You are on page 1of 12

The launching of River Esk Bridge 51

Rob Liddle Abstract


Senior Group Engineer The River Esk Bridge carries the southbound carriageway of the M6
Highways & Transportation motorway over the River Esk estuary and forms part of the recently
constructed M6 Carlisle to Guards Mill Motorway Extension which provides
the missing link in the motorway network between England and Scotland.
The bridge is a 180m long four span steel composite viaduct. Due
to site constraints the most economical and practical method of
construction was to launch the steelwork into position rather than
to lift the steelwork in by crane. The bridge steelwork, weighing
over 800 tonnes, was assembled on the northern approach to the
bridge and launched southwards over the River Esk estuary
This paper demonstrates that the design and construction of a launched
bridge can be significantly more complicated than the design of a
comparable bridge which is constructed using conventional methods, and
that there are many more load cases and construction details to consider.
This paper covers the approach for carrying out the analysis, design,
detailing and construction of the structure and focuses specifically on
the key issues relating to launching steelwork. It serves as a useful guide
and quick point of reference for the design of launched steel bridges.

Introduction
This paper covers the approach for
carrying out the analysis, design
and detailing of the River Esk Bridge
on the M6 Carlisle to Guards Mill
Motorway Extension. The Esk bridge
is a four span 180m long steel
composite viaduct over the River
Esk and carries the southbound
carriageway of the new section of
M6 Motorway. The span arrangement
is 31.4m/51.9m/51.9m/44.9m.
The south abutment is fully
integral, forming the point of
fixity, and the superstructure is
free to move longitudinally over Figure 1 - River Esk Launch
the piers and north abutment.
The bridge steelwork was assembled
on the northern approach to the
bridge and launched southwards over
the River Esk estuary. The total weight
of the steelwork was over 800 tonnes.
The reason for the launch was that
STRUCTURES

access to the river for steelwork


assembly and lifting was not possible
due to the tidal nature of the river and
the high risk of flooding. Also, lifting
the beams in from the adjacent A74
‘Metal Bridge’ was not possible due to
traffic management issues. The A74
Metal Bridge was refurbished to carry
the M6 northbound carriageway.
Figure 2 - River Esk Launch

5
51 The launching of River Esk Bridge

Analysis, design
and buildability

Line beam analysis of


launch phases
Launch Phases
The bridge steelwork was launched
southwards in two phases:
Phase 1 - The southern half of
the steelwork was assembled on
temporary land bases together with
a launch nose and tail, and then
launched southwards. The launch
platform comprised the landbases,
spaced at 28m/28m/28m, constructed
in the partially completed approach
embankment with the landbase
levels set so that the steelwork could
be set out and assembled to the
Figure 3 - Views of the completed bridge adjacent to the existing A74 metal bridge vertical alignment required for the
launch. The piers in the river were
constructed in temporary cofferdams
which were then converted into
temporary islands to allow safe access
and working at the piers without the
risk of flooding. The cofferdams and
islands were constructed higher than
the maximum predicted flood level.
Phase 2 - The tail was removed from
the Phase 1 steelwork. The northern
most steelwork spans were assembled
and attached to the steelwork already
launched. The tail was reattached to
the rear of the Phase 2 steelwork.
The whole bridge steelwork was
then launched. On completion of the
launch the temporary launch nose
and tail steelwork were removed.
The launch equipment comprised
strand jacking tendons which were
attached to the north abutment using
Figure 4 - Views of the completed bridge adjacent to the existing A74 metal bridge a steel hauling frame which was
embedded into the concrete stem of
The M6 Carlisle to Guards Mill A temporary nose and tail assembly is
the abutment to resist the hauling
scheme provides the missing also required to be spliced to the main
load. The tendons were attached
link in the motorway network steelwork to accommodate the large
to the launch tail via a large steel
between England and Scotland. deflections that occur. Many bridge
cross-beam which was attached to
The main difference between a static substructure and steelwork details
the end of all five beams to transfer
bridge design and a launched bridge were modified from a ‘standard
the hauling load into the beams.
design is that each section of the design’ to accommodate the effects
STRUCTURES

of the bridge launch and use of Choice of nose and tail length
steelwork elements is designed to
work in different ways, depending on temporary launching equipment. The longer the nose, the less
its position during the launch and also This paper focuses specifically on permanent steelwork would be
in the completed in-service condition. the launch-related aspects of the cantilevering at the leading span
The main girders and splices act in design and construction of the prior to ‘touch down’ at a support.
both hogging and sagging and the bridge, not on standard bridge A longer nose tends to reduce the
leading front span behaves as a very design and construction topics. cantilever moment as the nose
long cantilever during the launch. weight per unit length is normally
lighter than the permanent works.

6
The launching of River Esk Bridge 51

Figure 5 - Cross section of the deck


The use of a curved soffit is a
different approach from that
commonly used for post-tensioned
incrementally launched concrete
bridges in which the nosing usually
has a hydraulic height adjustable
tip to take up the deflection prior
to touch down at a support.
The tail needed to be profiled
to take account of the back
span ‘dropping’ off the land
bases and bridge supports.
Land bases are temporary supports
in the steel launch platform area
where the steel is assembled.
A curved profile is required in
the tail to gradually take up the
cantilever deflection and to prevent
the steelwork making a sudden
Figure 6 - View of the launch showing significant leading span cantilever drop as it moves off a support.
deflection and temporary cofferdam/island around an intermediate pier At each stage of the launch the
The nose bottom flanges need The nose profile should be detailed ‘touch-down’ positions in the
to be curved to compensate for to allow sufficient tolerance to ensure nose were calculated as they
the cantilever deflection of the the nose travels past the support were required by the steelwork
leading span and to prevent the bearings a sufficient amount before contractor – these being the location
steelwork clashing with the piers and ‘touch-down’. 1m was specified and in the nose which would touch
abutments as it passes over them. the vertical clearance at the tip was down first and also the angle of
165mm before ‘touch-down’ after the nose flange at touch down.
considering deflections. The maximum
cantilever deflection was 1112mm.
STRUCTURES

Figure 7 - Phase 1 steelwork assembled ready for launch

Figure 8 - Phase 1 steelwork launched and phase 2 steelwork attached ready for launch

7
51 The launching of River Esk Bridge

Figure 9 - Phase 2 launch complete

Launch bearing type


The steelwork was launched on
temporary launch bearings, set
351mm higher than the final position
and then ‘jacked' down onto the
permanent bearings. Launch bearings
are usually a steel roller/skate or
PTFE pads with lubricant applied to
the underside of the bottom flange.
Skates can sometimes damage the
paint to the underside of the bottom
flange and have a higher resistance/
coefficient of friction against the
launch forces. PTFE bearings were
chosen for the Esk launch.
Deflection analysis during launch
The software package STRAP was
used to analyse the structure. Line
beams were used to analyse the nose
and tail deflections. At some stages
during the launch uplift occurred at
a support, indicated by a negative
support reaction. The support was
removed from the line beam model
and the model solved again to obtain
the correct results. It was important
to accurately model the steelwork
weight distribution, especially the
plan bracing in the leading span,
nose and tail, to obtain the correct
results. Calculated deflections were
Figure 10 - Hauling frame attached to north abutment required to enable accurate profiling
on the nose and tail to accommodate
the predicted deflections.
STRUCTURES

Analysis of steelwork
Determination of launch phases The steelwork was analysed for the
The most cost effective solution Due to the curve of the road cases where it was supported on
was to launch from the north end alignment and compulsory purchase the land bases as well as on the
only. On some very long bridges the order (CPO) boundary, an assembly permanent supports. The former is
steelwork is launched from both ends area was prepared which was large especially important for modelling
but this requires heavy plant, access, enough for only half the steelwork tail deflections and to check that
assembly area and welfare facilities and therefore the steelwork had the steelwork does not bottom-
in two locations rather than one. to be launched in two phases. out on the ground when leaving a
Launching from one end only land base. To check for bottoming-
also minimises the number of out, the steelwork precamber
temporary land bases required. also needed to be considered.

8
The launching of River Esk Bridge 51

Design details to consider


Changes between hog
and sag affecting effective
length calculations
At every location along the bridge
each section of the steelwork
acts in either sagging or hogging,
depending on its position during
the various stages of the launch as
the steelwork is pushed over and
between supports. Effective length
calculations and section checks were
required for every scenario as follows:
• The number of bracings
in a span could vary
• The steelwork spans varying
span lengths as it is moved
over and between land bases,
abutments and piers Figure 11 - View of leading span and nose during the launch
• Sections changed from acting
in hogging to sagging
• Both the launch phase and in-
service case were considered.
For each steelwork section the most
critical hog and sag case was chosen
to calculate the beam effective length.
Splices were also subject to both
hog and sag moments and this was
considered in the splice design.
Intermediate bracings were treated
as discrete torsional restraints to BS
5400 Part 31 clause 9.6.4.1.2 and
BD13/062 designed to clause 9.12.2.
Effects of differential precamber,
setting out tolerances and
fabrication tolerances
At any point along the bridge the
levels of the beam bottom flanges
Figure 12 - Touch down at an intermediate pier position
will vary between adjacent beams.
The difference in level will be mainly
due to differences in precamber but
also a component from setting out
and fabrication tolerances. This would
not normally present a problem for
a bridge constructed conventionally,
however, for a launched bridge as
the steelwork is pushed over the
launch bearings at a support, the
steelwork will be forced up or down
STRUCTURES

as the level of the bearings is fixed.


Put another way, the difference
in level between adjacent launch
bearings at a support is fixed but the
difference in level between adjacent
flanges will vary throughout the span.
This level difference or ‘lack of fit’
results in distortion of the bracing
frames as the steelwork moves
over the supports imparting large Figure 13 - View of tail, temporary land base, launch bearings and strandjack launch system
forces into the bracing members.

9
51 The launching of River Esk Bridge

If the deflections are too large to be


accommodated, then beam lift-off at
a support will occur causing additional
large forces in the bracing members.
Plane frame analysis models of the
bracing were used to model these
effects as summarised below:
(i) Precamber values were
determined from the main
grillage of the completed
structure (for all in-service dead
and superimposed dead loads)
(ii) The differences in precamber
between beams across individual
braced bays were calculated
(iii) A plane frame model
including all 4 bracing bays
was set up to account for any
transverse distribution effects
(redistribution of vertical load)
(iv) The calculated differential
deflections were applied to the
plane frame model to determine
the forces induced in the bracing
and also calculate the altered
support reactions based on Figure 14 - Placing of jacks for removal of launch bearings prior to jack down
transverse distribution effects
(v) The system was rechecked for
lift-off effects as follows:
(a) The vertical force required
to produce the prescribed
deflection in the plane
frame was calculated by
removing the relevant
support and applying a force
to the model iteratively
(b) If the force required to
produce the deflection
was larger than the actual
support reaction that occurred
then it was assumed that
lift-off would occur
(c) The support reaction at the
lifted-off beam was transferred
to the two adjacent beams.
The additional dead weight in Figure 15 - Nose approaching launch bearings at a pier prior to touch-down
the bracing due to the lifted-
off beam was taken as being (e) The resulting forces from The total fabrication and setting
equal to the support reaction the effects of differential out tolerance alone was +/-
divided by the number of
STRUCTURES

beam levels were added to 10mm without taking account


bracing bays in half the span other coexistent loads effects of differential precamber. It is
either side of the support. for design of the bracing important to allow for the possibility
This is because for a lifted-off members and connections. of beam uplift since applying the
beam the weight of the beam Of course, a more sophisticated full deflections to the plane frames
and bracings is transferred space frame model of the whole models can generate massive
to the two adjacent beams steelwork could have been used to forces in the bracing members.
via several bracing bays simplify the number of operations, Initially the steelwork contractor
(d) The bracing plane frame but it was decided at the beginning suggested we provide both a top
was resolved by removing of the scheme to only use line and bottom ‘push-pull’ member for
the support where the beam models of the girders to each bracing set between beams
beam had lifted off model the launching effects. 2 and 3 as shown in Figure 16.

10
The launching of River Esk Bridge 51

TOP TIE MEMBER ORIGINALLY BOTTOM TIE LIFTED TO CLEAR


PROPOSED GUIDES IN BAY 2-3

BEAM 1 BEAM 2 BEAM 3 BEAM 4 BEAM 5

PUSH – PULL BRACING

LATERAL GUIDES AT
SUPPORTS TO PREVENT
LATERAL MOVEMENT

Figure 16 - Arrangement of bracing

The contractor had concerns that The bracing would be difficult to The vertical support reactions during
the bridge was not adequately remove, being over the river, and the launch comprised the steel self
braced between the group of with the EMJ formwork already weight, formwork on all but the
three beams and the pair and that in place. Therefore, from a health leading span and a proportion of
the two sections could deviate and safety and CDM perspective it the deck reinforcement and so the
apart. Launching 5 beams is not was decided to leave the bracing reactions were a lot less than the
a usual scenario as beams would in place. The bracing was also in-service support reactions. However,
normally be launched in pairs. checked for the in-service case. the web thicknesses required were
They proposed continuous bracing Web patch load checks on slightly thicker than those required
at all bracing locations should be unstiffened sections of web for the in-service condition to
used. This made the whole bracing accommodate the unstiffened
In the in-service condition the
system effectively fully rigid and bearing support scenarios. BS5400
steelwork at supports is stiffened
so prescribing large deflections Part 31 clause 9.9.6 and Annex A,
with web bearing stiffeners to allow
generated large forces resulting in ‘web patch loading’, were used to
the web to carry the vertical support
the need for excessively large bracing perform this check. It is noted that
reactions. However, for most of
members and bolted connections. some further refinement of the
the time during the launch, the
By removing the top member in design would have been possible
position of web bearing stiffeners
bay 2-3 the bracing system became using the more recently developed
or intermediate transverse web
more flexible as the group of 2 patch loading rules in EN 1993-1-53.
stiffeners would not coincide
beams (beams 1 and 2) could rotate with the position of the supports. Splices designed to
or flex relative to the group of Therefore the unstiffened parts of resist hauling load
three beams (beams 3, 4 and 5). the web were checked for carrying Splices were checked for carrying the
the vertical support reactions. horizontal hauling load together with
in span bending and shear effects.
Plan bracing requirements
During launching the leading span
acts as a long cantilever prior to
touch-down on a support. In BS5400
Part 3 the determination of the
effectiveness of lateral restraints is
based on how well the compression
flange of a beam is restrained against
lateral and rotational movement.
STRUCTURES

Without plan bracing, for a maximum


cantilever of 51m, the tip of the
steelwork would be unrestrained
and would sway significantly and
so the effective length would be
too large to enable a realistic plate
design. Triangulated plan bracing
was provided throughout the
leading span to prevent this sway
and fully restrain the steelwork.
Figure 17 - View showing launch track marks on bottom flanges and plan bracing left in place

11
51 The launching of River Esk Bridge

The analogy being a car being


pushed around a corner without
turning the wheel i.e. overcoming full
friction of the tyres on the ground.
This is a gross overestimate as this
‘steering’ effect does not occur. What
actually happens is that the curved
steelwork ‘drives’ itself around the
curve naturally when pushed.
The hauling load must overcome
friction to move the steelwork.
The largest horizontal force that
can be imposed on the supports
longitudinally in the direction of
movement is the vertical reaction
at that support multiplied by the
coefficient of friction of the bearings.
The horizontal load imposed on the
lateral guides, taking into account the
Figure 18 - Idealisation of symmetrical constant radius curve launch driving action, can be derived from
considerations of force and moment
equilibrium. A simple grillage or line
The plan bracing provided effective The bracing, which would eventually beam model of the deck in plan can
discrete lateral restraints where form the support bracing at the be used to consider equilibrium of the
the effective length was limited to piers and abutments on completion system to determine the hauling load
the distance between intermediate of the launch, was also checked and lateral guide forces. The bearing
bracings and enabled an efficient as intermediate restraints for the friction at each support is applied
use of steel plate. The plan bracing launch phase when positioned as a load parallel to the direction
was provided between at least two away from a support. of sliding. The hauling load can be
beams near the compression flange. Launch load effects due to plan found by putting a pin support at
Plan bracing was also required curvature of the superstructure the hauling end of the deck, acting
between all 5 beams in the end bay At first glance it might appear that parallel to the deck. The resulting
of the leading end of the permanent the lateral launch forces on the lateral guide forces are determined
steelwork i.e. just behind the nose PTFE lateral guide bearings would as the horizontal supported reactions
splice. This plan bracing was required be equal to the force required to acting perpendicular to the deck. The
for erection purposes and during push the steelwork sideways over assumption is made that the bearing
launching to prevent adjacent beams the support bearings i.e. the total friction on the guides is negligible
moving longitudinally relative to vertical load at the support multiplied and can be ignored. This would seem
each other, known as ‘leading’. by the coefficient of friction. reasonable since the guide reactions
are of relatively small magnitude
compared to the vertical reactions.
The hauling load and lateral guide
forces need to be calculated for
each key stage during the launch.
This is because the geometry, spans
and sum of support reactions,
and hence the hauling load, will
vary as the launch progresses.
For a simple symmetrical structure on
a constant radius horizontal curve,
the lateral guide loads can be easily
STRUCTURES

determined by hand calculation using


simple rules of equilibrium, as shown
in Figure 18. The simple example
assumes the steelwork is pushed
and pulled at both ends whereas the
more usual case, as with the River
Esk, is to push the steelwork from one
end only. Equal supports reactions
are also assumed for simplicity.

Figure 19 - Lateral PTFE guide bearing anchored to pier and


abutment bearing shelves with pig tail anchors

12
The launching of River Esk Bridge 51

Taking all moments about Launch load effects on When three or more beams are
point A summed to zero: abutments and piers connected together, either by cross
The substructures were checked bracing or top and bottom ‘push-pull’
F = 3P
for the load effects from the bracing, then load sharing can occur.
Summing all loads in plan launch hauling load, lateral guide This is termed ‘participating bracing',
along the y axis to zero: forces and friction effects of the where, as the deck deflects under
steelwork while being launched. load, some vertical load is transferred
The steelwork was also being through ‘transverse distribution'.
launched uphill by a gradient 0.3% The participating bracing was
The above assumptions are correct and this gradient was considered. modelled to determine the additional
for a deck on a constant radius The lateral and longitudinal forces load effects in the bracing members.
horizontal curve. For the case where on the piers and abutments due to Lubricant coefficient
the deck is on a varying radius moving the steelwork were considered of friction values
horizontal curve, or a combination in the design of the abutments and A lubricant was brush applied to
of constant curves and transition piers. The coefficient of friction the bottom flanges of the beams
curves, then additional lateral guide in the longitudinal and transverse during the launch to minimise
forces need to be considered. directions was taken as 11% (0.11) friction. The lubricant was actually
These additional forces result from and 5% (0.05) respectively. a soap normally used for removing
changing the plan curvature of the The north abutment was designed grease and oil, namely ‘Tufenega
deck from the initial constructed to resist the full hauling load and Green Gel’ (like Swarfega).
shape that is forced at any instant by the hauling frame was anchored
the guides. It is worth noting that if During the approvals process of
into the north abutment stem. the AIP the Highways Agency (HA)
these forces were too large then the The hauling load effectively pulled
assumption of ignoring friction on SSR requested a justification for the
the abutment into the fill and so assumed coefficient of friction values.
the guides would not be correct. passive resistance could be utilised. As mentioned in the AIP, the main
The additional lateral guide forces Participating bracing girders and substructure were checked
can be determined by modelling the for additional temporary loads due to
effects of the forced deflection of The optimum number of main beams
was investigated at the preliminary launching of the main girders, these
the deck in a simple grillage model loads are summarised as follows:
or by using simple beam formulae. design and value engineering stages
of the design. Cost comparisons (a) Wind loading to BD37/01
An impact factor of 1.5 was were made between 4, 5 or 6 beams.
applied to the calculated lateral (b) Loading due to differential
With an even number of beams vertical pre-camber as
guide forces and these forces were the bracing is usually arranged in
considered in the bracing design. specified in BS5400
discrete unconnected pairs i.e. for 6
(c) Lateral sliding friction loads
beams - three braced pairs. However,
exerted by temporary
for an odd number of beams the
launching guides due to the
bracing is arranged so that three
curved horizontal alignment of
beams are connected together. For
the deck, assuming a friction
the five beam case on the Esk there is
coefficient of 0.05 based on
a braced pair and a group of three.
data used for similar past
schemes as detailed below
(d) Longitudinal sliding friction
loads, assuming a friction
coefficient of 0.11 based on
data used for similar past
schemes as detailed below
(e) Longitudinal launching
forces applied on the tail
end of the steel deck.
STRUCTURES

The same launch method had


been completed successfully by the
steelwork contractor shortly before
the launch of the River Esk on the
new Swale Crossing forming part of
the 30 year DBFO contract for the
A249 Iwade Bypass between the Isle
of Sheppey and mainland Kent. To
ensure that the structure would not
Figure 20 - Strand-jack launching system with stiff cross beam transferring be subjected to excessive loads during
loads to tail beam ends - monitoring station under cover in background
launching, the steelwork contractor
had carried out extensive in-house

13
51 The launching of River Esk Bridge

Furthermore, to provide an additional


margin of safety a higher load factor
than that specified in BD37/01 was
Tapered bearing plate conservatively adopted to check the
Plate permanent works during launching to
girder allow for dynamic and impact effects.
A load factor of 1.5 was used for
both dead load and superimposed
dead loads, instead of 1.05 and 1.2,
together with the friction coefficients
stated above. Initial structural checks
Adaptor plate
Bearing
30mm thick
showed that the load effects on the
bolted to substructure due to the in-service
welded to
adaptor plate
base plate condition would be far in excess of
those generated during launching,
Cast in base
plate with
resulting in a very high safety factor
shear during launching ranging from 4.3 for
overturning up to 29 for shear; the
main girders safety factor was 1.75.
Figure 21 - Adaptor plate arrangement
The friction coefficients to be adopted
testing in order to determine the most If unexpectedly high loads were during the launch were deemed safe
suitable friction coefficients specifically indicated then the launch was to be to use and accepted by the HA SSR.
used for the scheme. The friction halted and the cause investigated The main girders were checked
coefficients stated above were based and resolved to continue the in biaxial bending for the effects
on data taken from continuously operation. The monitoring system of major axis bending due
monitoring the load effects on the provided a permanent digital to the launch and minor axis
structure during the Swale Crossing record of the hauling loads. bending due to wind loads.
launch. The same monitoring Prisms were attached to each
system was adopted for the River pier, at the top, middle and Geometry arrangements,
Esk scheme described as follows: bottom levels in order to check details and buildability
Strand jack loads were monitored for displacement and rotation of
The steelwork contractor would
during the launch operation - the substructure. Measurements
have preferred the bearing taper
calibrated pressure transmitters were taken continuously during
plates to be ‘through bolted’ to the
were installed in the hydraulic lines the launching operation by
bottom flange to avoid having to site
to the strand jacks and connected surveyors using EDM equipment.
weld and paint up over the piers.
to a laptop computer to monitor
However, due to space limitations
strand jack launch loads. This
for bolt locations the taper plates
provided a digital and graphical
were welded on site post launch.
display of the load being applied
Obviously the taper plates could
by the two jacks every five seconds
only be added once the steelwork
that were continuously monitored
was launched otherwise they would
by an engineer who was in radio
snag with the launch bearings.
contact with the Launch Controller.
A steel adaptor plate was used to
attach both the temporary launch
bearings and the permanent bearings.
At each bearing location a base
plate with shear studs was cast into
the bearing plinth. An adaptor plate
was welded to the base plate. The
temporary launch bearings were
bolted to the adaptor plate and
STRUCTURES

then removed after the launch.


The permanent bearings were then
bolted to the same adaptor plate
prior to the steelwork being lowered
down on jacks from the elevated
launch position onto the permanent
bearings. This was a practical detail
to allow the use of two types of
bearing in the same location. All
site welding was painted to full
Highways Agency specification.
Figure 22 - Split bottom flange splice plates

14
The launching of River Esk Bridge 51

The temporary launch bearings This also applied to the launch nose At the piers sufficient room was
comprised two 300 long x 200 wide and tail. In the final design of the available to jack down the steelwork
PTFE bearings in a line (600 long). permanent steelwork all bottom from under the bottom flanges of
The whole rocker bearing assemblies flanges were 900mm wide and the main beams as the piers are
were typically 780mm x 370mm. all top flanges 600mm wide. The 1500mm wide. However, at the
During the launch at least two flange sizes varied in the nose and north and south abutment the
points of lateral restraint were tail for economy except in bay 2-3 bearing shelves were much narrower
required at all times to prevent the where the same outstand as for and so no room was available to
steelwork shifting out of line. the main steelwork was required. place the jacks under the main
Web to flange welds were prepared in flanges. At the south abutment no
During launching the steelwork was
a T & I machine and were not ‘fitted’. permanent bearing plinths were
351mm higher than its final in-service
Therefore for web patch load checks to be provided and so jacking was
position. At each support a pair of
from the support reactions the weld made more difficult. To solve the
lateral guides was provided between
was checked for resisting the direct problem, the bracing adopted at
beams 2 and 3. The bracing in this
patch load since the the patch load these locations was mid–height
bay was lifted higher than in adjacent
would not be transferred from the horizontal I sections, with stiffened
bays in order to clear the guides. A
flange to the web in direct bearing jacking points provided either side of
distance of 350mm from underside
but via the web to flange welds. each main beam to enable jacking.
of bracing to underside of bottom
flange was required to clear the A safe maximum launch wind speed
guides. Bay 2-3, being a push-pull was specified on the drawings.
Conclusions
bracing bay, was easier to modify The wind speed corresponded to This paper demonstrates that
than an adjacent cross-bracing bay. a 10 year return period with a 3 the design and construction of a
Once the launch was complete the second gust speed of 18m/s. launched bridge can be significantly
structural steelwork was jacked The permanent formwork and a more complicated than the design
down into its final position. Initially proportion of deck reinforcement was of a comparable bridge which is
the preferred sequence was for the added to the steelwork prior to the constructed using conventional
steelwork to be jacked down fully, one launch on all but the leading span methods. There are many more
support at a time. However, deflection to minimise construction operations load cases, load effects and details
calculations were carried out to working at height and also mitigate to consider. However, in situations
determine what bending moments access problems. A cost comparison where access to the bridge site or
would be induced in the steelwork was made between EMJ and Omnia traffic management issues make
by this imposed deflection (351mm). formwork. EMJ was chosen as it conventional bridge construction
It was found that lift-off from the is half the weight of Omnia. difficult, bridge launching can offer
jacks would occur at some support an economical solution. This paper
At the integral south abutment the
locations before reaching the required summarises some of the key issues
wall reinforcement was required to
level. The jacking sequence was relating to launching steelwork.
run vertically up into the diaphragm
revised to allow only jacking in stages and lap horizontally into the deck The first phase of the launch was
at some supports to prevent lift-off. slab. In normal construction starter successfully completed on 16 May
Bottom flange splice cover plates bars are usually left protruding where 2007 and the second phase on 11
comprised two separate plates the diaphragm is to be cast both June 2007. The scheme was opened
350mm apart rather than a single in the front and back face of the to traffic in December 2008
plate. This was to ensure the splice abutment stem/diaphragm. Because
plates ran either side of the launch of the launch operation these bars Acknowledgements
bearings. Bottom flange butt welds would clash with the steelwork and
The author would like to acknowledge
were ground flush where there nosing. A 300 wide x 1800 deep
Fairfield Mabey Ltd, the Steelwork
was to be contact with the launch box-out was provided on the back
Contractor, for sharing their
bearings and the guides in order to face so that the kicker bars could
knowledge and expertise on launching
prevent snagging and unnecessary be left protruding below the level
steelwork. The author would also like
high hauling loads. This was the of the steelwork. For the front face
to acknowledge the Main Contractor
central section (300mm wide) bars couplers were used instead of
- Carillion, the Lead Consultant -
of the underside on all girders, starter bars. The reduced thickness
STRUCTURES

Capita and also the Sub-Consultants


and the edges of the two inner of abutment stem was checked
(Bridge Designers) Grontmij.
girders, which were in contact with for the temporary load cases.
the lateral guides. All other butt At the north abutment the
welds were to be dressed only. inspection gallery starter bars were
Bottom flanges needed to have required to lap into the back of
the same outstand dimension the gallery wall. These bars were
in bay 2-3 so that the lateral kept as low as possible by slightly
guides would always be in lowering the gallery floor.
contact with the flange edge.

15
51 The launching of River Esk Bridge

References
1. BS5400 : Part 3 (2000): Design of steel bridges. British Standards Institution, London.
2. BD13/06 (2006). Design of steel bridges. Use of 5400-3:2000. Highways Agency, UK
3. BS EN 1993-1-5 (2006) Design of Steel Structures. Part 1.5: Plated
structural elements. British Standards Institution, London.
STRUCTURES

16

You might also like