BILL OF QUANTITIES FOR EQ1,EQ2,EQ3 & MME

COLLECTION TANK.
Date 5/9/2019 R3
Date 5/4/2019 R2
Date 5/3/2019 R1
Date 4/30/2019 R0

SR.NO ITEM DESCRIPTION TOTAL

1 Vertical Walls A+B :-


Concrete (M30) 125.40 m3

2 Vertical Wall C :-
Concrete (M30) 28.80 m3

3 Raft :-
Concrete (M30) 141.76 m3

4 PCC M-10 (1:3:6) :-


Concrete Vol. of concrete 26.51 m3

5 Rubble Solling :- 230mm Thick 84.00 m3

6 Sand Filling :- 300mm Thick 106.05 m3

SUMMARY

WASTAGE TOTAL
ITEMS UNIT TOTAL 5%
CONCRETE (M-30) m3 295.96 14.80 311 m^3
CONCRETE (M-10) m3 26.51 1.33 28 m^3
RUBBLE SOLING m3 84.00 4.20 88 m^3
SAND FILLING m3 106.05 5.30 111 m^3
SR.NO ITEM Description Dia Length Nos Kg/m Total

Wall A & B
1 Vertical Bars in wall Inner Perimeter 12T 4.90m 409 0.89 1783.649
Outer Perimeter 12T 4.90m 421 0.89 1835.981

2 Extra Vertical Bars in wall Inner Perimeter 12T 1.60m 409 0.89 582.416
Outer Perimeter 12T 1.60m 418 0.89 595.232

3 Horizontal Bars in walls Inner Perimeter 10T 81.80m 15 0.62 760.74


0-2m part Outer Perimeter 10T 83.60m 15 0.62 777.48

4 Horizontal Bars in walls Inner Perimeter 12T 81.80m 10 0.89 728.02


Rest part Outer Perimeter 12T 84.20m 10 0.89 749.38

5 Extra Horizontal Bars Corner 16T 24.00m 10 1.58 379.2


Rest part Central 16T 32.40m 10 1.58 511.92

Wall C
6 Vertical Bars in wall 1st face 12T 4.90m 120 0.89 523.32
2nd face 12T 4.90m 120 0.89 523.32

7 Extra Vertical Bars in wall 1st face 16T 1.60m 120 1.580 303.36
2nd face 16T 1.60m 120 1.580 303.36

8 Horizontal Bars in walls 1st face 10T 27.60m 20 0.62 342.24


0-2m part 2nd face 10T 27.60m 20 0.62 342.24

9 Horizontal Bars in walls 1st face 12T 27.60m 10 0.89 245.64


Rest part 2nd face 12T 27.60m 10 0.89 245.64

10 Extra Horizontal Bars 1st face 12T 10.80m 10 0.89 96.12


Rest part 2nd face 12T 10.80m 10 0.89 96.12

11 Footing Raft 450mm thk. Along X 12T 35.30 52 0.89 1633.68


Along Y 12T 10.40 52 0.89 481.31
Along X 8T 35.30 52 0.40 725.06
Along Y 8T 10.40 52 0.40 213.62

12 Footing Raft 300mm thk. Along X 12T 30.10 52 0.89 1393.03


Along Y 12T 5.20 302 0.89 1397.66

13 Footing Raft 300mm thk. 8T 2.30 80 0.40 72.68


Extra Bar

12 Haunch 8T 0.40 848 0.395 133.984

17776 Kg

Total Reinforcement including 5% wastage 18665 Kg