You are on page 1of 5

Troubleshooting

batching problems
Establishing benchmarks helps
solve problems rapidly and effectively

t’s 6:33 a.m. and Ken is already hav- button and both 1⁄2-inch and 1-inch rock By David Hall

I ing problems. As the batchman as-


signed to one of the largest pours of
the summer, he has big trouble. The
plant had batched perfect concrete the
evening before. But today Ken is taken by
fall. He is getting panicky now.
Ken senses that this is not going to be an
ordinary problem. The trucks are backing
up deep in the yard. In desperation, Ken
pulls the solid-state optocoupler module
surprise on the very first load as he watch- for the 1-inch rock out of the computer
es the scale displays climb way too fast for cabinet. “There, that should get us going.
the mix and load size. We’ll just have to troubleshoot this after the
As the batch is completing, he looks out big pour is over,” Ken says to himself.
the window and sees the problem. The mix He decides to test his theory by pushing
is calling for 1⁄2-inch rock and although the the 1⁄2-inch rock button just enough to see
1
⁄2-inch rock gate is opening, so is the 1- the gates crack open. Unfortunately, the 1-
inch rock gate. Ken’s first thought is that inch rock gates open, too. The usually cool
the batching computer is telling the 1-inch Ken lets out a string of expletives as he sits
rock gate to open. down hard on the wooden stool by the
“That darn Joe probably edited the gate computer console.
assignments and didn’t tell anyone,” Ken One of the drivers pokes his head into
says out loud. He pulls up the gate assign- the batch house to see what is causing the
ments, but they are correct. Ken’s face delay. “We got trouble boss?” the driver
flushes as he says aloud, “Okay, Joe, I owe asks. Ken glares at him as an answer. “I
you an apology.” don’t understand,” the driver says. “It was
Ken next reasons that the computer must batching fine last night … just before Lon-
be messing up. He knows enough about nie rewired the horn.”
his batching control system to realize that It doesn’t register with Ken immediately.
he can bypass the computer entirely by ac- All he can think about is the possibility of
tuating the gates from a manual control the huge order being canceled. Finally, it
panel. Ken presses the 1⁄2-inch rock gate continued on page 721

Problem: Random overweighs Overlap

Symptoms:
Problem happens on large loads
Problem happens on every mix with 3⁄4-inch rock
Problem not there on all other rock sizes

Conclusions:
Aggregate batcher and scales are okay
Look for common or
Freefall compensation for 34⁄ -inch rock is misset overlapping problems to
help reduce the time it
Goal: Look for common or overlapping symptoms takes to isolate and di-
agnose a problem.
strikes him. Lonnie had been in the com- Backtrack to go forward
puter cabinet last night rewiring the horn. Ken’s early morning experience is typical
Ken hadn’t given it a thought, since the of many problems that are nearly impossi-
horn was working fine. ble to plan for. Whenever things are going
Ken hops off his stool and goes to the fine and then suddenly go sour for no ex-
back of the computer cabinet. All the horn plicable reason, there is usually a critical
connections are neat and tight. He looks piece of the puzzle missing. Nine times out
down on the next row of terminals and lo- of ten the missing piece is an unnoticed,
cates the 1-inch rock gate terminal. He no- inadvertent action by a human. Whenever
tices that it happens to be right next to the things don’t add up, go over everything, no
1
⁄2-inch rock gate terminal. The light bulb matter how unrelated, that took place just
comes on in his head as he realizes what before the breakdown or problem. The an-
must have happened. swer will usually be obvious.
He looks carefully at the terminals. Sure
enough, right behind where the wires poke
out of the keepers, there is a single strand
of copper wire, nearly invisible between
the I/O rack and the terminals. It is, as Ken
had guessed, bridging the 1⁄2-inch rock gate
signal over to the 1-inch rock gate terminal.
Ken now has a clear mental picture of
what must have happened. Lonnie was
stripping the insulation off the wire and ac-
cidentally nicked a strand that fell into the
cabinet. Ken removes the bridge and tests
the gates again. He is ecstatic to see them
open one at a time.

Solving real-world problems


Ken’s dilemma is just the first of several
real-world batching troubleshooting meth-
ods that will be examined in this article.
Each method is illustrated with an actual
problem. As you read them, focus on the
methods used to isolate, identify, and elimi- Ken was aided by the fact that he had a Divide and conquer:
nate the problem. Keep in mind, also, that solid working knowledge of his automation In each successive step
of this troubleshooting
these methods will work for any type of system. He had taken the time to attend a technique, the problem
troubleshooting problem, whether it be a training seminar at his automation company, is subdivided into two
batch plant or a front-end loader. where he had learned to operate his batch- parts: 1) the part with
“Trouble” on a batch plant is anything ing controls efficiently and to quickly isolate the problem and 2) the
part without the prob-
that slows down production or delivery or common control and plant problems. Even lem. As the process con-
degrades the quality of the concrete being though the training had taken place more tinues, the part with the
produced. Trouble comes in several forms: than a year before, Ken was able to utilize problem gets smaller,
product quality problems, production the survival skills he had learned and apply and the problem takes
less time to troubleshoot.
speed problems, accuracy problems, and them in this critical situation.
reliability problems.
The root cause of one type of problem Establishing benchmarks
may initially appear to be in a different area. The first step in a systematic approach is
For example, a lack of plant maintenance (a to isolate and identify problem sources.
reliability issue) may be mistakenly tagged Unless you know what is normal at every
as an accuracy problem. In fact, plant main- point in the process, you can’t begin to iso-
tenance problems can show up as a factor late, much less identify, what is wrong.
in every category. Poor gate maintenance, The key is to take your batching opera-
for example, can lead to excessive jogging. tion’s pulse regularly. Record these pulse
Excessive jogging in turn, can cause slower points and compare them to the same read-
batching, decreased accuracy, and a slow- ings taken when the plant was running nor-
down in overall production speed. mally. This technique is known as bench-
marking. Benchmarking is based on the
concept that any process, no matter how tion, creating a very undesirable result.
complex, can be effectively solved by hav-
ing enough measurements at different points Fixing subtle problems
in the process in both the normal, running- Without regular performance measure-
well condition and in the abnormal, trou- ments, subtle problems can take root and
bled state. These measurements provide the grow so gradually they are not noticed un-
information needed to determine the validity less they are compared to peak perfor-
of the symptoms. They help eliminate false mance measurements. A prime example of
symptoms and ensure that you won’t run such a situation is a poorly calibrated mois-
out of troubleshooting clues before the ture meter. A drifting moisture probe and
cause of the problem is determined. meter can cause intermittent slump or wa-
Once the problem is isolated, detailed ob- ter trim errors whenever sand moisture
servations are often necessary to separate content gets in the high range. If the probe
the true cause from the list of suspect caus- under-reports sand moisture, the computer
es. For example, let’s say you are getting will add water to compensate, resulting in
excessive slump.
Another gradually worsening problem is
excessive buildup of cement on the inside
of a cement batcher. If not removed regu-
larly, this slow buildup of cement may
cause you to tare off too much weight and
result in the sudden release of the built-up
cement into one load.
Many speed problems are addressed by
expensive plant steel modifications when
they could be solved more economically
with an automation software enhancement.
If your slow production rates are killing your
competitive advantage because one material
routinely takes longer to batch, check out
available software options for your batching
automation. Chances are, there is an inex-
pensive software option that will enable the
faster material to begin production on the
following batch while the slower one finish-
es discharging on the current batch. This
software solution can cost up to 50 times
less than modifying the plant itself.
The solutions to most batching problems
are surprisingly obvious, provided you have
gathered enough symptoms to describe the
Clos in g the l o o p : sporadic high-side, out-of-tolerance batch problem. The following techniques may be
Knowledge of normal weights. The out-of-tolerance measurement used separately or in combination. They are
operation parameters
leads to establishing
recordings flag the problem. Careful obser- guaranteed to reduce the time it takes to
benchmarks which are vations recorded during the out-of-tolerance isolate and diagnose a problem.
used to rapidly trou- batches yield more details. Without the de-
bleshoot plant equip- tailed symptoms, you may never realize that Symptoms with like factors
ment problems.
the overweighs occur only on large loads Mike experiences significant overyields
and only on one particular aggregate. on some days, and correct yields on other
Visual inspection of the overhead bin days. He is puzzled by the fact that every
gates for the problem aggregate turns up the problem load has correct batch weights on
fact that whenever the gates are held open cement, admixtures, and coarse aggregate,
beyond a certain length of time during large but consistently overyields. Since the batch
loads, the worn teeth allow one gate to slip weights are correct, Mike zeroes in on the
out of mesh with the other gate, causing the sand because he knows there is an interac-
gates to close with difficulty. If the problem tion between sand and water in terms of
had gone undetected much longer, the gates yield.
would probably jam in the full open posi- Mike rules out freefall compensation set-
tings because the load overyields each batcher, notes that the cement Handling multiple problems
occur consistently, by about the weight is drifting, and the aggregate The techniques discussed previ-
same percentage, no matter what reading is steady. Steve then turns ously are highly effective for black-
the load size. Mike is just about to off the power to the batch control, and-white problems. But what if
pull out what little hair he has left unplugs the cement scale pot cable there are multiple problems that
when he notices that the overyields and the aggregate scale pot cable. show the same symptoms? Let’s vis-
are particularly frequent on days He reverses the plugs so that the it a plant that once was a model of
when the sand moisture content aggregate scale pot is feeding into production efficiency. Suddenly
measures fairly high. This one extra the cement scale input and vice- and without explanation the plant
fact forces the problem out in the versa. Steve turns the batch control batch weights become erratic.
open. back on and notices that the aggre- Sometimes it overweighs and gives
The solution is determined only gate readout is now drifting all over out-of-tolerance messages. At other
after Mike has gathered enough the place and the cement readout is times it underweighs and jogs to
facts—and discarded enough pieces rock-steady. Since the problem completion. The 1⁄2-inch rock mater-
of information that do not fit the moved to a different readout when ial is especially erratic.
situation. The solution to the prob- the scale pot cables were reversed Jim, the owner, spends a day in
lem is that the high-end calibration and the cables lead outside to the the batch house observing produc-
point on the moisture probe is set plant, Steve has now cut the possi- tion. After a few loads, Jim begins
too high. The reported moisture on ble hiding places of the problem to notice a pattern. If there is a
high-moisture days is greater than neatly in half. break in the pace of production, the
the actual sand moisture content. Steve now concentrates on the first batch after the break tends to
This is causing Mike’s batching au- plant itself, with full confidence that underweigh. The next batch is on
tomation to hold back more water the problem is definitely out there. the low side of the target, and the
and add more sand to compensate He climbs up on the plant and following batches get progressively
for the false moisture content. The checks the scale pot. It appears to higher weights and fewer jogs.
result is correct batch weights, but be fine. The scale lever pivots are Jim knows that when everything
significant overyielding. tight, the knife edges are fine, and is running properly the batch con-
Steve knows that the scale is track- trol hits the target weights on every
Divide and conquer ing accurately. The wind is blowing material consistently. He knows he
Another effective approach is to out of the north, making it very cold will have to look elsewhere for the
logically whittle the problem down on the cement silo end of the plant. root cause of the problem. Jim goes
to size. This is a highly efficient Steve goes to the south side of down to the air compressor and
troubleshooting technique. Every the plant to visually compare the takes a look at the air tank. He no-
time you subdivide the problem in- condition of the aggregate scale tices that the motor never stops
to two parts—1) the part with the pot. He notices that the aggregate running and the air tank water
problem and 2) the part without weigh hopper is motionless. He bleed valve is not fully closed. Jim
the problem—the part with the goes back to the cement end and closes the valve securely, and the
problem gets smaller and smaller, notices that the cement weigh- compressor motor stops running af-
and takes less time to troubleshoot. batcher is swaying ever so slightly ter a few minutes.
Let’s walk through another situation in the wind. The cause of the prob- Jim tracks the batch weights over
to get the feel for how this tech- lem literally hits Steve in the face: the next few days and confirms
nique can be applied. The wind. Steve tracks the batch re- that each material batches perfect-
The cement scale on Steve’s plant sults along with wind speed and di- ly—except for the 1⁄2-inch rock. The
overweighs sometimes, under- rection for a couple of days. Sure 1
⁄2-inch rock batch weights are still
weighs at other times, and never enough, the loads that have cement erratic compared to the way it has
seems to fit any pattern. The manu- weigh accuracy problems and fre- batched in the past. Upon inspec-
al batch panel scale readout drifts quent jogs happen when the wind tion, the cylinder seals on the 1⁄2-
up and down on the cement scale, is out of the north and gusting. inch rock feed gate cylinder prove
but the aggregate scale readout is The solution is easy—and inexpen- to be worn out. Jim also notices
steady. The aggregate batcher, at sive. Steve merely dials in more scale the length of the air hose from the
the other end of the plant is rock- motion electronic compensation that control solenoids is significantly
solid and batches perfectly. The is available in his batch control. This longer than the other gates. Jim
first step Steve takes, using the sub- feature is available on most types of has the seals replaced and the
divide method, is to isolate the batching controllers. It has the effect hose run shortened. Those actions
problem to either the plant or the of an electronic shock absorber to fil- solve the problem.
batching control. ter out minor signal swings resulting Jim now has the most accurate
Steve weighs up some material in from batcher swaying. loads ever produced at this plant.
Material overconsumption goes effort required to do even basic
down, profitability goes up, and the benchmarking. The day-to-day
customers are more satisfied with challenges of taking care of busi-
their quality concrete. ness often overshadow the need to
Once things are running smoothly, plan for what might happen. Yet
Jim is tempted to breathe a sigh of deep down inside, we must all ac-
relief and go back to business as knowledge that new problems will
usual. However, he just can’t get surely crop up sooner or later.
over the fact that something so sim- The best we can hope to accom-
ple and obvious could have escaped plish is to keep our guard up by
attention for so long. Jim decides to keeping a close watch on the vital
take steps to prevent future situa- signs of a healthy operation. When
tions from getting out of control. trouble does strike—and we all get
The first thing he does is to call our fair share—the difference be-
his automation company and get an tween a successful producer and one
adjustable air pressure sensing caught in a downward spiral of prob-
switch installed on the compres- lems might prove to be the availabili-
sor’s main air manifold. This switch ty of information that can make
signals the batchman through the problems easier to troubleshoot.
batch control computer whenever The best troubleshooting tools of
manifold air pressure drops below all are the knowledge provided by
a preset level. The second thing Jim the benchmark data and prevention
does is pick a routine mix design by acting on the benchmark data.
and write down the batch times for As Vernon Law once said, “Experi-
a given load size and truck loading ence is a hard teacher. First it gives
times—now that the plant is run- the test, afterward the lessons.”
ning well. While he is at it, Jim Recording accurate benchmarks can
waits for a heavy production sched- give you the same advantage come
ule and puts a stopwatch to one troubleshooting time. It’s compara-
full day of truck movements. He ble to reading one chapter ahead of
computes and records the average the teacher. ✥
in every category. Jim now has a
baseline benchmark to judge every David Hall is marketing manager for
aspect of batching performance. Command Data Dallas Division, man-
Jim knows that even if the im- ufacturers of Eagle batching control
proved business activity resulting systems.
from improved plant performance
will not allow time for regular
benchmarking, he still has the base-
line benchmark to fall back on
when performance deteriorates,
and it eventually will.
He realizes that most truck manu-
facturers must have felt the same
way when they put oil pressure,
water temperature, and battery
charge gauges on their vehicles.
These continuous benchmarks give
early indication of when something
critical to the truck’s operation mal-
functions. They often give warning
before the problem becomes dis-
abling. Gauges give valuable insight
into the cause of a problem. They
also provide confidence that the
truck will get you there, when they PUBLICATION #J950719
are in the normal range. Copyright © 1995, The Aberdeen Group
It is hard to justify the time and All rights reserved

You might also like