Professional Documents
Culture Documents
result, substantial sums of money were allocated and spent during the
drive the pace of energy demand are population and domestic product.
taken the country from 300 million people in 1947 to over one billion
23
people today is putting a strain on the environment, infrastructure,
since 1991. The annual GDP (gross domestic product) growth rate has
risen from 4.4% in 2000/01 to 8.1% in 2003/04. The high growth rate
the industry and service sectors also maintained the momentum with
the GDP from these two sectors accelerating from 6.4% and 7.1%,
growth during the same period h a s declined from 23.86% for 1981-91
India 2001). The cumulative effect of the above has led to an increase
24
capita commercial primary energy consumption in India is about 350
2004b).
All over the world, the ability to generate and consume electric
year 2003 is 2548 KWHR/Year. During 2003, the average per capita
and primary energy while the poorest use only 5 percent. "World
achieve these.
25
needs to be added by 2012 (i.e.) by the end of the 11*^ Plan, to bridge
the gap between demand and supply of power. This would necessitate
and distribution.
ENERGY SOURCES
26
in the country are coal, hydro-power, lignite, oil and natural gas and
nuclear power.
COAL
India. The coal reserves in the country are estimated to be around 234
billion tonnes. About 86 percent of the coal reserves are in the non-
and consumes about 76 per cent of the total coal dug out. With the
over 70 per cent of the installed capacity in the country, the total
energy matrix for a long time, accounting for nearly 50% of the total
accounting for 8.6% of the world total. However, only 17.96 billion
2002). The domestic demand for coal is estimated to grow from 340.1
27
2 0 0 6 / 0 7 and 5 1 5 M T i n 2011/12, thereby leaving a gap of 55 MT In
power could have been more, if only the availability of coal had been
the coal supplies are from Coal India Limited (CIL) a Govt, of India
which over 30% was taken by NTPC and about 60% by SEB's.io
Coal Reserves
billion tonnes. Bulk of the coal reserves lie in the non-coking category
and coking coal reserves are rather limited. The coal reserves are also
28
states of Bihar, Orissa and West Bengal. Other States with sizeable
coal reserves are Madhya Pradesh (17.5%) Andhra Pradesh (6.7%) and
Maharastra (3%).
TABLE 2.02
PRODUCTION OF COAL
TOTAL COST OF
YEAR
PRODUCTION [M.Ts.l
1997-1998 301.34
1998-1999 313.68
1999-2000 323.56
2000-2001 333.77
2001-2002 346.56
2006-2007 473.00
2011-2012 572.00
29
TABLE 2.03
COAL PRODUCTION
India produced 66.8 million tonnes of coal during the period, three
percent more than 64.5 million tonnes produced in the same period of
2002.13
programme for the next three to four decades contributing more than
the year 2010. In view of limited known reserves of oil and natural gas
sector alone would require about 550 million tonnes of coal by the
30
year 2010. In order to build a coal production capacity of this order,
cent and in the Indian context, it is 60 per cent. The dominant role of
over long distance will also have to be adopted as a policy and Coal
The Indian coal obtained from open cast mining is one of the
becomes the costliest. The additions like royalty, cess, railway project
costly as the basic price. This calls for revision of the tariff structures
31
HYDRO-ELECTRICITY
flow from their sources in mountains and hills, they provide plenty of
M.W., i.e. 37.1 per cent was hydro power. The first few years of
1962-63. Unfortunately this was the last year when it had the
predominant share, i^
extremely essential for the reliability, and the higher its capacity the
system and besides it led to over reliance on thermal and gas based
32
stations. In fact in some countries in the west, the share of hydro
(41%) and Brazil (31%) the utilisation of only 17%) of its hydro
India. 21
Gangetic plain and the Southern Peninsula which offer plenty of scope
development varies from region to region and from State to State . The
33
TABLE 2.04
34
If the hydro thermal ratio has to be improved from the present
Taking this into account, there are some positive signs. Development
concerned. 28
LIGNITE
35
Nadu and the remaining lignite deposits are located mostly in
blocks for future exploitation. In the last five years, large potential for
lignite across the state h a s come to light in Bahur block North East of
Cuddalore District.
of the planning commission and the Ministry of coal. The last decade
tonnes. 31
36
TABLE 2.05
Rajasthan 2,954.26
Gujarat 1,769.76
Kerala 108.30
Total 35.362.21
Table 2.05 shows that Tamilnadu & Pondicherry account for
86% of the total lignite reserves in the Country. In Tamil Nadu, the
District of Cuddalore.^^
stations are:
37
In view of the inflammable nature of lignite, it would not be
Bed Combustion (FBC) technology, but this will add to the cost.
distances from the coal mines. The additional cost of lignite based
partly off-set by the house expenses in the movement of coal over long
discrete strata and there are difficulties in mining the deeper ones
this technology and try to evolve new methods for mining the deeper
strata.33
38
recoverable reserves of crude oil and natural gas as on 31 March 2003
were 740 MT and 920 BCM (billion cubic metre), respectively. The
2004 was 125.97 MTPA (million tonnes per annum). The production of
gas demand is growing at the rate of about 6.5% per year, and it is
Despite such high growth rate, the Indian natural gas market is still
39
international average of 24 percent. The power sector is one of the
• NUCLEAR POWER
nuclear power the fast breeder test reactors (FBR) will be developed. A
40
the country and further improvements are being carried out. The
2020.35
Electricity Boards in various parts of the country in the early 50s and
with the advent of the Five Year Plans, a significant step was taken in
41
into force providing for the administrative and legal frame work for the
organization of power sector. This Act paved the way for the formation
like the Bhakra Nangal, DVC, Hirakund and Chambal Valley were
taken up. The emphasis in the Second Plan was on the basic and
During the Third Plan the accent was on extending power supply to
rural areas. The significant developments during this phase were the
planned programme. The three Annual Plans that followed the Third
the Third Plan. The Fourth Plan (1969-74) envisaged the need for
power. This period also saw major structural changes in the price of
42
petroleum and crude which were mostly Imported at that time. The
During the Fifth Plan i.e., 1974-79, the Centre got itself involved
supplement the efforts at the State level and took upon itself the
the Fifth and Sixth Plans. Moreover, the first half of the Seventh Plan
added was about 21,500 MW, while in the Eighth Plan, it came to only
43
about 15,000MW. During the Eighth Plan period, capacity created in
privatisation of distribution.
The need for these changes h a s certainly not come about from
within the SEBs- they are simply being forced on the Boards by the
World Bank.39
The actual addition to capacity during the Eight Plan period was
only 16423MW, or a little over half the target. This was significantly
Plan Period.4o
remained acute during the Eighth Plan, the power supply position did
44
against a PLF of 55.3% during 1991-92, the average PLF during the
Power Sector. It would appear that there was a virtual 'gold rush' into
the Power Sector, through the capacity addition that eventually came
225MW).
45
TABLE 2.06
Tenth
Seventh Plan Eighth Plan Ninth Plan
Sources Plan
Total Actual Total Actual Total Actual Proposed
Thermal 15,999 17,093 20,156 13,555 29,545 15,477 25,417
Plan Performance."^3
major public and private sector power projects across the country,
which suggest that the bulk of the capacity additions by the private
46
sector would be constrained due to issues related to payment security,
TABLE 2.07
47
TABLE 2.08
Economy can be gauged from the fact that substantial resources have
been earmarked for its development since early fifties. From a mere
Rs.260 crores in the First Five Year Plan allocation to this sector it
went upto Rs. 19,265 crores in the Sixth Plan and then to Rs.34,274
48
In 1998, it was 89, 167 MW, while in 2003, it was 107, 973MW. The
crores in the 9^^ Plan to Rs.2,36,625 crores during the lO^h Plan.47
power and coal based thermal power have been the miain sources of
that h a s taken place, the power supply industry has been under
49
The transmission and distribution net work h a s also increased
2003.52
MW in 2003.53
renewable energy resources. Coal, oil, and natural gas are the three
50
a significant change in the pattern of supply and consumption of
TABLE 2.09
traditional sources of energy like fuelwood, dung, and crop residue for
about 65% is met through fuelwood. The energy demand for non-
51
commercial fuels is estimated to rise overiiime from 151.3 MTOE in
2006/07 to 170.25 MTOE in 2011/12. Over the years India has done
well in creating new generating capacities but stiU Indian Power Sector
capacity needs to be added by 2012 to bridge the gap. The total energy
concern that in spite of the burgeoning demand for power, the annual
per capita consumption of India about 350 kWh is among the lowest
52
TABLE 2.10
PER CAPITA GDP & ELECTRICITY CONSUMPTION OF
DIFFERENT COUNTRIES^s
Per Capita
Per Capita
Elect.
Country GDP(S) PCEC/PCGDP
Consumption
(PCGDP) (PCEC)
Sri Lanka 3250 319.982 0.098
Guatemala 3700 379.511 0.103
Philippines 3800 465.995 0.123
Indonesia 2900 383.012 0.132
Pakistan 2000 411.851 0.206
Swaziland 4000 831.412 0.208
India 2200 502.848 0.229
Egypt 3600 946.767 0.263
China 3600 955.753 0.265
S5nia 3100 1083.734 0.350
Zimbabwe 2500 923. 516 0.369
Jordan 3500 1418.807 0.405
Iraq 2500 1119.661 0.448
Jamaica 3700 2363.639 0.639
Uzbekistan 2400 1692.148 0.705
53
gap between the required and the available electricity was
PRESENT POSITION
54
INDIAN POWER SECTOR - SUPPLY SIDE
power.
of power for completion during 10^^ and the 11^ Five Year Plans while
55
43000MW additional Power generation capacity has been planned for
the IQth plan 64,000MW target h a s been fixed for the 1 l^h plan.
The central sector was slated to add 21,000MW in the 10^^ Plan
and 27000MW in the 111^ Plan. The State sector will ad 8000MW and
llOOOMW respectively during the 10*^ and 11** plans. The target for
THE FUTURE
the current level of 325 MTOE by 2030 (lEA 2002). Such a growth in
56
TABLE 2.11
1997/98 55 35 7 2 1
2001/02 50 32 15 2 1
2006/07 50 32 15 2 1
2010/11 53 30 14 2 1
2024/25 50 25 20 2 3
2.11. Though the share of coal is expected to decline from 55% to 50%
matrix. The share of natural gas and nuclear source is also expected
consumption by 2006/07.
57
Furthermore, going by the estimated energy demand figures
provided in the Tenth Plan document (Table 2.12), the demand for
end of the Tenth and Eleventh Plans. The demand for coal is expected
of the demand for coal is expected to come from the power sector,
new clean coal technologies for power generation have made coal a
TABLE 2,12
58
STRENGTHS AND WEAKNESS OF THE POWER SECTOR
billion tones can meet the country's coal requirement for 250 years at
that Indian demand for energy will remain high and coal alone can
sustainable basis the Indian coal industry can hope to flourish for
59
1. VAST HYDRODELECTRIC POTENTIAL
For the past three decades, hydropower has had a sub optimal
40:6063 and add about 25,000 Mw each in the Eleventh and Twelth
Plan Periods. This is over and above the target of adding 14,000 MW
during the Tenth Plan Period. A vast hydro potential exists in the
exploited so far.
TABLE 2.13
UNTAPPED HYDRO POTENTIAL 64
Potential Share in
No. of at 60 total
River basin
schemes percent
PLF(MW) (%)
60
EMERGENCE OF STRONG AND GLOBALLY COMPARABLE
CENTRAL UTILITIES (NTPC POWER GRID)
Over the last Twenty Five Years. National Thermal Power
largest power utilities in Asia, known for its speedy project execution
with achieving all targets set for it by the Government of India. In the
Asia week survey for the year 2001, of the top 1000 companies of the
perspective transmission plan for short, medium and long term for
61
LARGE POOL OF HIGHLY SKILLED TECHNICAL PERSONNEL
millennium. 67
and SERCs in the states, a strong need h a s been felt to reorient the
developmental agency. The expertise and skills available with CEA are
power sector. 68
choice of technology and fuel use; tariff determination and norms for
62
ENABLING FRAMEWORK FOR PRIVATE INVESTORS
more investments, especially from the private sector. One of the major
make the power sector financially viable. The main elements of power
formulated policies.'^i
63
voltage and Low or high supply frequency have added to the 'power
woes' of the consumer. The major reasons for inadequate erratic and
capacity.
fell short. As against the target capacity addition 40245 M.W, the
actual addition was only. 19015 M.W (47%). Private sector achieved a
dismal 29% of its target (le.) 5061 M.W against a planned 17589
M.W. 73
projections made in the 16* Electric Power survey, over 1,00,000 M.W
64
additional generator capacity needs to be added by 2012 to bridge the
those which can be commissioned in the 10* and 11*^ plans joining
growth of the energy sector. The growth h a s been further retarded due
65
LACK OF OPTIMUM UTILIZATION OF THE EXISTING
GENERATION CAPACITY
region. 78
In eastern India it is below 250 ICWHr. Yet for the last few years
66
registered power surplus. In all the three states namely Bihar, Orissa,
HVDC Bipole.
the capacity of inter-regional lines by the end of the 11th plan would
67
INADEQUATE AND AGEING SUB TRANSMISSION AND
DISTRIBUTION NETWORK LEADING TO POWER CUTS AND LOCAL
FAILURES/FAULTS
capacitors.
priority as it will have positive effect on low voltages, line losses and
India is either lost or stolen. ^3 Normally any customer may not opt for
68
services. After regularization of unauthorized services during 1996-
The officers and staff who also know such cases did not take
effectively is therefore, not going to be easy for the SEB's. Unless the
improve. 85
Most of the States with large T and D losses are in the northern
of the total T and D losses in the country. The Western states had the
states, which had a low loss level, recorded a n average loss of over 23
69
percent in 1996-97. Among the States, Orissa topped the list with
was? It was found out that in most cases rural consumption including
high side and the figures of distribution loss for the whole state were
70
100 percent metering and management information system for
reduction of t & d losses
levels,
such a way as to reduce the length of low tension (LT) lines, (c)
mapping of the entire distribution system, and (f) load flow studies
distribution systemt.^o
71
Setting Tariffs is the key function of the State Electricity
Regulatory Commission Act 1998 (ERC Act) and under the State
Electricity Reforms Acts (the State Acts), the SERCs have been given
for wholesale, bulk, grid and retail supply of electricity within the
per Sixth Schedule of Electricity (Supply) act 1948. The tariff setting
procedure is elaborate and requires time and efforts both on the part
make sure that, by controlling the level and structure of prices (tariffs)
the utility recovers all costs that are prudently incurred and earn a
prevent the utility from capturing monopoly profits while ensuring the
72
increasing. The Planning Commission, in its latest report on the
paise per unit and commercial losses of SEBs are of the order of
the power sector in India. Therefore, to realize the goal set by the
is imiperative to bridge the gap between the cost of supply and retail
73
TABLE 2.14
Frequent revisions in the tariffs will not provide long term stable
74
For villages and hamlets electrification at 3 percent, and tribal
subsidy Rs.594 Crore have been provided for the Tenth Plan.
everybody in our life then mandatory steps may not be far away.
75
save energy; only some awareness and little efforts are required.
Energy saving m u s t be a part of our routine life. This Avill help the
specified period. ^^
and the outcome of a study shall form the basis for detailed and
76
Various innovative and modem techniques have been evolved
innovative ideas will allow better cash flow for SEBs, as the consumer
endeavour for electric service provider to give the best attention to his
Over the last 50 years the Indian Power Sector h a s lived with
realities.
With about Rs. 14,000/- Crores of annual loss, the Indian Power
77
$252 Billion in the next decade to meet the shortfall in the power
sector. The country h a s to add more t h a n 100 GW during the lO^h and
11th Plans (until 2012). To achieve this target, Rs. 11,000/- billion is
needed. But the resources available will be only about a third of this
of electricity. The skewed tariff structure, with low tariff for agriculture
paise and the gap 3.70 paise. In 1990-91, the average cost was 112.32
paise per unit and the average realization 86.84 paise, leaving a gap of
realization to 198.96 paise and the gap to 37.56 paise per unit. The
78
Rs.5,938 Crore, domestic consumers Rs. 1,310 Crores and inter-State
Crores.
this critical element crippling the power sector. Initially the result of
vote bank policies, power tariff differences did come up for review by a
not materialized and one still hears of free power supply promises by
79
RESULTS OF SUBSIDY
A hefty subsidy on supplying power free to agriculture, and a
segments notably industry. The high price complied with poor quality
For ages. States have made people believe that power is for
them with poor levels of efficiency. As they do not have to pay for the
STEPS TO REVIVE
A Government committee recommended that half the dues be
written off. While the other half settled by way of an issue of interest
agriculturists since power h a s been free for them and they have
80
become used to this. But how much to pay is a matter that should be
to pay. The problem with subsidies in India is not their mere existence
b u t how they are administered. The process is opaque and allows the
electricity sector.
have undertaken crucial reforms and signed MOUs with the Centre to
81
the amounts by money orders contributed to the prevention of
satisfaction over the arrangement and promptly paid the bills raised
are to be charged a higher level than the farmers and the low tension
and high tension industries get the higher cost bulk supplies from
Thus in the interest of consumers at large and for the long term
consumers who cannot afford the real price. In fact, subsidies are
result, other consumers especially industry pay very high prices which
82
power still a lot of work h a s to be done since providing subsidization is
83
TABLE 2.16
84
REGULATORY FRAMEWORK WILL ENSURE ACHIEVEMENT OF
THE OBJECTIVE
the legal framework which was set by the India Electricity Act of 1910
and the Electricity [Supply] Act of 1948. Some major changes were
Act, 1910, the Electricity [Supply] Act, 1948 and Electricity Regulation
85
ELECTRICITY ACT - 2 0 0 3
Electricity Bill was passed by Lok Sabha on 9^^ April, 2003 and by
Rajya Sabha on 5 * May, 2003 and the Electricity Act came into effect
Act, 1910, the Electricity (Supply) Act, 1948 and the Electricity
of:-
d) Rationalisation of tariff
policies.
86
4. integrating technical infrastructure like the Central and State
dispatch centers. ^ ^^
Broadly the following are the salient changes proposed in the power
sector.
clearances.
transmission businesses.
parties.
Governments.
87
• Explicit directives have been given to eliminate cross-
commercial principles.
The Indian Electricity Industry, a little over hundred years old, has
supply companies.
thrust towards the public sector, in the first two decades after
late 1970s, SEBs were not able to generate the required power
half of the 1970s and the early part of the 1980s saw the
88
the Central Government. In 1989, the transmission assets of the
on its companies, the States were not able to mirror this while
89
effectively bring about a competition between private and public
90
Distribution
the Central Government. The new Act laid down the various
retail sale.^^^
the Act, they have more autonomy in purchase decisions including the
91
ability to trade b u t they still do not have the incentives for least cost
This will change only when they participate in a full fledged wholesale
Subsidies
The Act and the draft NTP have an explicit policy goal to
what it costs to serve them. The primary tcirget is farmers who pay
either little or nothing for their power. The goal is to make the utilities
to pay. 120
Tariff
92
a) The principles and methodologies specified by the Central
optimum investments.
Licensing
By far the more significant changes brought about are the area
93
standards of connectivity with the grid. Sec. 14 and 15 stipulate
The vital areas of choice of technology, fuel mix and plant size which
which are the main source of power are depleting assets of the nation
Market reform
and the State Transmission Utility (STU) in the States. Any company,
owned by the government, can be the CTU which is charged with the
the supervision and control of the CTU. They will transact with the
94
been created which ensures the dominance of a publicly owned
The PTC will assist in the development of mega projects, which will
since they will sell power directly to the PTC under a composite
scheme for the generation and sale of power in more than one state.
brining all five regions under the new tariff mechanism. It has
95
WhyABT
Prior to independence small generating stations used to supply
grids in the 60's and regional grids in the mid 70's. By integration of
power Avithin and across the regions with reliability, security and
96
TABLE 2.17
the Centre owns or controls 30% of the nation's installed capacity, the
states own about 60%. The supply of power should be matched with
the demand for it. If supply tends to exceed demand the generating
97
TABLE 2.18
following are the major reasons for a grid to trip and collapse (1)
(2) Overdrawal of the Power by states above the day to day directive of
the RLDC when several states turn errant the frequency dips. If
grid trips.
98
been made in solving them. One important reason for this has been
had released its order, on the Availability Based Tariff (ABT) for the
Implementation of ABT
below.
Generating Stations which supply power to more than one state come
under ABT, as per CERC. It may be noted that to regulate the tariff of
Thus generators in the states will come under SERC control. After
99
introduction of ABT, the grid discipline has improved and the
charges shall be worked out on the basis per KW Hr., rate on ex-bus
charge is the fuel charge (ex-bus). Apart from the two charges a
depending upon who h a s deviated from the schedule and also subject
to the grid conditions at that point of time. This is the demand, which
charges.
100
ABT OPERATION
considered as one time block. Daily by 08.00 Hrs., the generator has
to declare its availability (Declared capacity) for each time block for
11.00 Hrs., the RLDC will request SEBs (State Electricity Board) to
furnish their next day's requirement. By 15.00 Hrs, SEBs will furnish
and to the SEBs about its drawals, for the next day. By 22.00 hrs,
is prepared for the next day. From 00.00 hrs, the ABT schedule for
RLDC need not be one and the same. The generator will get the
capacity charges for its declared capacity. The generator will get the
scheduled generation will form the basis for U l . The u l rate will be
101
(CERC) has announced the new reform as a panacea for all
and transmission companies claim that the move would hit them
below the belt. ABT in the present form h a s many changes adverse to
Thus ABT reduces profit margin on one hand and on the other
measure. In such condition the cheapest power will get first priority
102
d) It is a new system of more relevant incentives and
being implemented all over India. The frequency and voltage profiles
generation and the rest being losses. The power theft alone is
the power sector in a short time. The total outlay under APDP for
2000 - 01 was Rs. 1,000 crores and for 2001-02 Rs. 1,500 crores, with
103
a likely enhancement to over Rs.3,000 crores from 2002-03 onwards.
APDP which will continue till 2012 will offer the States 50 per cent (25
percent grant and 25 loan) of the project cost with the balance 50 per
resources.
distinct.
• GIS and digitized mapping for each district will ensure quick
response to outages.
104
• A proper voltage and reliable power supply may result in
depletion. ^29
consultants during 1990's, the States were asked to break their SEBs
But the results have not been encouraging. Other States where
encouraging, ^^o
the Ninth Plan was only a mere 29% of the targeted addition, ^si The
105
£ind coming up to the more recent Draft Electricity Bill 2003 have
improve the financial viability of the sector. But into separate entities
The following are the major attraction of the Indian power industry"
invited.
to all utilities.
106
• The Bureau for Energy Efficiency h a s been setup to lay down
benchmarking proposed.
power sector.
107
process. In the initial years there was a considerable hydel capacity,
power projects have come up. All the subsequent capacity additions
have been thermal. The ratio of hydel: thermal energy stood at 24:74
by the end of 1998-99. This may become 20:80 in the years ahead.
Icikhs kWh in 1947 and the activity was mainly concentrated around
per cent of the capacity in the utilities while the central sector
108
accounted for 27 percent. The rest was owned by private sector. In the
of only 7.5 percent during the decade. The Sixth and Seventh Five-
(8.1 percent) per annum. The 1990's showed a poor growth in capacity
4.4 percent per ctnnum. The installed capacity in all the three sources
109
percent and nuclear power generation capacity between 2.39 percent
forecast in the 16*^ EPS report. To meet the demand as per the
would be required during the 10th Plan period out of which 28328 MW
tariff to the consumers and also ensure overall energy security of the
go for new nuclear plants forced the country to depend on and expand
110
REFERENCES
1. Dr. G. Sudarsana Rao, "A Review ofThermal Power Generation
July-Sep.2002. P.30.
2004.
P.29.
Ill
10. Ibid 4.
12. Suhir Raha Coal-The Best bet for India's Energy Security
13. Energy : Coal, Monthly Review of the Indian Economy, Centre for
P.27.
18. Ibid 9.
20. Ibid 9.
22. Ibid 9.
23. Ibid 9.
112
24. Accelerating Development of Hydro Projects. Blue Print for Power
25. Ibid 9.
May 2002 P. 17
31. Ibid 9.
35. Ibid 9.
36. Ibid 9.
113
40. Dr.M.R.Srinivasan, Power Fifty Years after Independence, Power
1999 P.5
42. E.P.S. Seirma, Power Scenario during Ninth five year Plan Power
45. Power Sector shortfall in capacity Additions, Fair & Near in Water
lssn.0377-0036. Sept-2003.
50. Ibid 9.
51. Ibid 4.
114
52. S.Viswanthan and G.Balachandar cover stoiy Industrial
0036,Aug.2003, P.34
P.31.
Sector in India, The 2004, India Power Conclave, New Delhi 2004
No.3, Oct.2001,P.8.
61. IbidP.8
India. P. 10.
115
64. In force Hydro Power. Initiatives in Hydro, Power Line Volume 8-
P.3
116
78. Ibid 73.
P.30.
83. The Energy Times, 2002 Centre to reward best over utilities. Fair
and Near in Water & Energy, Vol. 12, No.4, Jan.2003, P.35
117
92. RL.Chechani, Mulki year Tariff setting, India Power, Vol.IX, No.3,
J u l y - S e p . 2 0 0 1 , P.27.
P.30.
97. Blue Print for power sector development. Electrical India March
2004, P.37
99. Ashok Bajpai, Key Role of electrical India Vol.44, No.4 Issn.0972-
P.44
118
104. News Brief:-Power Sector Needs US $252 Billion, India Power
108. Power failure (Busines Standard - July 30,2003) Fair & Near,
111.Ibid 110.
Neyveli, P . l l to 18.
119
117.G.S.Murali Krishna, Impact of the Electricity Act, Power Line, .8,
0972-3277-Dec.2003, P. 14.
123.1bid 116.
1, ABTinNLC.
129.1bidll6
120
132.R.N.Singh Regulation of inputs for power generation. The 2004
121