
Guide :
Ensure antenna height, orientation,
mechanical and electrical tilt are
based on TSSR/datafil. Ensure the
antenna has a tilting bracket and
installed correctly, lock washer and
double nuts must be installed. The RF
antenna is not obstructed by other
antennas, poles or structures within
the site and can be re-panned.AISG
cable properly connected and
labeled going to RRU/SBT.
MUST BE PROPERLY
TIGHTENED AND NO
MISSING NUTS
• Must show the antenna with Label, to identify the Site ID, Sector, Bands and the Azimuth value
• Picture shows the antenna in the middle and it is straight
• 10% of the picture is showing the sky, ensuring the picture is not tilted down
ANTENNA SHOW NO BLOCKING
SERIAL NUMBER
RRU 850
RRU 900
Guide :
All grounding connections must be
properly tightened and utilized individual
bus bar hole with correct terminal lugs,
properly crimped and with shrinkable
tube. Grounding cable size must conform
with the installation standard.
Guide :
The site is cleaned before personnel
leave. Site should be clutter free and
equipment installed should be
cleaned with no dirt on the
enclosure.
Type: Photo/Video
END