You are on page 1of 45

Annexure-II

Recommendations of Board of Chief Engineers on HLTC Recommendations

Sl. Reference Existing Text Proposed Text Recommendations of Board of Chief Engineers
No. to PS
I PS 23 Data The materials and labour utilized The materials, labour and machinery utilized in the The materials, labour and machinery utilized in the execution
(1) in the execution work by the execution work by the contractor shall not be less than work by the contractor shall not be less than that given in the
contractor shall not be less than that given in the A.P. Revised Standard Data for the sanctioned estimate data.
that given in the A.P.P.W.D. relevant item
standard data for the relevant
item
I P.S. 27 Test Note at the end of P.S. 27: Note at the end of P.S. 27:
(2) inspection For all works costing more than Rs. 2.00 Crores or For all works costing more than Rs. 5.00 Crores or as
and as may be modified by any competent authority may be modified by any competent authority from time
rejection of from time to time, the Contractor shall submit a to time, the Contractor shall submit a quality plan and
defective quality plan and also show proof of owning Quality also show proof of owning Quality Laboratory or having
materials Laboratory or having a tie-up with an established a tie-up with an established Quality Laboratory.
and work Quality Laboratory.
The Tender Schedule/Agreement should mention about
the details of testing equipment required for the
specified work. All Departments to act accordingly.
I P.S. 28 Any defects, shrinkage or other Any defects, shrinkage or other faults which may appear Any defects, shrinkage or other faults which may appear within
(3) Defects, faults which may appear within within two years or such reasonable time as two years or such reasonable time as specified therein in
shrinkage six months from the completion specified therein in case of the original works and case of the original works, Special Repair & Periodic
etc., after of the works arising, in the
one year or such reasonable time as specified Maintenance (SR&PM) works of R&B Dept., and
completion opinion of the Executive Engineer,
therein for Special Repairs nature falling under
from faulty materials or one year or such reasonable time as specified therein for
workmanship not in accordance maintenance works from the completion of the works
Special Repairs nature (other than R&B Department)
with the drawings and arising, in the opinion of the Executive Engineer, from
falling under maintenance works from the completion of
specifications or the instructions faulty materials or workmanship not in accordance with
the works arising, in the opinion of the Executive Engineer,
of the Executive Engineer, shall, the drawings and specifications or the instructions of the
upon the directions in writing of from faulty materials or workmanship not in accordance with
Executive Engineer, shall, upon the directions in writing of
the Executive Engineer and with the drawings and specifications or the instructions of the
the Executive Engineer and with in such reasonable time
in such reasonable time shall be Executive Engineer, shall, upon the directions in writing of the
specified therein, be amended shall be specified therein, be amended and made good by
Executive Engineer and with in such reasonable time shall be
and made good by the contractor the contractor at his own cost, unless the Executive
specified therein, be amended and made good by the
at his own cost, unless the Engineer shall decide that the contractor ought to be paid
contractor at his own cost, unless the Executive Engineer shall
Executive Engineer shall decide for the same at the rates agreed or such reduced or other
decide that the contractor ought to be paid for the same at the
that the contractor ought to be rates as the Executive Engineer may fix and in case of
paid for the same at the rates rates agreed or such reduced or other rates as the Executive

1
Sl. Reference Existing Text Proposed Text Recommendations of Board of Chief Engineers
No. to PS
agreed or such reduced or other default, the Executive Engineer may employ and pay Engineer may fix and in case of default, the Executive Engineer
rates as the Executive Engineer other persons to amend and make good such defects, may employ and pay other persons to amend and make good
may fix and in case of default, the shrinkage or other faults or damage and all expenses such defects, shrinkage or other faults or damage and all
Executive Engineer may employ
consequent thereon and incidental thereto shall be borne expenses consequent thereon and incidental thereto shall be
and pay other persons to amend
and make good such defects, by the contractor. borne by the contractor.
shrinkage or other faults or Note: No defect liability period is necessary for Annual Note: No defect liability period is necessary for Annual
damage and all expenses maintenance works maintenance works
consequent thereon and [In the event of Government taking over portions of the
incidental thereto shall be borne works as and when they are completed, the liability of the [In the event of Government taking over portions of the works
by the contractor contractor shall be limited to the period of two years or as and when they are completed, the liability of the contractor
such reasonable time as specified therein in case of the shall be limited to the period of two years or such reasonable
[In the event of Government
taking over portions of the works original works and one year or such reasonable time time as specified therein in case of the original works,
as and when they are completed, as specified therein for Special Repairs nature falling Special Repair & Periodic Maintenance
the liability of the contractor shall under maintenance works from the date of taking over (SR&PM) works of R&B Dept., and one year or such
be limited to the period of six the portion or portions of the work, provided that the reasonable time as specified therein for Special Repairs
months from the date of taking portion or portions taken over has no connection with the
over the portion or portions of the nature(other than R&B Department) falling under
remaining portions of the main work and is independent maintenance works from the date of taking over the portion or
work, provided that the portions
or portions taken over has no of it] portions of the work, provided that the portion or portions
connection with the remaining [Subs. By G.O. Ms. No. 1007, Tr. TR&B (C1) Dept., dt. 5- taken over has no connection with the remaining portions of
portions of the main work and is 11-1976]. the main work and is independent of it]
independent of it] The contractors are responsible for the quality of works [Subs. By G.O. Ms. No. 1007, Tr. TR&B (C1) Dept., dt. 5-11-
[Subs. By G.O. Ms. No. 1007, Tr. executed till the expiry of the defect liability period as 1976].
TR&B (C1) Dept., dt. 5-11-1976]
prescribed therein. Each department should formulate The contractors are responsible for the quality of works
and issue guidelines based on the nature and life span of executed till the expiry of the defect liability period as
works as stipulated in para 25 of Annexure-I to G.O. Ms. prescribed therein. Each department should formulate and
No. 94, I&CAD (PW-COD) Dept., dt. 01.07.2003 issue guidelines based on the nature and life span of works as
stipulated in para 25 of Annexure-I to G.O. Ms. No. 94, I&CAD
(PW-COD) Dept., dt. 01.07.2003

2
Sl. Reference Existing Text Proposed Text Recommendations of Board of Chief Engineers
No. to PS
I P.S. 41 Tolls The contractors shall, unless The contractors shall, unless otherwise specifically stated
(4) and otherwise specifically stated in in the tender notice and subsequently on this basis in the
seignorage the tender notice and contract be responsible for the payment wherever
subsequently on this basis in the payable of all import duties, tolls, octroi duties,
contract be responsible for the seigniorages, quarry fees, etc., on all materials and
payment wherever payable of all articles that he may use.
import duties, tolls, octroi duties,
seigniorages, quarry fees, etc., on The contractor shall be solely responsible for the payment
all materials and articles that he of GST under the provisions of the Andhra Pradesh
may use. Goods and Services Tax Act, as in force for the time
being and the rates for the various items of work shall Agreed
The contractor shall be solely remain unaffected by any change that may be made from
responsible for the payment of time to time in the rate at which such tax is payable.
sales tax under the provisions of
the Andhra Pradesh General Sales Notwithstanding anything Customs Tariff Act 1975 and
tax Act, as in force for the time as amended from time to time the rates for items
being and the rates for the involving the use or supply of articles obtained by the
various items of work shall contractor from outside India shall remain unaffected by
remain unaffected by any change any changes that may be introduced in the Customs
that may be made from time to duties.
time in the rate at which such tax
is payable.

Notwithstanding anything
contained in Section 10 of the
Indian Tariff Act of 1894 the rates
for items involving the use or
supply of articles obtained by the
contractor from outside India
shall remain unaffected by any
changes that may be introduced
in the Customs duties.

I P.S. 45 [(b) It shall be Contractor’s sole [(b) It shall be Contractor’s sole responsibility to protect Agreed.
(5) Accidents – responsibility to protect the Public the Public and his employees against accident from any
Hoarding, and his employees against cause and he shall be indemnify Government against any
Lightings, accident from any cause and he claims for damages for injury to person or property,
Observation shall be indemnify Government resulting from any such accidents, and shall where the
s– against any claims for damages provisions of the Workmen’s Compensation Act, 1923,
Watchmen for injury to person or property, apply, take steps to properly insure against any claims
resulting from any such accidents, thereunder. The contractor shall execute the ‘Indemnity

3
Sl. Reference Existing Text Proposed Text Recommendations of Board of Chief Engineers
No. to PS
and shall where the provisions of Bond’ in the prescribed form noted below for the payment
the Workmen’s Compensation of claims coming under (a) Workmen’s Compensation Act,
Act, 1923, apply, take steps to 1923, (b) Minimum Wages Act, 1948, (c) Payment of
properly insure against any claims Wages Act, 1936, (d) Contract Labour (Regulation and
thereunder. The contractor shall Abolition) Act, 1970, (e)AP Buildings and other
execute the ‘Indemnity Bond’ in constructions Workers Welfare Cess Act, 1998, (f)
the prescribed form noted below AP Buildings and other construction workers Act
for the payment of claims coming 1996, and all other such Acts in force and that may be
under (a) Workmen’s enacted from time to time during the currency of the
Compensation Act, 1923, (b) agreement.
Minimum Wages Act, 1948, (c)
Payment of Wages Act, 1936, (d)
Contract Labour (Regulation and
Abolition) Act, 1970 and all other
such Acts in force and that may
be enacted from time to time
during the currency of the
agreement.
I P.S. 58 Date On notification of possession of Upon signing the agreement, the contractor shall Date of agreement is the date of handing over
(6) of the site (or premises) being given forthwith begin the work, shall regularly and continuously of the site normally for projects (unless &
commencem to the contractor by letter proceed with the work and shall complete the same
ent and registered for acknowledgement (except for painting or other work which, in the opinion of
otherwise a different date of handing over site
completion: as provided in paragraph 10 the Executive Engineer, it may be desirable to delay) by mentioned in the agreement ), and upon signing
Supra, he shall forthwith begin the date of completion as defined in “Articles of the agreement, the contractor shall have possessed of the
the work, shall regularly and Agreement”, subject, nevertheless, to the provisions of site ( or Premises) and shall forthwith begin work, shall
continuously proceed with them, extension of time mentioned in the next clause. The regularly and continuously proceed with the work and shall
and shall complete the same contractor shall under no circumstances be entitled to complete the same ( except for painting or other work which,
(except for painting or other work claim any damages from Government if he incurs any in the opinion of the Executive Engineer, it may be desirable to
which, in the opinion of the expense or liabilities to payment under the contract delay) by the date of completion as defined in “ Articles of
Executive Engineer, it may be before the date of commencement defined above. The Agreement” subject, nevertheless, to the provisions of
desirable to delay) by the date of contractor shall have the right to withdraw from the extension of time mentioned in the next clause. The contractor
completion as defined in “Articles contract and obtain refund of his security deposit if such shall under no circumstances be entitled to claim any damages
of Agreement”, subject, intimation of handling over the site is delayed more than from Government if he incurs any expense or liabilities to
nevertheless, to the provisions of two months from the date of acceptance of the payment under the contract before the date of commencement
extension of time mentioned in agreement by competent authority. defined above. The Contractor shall have the right to withdraw
the next clause. The contractor from the contract and obtain refund of his security deposit if
shall under no circumstances be such intimation of handling over the site is delayed more than
entitled to claim any damages two months from date of acceptance of the agreement by
from Government if he incurs any competent authority.
expense or liabilities to payment
under the contract before the

4
Sl. Reference Existing Text Proposed Text Recommendations of Board of Chief Engineers
No. to PS
date of commencement defined
above. The contractor shall have
the right to withdraw from the
contract and obtain refund of his
security deposit if such intimation
of handling over the site is
delayed more than two months
from the date of acceptance of
the agreement by competent
authority.

I Clause (c) [Note ;- The contractor who Completely deleted Agreed


(7) under PS makes a standing security deposit
60. Delay in of Rs. 1,00,000 (Rs. one lakh)
commencem with the Chief Engineer under
ent or whom he wishes to tender for
Progress or works is eligible for concessional
neglect of rates of Earnest money deposit
work and and retention from bills. However,
forfeiture of for the purpose of forfeiture under
earnest the above clause, security deposit
money will be reckoned at the normal
security rate, assuming that there is no
deposit and standing security and not at the
withheld concessional rate].
amounts [Amended by G.O. Ms. No. 471,
Tr. R&B (C) Dept., dt. 07-10-
1983]

I P.S. 61- Note 1: “Tenders shall be called for, for the works taken Agreed.
(8) Suspension over under clause (61) of PS to APSS based on the
of works by revised estimates prepared with the prevailing SSRs. In
the case the revised estimate exceeds, the original estimate
contractor beyond the powers of officers, the position shall be
brought to the notice of the Government for orders. The
Chief Engineers are competent to sanction the Revised
Estimate if revision is purely due to increase in SSR, as
per orders issued in GO Ms. No. 157 Dated. 07.05.1980.”

5
Sl. Reference Existing Text Proposed Text Recommendations of Board of Chief Engineers
No. to PS
I P.S. 68- Note 1: Not to deduct the FSD @ Note 1: Not to deduct the FSD @ 2.5% in the final bills if Agreed
(9) Payments 2.5% in the final bills if the final the final bills are submitted after completion of the Defect
and bills are submitted after liability period, subject to obtaining the required
Certificates completion of the Defect liability certificates. b) Not to insist for extension of BGs at the
period, subject to obtaining the time of payment of final bills for which the Defect liability
required certificates. b) Not to period is completed subject to obtaining the required
insist for extension of BGs at the certificates.
time of payment of final bills for
which the Defect liability period is
completed subject to obtaining
the required certificates.
I P.S. 69 Note 1: In respect of EPC works Note 1: In respect of EPC works the retention amount in Agreed
(10 Interest on the retention amount in excess of excess of 2.5% of value of work done shall be released
) money due 2.5% of value of work done shall against unconditional BG in multiples of Rs. 25 Lakhs ( in
to the be released against unconditional respect of contracts of Rs. 100 crores and below) and Rs.
contractor BG in multiples of Rs. 25 Lakhs ( 50 Lakhs (in respect of contracts of above Rs. 100 crores)
in respect of contracts of Rs. 100 , if the rate of progress is maintained. The unconditional
crores and below) and Rs. 50 irrevocable BG shall be for the period till the final bill is
Lakhs (in respect of contracts of paid. In the final bill 2.5% of value of work is to be
above Rs. 100 crores) , if the rate retained and kept under deposits. The same shall be paid
of progress is maintained. The after defect liability. If the final bill is submitted after
unconditional irrevocable BG shall completion of the defect liability period, the FSD @
be for the period till the final bill 2.5% shall not be deducted as per Note.1 inserted
is paid. In the final bill 2.5% of in the PS 68 to APDSS
value of work is to be retained
and kept under deposits. The
same shall be paid after defect
liability.

6
Sl. Reference Existing Text Proposed Text Recommendations of Board of Chief Engineers
No. to PS
I P.S. 70 The contractor agrees that before The contractor agrees that before payment of the final bill
(11 Acceptance payment of the final bill shall be shall be made on the contract, he will sign and deliver to
) of final made on the contract, he will sign the Executive Engineer either in the measurement book
measureme and deliver to the Executive or otherwise demanded a valid release and discharge
nts Engineer either in the from any and all claims and demands whatsoever for all
measurement book or otherwise matters arising out of are connected with the contract.
demanded a valid release and Provided that nothing in this clause shall discharge or
discharge from any and all claims release the contractor from his liabilities under the
and demands whatsoever for all contract. (Deleted the text “He shall also produce a
matters arising out of are certificate from the income tax authorities that all
connected with the contract. income tax payable by him up-to-date has been
Provided that nothing in this duly paid in the case of contracts the value of which Agreed
clause shall discharge or release is over Rs. 10,000”. It is further expressly agreed that
the contractor from his liabilities Executive Engineer in supplying the final measurement
under the contract. He shall also certificate need not be bound by the preceding
produce a certificate from the measurements and payments. The final measurements, if
income tax authorities that all any, of the Executive Engineer shall be final, conclusive
income tax payable by him up-to- and binding on the contractor.
date has been duly paid in the
case of contracts the value of
which is over Rs. 10,000. It is
further expressly agreed that
Executive Engineer in supplying
the final measurement certificate
need not be bound by the
preceding measurements and
payments. The final
measurements, if any, of the
Executive Engineer shall be final,
conclusive and binding on the
contractor.

I P.S. 73 Note 3 The Arbitration Note 3 The Arbitration proceedings will be conducted in
(12 Arbitration proceedings will be conducted in accordance with the provisions of the Arbitration and
) accordance with the provisions of conciliation Act 1996 and amendment act ‘The Agreed.
the Arbitration Act 1940 as Arbitration and conciliation (amendment) Act, 2021
amended from time to time. The (No. 3 of 2021) and as amended from time to time.
arbitration shall invariably give The arbitrator shall invariably give reasons in the
reasons for award award

7
S.No. Subject Recommendations of the HLTC Recommendations of Board of
Chief Engineers

II (1) Amendment to GO Ms. No. 41, Water Resources (Reforms) Dept. dt. 24.05.2018

Administrative Approval against Capital Heads of Account:- The HLTC recommended to amend the GO Ms. No. 41 Water
As per rule 37 of AP Government Business rules, the concurrence Resources (Reforms) Dept. dt. 24.05.2018 withdrawing powers
from the Finance department is required for according delegated to CE/ SE/ EE for according Administrative approval against
Administrative Approval against Capital Heads of Account.
the Capital Heads of Account.
The HLTC observed deviations in practice.
For Read Agreed in case of capital expenditure.
Nature of Powers Cadre Delegation of powers as per GO Ms. No. 41, WRD (Reforms) Administrative Department concerned in
Dept. dt. 24.05.2018 Government shall accord Administrative Approval
Administrative For Plain Areas For Tribal Areas with the concurrence Finance Department In case of Revenue Head of Account
Approval to estimates as per BoCEs recommendation dt.
for works (other than CE Rs. 20 Lakhs Rs. 30 Lakhs 15/11/2021
Residential buildings
and electrical works) SE Rs. 10 Lakhs Rs. 15 Lakhs

EE Rs. 1.0 Lkah Rs. 1.5 Lakh


Administrative CE Full
approval to Powers
Works of
repairs in SE Rs. 2
nature of Lakhs
Revenue Head (within
of Account (As allotted
per FRBM Grant)
norms
EE Rs.
conforming
30,000/-
Budget
(within
Allocation)
allotted
(For works
Grant)
other than

8
Residential
Building

For Residential CE Upto Rs.


Buildings 10 Lakhs

II (2) Validity of estimates for Annual Maintenance/ Operation and Maintenance

As per Article 198 of AP Financial Code Vol.I and The HLTC recommended for relaxation of the rule relating to validity of The ordinary repairs under
para 136 and 137 of APPW ‘D’ code, the Ordinary the Estimates exclusively for the purpose of payment of bills but not Revenue Head may be
repairs estimates for Roads and Buildings lapse on for execution of works. concurred and Urgent
the Last day of the Financial Year. In case of Repairs/ Emergent Repairs
sanctions shall continue as per
Irrigation works, separate dates have been
codal provisions.
stipulated.

The HLTC observed that in certain cases the


payments are not being made in full in the financial
year resulting in spill over of the liabilities to the
next year estimates.

Relaxation of the rule relating to validity of the estimates for AMEs/ O&M for the purpose of payment of bills

 As per Article 198 of AP Financial Code Vol.I and para 136 and 137 of APPW ”D” code, the ordinary repairs estimate for Roads and Buildings lapse on the last day of the Financial Year. In case of
Irrigation works, separate dates have been stipulated therein.
 The HLTC recommended to relax the rule relating to validity of the estimates for AMEs/ O&M for the purpose of payment of bills as in certain cases the payments are not being made in full during
the financial year.
Recommendation of HLTC subject to fulfilling of the following conditions:
1. It shall be mandatory for Engineering Departments concerned to put in place the Manual for Maintenance of all the assets such as Roads, Buildings, Dams, Canals etc., immediately

9
BoCEs agreed to the proposal.
2. The CCOs shall ensure appropriate provision in the BE to meet the cost of Maintenance as per norms
BoCEs agreed to the proposal.
3. The DDOs shall prefer the bills invariably in CFMS within the validity of the estimates as stipulated in the code. The relaxation granted now is only for the purpose of the payment but not for
execution of the work.
BoCEs agreed to the proposal.
4. While according technical sanction the following certificate shall be furnished invariably:
“Certified that the liabilities are not included in the estimate for Annual Maintenance/ O&M/ Ordinary repairs and it is prepared strictly adhering to the Physical and Financial norms approved by
the Government and the provisions made in the estimate are not overlapped.”
The BoCEs opined that the considering the liabilities in the estimate are not practicable and hence issuing of certificate is not necessary.

II (3) Amendment to GO Ms. No. 52, Water Resources (Reforms) Department dt. 06.10.2021

Para 297(3) of AP Public Works Accounts Code The following Para is to be added as column 4 at S.No. 1 to GO The BoCEs opined that the
Ms. No. 52, Water Resources (Reforms) Department, dt. GO Ms. No. 52 is only
The fact of check measurement by the sub divisional officer or the EE should 06.10.2021 enhancing the estimate
invariably be noted in the measurement book at the time of check value limits of the earlier
measurement and the items check measured should be indicated by the initials “The 15% of the total value of work done in each stage should be issued instructions. The
of the checking officer, which should be placed on the left side of the column the value of items that initialed by the Superintending Engineer Check measurement is to be
“particulars” in line with the item check measured. and not the value of entire items covered in certificate pages from done as per the codal
provisions and all are
– to page – as is being followed now, as per the provisions of Para
Para 294 of AP Public Works Department Code: The item in the measurement following the same. Hence,
294 of APPW ‘D’ Code”.
books actually check measure should, as a rule be initialed by the checking no need of amendment of
officer. Further, the EE/ Divisional Engineer should check measure at least once the G.O. Ms. No. 52, dt.
06.10.2021
all individual works costing Rs. 50,000 and more. The check measurement to be
done by the EE/ Divisional Engineer should be spread out throughout the year The following Para is to be added as column 4 at S.No. 2 to GO
Ms. No. 52, Water Resources (Reforms) Department, dt.
and there should be no rush of check measurement towards the end of the
06.10.2021
financial year. The frequency of check measurement should be correlated to the
amount of bills to be paid in the respective months. “The 30% of the total value of work done in each stage should be
the value of items that initialed by the Executive Engineer and not
the value of entire items covered in certificate pages from – to
Para 2 (viii) of GO Ms. No. 84 dt. 06.06.2000 page – as is being followed now, as per the provisions of Para 294
of APPW ‘D’ Code”.
All the SEs shall invariably check measure all the works costing Rs. 50 lakhs and

10
above at 1/3rd, 2/3rd stage of work and before final measurements and his
check measurements covering not less than 30% of the total expenditure
incurred each time. Similarly all the EEs shall invariably check measure all the
works costing Rs. 5 lakhs and above and his check measurements covering all
the major items not less than 30% of the total expenditure incurred each time.
A certificate to that extent that check measurements by SE/ EE have been
carried out shall invariably be recorded at the time of making payment duly
giving reference to the M.Book

II Works of Emergency Nature:


(4)
Issue Existing procedure being followed Suggestion of HLTC Recommendations of Board
of Chief Engineers

a. Para 177(a), 178 and Appendix XI of APPWD In case of emergent nature of work such as The HLTC has requested to refer the subject to The subject matter needs further
code read with Article 169 and 170 of APFC Vol.I the BoCEs: examination of the BoCEs and
1. Temporary Restoration of Breaches occurred
deals with the procedure to be followed in case hence deferred to the next BoCEs
to Canals/ Roads etc., due to Floods 1. Defining the nature of urgency and
of Emergency works. meeting.
categorisation of works to be taken up as
2. Making arrangements for visits of VVIP i.e.,
b. As per Article 299 of the APFC Vol.I when a ‘Emergency’
loss occurs by way of damage to any immovable Hon’ble President and Vice President of India,
Hon’ble Prime Minister of India, Hon’ble 2. To design the standard format of work order in
property belonging to the Government due to
Governor of State and Hon’ble CM etc., the such cases and
any calamity such as Fire and Floods or to any
cause other than fair wear and tear, the head of authorities i.e., EE/ SE/ CE are entrusting the 3. To formulate the procedure to be followed and
works on nomination basis as per their
the office concerned should send final detailed to ensure the quality of works taken up on
report to the HoD and to Accountant General in respective delegation powers in anticipation of emergency.
administrative sanction.
Form-20
However, in certain cases under the guise of
c. The Government vide GO Ms. No. 41, WRD
emergency, works are taken up in violation.
(Reforms) dt. 24-05-2018, have issued orders
enhancing the powers of the EE/ SE/ CE for Such practice should be desisted.
entrust of works on Nomination basis:

11
EE- 1 Lakh
SE- 2 Lakhs
CE- 3 Lakhs

II Treatment of Single Tender


(5)
As per instructions issued vide Govt. Memo No. The HLTC has observed that the procedure The HLTC opined that The subject matter needs further
1763-D/ 70-3, PWD (projects Wing) Dated. stipulated is being followed in practice. examination of the BoCEs and
30.09.1970, and also as per Government memo 1. In view of E-Procurement in place, single hence deferred to the next BoCEs
tender with discount may be considered.
No. 1720-D-72-6, PWD(PW) Dt. 27-10-1972, the meeting.
single tender shall not be accepted except in 2. single tender at estimate rates and with tender
case of extreme urgency or else fresh tenders premium shall be discussed in detail by the BoCEs
should be called for after some time and come up with the detailed procedure.

3. To suggest validations to be made in E-


Procurement Portal keeping in view the reverse
tendering process.

II 1. Preparation of DPRs by the Private consultants (or)


(6)
2. Preparation of DPRs by the departmental officers.

DPRs preparation The HLTC observed deviations in practice: HLTC opined to refer the matter to the BoCEs:

1. The selection of Engineering consultants for 1. To evolve proper terms and conditions (both
preparation of DPRs is being done by calling Financial and Technical keeping in view the
quotations instead of inviting through E- advancement in technology) for awarding the
Procurement. work of preparation of DPRs of various projects. The subject matter needs further
examination of the BoCEs and
2. The cost for preparation of DPRs and 2. Broad categorization of works that required to
provisions at different percentages ranging be awarded to private Engineering consultants. hence deferred to the next BoCEs
from 0.50% to 1.50% are being made in the meeting.
3. To fix up the cost payable to Private
estimates without giving any break up for the
Engineering consultants for preparation of DPRs
cost.
for various category of works.
3. As per GO MS. No. 69, Finance (Budget-I)

12
Department, dt. 14.08.2019, the expenditure 4. To deliberate and identify the works where the
for preparation of DPR shall be drawn under preparation of DPRs can be taken up
Detailed Head 280/289 Service based on the departmentally.
Professional Services.

The HLTC also opined that there is no


standardized procedure

1. for arriving the cost for preparation of DPRs


to various projects.

2. for fixation of qualification and experience


criteria of Engineering consultants to participate
in tenders to take up the work of preparation of
DPRs for various projects

3. No uniformity in the percentage of payment


to be released to the consultant at different
stages of work.

4. No penal clause for lapse on the part of the


consultants in the Agreement for DPR

5. Norms for preparation of DPRS


departmentally keeping in view of the
advancement of technology

Suggestions related to Extension of Time (EoAT), Physical Milestones, Quality Control Certificate and levying of Liquidity Damages (L.D.s) and L.S. Provisions in Estimates

Issue Existing procedure being followed Amendment proposed by HLTC Recommendations of Board
of Chief Engineers
III(1). Extension of Time (EoAT) There is no common procedure while issuing I) It is proposed that 1stEoAT may be sanctioned by the Agreement I. For Works costing less than Rs.
EoAT to the contractor. Committee studied the concluding Authority with a maximum limit upto 25% of Agreement 100.00 Crs:
orders of all Engineering Departments and period.
a) 1stEoAT for 25% of Time-
decided and recommended to implement a ii) 2ndEoAT can be sanctioned by the next higher authority upto 50% of

13
common procedure to all Engineering the period of Agreement excluding the 1stEoAT 25% time. Agreement Authority to
Departments while sanctioning EoAT to the sanction.
iii) Further EoAT will be sanctioned by the Government
contractor.
b) 2nd EoAT for above 25% to 75%
iv) The sanction should be based on the percentage of work done and
left over portion Time
To be sanctioned by the Next
v) The EoAT can be sanctioned with liquidated damages normally Higher Authority not beyond CE
vi) If the EoAT sanctioned without Liquidated Damages, there should
be valid reason and it is supported by the documentary evidence c) For further EoAT (beyond 75% of
issued by the competent authority and necessary check list. agreement period) will be
sanctioned by the Engineer-in-
Chief/ Chief Engineer

II. For Major Works costing greater


than Rs.100.00 Crs:

a) 1stEoAT for25% Time- Agreement


Authority shall sanction.

b) 2nd EoAT for above 25% to 75%


time
To be sanctioned by the HoD

c) For further EoAT (beyond 75% of


agreement period) will be
sanctioned by the Government.
Issue to be finalized in the next
BoCEs meeting.
III(2). Physical Milestones At present, only financial milestones are being It is decided that Physical Milestones are to be prepared with duly
followed and no physical Milestone programme fixing Agreement time and Bar Charts in excel sheets by the concerned
is in place. executing department on priority base, component wise and monthThe subject matter needs further
examination of the BoCEs and hence
wise with physical and financial duly following agreement clauses.
deferred to the next BoCEs meeting

14
III(3). Quality Control Certificate The HLTC discussed department wise that different types of 1. No QC certificate is required for
procedure/ formats are being followed for issuance of QC Certificates. works costing up to Rs. 10.00 Lakhs
The HLTC has reviewed the QC certificates being submitted by and Annual Maintenance Works.
different Departments/ Corporations at different stages. On detailed
2. QC certificate is required at the
deliberations, the Committee has agreed to bring uniform Quality
time of final Bill only for works
Control certificate to be accompanied with every Work Bill. The
uniform QC certificate for audit purpose for all the Departments/ costing Rs. 10 Lakhs to Rs. 40 Lakhs
Corporations, a draft QC certificate is placed at below. However, the 3. QC Certificate is required for stage
Committee felt that QC reports are to be prepared & approved as per wise for work bills @ 30%, 60% and
departmental norms and also QC manual by the different departments for final bill for the works costing
at their level without fail. between Rs. 40 Lakhs to Rs. 200
Lakhs.

4. The QC certificate to be
accompanied for every work bill for
the works costing above 200.00
lakhs.

5. All the Departments shall adopt


the QC Certificate as proposed by
HLTC

GOVERNMENT OF ANDHRA PRADESH


QUALITY CONTROL CERTIFICATE
(To be accompanied bill presented to PAO’s Office)
Certificate No. : Date of Inspection
Name of the Department :
Name of the Work :

15
Est. Value & No. :
Admin. Sanction No. & Dt. :
Agt. Value & No. :
Agt. Period :
EOT :
M.Book No. & Page :
Value of work done :
(Indicated from Page to Page of MB)
Recovery Proposed :
Reasons for Recovery Proposed :
(i) Certified that necessary QC checks have been carried out randomly and periodically as per the department norms, duly verifying the relevant records and field registers maintained by the
Agency/ construction staff. The Quality Test proves satisfactorily.
(ii) Certified that necessary QC checks have been carried out randomly and periodically as per the department norms, duly verifying the relevant records and field registers maintained by the
Agency/ construction staff. The Quality Test proved not satisfactorily and recommends recovery of Rs……………….towards defective work……………………………………………..
Asst. Exe. Engineer Dy. Exe. Engineer

Executive Engineer

Issue Existing procedure being followed Amendment proposed by HLTC Recommendations of Board of Chief
Engineers
III(4). Levying of Liquidity Damages The HLTC opined that the LDs should be linked with EoATs
(L.D.s) subject to furnishing documentary evidence issued by
Competent Authority of respective Departments with valid
reasons. If no authenticated document from the Competent The subject matter needs further examination of the
authority is furnished for extension of time (EoAT), LDs shall BoCEs and hence deferred to the next BoCEs

16
be imposed invariably as per the milestone programme meeting.
specified in the agreement.

III(5). L.S. Provisions in estimates

The HLTC observed that nearly 34 L.S. provisions are being made in the estimates. The said 34 provisions are pruned to 11 L.S. provisions giving justification for merger/ deletion as detailed
below:

S.No. Subject Justification Recommendations of Board of Chief


Engineers
1 Provision towards VAT or GST Since VAT/ GST is to be added to the Total value of work done it should be retained without Agreed
mentioning %.
2 Provision for Price Adjustment Since Price Adjustment is to be added / reduced to the Total value of work done it should be
retained.
3 Provision towards Seignorage Since Seignorage is to be added to the Total value of work done it should be retained
Charges
4 Provision for NAC Since NAC is to be added to the Total value of work done it should be retained.
5 Provision for unforeseen items Since unforeseen items of work is a standard provision in the Estimate
of work
6 QC Charges Some departments like PR meeting the QC equipment and other contingent charges from this To be retained
provision
7 Provision for Consultancy Proposed for retention as some of the other LS items are to be merged in this one Agreed.
charges
8 Provision for Engineering Different Corporations have different percentage of PS charges. Hence % proposed for deletion. To be retained as the salaries of the staff in the
Supervision charges corporations are based upon the percentages.
9 Provision for other department Payments to other departments like R&B for road cutting charges, Electricity Dept., for shifting/ To be retained. But, payments are to be made
charges erection of poles, electrical lines etc., against the demands issued by the other
departments.
10 Provision of pump sets The provision is compulsory for departments like RWS, PH, APSIDC for supply of water To be retained. However, based on the
11 Name Boards, Sign Boards The provision is compulsory for displaying the details of the scheme / project, sign boards etc., specification, quantities, the actual rates would be
finalized in the work slips/ working estimates before
making payment.
12 Provision for Transco charges Merger with item No. 9 Agreed.
13 Provision for Signage Board Merger with item no 11 Agreed.
14 Survey and investigation Merger with item No. 7 Agreed.
preparation @0.30% on the cost
of drip estimate

17
15 Establishment charges @15% Merger with item no. 8 Agreed.
16 Provision for Foundation/ Merger with item no. 5 Agreed.
inauguration charges
17 Photography/ Video Charges Merger with item no. 5 Agreed.
18 Soil Testing Charges Merger with item No. 7 Agreed.
19 DPR Charges Since separate sub-detailed head of account is proposed for meeting the charges The provision is needed when it is to be charged to
the work estimate where there is no separate
administrative sanction for preparation of DPR.
20 LabourCess Since the Government decided as a policy matter that the Labour Cess is the responsibility of Agreed.
Contractor

21 Provision for Landscaping It has no relevance Agreed to delete.


22 Provision towards EPABX & LAN The provision has no relevance
system
23 Provision for Equipment The provision has no relevance
24 Maintenance Charges The provision has no relevance
25 CCA amount to be paid to The provision has no relevance
irrigation circle
26 Provision for Capacity building/ The provision is being misused. All the contingent bills which are not payable under existing rules are
Sensitisation of members of being processed under this provision.
beneficiaries committee@0.50%
on cost of project
27 Publication Charges Separate head of account is there for meeting publication charges Agreed to delete.
28 O&M Charges O&M of works taken up by sanction of separate maintenance estimates. Hence the provision has no Agreed to delete.
relevance.
29 Provision towards Service Tax Since this LS provision subsumed in GST, the provision has no relevance

30 Provision towards work The provision has no relevance Agreed to delete.


contingencies
31 Provision for limited distribution The provision has no relevance Agreed to delete.
@ head work site
32 Provision for non-refundable The provision has no relevance Merged with Item No.9
deposit for Forest authorities to
obtain Forest clearances
33 Provision for LA Land Acquisition payments are being charged to separate HoA, the provision has no relevance. Depending upon the necessity, this provision is to
be considered

18
III(6) L.S. Provision in estimates towards unforeseen Item

Issue Existing procedure being followed Amendment proposed by HLTC Recommendations of Board of Chief Engineers

Unforeseen 117 – A. In the estimates for major works, provision up to 2 The HLTC after detailed deliberations has recommended that provision for unforeseen item can be allowed in four
Item percent of the estimated cost of the works portion may (4) slabs on Estimate Value as follows:
ordinarily made for “unforeseen works”. When found
necessary, this provision may be utilized for new items of S.No. Estimate Value Percentage
works which are required by the administrative authority (%)
Agreed
and which are essential for the fulfillment of the precise
1 Up to Rs. 20.00 crore @2%
object for which the estimate for the main work is
intended. The working estimates for such works will be 2 Rs. 20.00 Cr to Rs. 100 Cr @1.5%
sanctioned by the Executive Engineer upto a limit of Rs.
2,500/- for each item and by the Superintending Engineer 3 Rs. 100.00 Cr to Rs. 500 Cr @1%
beyond this limit – vide Paragraphs 417 (g) and 428 (f).
4 Rs. 500 crore and above @0.5%

Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

1 2 3 4 5 6

IV(1) Sl. No. 3 of Technical Comparison of the RE with The committee observed that The Technical sanctioning authorities are
Sanction AS and TS:- comparative statement is available in instructed to comply with the provisions of
CFMS Phase-II. the codes and instructions issued by the
Contents of the Para 102
Government from time to time scrupulously
read with Para 214 and from The Government felt the need to
without any deviation.
Para 415 to 430 of APPWD reiterate the provisions of the Code

19
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

code read with GO Ms No. and Orders issued by the Government In the RE, the reasons warranted for such
41, Water Resources from time to time in respect of excess shall be explained in detail giving
Agreed.
(Reforms) Department, dt. powers to sanction the RE justification for excess.
24.05.2018 stipulate the
The Technical sanctioning authorities are
procedures to be followed at
instructed that in case of any change of
the time of approval of RE
with reference to Original design or alignment the approval of the
authority who originally sanctioned the
Estimate (Subject to limits
scheme shall be obtained before approval
specified in the GO referred
to above to accord sanction of the R.E. as per competency
excess over Estimate)within Concerned Engineering Departments and
the ambit of administrative DoWA is instructed to ensure compliance to
sanction the instruction.

IV(2) Sl. No. 7 of Technical Leads provided in the The committee observed the The EE/SE/CE is instructed to follow the The EE/SE/CE is instructed to follow the
Sanction and Sl. No. 7 Estimate shall not be enhancement of leads stating the provision of the codes and ensure provision of the codes and ensure
of Billing changed:- reasons as non-availability of the compliance to the recommendations of the compliance to the recommendations of
materials at specified source as per HLTC scrupulously without any deviation. the HLTC scrupulously without any
As per section No.11
estimate resulting extra Financial deviation.
(Tenders) of Part-II of Commitment on the state exchequer. They are also instructed not to resort to
APPWD code (Para 4 of the deletion of an item of side earth from the They are also instructed not to resort
Government Memo No. The committee has recommended to purview of OE for replacing with borrowed to deletion of an item of side earth
1348/ Y/ 68-4, dt. 24-11- capture the location and distance of earth/ selected earth for the reason that no from the purview of OE for replacing
1970, every bidder is the nearest quarry duly attaching the side earth or suitable side earth is available with borrowed earth/ selected earth
expected to inspect the site quarry map to prevent extra leads during the execution. After concluding the for the reason that no side earth or
of work before quoting his duly certifying that lead from nearest Agreement, acceptance for enhancement of suitable side earth is available during
rates and satisfy himself quarry and shortest route was only leads is strictly prohibited as it is the the execution. After concluding the

20
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

about the quality and considered. responsibility of the contractor to procure Agreement, acceptance for
availability of material as the suitable materials by abiding the clause enhancement of leads is strictly
Government will not accept in the Agreement. prohibited as it is the responsibility of
for any enhancement of the contractor to procure the suitable
The DoWA is instructed to ensure
lead. materials by abiding the clause in the
compliance to the instructions.
Agreement except in Special
situation with prior approval
of the Technical Sanction
Authority.
.

IV(3) Sl. No. 13,16 and 17 of 1. Justification for


The committee has noticed that The EE/SE/CE are instructed to follow the The BoCEs objected to the proposed
Contract Supplemental items
certain items of the work covered in provisions of the codes scrupulously and certification as the inclusion of non-
contingent on main work and the scope are being replaced with furnish the following certificate while contingent items should be on the
execution of those items items relatively, besides change of according sanction to the RE. discretion of TS authority as per the
through original contractor.specification and change in following reasons:
“Certified that, the items which can be
classification of soil, and also
2. Execution of Additional observed that items which can be executed independently without effecting i) The original estimates would be
items not contingent on or interfering with the execution of main prepared based on the trail pits and
executed independently are included
Main work after calling work (not contingent on main work) are not sample checks/tests. There would be

21
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

tenders:- in the RE and entrusted to the covered in the R.E. and the items of the possibilities where change in
original agency. work which are covered in the R.E. are classification of soils or need of change
As per Note 6 under Para
essential for completion of the main work.” in specifications while execution
154, Para 176 (e) of The committee recommended for depending on the requirement.
APPW”D” code read with PS instructions for proper compliance to The DoWA is instructed to ensure the same
63 to APDSS and Para 13-6-1 the provisions of the codes and ii) Sometimes, it would be economical
of PAO(WA) Manual instructions issued by the or time saving to take up certain
stipulates procedures to deal Government from time to time to authorized extras through the original
with Supplemental items and avoid such tendencies. contractor though it can be executed
Additional items contingent independently.
on Main work and non-
contingent on main work.

IV(4) Sl. No. 2,4 and 6 of Proper Classification of Mostly in Irrigation and R&B The Authority who is empowered to accord Agreed in case of capital works.
administrative sanction works duly indicating proper Department, large numbers of works Administrative Sanction for ordinary repairs
and Sl. No. 31 of Billing HOA while according relating to Ordinary repairs/ O&M are shall follow the provisions of the codes and However, In case of Revenue works the
concerned HOD should be given the
Administrative Sanction to being taken up. The Committee has Manuals scrupulously.
authority for change of HOA.
avoid of duplication in suggested to provide Check list at bill
sanction:- The Paras 88 to stage that The following certificate shall be furnished
while according administrative sanction.
99, 133,134,142 of APPWD
1. Certified that the authority who
code and Article 147 of AP Certified that, works for which the A.S. is
Financial code Vol-I and accorded original sanction only issued
the amendment changing the HOA/ accorded is properly classified as per
Chapter III of AP PWA code provisions stipulated in the code and not
Category of the work as per
and Para 5-7-1 and Para 5-2- covered the same work in any other
5 of PAO (WA) Manual competency.
schemes.
stipulate for proper 2. Certificate to the effect the works
classification of works They are also instructed to indicate
taken up under the present scheme is
(Original/ Special repairs/ not covered/ duplicated in any other appropriate Head of Account in the A.S. and
Ordinary repairs etc., ) and any subsequent changes in the Head of
scheme.
also the necessity to obtain Account for all works including works

22
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

Administrative Approval sanctioned against Capital HOA, the orders


from the competent of the Govt., shall be obtained.
authority.
Check List:-
As per Para 148 of APPWD
Code it is irregular to classify 1. The work sanctioned now is not covered
in any other scheme (AS stage)
under “Special Repairs” an
Estimate which provides for 2. The classification of the work is strictly
items of ordinary repairs for made as per provisions of the code.(AS
the reasons that the repairs stage)
cannot be completed before
the date fixed for the closure 3. Whether the orders of the Government
of Annual Maintenance for change of the HOA are received? (At Bill
Estimates. Creation stage)

The DOWA shall take necessary action in


consultation with CEO APCFSS to provide
check list in CFMS at AS and Bill Creation
Stage.

IV(5) Sl. No. 1,2 of Technical The Detailed estimate must The committee suggested to provide The technical sanction authorities are Agreed
Sanction be informative:- necessary check list in CFMS Works instructed to comply with the provisions of
Module as indicated below: the code and follow the instructions issued
Para 112 to 149 under by the Government meticulously to ensure
section-E (preparation of 1. Whether the detailed estimate is
preparation of estimate realistically. It is
estimates) under Chapter-II accompanied by a specification
mandatory on the part of the Technical
(Works) of AP PW ”D” code report, approved plans, drawings and sanction authorities to see that all the
stipulate that the detailed designs?
relevant documents are accompanied the
estimate shall be informative
2. Whether the site is inspected by estimate.
and must be accompanied by

23
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

approved drawings and the competent authority and certified The DOWA shall take action in consultation
designs. The Government accordingly? with CEO APCFSS to provide check list in the
vide GO Ms. No. 37, CFMS works Module at Estimate stage.
TR&B(B.1) Dept. dt. 3. Whether the shortest lead was
considered from the location of the 1. Whether the AS is accorded or not?
30.01.1997 and vide GO. MS.
selected quarry to site of work while
No. 94, I&CAD(Reforms) 2. Whether the site is inspected by the
Dept., dt. 01.07.2003 have calculating the cost of conveyance as
competent authority and report of
per lead statement?
issued certain instructions inspection is enclosed?
for compliance while
preparation of estimate. 3. Whether the detailed estimate is
accompanied with the report of
Specifications and necessity to take up the
work, approved Drawings and Designs, Soil
Classification report?

4. Whether the shortest lead was


considered from the location of the
selected quarry to site of work while
calculating the cost of conveyance as per
lead statement and certificate to that effect
is furnished in the lead statement?

5. In case of excavation/ dismantlement


whether necessary provision for anticipated
credits was made?

6. Whether the provision for permissible


reimbursable items is properly provided in
the estimate?

24
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

7. Whether the status of shifting of Utilities


is furnished?

8. Whether the Status of clearances such as


Forest, Hydrological and Environmental
clearance etc., wherever necessary are
furnished?

IV(6) Sl. No. 9 of Technical Yard sticks to be followed for The Committee stressed the need for
The Technical Sanction authorities are
Sanction preparation of Annual reiteration of instructions for proper
instructed to follow scrupulously the yard
Maintenance Estimates/ sticks stipulated for preparation of Annual The subject matter needs further
compliance to the yard sticks to be
examination of the BoCEs and hence
Operation and Maintenance followed in preparation of
Maintenance Estimates/ O&M Estimates. It
deferred to the next BoCEs meeting.
Estimates for Maintenance maintenance estimates to avoid cost
shall be mandatory on the part of
of various assets of the overrun. concerned Engineering Departments to put
Government such as Roads, in place the Manuals for maintenance of
Buildings, Dams and Canals The committee suggested to insist various Assets.
the following certificate from the
etc.
authority who accorded the TS as The following certificate shall be furnished
The para 136, 137 and 144 mentioned below. while according technical sanction
and section 23 of Part-II of
AP PW “D” code read with “Certified that the estimate for “Certified that the Estimate for Annual
maintenance of the work is prepared Maintenance/ O&M work is prepared
Para 198 of APFC Vol-I read
with G.O. Ms. No. 132, as per financial norms approved by strictly adhering to the physical and
TR&B(R1) Dept., dt. 22-06- the Government and there is no cost financial norms approved by the
overrun” Government and the items of the work
2005 and G.O. Ms. No. 35,
covered in the Estimate are as per yard
TR&B (Roads-I) Dept., dt. 17-
09-2019 stipulates procedure sticks.”
to take up Annual The DOWA shall ensure compliance to the
maintenance of various instructions.

25
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

public assets.

IV(7) Sl. No. 4 of contract Compliance to the remarks The HLTC observed that in practice, The Agreement concluding authorities are
and 8 of Tenders of the COT:- the works are being executed without instructed to comply with the remarks of
compliance to the remarks the COT before concluding the agreement
As per GO Ms. No. 94, I&CAD communicated by the COT resulting and the following certificate shall be
Dept., dt. 01.07.2003 read
in unnecessary increase in project furnished in the Agreement forwarding slip
with GO Ms. No. 41, Water
cost. The Committee has suggested
Resources (Reforms) Dept. to insist the following certification at “Certified that the COT has approved the
dt. 24.05.2018, the Tenders tenders vide Proc. No…..dt. And the
the time of Agreement and bill
costing above Rs. 10 Crores agreement was concluded after complied
respectively. Agreed
shall be verified and with the remarks communicated by the
accepted by the COT Agreement:- COT”.

1. Certified that the COT has The authenticated copy of COT proceedings
approved the tenders vide shall be appended to the agreement.
Proceedings No…….dt. ...and remarks
raised by the COT/ Competent The DOWA shall take action in consultation
with CEO APCFSS to provide the check list at
authority are complied with.
Agreement stage.
Bill:-

Certified that the remarks pointed


out by the COT are complied with.

IV(8) Billing Sl. No. 3 and 4 Quality control Measures:- The committee during its The DDOs are instructed to disallow the
deliberations observed that there are portion of work which is not met with the
As per G.O. Ms. No. 23,
incidences that the QC authorities are standards of the quality as per
I&CAD (PW:COD) Dept., dt.
issuing the QC certificates indicating specifications while preparing the bill duly
05.03.1999, the Government

26
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

have issued orders to see certain adverse comments on the furnishing the following certificate:-
that the quality audit is done work besides proposing the recovery
“Certified that the work covered in the bill The subject matter needs further
periodically and also evolve as a measure of penalty besides
suitable punitive action insisting the contractor for was inspected by the quality control examination of the BoCEs and hence
authorities and the rectifications pointed deferred to the next BoCEs meeting.
against the contractors as rectification of defective work before
out have been carried out by the contractor
well as Engineers in charge of making payment. The committee
the work who violate proper suggested for submitting ATRs by the and necessary ATRs are furnished to the
Q.C. Authorities.”
quality standards. EE on the remarks raised by the QC
authorities along with the bill. The DOWA shall take action in consultation
with CEO APCFSS to provide said certificate
in the check list in the CFMS works Module
at bill creation stage.

IV(9) Sl. No. 10 of Technical Any alteration in the designs The committee stressed the need for The Technical Sanctioning authorities are The BoCEs opined that the permission
Sanction and Sl. No. 10 during the course of reiteration of the provisions to ensure instructed that in case of any change of of originally sanctioning authority may
of Billing. execution shall be approved that the approval of the authority for design or alignment, the approval of the be obtained by the technical
by the competent authority:- the deviation in designs who authority who originally sanctioned the sanctioning authority in cases of
sanctioned the scheme originally. scheme shall be obtained and the following important structural alterations and
Para 187 of APPWD code and
certificate shall be furnished in the Revised alterations involving huge outlay.
Article 196 of AP Financial Technical Sanction.
code Vol.I read with Para 5 of
the Executive instructions “Certified that the approval for deviations
“Certified that the approval for
stipulated vide Government to the Finalized Drawings and Designs has
memo no. 3A/ TC/ 66-1PW; been obtained from the authority who important deviations to the
dt. 21-01-1967 incorporated Finalized Drawings and Designs has
sanctioned the scheme originally and such
under Para 154 of APPWD been obtained from the authority who
deviations are inevitable to ensure proper
code stipulate that the completion of work.” sanctioned the scheme originally and
Departmental officers should such deviations are inevitable to ensure
The DOWA shall take necessary action in proper completion of work.”
not change the design or
consultation with CEO APCFSS to provide

27
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

alignment of any structure. the Check list at RE stage in the CFMS The DOWA shall take necessary action
in consultation with CEO APCFSS to
Where important structural
provide the Check list at RE stage in the
alterations are CFMS
contemplated, though not
necessarily involving an
increased outlay, orders of
the original sanctioning
authority should be
obtained.

IV(10) Sl. No.6 of Technical Competency to approve the The committee after deliberation has The Technical sanction authorities are The observed data shall be got
Sanction Observed data:- suggested to refer the matter to instructed that the observed data shall be approved by the next higher authority
BoCEs for deciding the competency got approved from the ENC to ensure of Technical sanctioning authority as
As per Govt. Memo No. 102-
for approval of the observed data and uniformity, quality and economy in cost. certain observed datas could be site
y/72-10 PWD; dt. 02-04- also the rates for items not covered in specific.
1973, Government have The ENCs are instructed to take action
the SSR.
decided that the CEs should accordingly pending decision from the Further, the observed data with huge
obtain the data worked out BoCE. financial implication may be placed
in usual manner from the EE before the BoCEs for examination
through SE. The data should The DOWA is instructed to ensure
compliance to the instructions. Further, any data observed or derived
be examined by the Quality
control wing wherever they from the existing data or adopted
are present and if, there is from other source shall be placed
before the BoCEs to include in the
no such organization, the
standard data.
data and Non-SSR rates
should be examined by the
cell to be constituted

IV(11) Sl. No. 9 of Tenders Checking of the computed The committee felt that consequent The Executive Engineers are instructed to The BoCEs recommend

28
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

Tenders by the DAO(W):- on introduction of E-Procurement, assign the role of checker to the assigning the role of checker
the DAO is not involved in Tender DAO(works) in the E-Procurement process
As per Para 93 of APW “A” in the offices of EE and SE
process. In the E-Procurement next below to EE to comply with the
code the DAO(W) is process, there is a provision available provisions of APW “A” Code. based on the cadre available
responsible for arranging for in the respective offices.
for assigning the role of Checker next
checking the computed The Superintending Engineers are
below to the EE
tenders i.e., for seeing that instructed to assign the role of checker to
satisfactory and efficient the next technical authority to the SE at
arrangements are made for circle level i.e., EE/DEE who will assist the SE Read EE As DSE at Circle Level &
checking the tendered in checking of Tenders.
Read DEE As PA to EE/Dy.sEE at
documents
Division Level for all departments
except PR Department.

In PRED, there is a PA to EE post in the


cadre of DEE who is checking the
tenders in e-procurement next below
to EE.

Superintending Engineers are


instructed to assign the role of checker
to the next technical authority to the
SE at circle level i.e., EE/DEE who will
assist the SE in checking of Tenders.

Amend Para of APW(A) Code.

IV(12) Sl. No. 2 of Contracts Avoidance of the Delay in The committee has noticed the The Agreement concluding authorities are
concluding the Agreements incidences of delay on the part of the instructed that the Agreement shall be
by the Agreement concluding Agreement concluding Authority. concluded within 07 working days from the

29
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

authorities:- Hence the committee suggested to date of receipt of relevant documents from
refer the matter to the BoCE to fix up the lowest bidder without any delay.
Point No. 3(ii) under
the maximum time gap between the
Appendix-IX (Agreements) of date of tender acceptance and date If the lowest bidder failed to respond within
the PAO (WA) Manual, the stipulated period from the date of issue
of concluding the agreement.
stipulate that there should of LOA, action shall be taken as per rules.
not be inordinate delay in
The concerned Engineering Departments
conclusion of the
Agreement. shall follow the above instruction
scrupulously.
As per existing orders of the
The DoWA is instructed Agreed
Government, the successful
tenderer has to submit all
the required documents and
sign an agreement within the
time stipulated in Letter of
Acceptance.

As per G.O. Ms. No. TR&B


(Roads-V) Dept., dt.
06.06.2008 on failure to do
so, the agreement
concluding authority
concerned will suspend the
business of the erring
tenderer for a period of one
year duly forfeiting the
E.M.D. paid by him without
issuing any further notice.

30
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

IV(13) Sl. No. 23 of Billing In respect of EPC contracts The High-Level Technical Committee As per Para 309 of APPWA code, the The subject matter needs further
whether the quantities are tohas felt that there is need for Engineer-in-Charge should check the claim examination of the BoCEs and hence
be linked with the payment thorough examination to clarify with reference to the measurements/ deferred to the next BoCEs meeting
schedule:- whether the quantities are to be Levels recorded to ensure that the
linked with the percentage as per percentage of payment is arrived at in
In the G.O. Ms. No. 50,
payment schedule. proportion to the work executed and
I&CAD (PW-Reforms) Dept., recorded.
dt. 02-03-2009, Government
have issued orders amending Therefore, the EEs are instructed to check
Para 309 of AP PW “A” code the claim as per said provisions of the code
stipulating the Engineer-in- without any deviation.
Charge should check the
The DoWA is instructed to ensure
claim with reference to the
compliance to the said provision of the
measurements recorded vis-
à-vis Payment Schedule. code.

IV(14) Sl. No. 32 & 33 of 1. Proper realization and The Committee suggested to refer There is no need to refer the matter to the The rules may be modified based on
Billing accounting of the cost from the matter to BoCE for framing BoCE because the existing rules would case specific. The order cannot be
the sale of dismantled proper guidelines for utilization/ address the subject well. generic as the BoCEs opined that in
material such as useful disposal or retrieval material to the case of emergency works, protection of
The EEs are instructed to follow the
wood, steel, etc., from best advantage of the Government. dismantled material is very much
dismantlement of structures. provisions of the codes for proper difficult and hence the said proposal is
accounting, utilization of the useful material
Useful soil, Hard rock to be adopted on case specific basis.
and also realization of sale proceeds to the
artifacts etc., obtained from
the excavation during course best advantage of the Govt., through E-
Auction platform without giving any scope
of execution are carried out.
for pilferage. The Monthly report shall
2. Procedure was stipulated invariably be furnished to the SE and PAO/
in the Executive Instructions APAOs till the realization and accounting of
under Para 154 and Para

31
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

423(b) of APPWD Code, for the sale proceeds.


proper estimation of the
anticipated credits on
account of retrievals if any
which are useful and fetch
value from their disposal.

IV(15) Sl. No. 1 of Billing E-Procurement is to be The committee opined that check list The EE/SE/CE is instructed to follow the Deferred to the next BoCEs meeting to
adopted for all works costing is required for enforcement of rules orders issued in the GOS without violation be discussed along with emergency
Rs. 1 lakh and above:- at agreement stage in the form of except in respect of cases where the Govt., nature of works.
certification which shall be as ordered for exemption from E-Procurement
The E-Procurement follows:- Process (Works to be entrusted on
procedure was introduced
Nomination to the Notified Committees).
vide G.O. Ms. No. 2, Fin 1) “Certified that the work is
department, dt. 03.02.2014 entrusted on nomination basis.” (Yes/ The following certificates shall be furnished
and G.O. Ms. No. 61, PR&RD Not applicable) while submitting the agreement/ work
Dept., Dt. 01.04.2014. order/ purchase order in respect of which
2) Certified that the work is entrusted
According to said GOs, E- the E-Procurement procedure was not
Procurement shall be through e-procurement. (Yes/ Not followed.
Applicable)
followed for all works and
“Certified that the Govt., vide GO/ Memo
material procurement (for
works and for stationery/ No….dt….has permitted for exemption
from the process of E-Procurement”
livery supplies for offices
etc., ) costing Rs. 1.00 Lakh The Orders issued by the Government
and above. exempting from E-Procurement without
The e-procurement platform concurrence from the Finance department
shall not be considered in Audit.
should be adopted so as to
enhance transparency and The DOWA in consultation with CEO CFSS
bring uniformity across all shall take necessary action for incorporation

32
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

the departments except in of the said certificate in the Check list at


respect of works costing Rs. Agreement stage in CFMS module
5 lakhs and below which are
to be entrusted on
nomination basis to the
committees such as WUA,
Village Committees SHGs
etc.,

IV(16) Sl. No. 20 of billing Sand Policy:- The Committee felt the necessity for The DDOs are instructed to furnish the Agreed
effectively implementing the following certificate while submitting the
Government vide Memo No: provisions of the GOs so as not to bills.
3066/ M.II(1)/2016-3, dt. 04-
lead any undue benefit to the agency
03-2016 have issued “Certified that the claim of the agency is
to the detriment of State exchequer.
instructions to make checked strictly in accordance with the
The committee has suggested
available the sand to the applicable sand policy as per the GOs issued
incorporation of a certificate in CFMS
public without charging any works Module at Bill creation stage. from time to time, without any deviation.”
fee from 2nd March, 2016.
The WRD vide GO Ms. No. The DoWA shall ensure compliance to the
instructions.
125, Water Resources (WRG-
GRC) Dept., dt. 29-12-2016 The DoWA shall take action in consultation
has issued orders for with CEO CFSS to ensure provision in CFMS
recovery of cost of the sand Works Module for capturing the differential
from the bills of the cost in sand involved on account of change
contractors. The in sand policy.
Government vide G.O. Ms.
No. 70 III & C (Mines-II) Dept.
dt. 04-09-2019 have issued
orders introducing new sand
policy in place of Free sand

33
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

policy with effect from


04.09.2019.

The WRD vide memo No.


ICD01-
C/R0MISC/23/2020/Reforms-
4, dt. 30.12.2020 have issued
instructions on the
recommendations of the
BoCEs for allowing new sand
rates for ongoing works
subject to condition that
“Placing proper mechanism
to ensure that the cost of
sand so loaded in the
estimates (Whatever the
cost, Government pays
towards the cost of sand to
contractors) must be
credited back to Government
account through Nodal
department i.e., III &
Commerce (Mines)
Department in Toto.

IV(17) Sl. No. 22 of Billing Ensuring provision in the The committee felt that any The following instructions are issued for
Estimate/ RE for reimbursement though legitimate, compliance.
reimbursable items;- shall not exceed the provision in the
All the Engineering Departments are
sanctioned estimate. The committee
The Government vide GO instructed to ensure adequate provisions in
suggested to give instructions to the

34
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

Ms. No. 94, I&CAD (PW-COD) DOWA to ensure that the the sanctioned Estimates/ R.E.s for claiming
Dept., dt. 01.07.2003 have reimbursable items are limited to the expenditure towards reimbursable items.
issued orders permitting provisions available in the estimate
certain provision such as fee technically sanctioned. In respect of GST, the departmental
Agreed.
authorities are instructed that the savings
for Tech Agent, VAT, BG
accrued on account of adoption of
Commission, Insurance
Charges etc., to be added to reformulated rates shall not be diverted for
taking up the additional work and the so
the Estimate in order to
accrued amounts along with the provision
make it a realistic estimate.
of VAT available in the sanctioned Estimate
Subsequently, the shall be utilized for meeting the fresh
Government have issued provision of the GST.
orders dispensing with the
The DOWA shall ensure compliance to the
provisions of technical agent
Fee and Insurance Charges. instructions.
Consequently, the The DoWA shall take necessary action in
Government vide GO Ms. No. consultation with CEO CFSS to provide
27, TR&B (R.III) Dept. dt. 29- necessary controls in the CFMS works
06-2015 have issued module to restrict the reimbursement to
instructions for providing the extent of provisions as per OE/ RE at bill
provision towards NAC @ creation stage.
0.10% of the amount
Estimate. Subsequently, the
Government, vide GO Ms.
No. 83, Water Resources
(Reforms) Dept., dt. 05-08-
2015 have issued
instructions to exclude
seignorage charges from

35
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

basic rates and moved the


same to Part-B provision of
the Estimate like NAC, VAT
etc., Consequent on
introduction of GST,
subsuming the VAT and
Excise Duty, the Government
vide G.O. Ms. No. 58, Finance
(WR.II) Dept. dt. 08.05.2018
issued instructions for
revision of estimates with
reformulated rates
(excluding Tax element in the
rates). The Secretary to
Government (R&E) Finance
department vide Memo No.
17023/107/FMU-
TR&B/2019, dt. 15.04.2019
have issued instructions to
ensure that the total
expenditure excluding
Tender Premium, Price
Adjustment and GST should
not exceed the
Administrative Approval
while arranging payment till
issue of comprehensive
orders.

36
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

With regard to Price


Adjustment, the
Government, Vide G.O. Ms.
No. 62, WRD dt. 30.11.2021
have issued comprehensive
orders. As per Para 2(e) of
the G.O. Price Adjustment
shall be paid without
reference to the provision
available in the estimate.
However, provision should
be ensured as per actual in
the RE by the Technical
sanctioning Authority

IV(18) Sl. No. 25 of Billing Precautions to be taken in The committee felt the need to take The EE/ SE/ CE are instructed to take Agreed.
respect of AG IR Paras/ CAG precautions while making payment of prompt action for compliance to the audit
Paras/ Audit Notes/ V&E Final bills to ensure that no AG IR notes, IR Paras, Vigilance & Enforcement
cases/ Court attachments Paras/ Audit Notes/ Vigilance cases Dept., objections, QC objections, Court
while payment of Final Bills:- and Court attachments are out- attachment etc. They are instructed that if
standing on this work. any amount is recoverable from the agency
Para 96 to 100 of APWA
on account of the above nature of
Code and Para Para 408 of objections the same shall be recovered
APPWD code stipulated for
immediately from the amount payable to
compliance to the Audit
the agency without waiting till receipt of
Notes, IR Paras final claim.
communicated by the
Accountant General to the The DDOs are instructed to furnish the
Divisional Officer within the following certificate while submitting the
stipulated time frame. As per

37
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

Sl. No. (11) of Annexure-I to final bill.


G.O. Ms. No. 491 PWD dt.
“Certified that there are no Audit Notes/ IR
14.05.1973, the Final bills
should not be held except to Paras/ Vigilance and Enforcement
department / QC Objections/ Court
the extent of the disputed
attachments etc. are pending against the
amount.
work.”

The DoWA and CEO CFSS shall take action


to provide necessary provision in the works
module mandatorily at Bill stage for
uploading the documents relating to above
subjects.

IV(19) Sl. No. 3 of Contracts Forwarding slip in the The committee suggested to reiterate The Model forwarding slip to agreement is Deferred to the next BoCEs meeting as
prescribed form shall be the instructions for attaching the appended herewith for guidance and Annexure-I is not furnished by HLTC.
attached to the Agreement:- proper forwarding slip to the incorporation of additional information
Agreement. wherever necessary (Annexure-I). The
The forwarding slip contains
agreement concluding authorities are
details like reference to AS,
instructed to furnish the forwarding slip
TS, details of NIT, details of along with every agreement.
EMD remitted and total
value of the Contract, details
of lowest bidder etc.,

IV(20) Sl. No. 8 of Contract Interest on Mobilization The committee opined that when The DDOs are instructed to recover the rate Agreed.
Advance:- interest on Mobilization Advance of interest towards mobilization advance as
clause exists in Agreement it shall be specified in the agreement. Any subsequent
As per Para 17 of G.O. MS.
collected at the borrowing rate fixed reduction of rate of interest incorporated in
No. 94, I&CAD (PW-COD)
by the Government. The committee the agreement is not permissible. In order
Dept., dt. 01-07-2003, the suggested reiterating the to watch the real time data on outstanding

38
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

facility of mobilization instructions. Mobilization Advance and the validity of the


advance up to 10% of the BGs in support thereof, a provision shall be
contract value for the works made in the CFMS Works module to capture
costing more than 1 Crore the data.
was made available to the
The DoWA shall take necessary action in
contractors against the an
unconditional and consultation with CEO CFSS to provide
necessary provision in the CFMS to capture
irrevocable Bank Guarantee.
the details of the Outstanding Advance and
The advance will attract a
suitable rate of interest (as details of the BGs in the CFMS to have the
real time data.
per Government Borrowing
rate). Subsequently, the
Government, vide GO. Ms.
No. 83, WRD (Reforms)
Dept., dt. 17-12-2019, have
issued orders dispensing
with the payment of
Mobilization Advance subject
to condition that in respect
of EAP works and works
taken up under World Bank
Assistance the clauses
regarding MA as per their
standard conditions may be
permitted, if they are
mandatory.

In the said G.O., it was also


ordered to continue the

39
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

relevant agreement clause of


MA in respect of existing
contracts as on the date of
issue of above orders to
avoid contractual litigation.

IV(21) Sl. No. 10 of Contract Employment of Technical The committee suggested to map the The Agreement concluding authorities are
and Sl. No. 1 of Billing Persons:- details of the Technical Persons instructed to indicate the names of the
engaged on the work duly capturing technical persons together with the
As per G.O. Ms. No. 158,
their Aadhar number. Qualification as technical qualification and Aadhar
PWD, dt. 21-02-1975, in case
per information noted in the identification in the agreement.
of LS and K2 contract, the Agreement to ensure presence
contractor has to engage The certificate as indicated below shall be
accountability of the Technical
technical persons for all persons for proper supervision of the furnished along with bill. Agreed.
works costing more from Rs.
work “Certified that the technical persons whose
50,000/- and above as per
names are furnished in the agreement are
scales indicated therein.
present at site of work during the course of
The technical person shall the execution.”
present during the course of
Execution of the work for The DoWA shall take necessary action in
consultation with CEO CFSS for arranging
supervision and to take
provision in CFMS works module at
instructions from the
Engineer-in-Charge. Agreement stage to map the details of the
technical person as suggested by the
The contractor shall pay Committee.
remuneration to the
technical person

40
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

IV(22) Sl. No. 19 of Billing The date of recording the The committee suggested to consider As per GAD V&E appraisal Note dt. Agreed.
Measurement in MB/ LFB is the date of recording of 01.08.2003, the DDOs are instructed to
the basis for recovery of the measurement in the MB as criteria consider the date of recording of work
Seignorage Fee in case of for considering the seignorage executed as per the MBook/ LFB as the
revision of rates:- charges instead of removal of basis to recover the seignorage charges in
material from the quarry. The case of any revision from time to time. A
The seionarage charges are committee has also suggested to suitable clause shall be incorporated in the
to be recovered keeping in
ensure statement indicating the tender documents to that effect.
view of the material
theoretical requirement of materials
consumed on the work. like Cement, Steel, Bitumen, etc., for The statement of actual consumption of
material as per specification shall be
The same shall be credited to every bill as it will be helpful to check
recorded in the Bill abstract M-Book of
the concerned HOA of Mines the calculation of Price Adjustment.
every bill with cumulative quantities and for
and geology Department.
the work covered in the running bill.
In case of any revision of Fee,
The DOWA is instructed to ensure
the same shall be compliance to the instructions.
compensated to the
contractor.

The GAD V&E Dept., Vide


Appraisal Note No. 84 dt.
04.07.2003 which was
endorsed by the Director
Mines and Geology vide Lr.
No. 24973/ Vg/ 2003 dt.
27.12.2003 has suggested to
modify the agreement
conditions to the effect “
theSeignorage Fee shall be

41
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

recovered at the rates


prevailing as on the date of
Recording of measurements
in MB/ LFB.”

IV(23) Sl. No. 34 of Billing Estimate for Land Acquisition The Committee has observed that the The following instructions are issued for The subject matter needs further
and R&R cash benefits:- LAOs, RDOs and other R&R Officers compliance. examination of the BoCEs and hence
are submitting the bills in favor of the deferred to the next BoCes meeting
As per Paras from 166 to 168 beneficiaries without furnishing the a. The LAOs, RDOs and R&R authorities are
of APPWD code, the instructed that an estimate must be
Estimate directly debiting the
expenditure shall be met prepared separately for meeting the
expenditure to the HOA.
from the Estimate. provision towards LA and R&R cash benefits
The committee suggested to reiterate as different Heads of Account are being
The Government vide G.O. that LA and R&R payments shall be operated for booking the expenditure.
Ms. No. 171, Finance dt.
made against estimate provision.
12.08.2014, have stipulated b. The village wise details of the approved
certain procedures for beneficiaries to whom the R&R benefits are
processing the bills through sanctioned shall be incorporated in the
the BMS as detailed below: estimate as per sanction accorded by the
competent authority.
The process of online bill
preparation and submission c. Whenever the Government issued orders
is briefly detailed below:- for any modification of the Compensation/
Cash benefits, an RE shall be sanctioned by
a. Award/ Sanction order
the concerned LAOs/ RDOs/R&R officers.
wise details entered in the
system. d. In respect of Land Acquisition, the award
wise and village wise details shall be
b. Beneficiary’s data with
indicated as per sanction accorded by the
their Bank Account details
competent authority.
are entered in BMS by the

42
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

LAO e. The DDOs are responsible for the


accuracy of the beneficiaries mapped in the
c. Bill is prepared based on
CFMS.
the award/ sanction orders
issued. f. The sanctioned estimate shall be
uploaded in the CFMS in support of the bills
d. Bill details are submitted
being sent to the PAOs.
online in BMS portal and the
physical bill is submitted to The PAOs/ APAOs shall watch the
the PAO (W&P) expenditure as per norms to avoid any
scope of Irregularities.

If the bills towards LA are raised for drawl of


amount in favour of the DDO for depositing
in favour of the Hon’ble Courts as per
prevailing rules, DDOs must upload the
details of the amount deposited in favour of
the Hon’ble Court.

g. The interest if any accrued on the amount


drawn by the DDO till deposition of the
same in the court, the same shall be
accounted for to the Government.

h. There shall not be any delay in deposition


of the amount before the Hon’ble Court.

The DOWA shall take necessary action in


consultation with CEO CFSS.

1. To provide necessary provision to capture

43
Sl. Reference to Interface Existing criteria as per Code/ Suggestion of the HLTC Draft instructions now issued in the Recommendations of Board of
No. in the check List of 105 Manual/ Rule Annexure to UO Note NO FIN- Chief Engineers
items (as submitted by HODSOADWA/1/2021 dt. 16022022
the DoWA) addressed to WR Dept., AP Secretariat

the data to ensure that no duplication in


payments is allowed in the CFMS system.

2. To provide provision in the CFMS to


monitor the status of the remittance of the
amount drawn by the DDOs for depositing
in the Hon’ble Courts.

IV(24) Sl. No. 41 of Billing Handing over of the The committee observed deviations The DDOs are instructed to furnish the As the topic requires detailed
completed structures to the to the procedure in practice. A following certificate while submitting the discussion, the discussion on the topic
concerned Local Head of the detailed statement covering the all final bill in case of the works (Especially deferred to the next BoCEs meeting.
authority who deposited the aspects of handing over and taken buildings) taken up on behalf of the other
amount to take up the work over/ Formal intimation letter is departments under DCW.
(DCW):- desirable. The committee has
Certified that work was completed as per
suggested to reiterate the
As per Para 221 of the instructions. requisition received from……..(Name of the
APPWD code on completion Funding department/ Authority) on
of the work on behalf of …………..(date of completion of the work)
another department, the and a formal intimation letter duly
Executive Engineer shall indicating the details of building with
inform the local head of the fixtures and fittings has been sent to the
another department in local head of the funding agency vide Lr. No.
writing. Such formal ……………dt. …..(copy enclosed).
notification will constitute
In the absence of such certificate the bill
the handing over the work to
shall not be admitted for payment.
be department for whom it
was carried out. The DOWA is instructed to ensure
compliance the instructions.

44
45

You might also like