ISDP SMART QC

SUBCON GUIDE
BASIC THINGS
TO KNOW
BEFORE
DOING THE
SMART QC
TASK
ISDP EHS CLOCK IN GUIDE
ISDP SMART QC ACTIVITY FLOW
PM/APM Will dispatch the DU ID of Subcon For Smart
QC Task

Subcon will contact RCC thru whatsapp/viber and


inform them they’re ready to to the QC task

Subcon will contact RCC thru whatsapp/viber and


inform them they’re ready to to the QC task

Once done photo taking/uploading subcon will


inform the RCC that their task is ready for checking

RCC will check the photos

If all items are passed the RCC will update the subcon thru
whatsapp/viber. If not, RCC will advise the subcon to
reupload photos/rectify as per isdp remarks
ANY SMART QC TASK DISPATCHED THRU ISDP MOBILE IS SUBJECT FOR DELETION

Note:
➢ Only QC tasks dispatched from rollout plan will be accepted
➢ Subcon can ask support from RCC/PM/APM to dispatch their QC task
➢ Subcon should not dispatched their own QC task only EHS task is allowed
REASONS WHY SUBCON CANNOT SUBMIT THEIR TASK
INCOMPLETE UPLOAD/PHOTOS FOR VALID All valid items (items in subcon’s scope) should have an
ITEMS uploaded photo

UNMARKED “NA” IN DATA COLLECTION FOR All invalid items (items not in scope) should mark Na in
INVALID ITEMS data collection

NO “NA PHOTOS” FOR ITEMS WITH Must upload NA pictures for items with subitem which are
SUBITEM not scope of subcon (Combiner and RRU 1800)

MULTIPLE ACCOUNT USED IN ONE QC TASK Only one account should be used in one QC task

MULTIPLE PHONE USED IN ONE QC TASK Only one phone should be used in one QC task

Note!!! DO NOT BULK NA


NOC/SUBCON GUIDE FOR LMT SCREENSHOTS AND FILE UPLOADING
1. Go to https://app.Huawei.com/sdcp

2. Log in account
NOC/SUBCON GUIDE FOR LMT SCREENSHOTS AND FILE UPLOADING

Click ISDP SMARTQC

3
NOC/SUBCON GUIDE FOR LMT SCREENSHOTS AND FILE UPLOADING

Click SWITCH TO TASK EXPLORER


4
NOC/SUBCON GUIDE FOR LMT SCREENSHOTS AND FILE UPLOADING

SEARCH DU ID IN ALL TASK


5
NOC/SUBCON GUIDE FOR LMT SCREENSHOTS AND FILE UPLOADING

CLICK THE DU ID

6
NOC/SUBCON GUIDE FOR LMT SCREENSHOTS AND FILE UPLOADING

FIND LMT AND NMS


7 SCREENSHOT KCP
NOC/SUBCON GUIDE FOR LMT SCREENSHOTS AND FILE UPLOADING

8
CLICK UPLOAD

CLICK ONE ITEM


NOTE: MAKE SURE DATA
COLLECTION NA IS
UNTICKED.
NOC/SUBCON GUIDE FOR LMT SCREENSHOTS AND FILE UPLOADING

10

DRAG THE PHOTO


NOC/SUBCON GUIDE FOR LMT SCREENSHOTS AND FILE UPLOADING
CLICK SUBMIT

11

REPEAT PROCESS IN OTHER


ITEMS
HOW TO USE ISDP DOODLE TOOL
NOTE: SUBCON MUST ALWAYS IDENTIFY CABLES/EQUIPMENT/BREAKER ETC UNDER THEIR SCOPE USING DOODLE TOOL.

TAKE PHOTO

GO TO
GALLERY

2
HOW TO USE ISDP DOODLE TOOL

4
CLICK THE TOOL YOU NEED TO USE
(DRAW/ENCIRCLE/INSERT TEXT/REDO/ERASE)

CLICK THE ICON


BELOW

SAVE

5
PHOTOS WITH NA LONG/LAT AND DISTANCE WILL NOT BE ACCEPTED
LABELING GUIDE

❑ ALL LABELS MUST BE IN READ AWAY FROM CONNECTOR DIRECTION


CONNECTOR
READ AWAY

CONNECTOR
CONNECTOR
READ AWAY TOWARDS

CORRECT WRONG
LABELING GUIDE

❑ RECTIFICATION OF LABELS SHOULD BE DONE IN ONE FULL TEXT NOT PART BY PART

CORRECT WRONG
LABELING GUIDE

❑ BODY LABEL SHOULD BE PROPERLY FIX

X ELECTRICAL TAPE

WRONG CORRECT
HARDWARE
INSTALLATION
GUIDE
Scenario: If no RSL on site

RADIO STATION LICENSE


Standard : Long/Lat should be
Upload photo of radio station license seen in watermark if
located at the back of cabin door or no RSL on site
rectifier door.

Guide :
Upload clear and readable photo of
radio station license located at the
back of cabin door or rectifier door.

Output: RSL

Type: Photo

*if no RSL on site, take a photo of the back of the cabin door/rectifier (it is important that long/lat should be seen In the watermark)
INDOOR CABIN
Standard :
Upload 360 Degree indoor cabin
photo. Upload photo of indoor cabin
busbar.

Guide :
* Upload photo of Equipment room
where the BTS is located. Upload
photo of indoor busbar.
* Upload TSSR
* Enumerate scope and installed
materials

Output: 360 photos of indoor


cabin/TSSR file/scope

Type: Photo/text/file

*TSSR MUST BE UPLOADED BY THE SUBCON (THRU LAPTOP)


*SCOPE AND INSTALLED MUST BE PROPERLY ENUMERATED
ACPDB
Standard :
Upload ACPDB photo with readable
CB rating for every QC task

Guide :
ACPDB photos need to show
readable photo of AC Circuit Breaker
Rating

Output: ACPDB Circuit Breaker photo

Type: Photo
1 2

TMC/RACK INSTALLATION
Standard :
1. Upload photo of installed
Rack/Cabinet.
2. Upload photo of Rack/Cabinet
boltdown, grounding connection
from Rack/Cabinet to nearest bus
bar.
3. Picture of Level Meter taken on
top or side of Cabinet/Rack.

Guide :
Floor stand must be properly located
as per approved TSSR. Rack must be
properly grounded to nearest bus
bar. Rack base and ground fixed
expansion bolts installed firmly and
reliably bolt & nut installed in the
correct order.

Output: TMC/RACK

Type: Photo
TMC / RACK INCLINATION

3
3

Inclinometer is
accepted

*Cabinet/ Rack shall be properly aligned and leveled


*Cabinet/ Rack shall be free from scratches, dent, misalignment
1 2
Photo of Plug-in Units SERIAL NUMBER

Inside the BTS Cabinet


Standard :
1. Take a close view photo of the
Plug-in units inside the BTS Cabinet.
2. Take clear photo of installed
boards (UBBP, UMPT, UPEU) serial
number.

Guide :
All the Plug-in units or modules must
properly secured and tightened. 1
Output: BBU OVERVIEW/SERIAL
NUMBER UBBP/UMPT/UPEU

Type: Photo
BBU Overview
Standard :
1. Take a clear front view and side by
side photos of the newly installed BBU.
2. Take a clear photo of CPRI cable
labels terminated in the BBU.
3.Take clear photo of BBU grounding 1 3
connection from BBU and bus bar.
4 .Labels direction should be read away
from the connector.
ROUTED IN THE
5. Take clear photo of installed CABLE HANGER
equipment's serial number.

Guide :
BBU is properly installed in the cabinet
or TX rack. BBU Boards are properly
placed in their corresponding slot as 1 3
per Configuration Standard. BBU must
be properly grounded. If the BBU is
installed in an existing transmission
rack, BBU grounding can be connected
SERIAL NUMBER
to the racks body provided that the
rack is grounded properly as well,
otherwise, BBU grounding must be
directly connected to the busbar using
the 16mm2 cable size.

Output: BBU
2 5
Type: Photo

*CPRI installed should be properly groomed and routed/inserted in the cable hanger. NOTE:
* BBU module shall be properly labeled. ➢ if reused bbu for item 1, need to identify cpri under project using isdp doodle tool
*Unused sub-modules or PIU slots shall be covered with dummy plates/ panels. ➢ if reused bbu no need to upload item 3 and 5
CABLE LAYOUT STANDARD FROM SMART
DC Circuit Breaker Tapping point FORMAT FOR DC CABLE LABEL:
DCDU + DCDU NUMBER 1 NEGATIVE 1 POSITIVE
Standard :
1. Upload photos of DC cable
termination to CB.
2. Take a clear photo of DC cable
labeling.
3. Upload readable photo of rectifier
voltage display for every QC task.
SHOELUGS &
4. Upload readable photo of rectifier SHRINKABLE TUBE
load current display for every QC
task.

Guide :
Prior to the installation and
termination of the DC cables, check
the current rating of the proposed CB 3 4
based on the approved TSSR. The
termination of the DC cables must
tightened properly. The terminated
DC cables must installed with shoe
lug and shrinkable tube and proper
labels. Installed DC cable labels
should be at this format:
DCDU + DCDU NUMBER.

Output: DC circuit breaker/rectifier


display

Type: Photo
NOTE:
*YELLOW LABEL/FLAG LABELS ARE ALLOWED FOR LABELING
Regardless if there was dcdu power cable
*DC CABLE TERMINATION MUST HAVE SHOE LUGS/SHRIKNKABLE TUBE
*DC cables terminated between DCDU/ DCPDB and Rectifier DCPDB shall be used with proper lugs and sleeve shall be covered with terminated, there should always be an upload in
shrinkable tube rectifier current and voltage display
DCDU Overview
FORMAT FOR DCDU POWER CABLE LABEL:
Standard : RECTIFIER BRAND + RECTIFIER NUMBER + CB NUMBER
1. Take a clear front view and side by side
photos of the newly installed DCDU.
1 1
2. Take a clear photo of RRU power cable
labels terminated in the DCDU and end to
end grounding of dcdu.
3. Take clear photos of voltmeter reading
for input voltage measurement and
ammeter reading for input current
measurement for new and used existing
DCDU.
4. Labels direction should be read away
from the connector.
5. Take clear photo of installed equipment's
serial number.
1

Guide :
DCDU is properly installed in the cabinet or
TX rack with correct body label fixed in 2 2
DCDU terminal cover. DCDU must be
properly grounded. If the DCDU are
installed in an existing transmission rack,
DCDU grounding can be connected to the
racks body provided that the rack is 2
grounded properly as well, otherwise,
DCDU grounding must be directly
connected to the busbar using the 16mm2
cable size. DCDU power cable labels should
be at format: RECTIFIER BRAND + RECTIFIER
NUMBER + CB NUMBER.

Output: DCDU/DCDU INPUT VOLTAGE AND


CURRENT MEASUREMENT

Type: Photo
5 SERIAL NUMBER 3 3

METER SHOULD BE IN DC SETTING

DCDU BODY LABEL DCDU INPUT CURRENT


METER SHOULD BE IN DC SETTING

*RRU POWER CABLES MUST BE PROPERLY GROOMED


*FOR INPUT CURRENT AND VOLTAGE MEASUREMENT METER SHOULD BE IN DC SETTING
*FLAG LABEL OR YELLOW LABEL CAN BE USED IN DCDU POWER CABLE LABELING
*DCDU/ DCPDB SHALL BE PROPERLY LABELED
NOTE:
➢ IF REUSED DCDU NO NEED TO UPLOAD END TO END GROUNDING OF DCDU
➢ REGARDLESS IF DCDU IS NEWLY INSTALLED/REUSED NEED TO MEASURE DCDU INPUT CURRENT AND VOLTAGE
CABLE LAYOUT STANDARD FROM SMART
Transmission Termination
Standard :
Take end to end photos of the
transmission cables termination. SPIRAL CONDUIT
Labels direction should be read away
from the connector.

Guide :
All signal cable connections are
properly patched in its assigned Port
(electrical or optical) with
corresponding label. Make sure to
provide Spiral Conduit for TX Fiber
Cable.

Output: Transmission cable at bbu


side and transmission equipment
side

Type: Photo

*TX CABLE MUST BE PROPERLY LABELED END TO END


*TX CABLE MUST BE PROPERLY ROUTED
GPS Antenna Approved Coverage

GPS Antenna Installation


Standard :
1. Take Photo of the GPS Antenna,
Surge Suppressor, cable
waterproofing and cable clamping
and fixing.
2. Take clear photo of installed
equipment's serial number

Guide :
GPS Antenna need to be installed in
the approved proposed location.
Free from obstruction. Make sure to
waterproof the connection to the
antenna side. Fix the cable properly
using cable clamp and provide drip
loop for the cable before entering
the porthole.

Output: GPS antenna/suppressor

Type: Photo
1 GPS ANTENNA 1 GPS SUPPRESSOR 1 GPS SUPPRESSOR

WEATHERPROOFED

MUST BE PROPERLY
LABELED GROUNDING AT
SUPPRESSOR SIDE

LABEL

1 GPS SUPPRESSOR

SERIAL NUMBER

GROUNDING AT
BUSBAR SIDE
Jumper Cable Route
PROPERLY
SECURED
Standard :

Take photo and video of Jumper PROPERLY


cable route installed indoor and SECURED
outdoor from RRU to Antenna per
sector.

Guide :
Jumper cable should be properly
groomed, not obstructing other
equipment/cable, and should not
violate the bending radius. Jumper
cable should be properly labeled. MINUMUM
Jumper cable should be secured in BENDING RADIUS
AMB/Tower Leg to avoid cable DRIP LOOP
SHOULD BE
swaying due to strong wind. OBSERVED

Output: Jumper cable routing


DRIP LOOP
Type: Photo/Video
NOTE:
➢ Always identify jumper cables under project using isdp doodle tool for
*JUMPER CABLE LOOPING IS NOT ALLOWED easy checking
*IT IS NOT ALLOWED TO JOIN TWO OR MORE SHORT CABLES TO ACHIEVE THE TOTAL LENGTH OF A CABLE RUN. ➢ If there are existing jumper cable looping, subcon must identify and
*ROUTING SHALL BE DONE PROPERLY BY AVOIDING TENSION AND SHARP TURNS. remarks it is existing using isdp doodle tool
➢ For video minimum of 20 seconds per sector (must cover from rru to
antenna)
1
Properly
weatherproofed
Feeder Cable Installation
With Label

Standard :

1. Take photo of all Jumper-Feeder


connector weatherproofing.
2. Take photo of all feeder grounding Properly With Label
kit weatherproofing and feeder weatherproofed
grounding kit termination to busbar.

Guide :
Jumper-Feeder connector should be
properly weatherproofed based on 2 CORRECT
TERMINATION
standard weatherproofing and SHOULD BE IN THE
should be properly labeled. Feeder HOLE NEAR THE
CABLE
grounding kit should be
weatherproofed and terminated to
busbar

Output: Feeder cable installation


Properly
Type: Photo weatherproofed

• FEEDER AND JUMPER CABLE CONNECTORS SHALL BE SEALED WITH– 2 LAYERS OF ELECTRICAL TAPE,
FOLLOWED BY 3 LAYERS OF RUBBER TAPE AND 3 LAYERS OF ELECTRICAL TAPE. COMPLETE THE
SEALING BY USING CABLE TIE TO SEAL BOTH ENDS OF THE TAPE
• OVERLAPPING GROUNDING TERMINATION IS NOT ALLOWED
Cable Management
CABLESUBITEM:
ON EQUIPMENT
CABLE ON EQUIPMENTPORTHOLE
PORTHOLE
1 WITH CABLE
1
Standard : GLAND

1. Take photos of used porthole


properly sealed.
2. Take photos of cable routing from
BBU to porthole, porthole to vertical CABIN’S PORTHOLE
ladder and vertical ladder.
3. Upload required videos as per item
name. SEALED

Guide :
Power and Signal Cables are properly
routed in the cabinet/rack Power and
Signal Cables should not cross each
other nor be routed in only one side
of the cabinet/rack. Feeder, CPRI and
1 1
RRU DC Power cable must be OUTDOOR CABINET CABLE ENTRY
properly installed in the ladder with
its clips in the same direction at
regular interval of 1m apart. SEALED

Output: Cable management

Type: Photo/Video
NOTE:
➢ FOR VIDEO MINIMUM IS 20 SECONDS

NOTE:
*PORTHOLE MUST HAVE CABLE GLANDS AND PROPERLY SEALED ➢ SUBCON MUST ALWAYS IDENTIFY PORTHOLE USED USING ISDP DOOLE TOOL
CABLE FIXING
SUBITEM: CABLE FIXING
2 2 2 2
IF OUTDOOR TYPE,
POWER CABLE AND POWER CABLE
CPRI SECURED WITH SHOULD BE SECURED
CABLE CLIPS WITH LTC FROM
CABINET TO
RECTIFIER

INDOOR CABLE FIXING

NOTE:
➢ SUBCON MUST ALWAYS IDENTIFY CABLES UNDER PROJECT USING ISDP DOOLE TOOL (FROM BBU/DCDU TO
PORTHOLE INDOOR AND FROM HORIZONTAL LADDER TO VERTICAL)
EXCESS CPRI LOOPING
SUBITEM: EXCESS CPRI LOOPING

• [Scenario 1] For all tower types, recommended


location of CPRI loop is below outdoor horizontal cable
ladder near the porthole.

• [Scenario 2] For self-support tower with landing pad


but no corner mesh flooring, recommended location is
below outdoor horizontal cable ladder installed in the
landing pad of the tower.

• [Scenario 3] For lacking space below outdoor


horizontal cable ladder, install the loop inside the
equipment room below cable ladder/ tray (if still no
space available, vendor shall provide a separate rack for
CPRI loop management)
SCENARIO 1 SCENARIO 2 SCENARIO 3

• EXCESS CPRI SHOULD BE PROPERLY LABELED


• CPRI SHALL BE LOOPED PER TECHNOLOGY/ BAND AND SECTOR
High/Low Band 1 1 1 2
Combiners ZOOMED OUT PHOTO PROPERLY
WEATHERPROOFED
AND LABELED (INPUT)
Standard :

1. Take photo of all the combiners


installed (Indoor/Outdoor) showing
proper waterproofing and cable
labels.
2. Labels direction should be read
away from the connector.
3. Take clear photo of installed
equipment's serial number.

Guide :
Combiner are properly and securely
installed in its approved location
BODY LABEL
based on TSSR. Apply waterproofing PROPERLY SERIAL NUMBER
on jumper connectors terminated to WEATHERPROOFED AND
it when installed outside. Combiners LABELED (OUTPUT)
should always have body labels.

Output: Highband combiner

Type: Photo
• COMBINER MUST BE SECURED/FIXED WITH METAL STRAP
• COMBINER MUST BE PROPERLY LABELED ACCORDING TO BAND AND SECTOR
• ALL CONNECTORS TERMINATION SHALL BE PROPERLY WEATHERPROOFED FIX WITH METAL STRAP
COMBINER LABELING
HIGHBAND LOWBAND
Bandpass Filter (850/900) 1 PORTS WERE PROPERLY
2
WEATHERPROOFED AND
LABELED FIX WITH METAL STRAP
Standard :
1. Take photo of all the filters
installed (Indoor/Outdoor) showing
proper waterproofing and cable
labels.
2. Labels direction should be read
away from the connector.
3. Take clear photo of installed
equipment's serial number.

Guide : 1
Filters are properly and securely
BODY LABEL SERIAL NUMBER
installed. Apply waterproofing on
jumper connectors terminated to it
when installed outside. Filters should
always have body labels. Only L850
and GU900 requires Filters.

Output: Bandpass filter

Type: Photo
ZOOMED OUT PHOTO

• FILTER MUST BE SECURED/FIXED WITH METAL STRAP


• FILTER MUST BE PROPERLY LABELED ACCORDING TO BAND AND SECTOR
• ALL CONNECTORS TERMINATION SHALL BE PROPERLY WEATHERPROOFED
FILTER LABELING
850 900
Antenna
Standard : SUBCON’S VIEW (ISDP MOBILE) CHECKER’S VIEW (ISDP WEB)

1. Take photo of each antenna height


with tape measure, mechanical and
electrical tilt, compass on top of the
antenna to show orientation/azimuth
and antenna coverage, AMB
installation for AMB overview, and
antenna weatherproofing including
unused ports.
2. Take clear photo of installed
equipment's serial number.

Guide :
Ensure antenna height, orientation,
mechanical and electrical tilt are
based on TSSR/datafil. Ensure the
antenna has a tilting bracket and
installed correctly, lock washer and
double nuts must be installed. The RF
antenna is not obstructed by other
antennas, poles or structures within
the site and can be re-panned.AISG
cable properly connected and
labeled going to RRU/SBT.

Output: Antenna installation


• RF DETAILS MUST BE FILLED OUT BY THE SUBCON
Type: Photo/text
AMB INSTALLATION IN TOWER OVERVIEW

MUST BE PROPERLY
TIGHTENED AND NO
MISSING NUTS

*AMB MUST BE FREE FROM RUST AND CORROSIONS


*AMB MUST BE FREE FROM OBSTRUCTION
*CORRECT TYPE OF FIXATION USED, MOUNTS AND BRACKETS ARE TIGHTEN
WEATHERPROOFING AND LABELS

*ALL PORTS INCLUDING UNUSED PORTS SHOULD BE PROPERLY WEATHERPROOFED


*LABELS SHOULD BE IN READ AWAY FROM CONNECTOR DIRECTION
*ANTENNA RET DEVICE AND CABLE SHALL BE PROPERLY CONNECTED AND WEATHERPROOFED
ANTENNA COVERAGE

10 % Sky 10 % Sky 10 % Sky

• Must show the antenna with Label, to identify the Site ID, Sector, Bands and the Azimuth value
• Picture shows the antenna in the middle and it is straight
• 10% of the picture is showing the sky, ensuring the picture is not tilted down
ANTENNA SHOW NO BLOCKING

SERIAL NUMBER

*MUST SHOW THE INSTALLATION OF ANTENNA SHOWING NO BLOCKAGE OR SHOWING THAT IT


CAN BE REPAN AT LEAST 30 DEG LEFT & RIGHT
ANTENNA HEIGHT

*LABELLED WITH SITE ID AND SECTOR


*MUST SHOW IN THE PHOTO MEASURING TAPE IS COMING FROM THE GROUND
MECHANICAL TILT

*Clear Picture of the value in the Inclinometer


*The position of the inclinometer is straight and perpendicular to the antenna
*Labels are clearly seen specifying the Site ID, Bands, Sector ID and value of the Tilt
ELECTRICAL TILT

*Etilt Bar must be pulled slowly to show the value


*Labels are clearly seen specifying the Site ID, Bands, Sector ID and value of the Tilt
REMOTE RADIO UNIT 1 2
DC AND CPRI ARE
PROPERLY LABELED 3 PROPERLY CRIMPED
AND INSULATED
WITH SHRINKABLE
Standard : TUBE
Take photos of RRU with :
1. Full view of RRU photo with label
2. Photo of all the cable connections
with proper water proofing,
grooming and labeling
3. RRU grounding and termination at
the ground bar.
4. Labels direction should be read
away from the connector.
5. Take clear photo of installed WITH BODY LABEL
equipment's serial number. WEATHERPROOFED AND
3
LABELED
Guide :
RRUs are properly grounded. Ensure
all bolts of the RRU are standard
supply by HT, with correct size and 5
length, properly installed and
tightened (requires at least 3 SERIAL NUMBER
protruding threads). Conduct stress
PROPERLY CRIMPED
test by pushing the RRU. All unused AND INSULATED
ports of RRU must be properly WITH SHRINKABLE
weather proofed. RRU location must TUBE
conform with the Installation
standard or approved TSSR.RRU must
not be in sideway position when *RRUS SHALL BE PROPERLY LABELED
installed behind the antenna.
*PORTS SHALL BE PROPERLY WEATHERPROOFED
Output: Remote radio unit *GROUNDED WITH CORRECT CABLE TYPE, LUGS AND ARE PROPERLY CRIMPED AND CONNECTED TO THE
NEAREST OUTDOOR EARTH BAR/ BUSBAR
Type: Photo
RRU LABELING
RRU 700 UNIT 2 RRU 1800

RRU 850

UNIT 2 RRU 2100

RRU 900

UNIT 2 RRU 2300


UNIT 1 RRU1800
Outdoor Busbar Installation
and termination
Standard :
Take photo of all the ground bar utilized.
Including indoor bus bar, RRUs grounding
termination bus bar.

Guide :
All grounding connections must be
properly tightened and utilized individual
bus bar hole with correct terminal lugs,
properly crimped and with shrinkable
tube. Grounding cable size must conform
with the installation standard.

Output: Grounding busbar With down


conductor
Type: Photo
CLAYGO
Standard :
Upload 360˚ indoor and outdoor
photo and video showing site
cleanliness

Guide :
The site is cleaned before personnel
leave. Site should be clutter free and
equipment installed should be
cleaned with no dirt on the
enclosure.

Output: Indoor and outdoor 360


photos and videos

Type: Photo/Video
END