Professional Documents
Culture Documents
The Launching of River Esk Bridge PDF
The Launching of River Esk Bridge PDF
Introduction
This paper covers the approach for
carrying out the analysis, design
and detailing of the River Esk Bridge
on the M6 Carlisle to Guards Mill
Motorway Extension. The Esk bridge
is a four span 180m long steel
composite viaduct over the River
Esk and carries the southbound
carriageway of the new section of
M6 Motorway. The span arrangement
is 31.4m/51.9m/51.9m/44.9m.
The south abutment is fully
integral, forming the point of
fixity, and the superstructure is
free to move longitudinally over Figure 1 - River Esk Launch
the piers and north abutment.
The bridge steelwork was assembled
on the northern approach to the
bridge and launched southwards over
the River Esk estuary. The total weight
of the steelwork was over 800 tonnes.
The reason for the launch was that
STRUCTURES
5
51 The launching of River Esk Bridge
Analysis, design
and buildability
of the bridge launch and use of Choice of nose and tail length
steelwork elements is designed to
work in different ways, depending on temporary launching equipment. The longer the nose, the less
its position during the launch and also This paper focuses specifically on permanent steelwork would be
in the completed in-service condition. the launch-related aspects of the cantilevering at the leading span
The main girders and splices act in design and construction of the prior to ‘touch down’ at a support.
both hogging and sagging and the bridge, not on standard bridge A longer nose tends to reduce the
leading front span behaves as a very design and construction topics. cantilever moment as the nose
long cantilever during the launch. weight per unit length is normally
lighter than the permanent works.
6
The launching of River Esk Bridge 51
Figure 8 - Phase 1 steelwork launched and phase 2 steelwork attached ready for launch
7
51 The launching of River Esk Bridge
Analysis of steelwork
Determination of launch phases The steelwork was analysed for the
The most cost effective solution Due to the curve of the road cases where it was supported on
was to launch from the north end alignment and compulsory purchase the land bases as well as on the
only. On some very long bridges the order (CPO) boundary, an assembly permanent supports. The former is
steelwork is launched from both ends area was prepared which was large especially important for modelling
but this requires heavy plant, access, enough for only half the steelwork tail deflections and to check that
assembly area and welfare facilities and therefore the steelwork had the steelwork does not bottom-
in two locations rather than one. to be launched in two phases. out on the ground when leaving a
Launching from one end only land base. To check for bottoming-
also minimises the number of out, the steelwork precamber
temporary land bases required. also needed to be considered.
8
The launching of River Esk Bridge 51
9
51 The launching of River Esk Bridge
10
The launching of River Esk Bridge 51
LATERAL GUIDES AT
SUPPORTS TO PREVENT
LATERAL MOVEMENT
The contractor had concerns that The bracing would be difficult to The vertical support reactions during
the bridge was not adequately remove, being over the river, and the launch comprised the steel self
braced between the group of with the EMJ formwork already weight, formwork on all but the
three beams and the pair and that in place. Therefore, from a health leading span and a proportion of
the two sections could deviate and safety and CDM perspective it the deck reinforcement and so the
apart. Launching 5 beams is not was decided to leave the bracing reactions were a lot less than the
a usual scenario as beams would in place. The bracing was also in-service support reactions. However,
normally be launched in pairs. checked for the in-service case. the web thicknesses required were
They proposed continuous bracing Web patch load checks on slightly thicker than those required
at all bracing locations should be unstiffened sections of web for the in-service condition to
used. This made the whole bracing accommodate the unstiffened
In the in-service condition the
system effectively fully rigid and bearing support scenarios. BS5400
steelwork at supports is stiffened
so prescribing large deflections Part 31 clause 9.9.6 and Annex A,
with web bearing stiffeners to allow
generated large forces resulting in ‘web patch loading’, were used to
the web to carry the vertical support
the need for excessively large bracing perform this check. It is noted that
reactions. However, for most of
members and bolted connections. some further refinement of the
the time during the launch, the
By removing the top member in design would have been possible
position of web bearing stiffeners
bay 2-3 the bracing system became using the more recently developed
or intermediate transverse web
more flexible as the group of 2 patch loading rules in EN 1993-1-53.
stiffeners would not coincide
beams (beams 1 and 2) could rotate with the position of the supports. Splices designed to
or flex relative to the group of Therefore the unstiffened parts of resist hauling load
three beams (beams 3, 4 and 5). the web were checked for carrying Splices were checked for carrying the
the vertical support reactions. horizontal hauling load together with
in span bending and shear effects.
Plan bracing requirements
During launching the leading span
acts as a long cantilever prior to
touch-down on a support. In BS5400
Part 3 the determination of the
effectiveness of lateral restraints is
based on how well the compression
flange of a beam is restrained against
lateral and rotational movement.
STRUCTURES
11
51 The launching of River Esk Bridge
12
The launching of River Esk Bridge 51
Taking all moments about Launch load effects on When three or more beams are
point A summed to zero: abutments and piers connected together, either by cross
The substructures were checked bracing or top and bottom ‘push-pull’
F = 3P
for the load effects from the bracing, then load sharing can occur.
Summing all loads in plan launch hauling load, lateral guide This is termed ‘participating bracing',
along the y axis to zero: forces and friction effects of the where, as the deck deflects under
steelwork while being launched. load, some vertical load is transferred
The steelwork was also being through ‘transverse distribution'.
launched uphill by a gradient 0.3% The participating bracing was
The above assumptions are correct and this gradient was considered. modelled to determine the additional
for a deck on a constant radius The lateral and longitudinal forces load effects in the bracing members.
horizontal curve. For the case where on the piers and abutments due to Lubricant coefficient
the deck is on a varying radius moving the steelwork were considered of friction values
horizontal curve, or a combination in the design of the abutments and A lubricant was brush applied to
of constant curves and transition piers. The coefficient of friction the bottom flanges of the beams
curves, then additional lateral guide in the longitudinal and transverse during the launch to minimise
forces need to be considered. directions was taken as 11% (0.11) friction. The lubricant was actually
These additional forces result from and 5% (0.05) respectively. a soap normally used for removing
changing the plan curvature of the The north abutment was designed grease and oil, namely ‘Tufenega
deck from the initial constructed to resist the full hauling load and Green Gel’ (like Swarfega).
shape that is forced at any instant by the hauling frame was anchored
the guides. It is worth noting that if During the approvals process of
into the north abutment stem. the AIP the Highways Agency (HA)
these forces were too large then the The hauling load effectively pulled
assumption of ignoring friction on SSR requested a justification for the
the abutment into the fill and so assumed coefficient of friction values.
the guides would not be correct. passive resistance could be utilised. As mentioned in the AIP, the main
The additional lateral guide forces Participating bracing girders and substructure were checked
can be determined by modelling the for additional temporary loads due to
effects of the forced deflection of The optimum number of main beams
was investigated at the preliminary launching of the main girders, these
the deck in a simple grillage model loads are summarised as follows:
or by using simple beam formulae. design and value engineering stages
of the design. Cost comparisons (a) Wind loading to BD37/01
An impact factor of 1.5 was were made between 4, 5 or 6 beams.
applied to the calculated lateral (b) Loading due to differential
With an even number of beams vertical pre-camber as
guide forces and these forces were the bracing is usually arranged in
considered in the bracing design. specified in BS5400
discrete unconnected pairs i.e. for 6
(c) Lateral sliding friction loads
beams - three braced pairs. However,
exerted by temporary
for an odd number of beams the
launching guides due to the
bracing is arranged so that three
curved horizontal alignment of
beams are connected together. For
the deck, assuming a friction
the five beam case on the Esk there is
coefficient of 0.05 based on
a braced pair and a group of three.
data used for similar past
schemes as detailed below
(d) Longitudinal sliding friction
loads, assuming a friction
coefficient of 0.11 based on
data used for similar past
schemes as detailed below
(e) Longitudinal launching
forces applied on the tail
end of the steel deck.
STRUCTURES
13
51 The launching of River Esk Bridge
14
The launching of River Esk Bridge 51
The temporary launch bearings This also applied to the launch nose At the piers sufficient room was
comprised two 300 long x 200 wide and tail. In the final design of the available to jack down the steelwork
PTFE bearings in a line (600 long). permanent steelwork all bottom from under the bottom flanges of
The whole rocker bearing assemblies flanges were 900mm wide and the main beams as the piers are
were typically 780mm x 370mm. all top flanges 600mm wide. The 1500mm wide. However, at the
During the launch at least two flange sizes varied in the nose and north and south abutment the
points of lateral restraint were tail for economy except in bay 2-3 bearing shelves were much narrower
required at all times to prevent the where the same outstand as for and so no room was available to
steelwork shifting out of line. the main steelwork was required. place the jacks under the main
Web to flange welds were prepared in flanges. At the south abutment no
During launching the steelwork was
a T & I machine and were not ‘fitted’. permanent bearing plinths were
351mm higher than its final in-service
Therefore for web patch load checks to be provided and so jacking was
position. At each support a pair of
from the support reactions the weld made more difficult. To solve the
lateral guides was provided between
was checked for resisting the direct problem, the bracing adopted at
beams 2 and 3. The bracing in this
patch load since the the patch load these locations was mid–height
bay was lifted higher than in adjacent
would not be transferred from the horizontal I sections, with stiffened
bays in order to clear the guides. A
flange to the web in direct bearing jacking points provided either side of
distance of 350mm from underside
but via the web to flange welds. each main beam to enable jacking.
of bracing to underside of bottom
flange was required to clear the A safe maximum launch wind speed
guides. Bay 2-3, being a push-pull was specified on the drawings.
Conclusions
bracing bay, was easier to modify The wind speed corresponded to This paper demonstrates that
than an adjacent cross-bracing bay. a 10 year return period with a 3 the design and construction of a
Once the launch was complete the second gust speed of 18m/s. launched bridge can be significantly
structural steelwork was jacked The permanent formwork and a more complicated than the design
down into its final position. Initially proportion of deck reinforcement was of a comparable bridge which is
the preferred sequence was for the added to the steelwork prior to the constructed using conventional
steelwork to be jacked down fully, one launch on all but the leading span methods. There are many more
support at a time. However, deflection to minimise construction operations load cases, load effects and details
calculations were carried out to working at height and also mitigate to consider. However, in situations
determine what bending moments access problems. A cost comparison where access to the bridge site or
would be induced in the steelwork was made between EMJ and Omnia traffic management issues make
by this imposed deflection (351mm). formwork. EMJ was chosen as it conventional bridge construction
It was found that lift-off from the is half the weight of Omnia. difficult, bridge launching can offer
jacks would occur at some support an economical solution. This paper
At the integral south abutment the
locations before reaching the required summarises some of the key issues
wall reinforcement was required to
level. The jacking sequence was relating to launching steelwork.
run vertically up into the diaphragm
revised to allow only jacking in stages and lap horizontally into the deck The first phase of the launch was
at some supports to prevent lift-off. slab. In normal construction starter successfully completed on 16 May
Bottom flange splice cover plates bars are usually left protruding where 2007 and the second phase on 11
comprised two separate plates the diaphragm is to be cast both June 2007. The scheme was opened
350mm apart rather than a single in the front and back face of the to traffic in December 2008
plate. This was to ensure the splice abutment stem/diaphragm. Because
plates ran either side of the launch of the launch operation these bars Acknowledgements
bearings. Bottom flange butt welds would clash with the steelwork and
The author would like to acknowledge
were ground flush where there nosing. A 300 wide x 1800 deep
Fairfield Mabey Ltd, the Steelwork
was to be contact with the launch box-out was provided on the back
Contractor, for sharing their
bearings and the guides in order to face so that the kicker bars could
knowledge and expertise on launching
prevent snagging and unnecessary be left protruding below the level
steelwork. The author would also like
high hauling loads. This was the of the steelwork. For the front face
to acknowledge the Main Contractor
central section (300mm wide) bars couplers were used instead of
- Carillion, the Lead Consultant -
of the underside on all girders, starter bars. The reduced thickness
STRUCTURES
15
51 The launching of River Esk Bridge
References
1. BS5400 : Part 3 (2000): Design of steel bridges. British Standards Institution, London.
2. BD13/06 (2006). Design of steel bridges. Use of 5400-3:2000. Highways Agency, UK
3. BS EN 1993-1-5 (2006) Design of Steel Structures. Part 1.5: Plated
structural elements. British Standards Institution, London.
STRUCTURES
16