You are on page 1of 12

PERIMETER FENCE

@ 6 meter Span

CODE DESCRIPTION QTY UNIT

001 Excavation Works


Column Footing 0.81 cu.m.
Wall Footing (WF-1) 1.15 cu.m.
Backfill 1.59 cu.m.
TOTAL DIVISION 001
002 CONCRETING WORKS
a Formwork Accessories
Coco Lumber 2 x 2 x 8 32.00 bd.ft.
Coco Lumber 2 x 3 x 8 32.00 bd.ft.
Ordinary Plywood 1/2" 0.67 sheets
b Column and Wall Footings
Portland Cement 3.60 bags
Washed Sand 0.23 cu.m.
Gravel Y-Y 0.45 cu.m.
Gravel Base 0.16 cu.m.
Deformed Round Bar 12mm x 6.0m 8.20 lengths
Deformed Round Bar 8mm x 6.0m 5.25 lengths
Deformed Round Bar 10mm x 6.0m 2.67 lengths
G.I. Tie Wire # 16 0.50 kgs.
TOTAL DIVISION 002
003 CONCRETE MASONRY WORKS
a CHB Piling
CHB 4" 58.00 pcs.
Portland Cement 2.42 bags
Washed Sand 0.20 cu.m.

b Steel Reinforcement
Deformed Round Bar 10mm x 6.0m 3.33 lengths
G.I. Tie Wire # 16 0.40 kgs.

c Plastering
Portland Cement 1.09 bags
Washed Sand 0.09 cu.m.

TOTAL DIVISION 003


004 STEEL WORKS
a Fence Framing
GI Pipe Sched. 20 ,2" x 6m 2.83 lengths
Cyclone Wire 4' Heavy Duty 0.50 lengths
Spiral Safety Wire 0.50 lengths
Square Bar 1/2Y x 6m 2.73 lengths

b Other Materials
Welding Rod (Nihon Brand) 1.00 kgs.
Edger Blade 7" 1.00 pcs.
Hacksaw Blade 1.00 pcs.

TOTAL DIVISION 004

TOTAL
LABOR COST

DIRECT CONSTRUCTION
CONTRACTOR'S PRO
OVERHEAD, MISCELLANEOUS AND

DIRECT PROJECT COST @ 6m


DIRECT PROJECT COST @ 1m
DIRECT PROJECT COST @ 2,678
TOTAL PROJECT CO
TER FENCE
eter Span

DIRECT COST
LABOR
UNIT PRICE CODE
MATERIAL AND DIV. TOTAL
TOTAL
S EQUIPMENT

300.00 243.00
250.00 288.00
250.00 397.50 928.50
928.50

14.00 448.00
14.00 448.00
580.00 386.69 Vfooting Vcolumn
1,282.69 0.162 0.096
255.00 918.00
400.00 90.00
400.00 180.00
400.00 65.60
199.00 1,631.80 2.8 5.4
90.00 472.50 5.25
130.00 346.67
70.00 35.00 3,739.57
5,022.25

8.50 493.00
255.00 617.63
400.00 80.74
1,191.37
-
130.00 433.33
70.00 28.00
461.33

255.00 279.07
400.00 36.48
315.55
1,968.25

900.00 2,549.97
500.00 250.00
1,000.00 500.00
150.00 410.00
3,709.97

95.00 95.00
200.00 200.00
70.00 70.00
365.00
4,074.97

11,993.97

TOTAL 11,993.97 11,993.97


LABOR COST 0.40 4,797.59

DIRECT CONSTRUCTION COST + 16,791.56


CONTRACTOR'S PROFIT 10% 1,679.16
ERHEAD, MISCELLANEOUS AND CONTINGENCIES 10% 1,679.16

DIRECT PROJECT COST @ 6meters Span 20,149.88


DIRECT PROJECT COST @ 1meter Span 3,358.31
DIRECT PROJECT COST @ 2,678 meters Span 8,993,561.76
TOTAL PROJECT COST 9,000,000.00
Vwf
0.192 0.45
PERIMETER FENCE
@ 6 meter Span

CODE DESCRIPTION QTY UNIT

001 Excavation Works


Column Footing 0.14 cu.m.
TOTAL DIVISION 001
002 CONCRETING WORKS
Pre cast Column
Pre - Cast Posts (4" x 4" x 7') 5.00 pcs.
Portland Cement 0.96 bags
Washed Sand 0.12 cu.m.
TOTAL DIVISION 002
003 INSTALLATION OF CYCLONE WIRE
Cyclone Wire 6' 2.00 rolls
Deformed Round Bar 8mm x 6.0m 0.73 lengths
G.I. Tie Wire # 16 0.50 kgs.
Hacksaw Blade 1.00 pcs.
TOTAL DIVISION 004

TOTAL
LABOR COST

DIRECT CONSTRUCTION
CONTRACTOR'S PRO
OVERHEAD, MISCELLANEOUS AND

DIRECT PROJECT COST @ 8m


DIRECT PROJECT COST @ 1m
DIRECT PROJECT COST @ 2,678
TOTAL PROJECT CO
TER FENCE
eter Span

DIRECT COST
LABOR
UNIT PRICE CODE
MATERIAL AND DIV. TOTAL
TOTAL
S EQUIPMENT

400.00 54.00
54.00 54.00

0.162 0.096
350.00 1,750.00
265.00 254.40
450.00 54.00
2,058.40 2,058.40

500.00 1,000.00
120.00 87.60
85.00 42.50
75.00 75.00
1,205.10 1,205.10

3,317.50

TOTAL 3,317.50 3,317.50


LABOR COST 0.40 1,327.00

DIRECT CONSTRUCTION COST + 4,644.50


CONTRACTOR'S PROFIT 10% 464.45
ERHEAD, MISCELLANEOUS AND CONTINGENCIES 10% 464.45

DIRECT PROJECT COST @ 8meters Span 5,573.40


DIRECT PROJECT COST @ 1meter Span 619.27
DIRECT PROJECT COST @ 2,678 meters Span 1,658,396.13
TOTAL PROJECT COST 1,660,000.00
0.192 0.45
PERIMETER FENCE
@ 6 meter Span

#REF! 0.37
0.05

CODE DESCRIPTION QTY UNIT

001 Excavation Works


Column Footing 0.21 cu.m.
Backfill 0.05 cu.m.
TOTAL DIVISION 001
002 CONCRETING WORKS
a Formwork Accessories
Coco Lumber 2 x 2 x 8 6.67 bd.ft.
b Concrete Pedestal
Portland Cement 1.13 bags
Washed Sand 0.06 cu.m.
Gravel Y-Y 0.13 cu.m.
Gravel Base 0.01 cu.m.
Deformed Round Bar 16mm x 6.0m 0.80 lengths
Deformed Round Bar 10mm x 6.0m 2.38 lengths
G.I. Tie Wire # 16 0.25 kgs.
TOTAL DIVISION 002
003 Other Materials

Anchor Bolts, 16mm dia. X 200mm with nuts and washers (hot dipped) 4.00 pcs.

Base Plate 9mm thk., 400mm dia. 1.00 pcs.


EMT elbow 25mm 1.00 pcs.
EMT PIPE 25mm 0.40 lengths

TOTAL DIVISION 004

TOTAL
LABOR COST

DIRECT CONSTRUCTION
CONTRACTOR'S PRO
EQUIPMENT RENTA
MISCELLANEOUS AND CONT

DIRECT PROJECT COST for 1


DIRECT PROJECT COST for 10,0
TOTAL PROJECT CO
TER FENCE
eter Span

#REF!
0.19 0.13

DIRECT COST
LABOR
UNIT PRICE CODE
MATERIAL AND DIV. TOTAL
TOTAL
S EQUIPMENT

300.00 62.20
250.00 12.57 74.77
74.77

14.00 93.33
93.33 0.12566
255.00 288.39
400.00 25.13
400.00 50.26
400.00 5.03
395.00 316.00 2.8 5.4
130.00 309.83
70.00 17.43 1,012.08
1,105.41

200.00 800.00

1,500.00 1,500.00
60.00 60.00
850.00 340.00
2,700.00
2,700.00

3,880.18

TOTAL 3,880.18 3,880.18


LABOR COST 0.40 1,552.07

DIRECT CONSTRUCTION COST + 5,432.25


CONTRACTOR'S PROFIT 10% 543.23
EQUIPMENT RENTALS +5% 271.61
MISCELLANEOUS AND CONTINGENCIES +5% 271.61

DIRECT PROJECT COST for 1 pedestal 6,518.70


DIRECT PROJECT COST for 10,012 pedestals 65,265,255.64
TOTAL PROJECT COST 65,300,000.00

You might also like