Energy Test. RM3
Energy Test. RM3
B. Function Test
NO FUNCTIONS
1 Physical /Visual Inspection.
2 Electrical check.
3 Metering Minimum Current
4 Current Measurement
5 Voltage Measurement
6 POWER(MW-MVAR) Measurement
7 Accuracy Test
8 Maximum Demand
2. Electrical Checks:
Date :
TESTING ENGINEER SEC- CSD - Engineer
3. Metering
- CREEP TEST
4- CURRENT MEASUREMENTS:
0.50 1 1 1 1 1 1
1.00 2 2 2 2 2 2
5- Voltage Measurements:
Date :
TESTING ENGINEER SEC- CSD - Engineer
3 ph
3 Ph Phase Power factor MW meas. MVAR meas.
current
Voltage Angle
injected
applied (V) set @ Exp Actual Exp Actual Exp Actual
(A)
7. Accuracy Test
Result Result
IEC 62053-22
Test # Test Description Import Export
Limitations
(Error %) (Error %)
1 10% In, 100%Vn UPF ± 0.2 -0.0060 -0.0028
2 100% In, 100%Vn UPF ± 0.2 -0.0115 -0.0004
3 300% In, 100%Vn UPF ± 0.2 -0.0129 -0.0155
4 600% In, 100%Vn UPF ± 0.2 -0.0172 -0.0112
5 10% In, 100%Vn 0.5Lag ± 0.3 0.0165 0.0261
6 100% In, 100%Vn 0.5Lag ± 0.3 0.0030 0.0069
7 300% In, 100%Vn 0.5Lag ± 0.3 -0.0345 -0.0133
8 600% In, 100%Vn 0.5Lag ± 0.3 -0.0562 -0.0544
9 10% In, 100%Vn 0.8Lead ± 0.3 -0.0121 -0.0095
10 100% In, 100%Vn 0.8Lead ± 0.3 0.0013 -0.0087
11 300% In, 100%Vn 0.8Lead ± 0.3 0.0401 0.0028
12 600% In, 100%Vn 0.8Lead ± 0.3 0.0401 0.0375
Phase
3 Ph Voltage 3 ph current MW meas. MVAR meas.
Angle
applied (V) injected (A)
set @ Exp Actual Exp Actual
Date :
TESTING ENGINEER SEC- CSD - Engineer