Professional Documents
Culture Documents
EPC Compodium - 194-196 PDF
EPC Compodium - 194-196 PDF
193
location of delivery cistern, power supply, location of pressure main
connecting pump house and location of delivery cistern and discharge to be
delivered at cistern.
3) In an EPC contract, the total value of the contract is fixed subject to price
adjustment for certain material component. Some responsibilities towards detailed
engineering and preparation of detailed designs have deliberately been cast upon
the EPC contractor within the overall parameters of the project. However, different
design solutions could be proposed by the contractor which could be accepted by
the competent authority after due examination of the technological superiority and
establishing the best solution for the purpose in the project. Competent authority
as authorized by the Government is the final authority to accept a proposed design.
Further, in most EPC contracts the detailed survey, design and estimate
engineering is not complete at the time of agreement. They are done in the course
of execution of the project. All designs must be in compliance with the codal
provision, Government orders and practices. As is obvious, in such an exercise,
there would be cases where the cost to be incurred for a given component of a
project, due to approved design, might be more than what was originally estimated
by the department or there might be a situation where due to a certain design, the
cost could be less than the estimated cost for that component. Quite often, audit
suggests that the cost lesser than the estimated is a saving, which should accrue to
the Government, forgetting that there would also be components where there could
be an excess cost on components beyond the estimated which is cast on the
contractor. But in both the situations, the excess and less are unreal because, there
are no two approved designs and therefore there can not be two different costs to
arrive at excess or less. There is always only one best design solution for the
purpose of achieving project goals and the Government must get the benefit of
most efficient and technologically best suited design. As a general rule, the cost on
any component due to any implementation of approved design should always be on
contractor’s account within the cost of the total contacted amount under EPC until
and unless such designs effectively change any of the basic parameters as defined
above. In such a situation, where there are revisions in the design due to change in
the basic parameter then the modalities for effecting such a change in will be
decided with the prior approval of Government.
This Memo issues with the concurrence of Finance (W&P) Department vide their U.O.No. 1496-
F8(A1)/08 Dated 18.4.2008.
RAJIV RANJAN MISHRA,
SECRETARY TO GOVERNMENT
To
All the Engineers-in-Chief } I & CAD
Department All the Chief Engineers}
All the Superintending Engineers through Engineer-in-Chief
(Irrigation) Copy to all Sections in I & CAD Department
Copy to Finance (W&P) Department
Copy to PS to Special Secretary to
C.M. Copy to PS to Minister (M&MI)
Copy to PS to Special C.S. Finance
Copy to PS to Secretaries I & CAD Department, Secretary
(RRM). Copy to all Advisors
SF/SCs.
// Forwarded by order //
SECTION OFFICER
194
GOVERNMENT OF ANDHRA PRADESH
IRRIGATION & CAD DEPARTMENT
To
1. The Engineer-in-Chief, Irrigation, Errum Manzil, Hyderabad.
2. The Chief Engineer, HNSS, Ananthapur.
3. The Chief Engineer, TBP, Kadapa.
4. The Chief Engineer, Telugu Ganga Project, Srikalahasti.
5. The Chief Engineer, Velugonda Project, Ongole.
6. The concerned Superintending Engineer & Executive Engineer through their Chief
Engineers.
// Forwarded By Order //
SECTION OFFICER
195