Gomez Development

• Development Considerations

• Rowan Midland

• Mooring Design

• Subsea/Pipeline Installation & Commissioning

• Lesson’s Learned

1
Gomez Development
Key Features

• Gross Proved Reserves: ~100 Bcfe


• Gross Probable Reserves: ~50 Bcfe
• ATP Working Interest: 100%
• Well Test: 134 MMcfe/d
• Planned Wells: 5+

2
Gomez Development
Development Concept

• Leased Semi-Submersible Drilling Rig

• Production Modules on Aft Pipe Rack

• Pre-installed Mooring

• Produce Two Wells Initially

• Thru-tubing Well Intervention

3
Gomez Development

4
Gomez Development
Rowan Midland

• Earl & Wright Design

• Launched 1976

• Excellent Remaining Fatigue Life

• Adequate Variable Deck Load

• Limited Drilling Marketability

5
Gomez Development
Rowan Midland in Drydock

6
Gomez Development
Rowan Midland in Drydock

7
Gomez Development
Rowan Midland at Sabine Pass

8
Gomez Development
Rowan Midland Tow Out

9
Gomez Development
Rowan Midland on Tow

10
Gomez Development
Mooring Design

• 12 Point Mooring for 100 Yr Storm

• Polyester to Conserve VDL

• Utilize Existing 8 Wire Windlasses on Midland

• Install 4 New Chain Jacks & Fairleads

• Load Sharing Between Lines

11
Gomez Development
Mooring Permitting

• 1st Permanent use of SEPLA anchors

• Use of 6 Strand Wire Rope

• 3rd Permanent Installation to use Polyester

12
Gomez Development
Mooring Installation
• Availability of US Flag Vessels

• Use of Foreign Flag Vessels

• Jones Act Restrictions

• Vessel to Vessel Transfer Offshore

• SEPLA Follower & Embedment

• Load Test on SEPLA


13
Gomez Development
Mooring Inspection & Maintenance

• Special IMRR for Polyester & SEPLA

• Installation of Polyester Test Specimens

• Scheduled Replacement for Wire Rope

• Scheduled ROV Inspection

14
Gomez Development
Mooring Pattern

15
Gomez Development
Mooring Configuration

16
Gomez Development
Normand Cutter

17
Gomez Development
Normand Cutter

18
Gomez Development
Normand Cutter

19
Gomez Development
SEPLA Inserted into Follower

20
Gomez Development
BallGrab Connector

21
Gomez Development
Assembed BallGrab on Deck

22
Gomez Development
SEPLA Anchor

23
Gomez Development
SEPLA Follower

24
Gomez Development
Loading SEPLA into Follower

25
Gomez Development
Launching Follower

26
Gomez Development
Launching Follower

27
Gomez Development
Flooded Polyester Hawsers

28
Gomez Development
Polyester Vessel to Vessel Transfer

29
Gomez Development
Spooling Polyester in Maersk Assister

30
Gomez Development
Subsea/Pipeline Installation & Commissioning

• 10” Gas Export Line

• 8” Oil Export Line

• Weather Downtime During Commissioning

• Pigging Problems

• Dewatering Problems

31
Gomez Development
Field Layout

32
Gomez Development
Pipeline Route

33
Gomez Development
Midnight Express Installing Umbilicals

34
Gomez Development
Midnight Express Installing Umbilicals

35
Gomez Development
Hydraulic Umbilical

36
Gomez Development
Weather Downtime

Weather Downtime

100
80
60
40
20
0
Jan Feb Mar
37
Intrepid Express Defender
Gomez Development
New Pigs – 10” Gas line

38
Gomez Development
Remnants - Pigging 10” Gas line

39
Gomez Development
Gauging Pig - 10” Gas line

40
Gomez Development
Pigging 8” Oil line

41
Gomez Development
Remnants of Tracker Pig

42
Gomez Development
Pressure Trace – Pigging 8” Oil line

43
Gomez Development
Pressure Trace – Pigging 8” Oil line

44
Gomez Development
Missing Pig

45
Gomez Development
Rowan Midland on Location

46
Gomez Development
Lessons Learned

• Avoid Subsea Installation in Winter

• Dewater Pipelines from Shallow to Deep

• Avoid Scraper Pigs with Reeled Pipe

• High Water Volume Moves Stuck Pigs

• Older Rigs can be economically converted to FPF

47
Gomez Development
Lessons Learned

• Successful Fast Track Deepwater Project

• Sanction to Production in 16 months

• Ability to Expand to 6 Wells

• Currently Working on Increasing Capacity

• Current Deepwater Development favors Dry Trees

48