You are on page 1of 17

ADHIPARASAKTHI ENGINEERING COLLEGE

MELMARUVATHUR-603319

Department of

ELECTRICAL AND ELCTRONICS ENGINEERING

Paper on

FLYING WINDMILLS (OR) FLYING ELECTRIC


GENERATOR (FEG) TECHNOLOGY

Submitted by

A.Narendran
narenans24@gmail.com Ph: +918124220089s

T.A.DHEVA BARATH
Dheva135@gmail.com Ph :+918608406713

R.KATHIRESAN
Barathi135@gmail.com Ph: +918124432425

1
ABSTRACT wind tunnel tests than their land-
based counterparts; that is three
High Altitude Wind Power uses times more efficiency due to
flying electric generator (FEG) simple yet constantly abundant
technology in the form of and effective high altitude wind
what have been more popularly power, available only 15,000
called flying windmills, is a feet in the air by way of
proposed renewable energy clustered rotor craft kites
project over rural or low - tethered with existing anti-
populated areas, to produce terrorist technologies like those
around 12,000 MW of electricity used on the Mexican/American
with only 600 well clustered border radar balloons.
rotorcraft kites that use only
simple auto gyro physics to High Altitude wind power offers
generate far more kinetic energy itself as a clean and more
than a nuclear plant . powerful source of power
generation than anything
According to Sky Wind Power; available on-the grid at present
the overuse of fossil fuels and and if sky wind power corp. has
the overabundance of their way, FEG technology and
radioactive waste from nuclear flying windmills will take the
energy plants are taking our lead of a more sustainable future
planet once again down a path within the decade.
of destruction, for something
that is more expensive and far Flying electric generators
more dangerous in the long run. (FEGs) are proposed to harness
FEG technology is just cheaper, kinetic energy in the Powerful,
cleaner and can provide more persistent high altitude winds.
energy than those Average power density can be as
environmentally unhealthy high as 20 kW/m2 in
methods of the past, making it a approximately 1000 km wide
desirable substitute/alternative. band around latitude 30 0 in
both Earth hemispheres. At
The secret to functioning High 15,000 feet (4600 m) and above,
Altitude Wind Power is efficient tethered rotorcraft, with four or
tether technology that reaches more rotors mounted on each
15,000 feet in the air, far higher unit, could give individual rated
than birds will fly, but creating outputs of up to 40 MW. These
restricted airspace for planes and aircraft would be highly
other aircraft. controllable and could be flown
in arrays, making them a large-
The same materials used in the scale source of reliable wind
tethers that hold these balloons power. The aerodynamics,
in place can also hold flying electrics, and control of these
windmills in place; and with craft are described in detail,
energy cable technology getting along with a description of the
ever lighter and stronger. Flying tether mechanics. A 240 kW
windmills appear to be 90 craft has been designed to
percent more energy efficient in demonstrate the concept at

2
altitude. It is anticipated that Our preferred option is a
large-scale units would make tethered rotorcraft & tethered
low cost electricity available for balloons, tethered rotor craft -
grid supply, for hydrogen variant of the gyroplane, where
production, or for hydro-storage conventional rotors generate
from large-scale generating power and simultaneously
facilities. produce sufficient lift to keep
the system aloft. This
INTRODUCTION arrangement, using a twin-rotor
configuration, has been
Two major jet streams, the Sub- described and flown at low
Tropical Jet and the Polar Front altitude by Roberts and Blackler
Jet exist in both Earth (Fig. 1). More recent
hemispheres. These enormous developments have produced a
energy streams are formed by quadruple rotor arrangement
the combination of tropical (Fig. 2). Commercialization of
region sunlight falling and Earth the quad-rotor technology could
rotation. This wind resource is significantly contribute to
invariably available wherever greenhouse gas reductions.
the sun shines and the Earth Tethered rotorcraft, with
rotates. These jet stream winds four or more rotors in each unit,
offer an energy benefit between could harness the powerful,
one and two orders of magnitude persistent jet streams, and
greater than equal rotor-area, should be able to compete
ground mounted wind turbines effectively with all other energy
operating in the lowest regions production methods. Generators
of the Earth’s boundary layer. In at altitude also avoid community
the USA,Caldeira and concern associated with ground-
O’Doherty and Roberts have based wind turbine appearance
shown that average power and
densities of around 17 kW/m2 noise. Bird strike problems are
are available. In Australia, also less. However, tethered
Atkinson et al show that 19 generators would need to be
kW/m2 is achievable.These placed in dedicated airspace,
winds are available in northern which would restrict other
India, China, Japan,Africa, the aircraft. Arrays of tethered
Mediterranean, and elsewhere. generators would not be flown
Various systems have near population centers unless
been examined to capture this and until operating experience
energy, and these include assured the safety of such a
tethered balloons, tethered configuration.
fixed-winged craft, tether
climbing and descending kites,
and rotorcraft.

3
Electricity is conducted down
Fig. 1. Photograph of early the tether to a ground station.
two-rotor prototype in flight.
The craft simultaneously
At this time, the best generates lift and electricity.
tether for the rotorcraft appears However, it can also function as
to be a single, composite an elementary powered
electro-mechanical cable made helicopter with ground-supplied
of insulated aluminium electrical energy, and with the
conductors and high strength generators then functioning as
fiber. When operating as a motors. The craft can thus
power source, two, four, or more ascend or descend from altitude
rotors are inclined at an as an elementary, tethered
adjustable angle to the on- helicopter. During any lull
coming wind, generally a 40 periods aloft, power may be
degree angle. The wind on the supplied to maintain altitude, or
inclined rotors generates lift, to land on a small groundbase. A
gyroplane-style, and forces ground winch to reel the tether
rotation, which generates could be used to retrieve the
electricity, windmill-style. craft in an emergency.

4
kW/m2, and photovoltaic cell
conversion of energy into
electricity has an efficiency
Fig. 2. Rendering of Sky several times less than that of
WindPower Corp.’s planned wind power. High power
240 kW, four-rotor densities would be uninteresting
demonstration craft. if only a small amount of

THE BEST SPOTS TO


PLACE FEGs
total power were
Based on the ERA-15 available. However, wind power
reanalysis of the European is roughly 100 times the power
Centre for Medium-Range used by all human civilization.
Weather Forecasts, we Total power dissipated in winds
calculated the seasonal-mean, is about 15 times 10W. Total
climate-zone wind power Human thermal power
density from December 1978 to consumption is about 13 times
February 1994 .Computed 10 W. Removing 1% of high
power densities in high altitude altitude winds’ available energy
winds exceed a 10 kW/m2 is not expected to have adverse
seasonal average at the jet environmental consequences.
stream’s typical latitudes and
altitudes. This is the highest High altitude winds are a
power density for a large very attractive potential source
renewable energy resource of power, because this vast
anywhere on Earth. It exceeds energy is high density and
the power densities of sunlight, persistent. Furthermore, high
near surface winds, ocean altitude winds are typically just
currents, hydropower, tides, a few kilometres away from
geothermal, and other large- energy users. No other energy
scale renewable resources. For source combines potential
comparison, Earth surface solar resource size, density, and
energy is typically about 0.24 proximity so attractively.

5
The wind speed data from across converted power’s insertion into
the globe is recorded at heights the commercial grid are
from 263 feet to almost 40,000 expected to be as much as 20%,
feet over the last 30 years, and and are included in energy cost
calculated which regions would estimates
generate the most power. described in detail below.
According to the study, Tokyo, The flying electric
Seoul, Sydney and New York generator units (FEGs)
City all sit on a goldmine of envisioned for commercial
stratospheric wind power. power production have a rated
capacity in the 3 to 30 MW
During the summer months, range. Generators arrays are
Delhi and Mumbai could also contemplated for wind farms in
benefit from sky high turbines. airspace restricted from
But unfortunately for India, the commercial and private aircraft
gusts die down in the fall and use. To supply all U.S. energy
spring, reducing the energy needs, airspace for power
density in the atmosphere. generation is calculated to
restrict far less airspace than is
DESCRIPTION OF THE already restricted from civil
PREFERRED ENERGY aviation for other purposes.
CONVERSION SYSTEM While similar in concept to
current wind farms, in most
The currently proposed cases
new tethered craft consists of flying generator arrays may be
four identical rotors mounted in located much closer to demand
an airframe which flies in the load centers.
powerful and persistent winds. When operating as an
The tether’s insulated aluminum electrical power source, four or
conductors bring power to more rotors are inclined at an
ground, and are wound with adjustable, controllable angle to
strong Kevlar-family cords. The the on-coming wind. In general
conductor weight is a critical the rotors have their open faces
compromise between power loss at an angle of up to 50 degree to
and heat generation. We propose this wind. This disk incidence is
employing aluminum reduced in various wind
conductors with tether conditions to hold the power
transmission voltages of 15 kV output at the rated value without
and higher, because they are exceeding the design tether
light weight for the energy load.Rotorcraft can also function
transmitted. To minimize total as an elementary powered
per kWh system cost and reduce helicopter as described.
tether costs, the design allows The capacity, or
higher per meter losses and generating factor calculations
higher conductor heating than account for wind lulls or storms
does during which the generators
traditional utility power must be landed. However, the
transmission. Depending on projected capacity for flying
flight altitude, electrical losses electric generators is far higher
between the tether and the than for the best ground-based

6
wind turbine sites because of the GPS/Gyro supplied error signal
persistent winds at high data.
altitudes. (1) Total craft thrust (and total
High altitude wind speeds and power output) is controlled by
other conditions are measured at simultaneously equal, collective
12 A.M. and P.M. at major pitch action on all rotors.
airports worldwide by (2) Roll control is by
radiosonde weather balloons, differential, but equal, collective
and are reported on NOAA and pitch action between the port
other government websites. It is and starboard pair of rotors.
thus possible to calculate what (3) Pitch control is by
the past capacity of flying differential, but equal, collective
generators at those locations pitch action between the fore
would have been. and aft pair of rotors.
The U.S. average (4) Yaw control, via differential
capacity factor would have been torque reaction, is by
about 80% for craft flying at differential, but equal, collective
10,000 meters. At Detroit’s pitch changes on pairs of
latitude, the capacity factor was opposing rotors.
calculated at 90%, at San
Diego’s, 71%. This compares to Ground-based wind
capacity factors of about 35 turbines experience surface
percentage for ground-based feature turbulence not present at
wind turbines operating at the high altitude. In addition,
best sites. turbulence reaction is different
Fig. 2 above and Fig. 3 for a FEG. Ground-based
below show the four-rotor turbines are, more or less,
assembly with four identical rigidly mounted on support
rotors arranged, two forward, towers. Even when flexible units
and two aft. The plan-form of and procedures are used, direct
the rotor centerlines is and gust-induced moment loads
approximately square. Adjacent are significant for these ground-
rotors rotate in opposite based facilities. Considerable
directions; diagonally European and US research and
opposite rotors rotate in the development has been directed
same direction. towards relieving load
In this particular four excursions from nearsurface
rotor assembly, craft attitude in wind gusts.
pitch, roll, and yaw can be Flying electric
controlled by collective rotor generators have a great, inherent
pitch change. No cyclic pitch advantage over equivalent
control is needed to modify the ground-based facilities in their
blades’ pitch as they rotate, as is ability to reduce gust loads. This
needed in helicopter technology. is due to tether cable flexibility,
This should help reduce both as built-in elasticity and as
maintenance costs. Rotor changeable shape (drape) under
collective pitch variation then gust conditions. This flexibility
varies the thrust developed by very significantly alleviates gust
each rotor in the format loads and torques applied to the
described below using rotors, gearboxes, etc. This

7
means that gust loads in flying force acts on the tether and
units are reduced by more than attached object, slowing their
an order of magnitude compared orbital motion. The tether's far
to ground-based turbine gust end can be left bare, making
loads. Sky WindPower Corp. electrical contact with the
has developed programs that ionosphere via the phantom
demonstrate this gust alleviation loop. Functionally, electrons
process. Section V details the flow from the space plasma into
flight performance of these the conductive tether, are passed
flying generators. through a resistive load in a
ELECTRODYNAMIC control unit and are emitted into
TETHER the space plasma by an electron
emitter as free electrons. In
Tether is the connecting media principle, compact high-current
between the turbines up in the tether power generators are
air to the grid on the surface. possible and, with basic
Electrodynamic tethers are long hardware, 10 to 25 kilowatts
conducting wires, such as the appears to be attainable.
one deployed from the tether
satellite, which can operate on ELECTRICAL SYSTEM
electromagnetic principles as DETAILS
generators, by converting their
kinetic energy to electrical Flying electric
energy, or as motors, converting generators need to ascend and
electrical energy to kinetic remain aloft for short periods on
energy. Electric potential is grid-sourced energy. In low-
generated across a conductive wind conditions, only a small
tether by its motion through the proportion of output rating as
Earth's magnetic field. The grid sourced energy is required
choice of the metal conductor to to raise or maintain the craft
be used in an electrodynamic aloft. Voltages at the terminals
tether is determined by a variety of both the generator/motor and
of factors. Primary factors at the grid interface need to be
usually include high electrical kept within designed tolerances
conductivity, and low density. and/or be adjusted by timely
Secondary factors, depending on voltage regulation.
the application, include cost, In a national regulated
strength, and melting point. electricity market, such as that
An electrodynamic tether found in Europe and elsewhere,
is attached to an object, the a System Impact Study (SIS) is
tether being oriented at an angle required to connect a new
to the local vertical between the generator to the grid if the
object and a planet with a generator’s capacity is above a
magnetic field. When the tether minimum level, e.g. 5 MW.
cuts the planet's magnetic field, Even non-dispatchable
it generates a current, and “embedded generators“ require
thereby converts some of the Grid System Impact
orbiting body's kinetic energy to Assessments. The generator
electrical energy. As a result of proponent usually pays for the
this process, an electrodynamic generator-to-grid network

8
connection. Land and sea The latter, being developed by
locations for generation from equipment suppliers such as
renewable energy sources, ABB, Siemens, Mitsubishi, etc.,
especially wind energy, are often would allow polymeric cable
remote from the existing grid, stators and tether voltages at say
hence, connection costs are 33 kVac or more. Grid
often 50% of the total interfacing would then be easier
investment for new generating at bulk energy levels.
capacity. Also where a The jet-stream location
renewable energy source can drift north and south, so
generator is not n-1 reliable for seasonal mobility from one
availability, the Network prepared site to another could be
Connection Contracts usually a feature of flying generators’
include the costs of back-up grid utilization and optimization.
supply contingencies. These This could be advantageous in
relate to network charges when seasonal summer/winter
the renewable generator is not demand-side management
supplying. through peak-matching
Flying electric generator placement or
generators at altitude will have a relocations. This would include
relatively high availability, matching seasonal peaks for
around 80%. Reliability and rural industries, such as grape
peak premium sales could be processing, cotton harvesting,
enhanced by a link to a pumped and irrigation to urban air-
storage facility for off-peak conditioning etc.
filling/storage and peak-release Because arrays of flying
energy sales and generators could move north or
delivery. Energy could be stored south to follow seasonal shifts in
as hydrogen gas produced from wind patterns or power demand,
electrolysis, or as water it could be advantageous to have
pumped-back and re-released for “plug-in” flying generators at
hydroelectric generation. pre-arranged sites along an
Conventional ground- existing grid 33 kV, or more,
based wind energy systems overhead feeder with minimal
harvest only about 30% interfacing. This would use, for
availability. Flying electric example, a HV Live Line HV
generators, in single units of 20 Bypass cable, sometimes called
MW or more, can achieve about Temporary cable, with a mobile
80% availability with suitable or transportable High Voltage
sitting at land or sea locations. Generator switchyard circuit
These generators at altitude Breaker /metering unit.
involve power transmission over If the tether arrangement
lengths of between 4 and 8 km. were to contain three
Flying generator/tether voltages conductors, two could form the
between 11 kV and 25 kV ac single-phase circuit, while the
could be used on units of 30 third could be the ground wire
MW at the most extreme and control cabling function.
altitudes. Also there are recent Three-phase balance is then
modern innovations, which use achieved by adding other nearby
powerformers/motorformers. generator outputs to form single-

9
phase combinations for grid specific grid connections could
connection. Alternatively, if be an important SIS review
necessary, a transformer with item. A higher fault level at the
OLTC could be used, similar to connection site is desirable for a
that used for monoplex or 50 large motor start up. Generator
kVac duplex rail electric traction and tether performance depend
supply. This would be similar to on a good lightning storm
a rail traction supply transformer detection system. Surge
of 50 MVA and 132 kV three protection schemes and
phase to 25 kV ac positive and hardening of the control systems
25 kV ac negative to centre tap are also under examination.
earth.
When using a shipboard FLIGHT CONTROL USING
site, fixed ocean site, or a site GPS AND GYRO DATA
adjacent to a water-reservoir
which is remote from the desired Very accurate control is needed
FEG ground-surface connection to precisely maintain a desired
location, then the use of HVDC position in the sky. GPS with
on tethers, with gyroscopes is an ideal way to
surface/submarine cabling, provide the reference data
should be considered in necessary to provide this
combination with a HVDC control.
voltage The Global Positioning
motorformer/powerformerTM System (GPS) consists of a
design. In addition, a unit’s DC constellation of 24 satellites that
motor/generator commutation provide a continuous navigation
by conventional brushes might capability to users at any
be facilitated by more modern location on (or near) Earth in all
electronic switching or by weather conditions. With this
triggered Vacuum Gaps (TVG). system, currently operating with
Where an AC interfacing 29 satellites, real-time, three
transformer, or a HV AC /DC dimensional position
Converter Station (usually with information with accuracies on
an included transformer) is the order of 5-10 m can be
required for grid interfacing achieved.
connectivity, the economics of Main error sources for
scale would encourage more the system include signal
multiple-unit connections. propagation effects through the
A 60 MW to 150 MW atmosphere, satellite orbit and
grid connection composed of timing errors, and GPS receiver
three 20 to 50 MW airborne noise and signal reflection
units with a powerformerTM, or (multipath). When used in
HVDC AC/DC connection, can differential mode, where
perform as a synchronous measurement corrections are
condenser, thereby adding AC computed at a GPS reference
grid stability advantages in the station sited on a known
SIS. This will depend on grid location, accuracies can be
siting. improved quite easily to within a
Starting and retrieval few meters (DGPS).
characteristics of flying units at

10
Although generally used of the signal multipath, and
for positioning and navigation, antenna separation (wider
GPS can also be used for spacing yields higher attitude
platform attitude determination accuracies – Fig. 5). For the
and control. If three or more FEG, multipath could occur
GPS receivers and antennas are through the reflection of the
mounted on a platform, such as signals off the structure itself.
an FEG, the GPS carrier phase However, when antennas are
data can be used to directly separated by over 5 m on the
estimate the roll, pitch, and FEG, attitude accuracy should
heading of the platform in real- be better than 0.25 degree with
time at a rate of 1-20 Hz [18]. multipath present, which is well
The attitude parameter within the required attitude
accuracy is primarily a function control specifications.

hovering, some GPS satellites


Fig.5. Relationship between may be obscured since the FEG
the achievable GPS-derived may block reception signals
along the line-of-sight. Tests
heading and pitch accuracy and show that attitude parameters
antenna separation can still be estimated up to at
Two other factors must least a 45 degree tilt, however, a
be considered when using GPS gyroscope used as
for attitude determination and an auxiliary attitude sensor,
control on the FEG. One is the augments GPS availability and
rigidity of the structure itself. reduces noise. This has been
Antennas with maximum implemented for many
separation increase the applications, and overall
achievable accuracy, but accuracy is a function of the
function best with antennas gyro sensor characteristics.
located on a rigid frame. A
second factor is system DETAILS OF A 240 KW
performance during significant DEMONSTRATION CRAFT
FEG nose-up angles. These
angles range from 0 degree Sky WindPower Corp.
when hovering up to 45 degree has completed the design for a
when generating. While 240 kW demonstration craft.

11
Fig. 2 is an isometric view of ground facility is configured for
this craft. a DC supply to and from the
Two units will platform. The motor/generators
demonstrate the commercial are series connected.
viability, or otherwise, of the The craft’s rated output
flying generator concept. These is developed at an 18.4 m/s wind
craft have four, two-bladed speed at an altitude of 15,000
rotors turning in paired counter- feet (4600 m). The 11.5 m/s
rotation as described above. The autorotation speed is at the same
rotors are 10.7 m in diameter altitude. The power consumption
with solidity of 5%, and the un- in no wind (hover) at 15,000 feet
twisted blades are of (4600 m) is estimated to be
conventional construction. around 75 kW. Rotor speeds are
Collective pitch control on the in the range of 130 to 300 rpm.
rotors will be via electric The craft in this demonstrator is
actuators. The craft is designed designed to withstand a wind of
for operations up to 15,000 feet 35 m/s at 15,000 feet (4600 m).
(4600 m). Throughout the operating
The rotors are connected envelope the craft’s nose-up
to four separate gearboxes, attitude varies in the range 10
which drive four and 45 degree. At no time during
motor/generator units supplied these operations does the blade
by AC Propulsion. These incidence on the retreating blade
electrical machines are of high exceed acceptable values at the
armature speed to ensure a conventional reference station,
satisfactory power-to-weight while tip Mach numbers never
ratio. They are also electrically exceed about 0.6.
linked to ensure that rotor Finally, there is some
speeds do not vary with one merit in the view that the best
another. return on investment of these
Typical armature speeds are craft will be dependent on an
24,000 rpm. The four power optimal, operating altitude. At
units are mounted in an low altitudes the average wind
elementary, low-drag fuselage of velocity wanes, while at higher
fiber composite construction. altitudes, adjacent to the jet
The all-up weight of each craft stream core, the costs produce a
is estimated at around 1140 lbs less than beneficial return,
(520 kg). because of the need for a higher
The electro-mechanical transmission voltage as the
tether is designed to transmit altitude increases. Thus it will be
240kW at a voltage of 15kV. necessary to find the best return
The electrical transmission from an investment as a function
efficiency is 90%. The tether has of the maximum operating
two insulated aluminium altitude.
conductors embedded in a This aspect will be developed
Vectran fiber composite. The and confirmed over 12 months
tether’s specific weight is of flights planned during the
around 115 kg/km at a diameter demonstration program.
of 10mm. A sample has been
constructed. The electrical

12
COST AND PERFORMANCE per 3.4 MW. The balance of
PROJECTIONS AT THE station costs for the 100 MW
LARGE SCALE array, including site preparation,
facilities and equipment, spare
A. Scalability Considerations parts and construction is
As discussed in section $4,210,000. Taken together
IV. , the tethered rotorcraft is these initial capital costs come
inherently scalable in size and to $71,200,000 per 100 MW.
output, from small prototype
configurations of below 240 kW, C. Performance and Net
through commercially viable Annual Energy Production
systems with competitive costs Three design sites were
of energy, in the range of 3MW chosen for analyzing the output
to 30 MW per craft. Larger sizes of the 100 MW array, Topeka,
are more economical and may Kansas, Detroit, Michigan and
utilize more than four rotors to San Diego, California. Topeka is
maintain economy and a "Great Plains" site, Detroit is a
manageability of materials. site where a great deal of energy
In this section we is used, and San Diego is
analyze cost and performance of a site where capturing power
a four rotor, 3.4 MW (platform- from the wind is not normally
rated) configurations as might thought to be practical.
be deployed in an array over Net Annual Energy
various sites in the U.S. Because Production kWh/yr is
of losses described earlier, the determined by multiplying rated
actual output after conditioning power by a site capacity factor.
would be about 20% lower. The Capacity factors for FEGs of the
3.4 MW size was chosen proposed design are based on
because it is large enough to wind statistics provided by
provide competitive economics NOAA radiosonde readings for
in a four-rotor configuration, major airports near the design
and a rotor design that is within sites, normally taken daily at
the scope of currently available noon and midnight. FEGs are to
methods and materials. be flown at the most efficient
altitude for prevailing wind
B. Weights and Costs conditions, and capacity factor is
For cost illustration calculated in the normal manner.
purposes, we use a 100 MW In making these
array, comprised of 3.4 MW calculations we have taken into
FEGs. The cost estimates are account the projected operating
based on 250 FEGs/year characteristics of the 3.4 MW
production rate assuming prior design through the range of
production of 150 FEGs, in altitudes up to 9,000 meters.
accordance with NREL Over the current range of
guidelines. A 3.4 MW platform- interest the rated wind speed has
rated craft is estimated to weigh been
21,000 lbs (9500 kg) and cost approximated to the linear
$1,360,000. Adding ground variation (4), while the air
systems and production profits density varies according to
brings the total to $2,260,000

13
NACA Standard Atmosphere components are anticipated to
values. require replacement at 10 years
Capacity factors have and 20 years. Tether longevity is
been computed for the three a
design sites using software we risk. Replacement cost is
developed, from data estimated at 80% of the initial
downloaded from NOAA. The capital cost for the whole
data is for the year starting system. Expressed in per kWh
September 20, terms, the AOE for the Topeka,
2000 and ending September 21, Detroit, and San Diego sites are
2001. estimated at $0.0102/kWh,
V = 14m/s + 5.7m/s * $0.0103/kWh, and
H/10000m $0.0129/kWh,
respectively.
Where,
V Required wind speed in TETHERED BALLOONS
meters per second to operate at
rated capacity, and
H is Altitude in meters. AIRBORNE WIND
TURBINE
Capacity factors for
Topeka, Detroit, and San Diego
are 91%, 90% and 70%,
respectively. As a reserve
against storms, maintenance and
mechanical problems, we
assume 10% downtime. This
gives Net Annual Energy
Production figures of 581
GWh/yr, 575 GWh/yr and 447
GWh/yr, respectively for a 100
MW array at each of the three
sites.

D. Projected Cost of Energy

Annual Operating Airborne wind generator


Expenses (AOE) include Land
Lease Costs (LLC), Operations An airborne wind turbine is a
& Maintenance (O&M) and design concept for a wind
Levelized turbine that is supported in the
Replacement/Overhaul Costs air without a tower. Airborne
(LRC). AOE projections are wind turbines may operate in
necessarily subjective, since no low or high altitudes; they are
plant like this part of a wider class of airborne
currently exists. O&M costs are wind energy systems (AWE)
derived from an $82,000/yr addressed by high altitude wind
estimate for a 3.4 MW FEG, power. When the generator is on
multiplied by 29.4 FEGs/100 the ground, then the tethered
MW plant. Life-limited aircraft need not carry the

14
generator mass or have a covered. Some schemes require
conductive tether. When the a long power cable.and, if the
generator is aloft, then a turbine is high enough, an
conductive tether would be used aircraft exclusion zone. As of
to transmit energy to the ground 2008, no commercial airborne
or used aloft or beamed to wind turbines are in regular
receivers using microwave or operation.
laser. Airborne turbine systems
would have the advantage of Magenn Power Inc. is taking
tapping an almost constant wind, orders for their first commercial
without requirements for slip product, a 100kW device with a
rings or yaw mechanism, and price tag of $500,000. (MARS-
without the expense of tower Magnenn Air Rotor
construction. Kites and System(Tethered Balloons))
'helicopters' come down when
there is insufficient wind; The Magenn machines are
kytoons and blimps resolve the large ridged dirigibles that rotate
matter. Also, bad weather such on their tethers. The machines
as lightning or thunderstorms, require lots of helium to stay
could temporarily suspend use aloft and they are designed to
of the machines, probably work between 500 - 1000 ft.
requiring them to be brought elevation.
back down to the ground and

Fig: Magenn Air Rotor System (Tethered Balloon technology


(MARS) based FEG)

15
Magenn is targeting the device intrusion and no bird
as an alternative to diesel strikes.
generator sets for remote and  FEG wind farms would
emergency power applications. give capacity
Relatively low-level operation (generating) factors
of this systems means that it can around three times
operate just about anywhere greater than that from
without regard to airspace conventional wind farms.
restrictions.

ESTIMATED COSTS:

Sky Windpower estimate that DISADVANTAGES


their technology will be capable
of producing electricity for  Restricted airspace for
$0.02 per KWh, while a system airplanes to fly.
of raising a kite to a high  Not suitable for highly
altitude while turning a populated areas, unless
generator on the ground, and there are adequate safety
then changing its shape so that it measures provided.
can be drawn back down with  Seasonal variations in jet
less energy than it produced on streams speed across the
the way up, has been estimated globe can create dull
to be capable of producing periods for electricity
electricity for $0.01 per KWh- production by FEG.
both numbers being significantly
lower than the current price of CONCLUSION
non-subsidized electricity.
It has been shown that flying
electric generators can harness
ADVANTAGES & the powerful and persistent
DISADVANTAGES OF FEG winds aloft to supply electricity
for grid connection, for
hydrogen production or for
hydro-storage. Globally, upper
ADVANTAGES atmospheric winds provide an
enormous resource for this
 Environment friendly application. The environmental
 FEG technology is just impacts at altitude are minimal
cheaper , cleaner and with virtually no visual, or noise
have more efficiency. intrusion and no bird strikes.
 Low cost availability of The proposed systems lead
electricity. logically to rural/remote area
 FEG’s are unaffected by installations in regions of
surface feature restricted airspace. Full-scale
turbulence. facilities, using individual FEG
 The environment impact units of rated power around 30
at high altitude are MW, could easily form wind-
minimal with virtually farms equivalent in output to
no visual or noise regular coal, gas and nuclear

16
facilities. These wind-farms
would give capacity (generating)
factors around three times
greater than that from
conventional wind-farms. The
estimated bulk electricity cost
for the power so produced is
estimated to be of the order of
$20/MWh. High altitude wind
power is not science fiction. It
depends on currently available
technologies and engineering
knowhow, building on decades
of experience with wind turbine
and gyroplane technologies.
Harnessing high altitude wind
energy, using a combination of
essentially existing technologies,
appears to be thoroughly
practical and suggests that this
energy source can play an
important part in addressing the
world's energy and global
warming problems.

17

You might also like