You are on page 1of 9

1

JPA, Architect
Proposed MCN Three-Storey Mixed-Use Commercial Building

GENERAL CONDITIONS

GC-1 DEFINITIONS

a. The term “Owner” as used in this Specifications means the management


of the PROPOSED THREE STOREY MIXED USE COMMERCIAL BUILDING.

b. The term “Construction Architect/Engineer” shall mean the person executing the contract on behalf
of the Owner for the construction of the project and said Construction Architect’s/ Engineer’s duly
authorized assistants or representatives.

c. The term “Architect” means the designer, planner and consultant of the Owner.

d. The term “Completion of Contract” shall mean full performance by the Contractor of the
contractor’s obligations under the contract and all amendments and revisions thereof except the
contractor’s obligation concerning (1) release of liens and certificate of Contractor, (2) other final
documents. The term “completion” or “completion of the project” shall mean the contract and all
amendments and revisions thereof. The certificate of Completion, signed by the Construction
Architect/Engineer and approved in writing by the Owner shall be the sole and conclusive evidence
as to the date of completion.

e. The term “default” used herein shall include any such failure by the Contractor to make progress in
the prosecution of work so as to endanger the completion of the project within the calendar days
allotted.

f. Whatever in the specifications or upon the drawings the words “directed”, “required”, “ordered”,
“designated”, “prescribed”, or words of the import are used , it shall be understood that the
direction, requirement, designation, or prescription, of the Construction Architect/Engineer is
intended; and similarly the words “approved”, “acceptable to”, or “satisfactory to” of the
Architect/designer unless otherwise expressly stated.

g. Where “as shown”, “as indicated”, “as detailed”, or words of similar import are
used, it shall be understood that the reference is made to the drawings accompanying this contract
unless stated otherwise. The word “provided” as used herein shall be understood to mean
“provided complete in place,” that is, furnished and installed.

GC-2 DIVISION OF THE SPECIFICATIONS. These specifications are divided for convenience into sections as
set forth in the Table of Contents preceding these General Conditions. Any mention in these sections or
indication on the drawings of articles, materials, operations, or methods, requires that the Contractor furnish
each item so mentioned or indicated, of the kind, type or design and quality specified or shown on the
drawings, and that the Contractor furnish all labor, equipment, incidentals, and superintendence necessary
to complete the work in accordance with the true meaning and intent of these specification even though
such mention of articles, materials, operations, methods, quality, qualifications , or condition is not
expressed in complete sentences. Where devices or items, or parts thereof are referred to in the singular, it
is intended that such reference shall apply to as many such devices, items or parts as are required to

General Conditions
2
JPA, Architect
Proposed MCN Three-Storey Mixed-Use Commercial Building

properly complete the work. The Contractor shall coordinate the work covered in each sections with the
work of other sections. The necessary information: items, accessories, anchors, connections, patterns,
templates, etc., shall be delivered when required in order to prevent any delay in the progress and
completion of the work.

GC-3 SPECIFICATIONS AND DRAWINGS

a. The Contractor shall keep in the work place a copy of the drawings and specifications and shall at all
times give the Construction Architect/Engineer access thereto. Anything mentioned in the
specifications and not shown on the drawings, or shown on the drawings and not mentioned in the
specifications, shall be of like effect as if shown or mentioned in both. In case of difference
between drawings and specifications, the specifications shall govern. In case of discrepancy either
in the figures, in the drawings, or specifications, the matter shall be promptly submitted to the
Architect who shall promptly make a determination shall be at risk and expense. The Architect shall
furnish from time to time such detailed drawings and other information as he may consider
necessary, unless otherwise provided.

b. Omissions and misdescription. Omissions from the drawings or specifications or the misdescription of
details of work which are manifestly necessary to carry out the intent of the drawings and
specifications, or which are customarily performed, shall not relieve the Contractor from performing
such omitted or misdescribed details of work, but shall be performed as if full and correctly set forth
and described in the drawings and specifications.

c. Deviations from the drawings and dimensions therein given, whether or not error is believed to exist,
shall be made only after written authority is obtained from the Architect.

GC-4 PROGRESS SCHEDULE. The work shall be prosecuted with faithfulness and energy and in the order of
precedence as directed by the Construction Architect/Engineer. The Contractor shall submit a progress
schedule as follows:

a. The progress schedule shall be submitted within two weeks after the date of award of contract and
shall be subject to the approval of and/or modification by the Architect.

b. The progress schedule shall be in Chart Form or Critical Path Method (CPM) and shall show the
order in which the Contractor proposes to carry on the work, the dates on which he will start the
several salient features (including procurement of materials, plant and equipment) and the
contemplated dates for completing the same.

GC-5 TAXES, LICENSES, PERMITS, AND FEES. All taxes, licenses, permits and fees which may be due to the
local and/or National Government on account of the performance and completion of the work stipulated
herein and fees for testing of materials and specimens including Building and Occupancy permits shall be
paid for and obtained by the Contractor.

General Conditions
3
JPA, Architect
Proposed MCN Three-Storey Mixed-Use Commercial Building

GC-6 INSURANCE. The Contractor shall take out and maintain throughout the construction period insurance
in the following minimum requirements:

a. Workmen’s Compensation Insurance covering all employees in statutory limits who perform any of
the obligations assumed by the Contractor under the contract, except as specified herein.

b. Public Liability and Property Damage Liability Insurance covering all operations under the contract:
limits for bodily injury or death not less than P 25,000.00 for one person and P 75,000.00 for each
accident: for property damage, not less than P 25,000.00 for each accident and P 45,000.00
aggregate for accidents during the policy period.

c. Automobile Liability Insurance on all self-propelled vehicles used in connection with the contract,
whether owned, non-owned, or hired, public liability limits of not less than P 25,000.00 for one
person and P 75,000.00 for each accident; property damage limit of P 20,000.00 for each accident.

GC-7 CHANGES IN SPECIFICATIONS AND DRAWINGS. The Owner may, from time to time, during the
progress of the construction of the project, make such changes in, additions to, or subtractions from the
specifications and construction drawings as condition may warrant: provided, however that if the cost to the
Contractor shall be materially increased by any such change or addition, the Owner shall pay the Contractor
for the reasonable cost thereof in accordance with a construction contract amendment signed by the Owner
and the Contractor, but no claim for additional compensation for any such change or addition will be
considered unless the Contractor shall have made a written request therefore to the Owner prior to the
commencement of work in connection with such change or addition. Written notification shall be made by
the Owner to the Architect prior to any change in specifications and drawings.

GC-8 SUPERVISION AND INSPECTION.

a. The Contractor shall cause the construction work on the project to receive a constant supervision
by a competent superintendent (hereinafter called Superintendent) who shall be present at all
times during the working hours where construction is being carried-on. The Contractor shall also
employ, in connection with the construction of the project, capable, experienced, and reliable
foremen and such skilled workmen as may be required for the various classes of work to be
performed. Directions and instructions given to the Superintendent by the Owner shall be binding
upon the Contractor.

b. The Owner reserves the right to require the removal from the project of any employee of the
Contractor if in the judgment of the Owner such removal shall be necessary in order to protect the
interest of the Owner. The Owner shall have the right to require the Contractor to increase the
number of his employees and to increase or change the amount or kind of tools and equipments if
at any time the progress of the work shall be unsatisfactory to the Owner, but the failure of the
Owner to give such directions shall not relieve the Contractor of his obligations to complete the
work within the time and in the manner specified.

c. The manner of performance of the work, and all equipment used therein shall be subject to the
inspection, tests, and approval of the Owner. The Owner shall have the right to inspect all payrolls
and other data and records of the contractor relevant to the work. The Contractor will provide all

General Conditions
4
JPA, Architect
Proposed MCN Three-Storey Mixed-Use Commercial Building

reasonable facilities necessary for such inspection and tests. The Contractor shall have an
authorized agent to accompany the inspector when the final inspection is made and, if requested
by the Owner, when any other inspection is made.

d. The construction Architect/ Engineer may recommend to the Owner that the Contractor suspend
the work wholly or in part for such period or periods as the Construction Architect/Engineer may
deem necessary due to unsuitable weather or such other condition as are considered unfavorable
for the satisfactory prosecution of the work or because of the failure of the Contractor to comply
with any of the provisions of the contract: provided, however, that the Contractor shall not suspend
work pursuant to this provision without written authority from the Owner to do so. The time of
Completion hereinabove set forth shall be increased by the number of days of any such
suspension, except when such suspension is due to the failure of the contractor to comply with any
of the provisions of this contract. In the event that work is suspended by the Contractor with the
consent of the Owner, the Contractor, before resuming work, shall give the Owner at last twenty-
four (24) hours notice thereof in writing.

GC-9 DEFECTIVE WORKMANSHIP.

a. The acceptance of any workmanship by the Owner or the Construction Architect/Engineer shall not
preclude the subsequent rejection thereof if such workmanship shall be found to be defective after
installation. Any such workmanship found defective before final acceptance of the construction
shall be remedied by and at the expense of the Contractor. Contractor shall not be entitled to any
payment hereunder so long as any defective workmanship in respect to the project, of which the
Contractor shall have had notice, shall not have been remedied.

b. Notwithstanding any certificate which may have been given by the Owner or Construction
Architect/Engineer, if any workmanship which does not comply with the requirements of this
contract shall be discovered within one (1) year after completion of construction of the project, the
Contractor shall remedy any such defective workmanship within thirty (30) days after notice in
writing of the existence thereof shall have been given by the Owner. In the event of failure by the
Contractor to do so, the Owner may remedy such defective workmanship, and in such event the
Contractor shall pay to the Owner the cost and expenses thereof.

GC-10 QUALITY OF WORK AND MATERIAL. All materials, parts and equipments furnished by the Contractor
shall be new, high grade and free from defects and imperfections, unless otherwise hereinafter specified.
Workmanship shall be in accordance with the best standard practices. Both materials and workmanship
shall be subject to the approval of the Construction Architect/Engineer.

GC-11 PAYMENTS TO CONTRACTOR.

a. Within the first seven (7) days of each calendar month, the Contractor shall request partial payment
from the Owner for construction accomplish during the preceding calendar month furnished in
quadruplicate and certified by the Contractor, recommended by the Construction Architect and
approved by the Owner solely for the purpose of payment. Provided, however, that such approval

General Conditions
5
JPA, Architect
Proposed MCN Three-Storey Mixed-Use Commercial Building

shall not be deemed approval of the workmanship. Only ninety (90%) percent of each estimate
approved for each month during the construction of the project shall be paid by the Owner to the
Contractor prior to completion of the project. The Contractor shall submit a detailed breakdown of
the major items as outlined in the accomplished cost breakdown in the Proposal Form. The
approved breakdown will be the basis for payments when each item is in place or accomplished.
Total cost of the detailed breakdown shall be equal to the contract price.

GC-12 PROGRESS PHOTOGRAPHS.

a. The Contractor, at his expense, shall furnish to the Construction Architect progress photographs
that shall be takes monthly starting when the work begins and continuing so long as the work is in
progress, on the exterior or interior of the building, from station points designated by the
Construction Architect.

b. The photographs shall be 200mm x 250 mm. At each period four (4) exposures shall be taken, one
on each side or interior of the building. The Contractor shall clearly identify in the photographs the
type of work completed.

c. Twelve (12) prints, gloss-finish, (3) copies for each exposure shall be delivered to the Construction
Architect and all shall bear the date of exposures and name of the work.

d. No partial payment shall be considered for approval without the above-mentioned prints.

GC-13 RELEASE OF LIENS.

a. Neither the final payment nor any part of the retained percentage shall become due until the
Contractor, if required, shall deliver to the Owner a complete release of all liens arising out of this
contract, or receipts in full in lieu thereof and, if required in either case, an affidavit that so far as he
has knowledge or information, the releases and receipts include all labor and materials for which a
lien could be filed; but the Contractor may, if any subcontractor refuses to furnish a release or
receipt in full, furnish a bond satisfactory to the Owner, to indemnify him against any lien. If any lien
remains unsatisfied after all payments are made, the Contractor shall refund to the Owner all
monies that the latter may be compelled to pay in discharging such lien, including all costs and
reasonable attorney’s fee.

GC-14 ASSIGNMENT.

1. This contract shall not be assigned in whole or in part by the Contractor nor shall any part of the
work be sublet by the Contractor without the prior written consent of the Owner and such consent
would not relieve the Contractor from full responsibility and liability for the work hereunder and for
the due performance of all the terms and conditions of the contract. The owner’s consent to any
subletting of work hereunder shall not be granted in any event until the Contractor has furnished
the Owner with satisfactory evidence that the subcontractor is carrying ample insurance to the
same extent and in the same manner as herein provided to be furnished by the Contractor. If the

General Conditions
6
JPA, Architect
Proposed MCN Three-Storey Mixed-Use Commercial Building

contract is assigned or any part thereof is sublet, the Contractor shall exonerate, indemnify and
save harmless the Owner from and against any and all losses or expenses caused thereby.

GC-15 COMPLETION ON CONTRACTOR’S DEFAULT. If default shall be made by the Contractor or by any
subcontractor in the performance of any of the terms of this contract, the Owner, without in any manner
limiting its legal and equitable remedies in the circumstances, may serve upon the Contractor and the surety
or sureties upon the Performance Bond or Bonds written notice requiring the Contractor to cause such
default to be corrected forthwith. Unless within twenty (20) days after the service of such notice upon the
Contractor such default shall be corrected or arrangements for the correction thereof satisfactory to the
Owner shall be made by the Contractor or its sureties, the Owner may have such default corrected by
contract or otherwise for the amount and at the expense of the Contractor, and the Contractor and its surety
and sureties shall be liable to the Owner for any cost and expense in excess of the contract price
occasioned thereby. In such event, the Owner may take possession of and utilize, in completing the
construction of the project, any materials, tools, supplies, equipments, appliances, and plant belonging to
the Contractor or any of its subcontractors, which may be situated at the site of the project. The Owner in
such contingency may exercise any rights, claims, or demands which the Contractor may have against third
person in connection with this contract and for such purpose the Contractor does hereby assign, transfer
and set over unto the Owner all such rights, claims and demands.

GC-16 ATTORNEY’S FEE IN CASE OF SUIT. In case the Owner has to resort to the courts to protect and enforce
its rights hereunder the Contractor and his surety or sureties shall be further liable for attorney’s fee in an
amount equivalent to twenty (20%) percent of the amount involved, but not less than One Thousand
(1,000.00) Pesos and that venue of such action shall be in the proper Court holding session in.

GC-17 PATENT INFRINGEMENT. The Contractor shall save harmless and indemnify the Owner from any and all
claims, suits and proceedings for the infringement of any patents covering any equipment used in the work.

GC-18 COMPLIANCE WITH STATUTES AND REGULATIONS. The Contractor will comply with all applicable
statutes, ordinances, rules and regulations pertaining to the work. The Contractor understands that the
obligations of the parties’ hereunder are subject to the applicable regulations and orders of Government
agencies having jurisdiction in the premises.

GC-19 EXTENSION TO SUCCESSOR’S AND ASSIGNS. Each and all of the covenants and agreements
contained in the contract effected by the acceptance of this contract shall extend to and be binding upon the
successors and assigns of the parties thereto.

General Conditions
7
JPA, Architect
Proposed MCN Three-Storey Mixed-Use Commercial Building

GC-20 PERSONAL AND PROPERTY DAMAGE. Until the work is completed and accepted by the Owner, the
Contractor shall assume all risks and bear all losses that may result from any cause, to the work and to
existing structures and equipment, and to other property located on the premises or adjacent thereto,
belonging to the Owner, and he shall assume all damage or injury that may result to all such property and/or
to persons where such damage or injury is caused in connection with his work or is due to his negligence or
to his leaving open or unprotected portions of streets or other property.

GC-21 SUPERVISION. All work shall meet with the approval of the Construction Architect and shall be completed
in conformity with the plans and specifications approved by, and on file with the Owner, which plans and
specifications will be made part of the contract to be entered into for the work referred to herein. The
Contractor shall confer with the Construction Architect before commencing any work under the contract. The
Construction Architect or his representative shall have access to the work at all times. The Contractor shall
furnish all facilities for inspection at the construction site, and at shops or yards, and shall not cover up any
work requiring inspection until the same has been approved by the Construction Architect. If work should be
covered up before being inspected the Contractor will be required to remove such portions of the work as
may be necessary to disclose the part in question.

GC-22 IDENTIFICATION OF EMPLOYEES. The Contractor shall be responsible for furnishing to each
employee and for requiring each employee engaged in the work to display such identifications as maybe
approved and directed by the Construction Architect. All prescribed identification shall immediately be
delivered to Construction Architect for cancellation upon the release of any employee. When required by the
Construction Architect, the Contractor shall obtain and submit fingerprints of all persons employed on the
project.

GC-23 SHOP DRAWINGS. Shop drawings shall be submitted with the same size as the contract drawings
when practicable, but in no case shall exceed the dimensions of the contract drawings. Allow 38 mm border
at left hand edge of shop drawings for binding and uniform hanging in files at job site. The Contractor shall
make a preliminary check of all shop drawings for compliance with contract documents before submitting
shop drawings to Architect and he shall stamp each print with statement of compliance with this
requirement. The Contractor shall submit four(4) such checked prints to the Architect who will check it,
retaining one print for his file and returning three(3) prints to the Contractor approved, as noted, or
disapproved. If shop drawings are disapproved, the Architect will return it to the Contractor for resubmission.
The approval of the drawings by the Architect shall not be construed as a complete check, but will indicate
only that the general method of construction and detailing is satisfactory. Approval of such drawings will not
relieve the Contractor of the responsibility for any error that may exist as the Contractor shall be responsible
for the dimension and design of adequate connections, details, and satisfactory construction of all work.

GC-24 SAMPLES. The Contractor shall submit 2 set each of samples if required by the Architect and these
shall be properly identified with the contractor’s name and manufacturer’s name and catalog number, if
applicable.

General Conditions
8
JPA, Architect
Proposed MCN Three-Storey Mixed-Use Commercial Building

GC-25 LIGHT, POWER, AND WATER. The Contractor shall furnish temporary water, light, and power,
complete with connecting piping, wiring, lamps, meters, and similar equipment as required for the work. The
Contractor shall install, maintain and remove his temporary lines upon completion of the work. All expenses
in connection with temporary services and facilities shall be paid by the Contractor. Subsequent to the
setting of the permanent meters, the Owner will be responsible for payment of water and electrical bills
rendered for utility service through the respective permanent meters. The Contractor, however, shall pay all
costs incurred in the setting of the permanent meters.

GC-26 TEMPORARY OFFICE. The Contractor shall provide and maintain watertight office on the premises
where directed for his own and subcontractor’s use, and for use of the Construction Architect/Engineer. This
building shall be painted with operating windows, doors with locks, tables, benches, racks for drawings, and
adequate electric lighting.

1. The ceiling shall be 2.7 m high. Floor and wall shall be plywood or equivalent.

2. The Contractor shall provide janitorial service for these offices for the duration of the job.

GC-27 STORAGE SHEDS. The Contractor shall provide and maintain on the premises where directed,
watertight storage sheds for all materials which might be damaged by weather.

GC-28 TEMPORARILY TOILETS. The Contractor shall install and maintain in a sanitary condition suitable
toilets and urinals for use of workmen. These toilets shall be in a location approved by the Construction
Architect and connected to existing sewers, when feasible, or may be of the chemical type. These shall be a
minimum of one (1) toilet for each multiple of thirty (30) contractor’s employees or fractional part thereof,
working at the job site.

GC-29 LIGHTS, GUARDS, ETC. The Contractor shall provide such lights, guard, temporary fences and warning
signs as may be necessary for safety during all the time from the execution of the contract until the final
acceptance of the work, and shall be responsible for the installation and maintenance of lights, guards,
fences, and warning signs.

GC-30 REPAIRING INJURED WORK. All portions of the work that may be broken or injured by accident or in
the course of or on account of building operations, or by reason of any other cause whatsoever during the
progress of the work, shall be carefully and neatly repaired or reconstructed and the whole left in first-class
condition and turned over to the Owner ready for use. Should any part of the work of this contract be cut into
or damaged by other contractors, the Contractor and party causing such damage shall make adjustments
between themselves relative to reconstruction or repairs and payment for same.

General Conditions
9
JPA, Architect
Proposed MCN Three-Storey Mixed-Use Commercial Building

GC-31 OTHER CONTRACTS. The Contractor shall perform to work of the contract so that it will properly
coordinate with and fit the work performed by other contractors. He shall give the other contractors every
reasonable opportunity to perform their work, store materials, and place equipment therefore, and fit their
work to the work of other contractors. He shall furnish to the other contractors all information necessary in
order that they may properly connect and fit their work to his in ample time, so that they may have
reasonable opportunity to prepare their work therefore. He shall make the work of this contract ready to
receive the work of the other contractors at the time fixed therefore, and shall fit this work to that of the other
contractors at the time fixed therefore.

GC-32 COOPERATION WITH OTHERS.

a. The Contractor shall cooperate with others in the prosecution of all work and shall not interfere with
material, appliances or workers of the Owner or any other Contractor engaged by the Owner at the
site of the work.

b. All contractors engaged in work at the site, shall have insofar as practicable, equal use of the
premises and facilities. In case of disagreement regarding such use, the matter shall be referred to
the Construction Architect whose decision relative to said use shall govern.

GC-33 CLEANING. Upon completion of each part of the work as defined by the sections into which these
specifications are divided or as separated by the various trades involved in the work, each area shall be
cleaned of debris emanating from the work. The Contractor shall remove remaining excess materials,
waste, rubbish, debris and his construction and installation equipment from the premises. Any dirt or stains
caused by the work under the contract shall be removed from the surfaces of the structure and from
equipments and fixtures.

GC-34 WORK NOT INCLUDED. Any work shown or specified which is not to be done as part of the contract will
be marked “N.I.C.,” or will be specified in Section 1A General Paragraphs of this Specifications.

GC-35 UAP DOC. 301 That the United Architects of the Philippines, DOC. 301, known as the General Conditions
form a part of this document. Any applicable conditions and provisions not mentioned in this Construction
Master Specifications shall govern.

General Conditions

You might also like