You are on page 1of 7

Chapter Five: Comparison table

Comparison between MDB-FIDIC,PAA 2011 Conditions of Contract and applicable law on


Quality and Quality Deviation
After discussing all relevant clauses for our paper now we are trying to show differences in the
PPA 2011 and MDB FIDIC 2010 standard construction contract documents and the Civil Code
1960 applicable law. So, the table below shows the deviations of this materials.
CL. MDB-FIDIC Conditions 2010 CL. PAA 2011

4.1 Contractor’s General Obligation 34.1 General Obligation of Contractor


This clause sets out the This clause sets out the Contractor shall, with
Contractor's general obligation to due care and diligence, and in accordance with
“execute and complete the Works” the provisions of the Contract, design the works
and “remedy any defects”, and to the extent stated in the Contract, and
“take full responsibility for the care execute, complete and remedy any defects in
of the works” at Sub-Clause 17.2 in the works. The Contractor shall provide all
addition the Employer requires in control and supervision of the works, personnel,
this clause the Contractor to carry materials, plant, equipment and all other items,
out the design of part of the whether of a temporary or permanent nature
permanent works then the required in and for such design, execution,
requirement must be specified in completion and remedying of any defects,
the contract. insofar as specified in, or can be reasonably
Some performance design of inferred from, the Contract.
standard also stated in this clause
at c as „be fit for such purposes for
which the part is intended as
specified in the Contract”. The
works which is expected from this
clause will be checked by the Tests
on completion and Tests after
completion which is carried out
under clause 9.
4.9 Quality Assurance
The Contractor shall, if
requirements are so stated in the
contract plan, establish and
maintain a quality system which
confirms to those requirements. Any
such quality system shall be used
only as an aid to achieving
compliance with the Contract and to
document such compliance. Such
system shall not relieve the
Contractor of the responsibility to
comply with the Contract
7 Plant, Materials and Workmanship 80 Orgion and quality of works and Materials
This clause sets out the Contractor‟s This clause sets out the Contractor‟s Obligation
Obligation concerning the quality of concerning the quality of his work and the
his work and the procedure to be procedure to be followed for tests and in the
followed for tests and in the event event that an item of work fails the test
that an item of work fails the test.
7.1 Manner of Execution 80.2 Under this sub clause The works, components and
All manufacture of plant, the materials shall conform to the specifications,
production and manufacture of drawings, surveys, models, samples, patterns and
materials and all other execution of
other requirements in the contract. And also
the works should be in accordance
of “Proper workmanlike and Under sub clause
careful”, “recognized good practice”
and
“properly equipped facilities”.

7.2 Samples 80.4 Under this sub clause Even if materials or items to
The Contractor will supply samples be incorporated in the works or in the
such as “manufactures standard manufacture of components have been
samples of material and additional technically accepted.
samples instructed by the engineer
as a variation” at his own cost and
the employer if it is a variation if
such supply is envisaged by the
contract.

7.3 Inspection 81 inspection and test

This clause set out the Contractor‟s sub clause of 81.2 states that The Engineer shall
obligation to allow the Employer‟s be entitled, either by himself or his agent, to
personnel (Engineer) to enter the inspect, examine, measure and test the
site and any factories, quarries or components, materials and workmanship, and
other places where work is being check the progress of preparation, fabrication or
carried out for the works to check manufacture of anything being prepared,
the progress of manufacture plant fabricated or manufactured for delivery under the
and production and manufacture of contract in order to establish whether the
materials. The contractor must components, materials and workmanship are of
provide „access facilities, the requisite quality and quantity
permissions and safety equipment‟
to enable the person concerned to
inspect and check the materials,
workmanship and progress
The Contractor is required to give
notice when any work is ready for
inspection and before it is concealed
in any way.
7.4 Testing 81.2 Test
This clause deals with the procedures sub clause of 81.2 states that The Engineer shall
for tests specified in the contract and be entitled, either by himself or his agent, to
additional tests instructed by the inspect, examine, measure and test the
Engineer as a variation. components, materials and workmanship, and
check the progress of preparation, fabrication or
manufacture of anything being prepared,
fabricated or manufactured for delivery under the
contract in order to establish whether the
components, materials and workmanship are of
the requisite quality and quantity.

7.5 Rejection 82 Rejection


If as a result of Clause 7.4 Testing sub clause of 82.1 states that Components and
found to be defective or not in materials which are not of the specified quality
accordance to the contract then the shall be rejected.
Engineer can reject that item under A special mark may be applied to the rejected
Sub-clause 7.5, but must give reasons components or materials. This shall not be such as
for the rejection. However, if the to alter them or affect their commercial value.
engineer requires to be retested he Rejected components and materials shall be
can do so at same procedures and removed by the Contractor from the site within a
condition as per clause 7.4. period which the Engineer shall specify, failing
which they shall be removed by the Engineer as of
right at the expense and risk of the Contractor.
Any work incorporating rejected components or
materials shall be rejected. .

7.6 Remedial Work 82.3 under sub clause 82.3 The


As per the above clauses 7.4 and Engineer shall, as soon as reasonably practicable,
7.5, if are not in accordance to the give to the Contractor notice in writing of his
contract, the Engineer may instruct decision specifying particulars of the alleged
that plan, materials or any other defects
work removed from the site and under sub clause82.4
the item replaced. The Contractor
The Contractor shall with all speed and at his
must comply with the instruction
expense make good the defects so specified. If the
within a reasonable time, which Contractor does not comply with such order, the
may be stated in the instruction. If Public Body shall be entitled to employ other
the contractor is not voluntary to persons to carry out the same and all expenses
the remedy of the defect, the consequent thereon or incidental thereto may be
deducted by the Public Body from any monies due
Employer shall be entitled to or which may become due to the Contractor.
employ another person and deduct
the monies from the contractor.

9.1 Tests on Completion 85 Tests on Completion


Tests on completion are the tests that Sub clause 85.1 states that the works shall not be
are carried out after the works have
been completed and before the accepted until the prescribed verifications and
Engineer will issue the Taking-Over tests have been carried out at the expense of the
Certificate.
Contractor. The Contractor shall notify the
In this clause the Contractor must
give before 21 days‟ notice to the Engineer of the date on which such verification
Engineer when he will be ready to and tests may commence. And also under
carry out the Test on Completion and
sub clause 85.2 Works which do not satisfy the
the tests must be carried out within
14 days after this date, on a date terms and conditions of the Contract, or in the
instructed by the Engineer. This absence of such terms and conditions, which are
clause also includes works or plants
which are designed by the contractor not carried out in accordance with trade practices
should submit the documents as per in the Federal Democratic Republic of Ethiopia,
the Clause 4.1 especially (d)
shall, if required, be demolished and rebuilt by
From the Engineer it also expected to
make allowances if there is usage of the Contractor or repaired to the satisfaction of
the Employer on the performances or the Engineer,
other characteristics of the works.
The Contractor shall submit a
certified report of these tests to the
Engineer.

9.2 Delayed Tests


This clause deals with when Tests on
Completion are delayed. If the tests
are delayed by the Employer then
the Contractor should give a notice
to the Engineer and has a remedial
right of extension time and cost plus
profit. If the delay lasts for more
than 14 days then as per Clause
10.3, the Employer is deemed to
have taken over the works or
section on the date when the Tests
on Completion would otherwise
have been completed.
If the tests are delayed by the
Contractor then the Engineer may
give notice for the
Contractor to carry out the tests
within 21 days or Employer‟s
personnel may proceed with the
tests at the Contractor‟s risk and
cost
9.3 Re-testing 81.6 Re-testing
This clause requires Sub-Clause 7.5 If the Engineer and the Contractor disagree on
and sets out if “the Works or a the test results, each shall give a statement of his
Section” has failed to pass the Tests views to the other within 15 days after such
on Completion as per the SubClause disagreement arises. The Engineer or the
7.5, the Engineer may reject and Contractor may require such tests to be repeated
after the Contractor at the on the same terms and conditions or, if either
appointed time make the defecates party so requests, by an expert to be selected by
good the engineer can require a common consent. All test reports shall be
repeat test as per the terms and submitted to the Engineer who shall
conditions of the contract. communicate the results of these tests without
Clause 9.4 Failure to pass Tests on delay to the Contractor. The results of the
Completion retesting shall be conclusive. The cost of the re-
testing shall be borne by the party whose views
This Sub-Clause deals with failure by
are proved wrong by the re-testing.
“the Works or Section”. And gives to
the Engineer (a) to order retesting of
Tests on Completion (b) and (c) to
instruct the Contractor to remove
and replace plant or material or
remove and reexecute other work. If
the Contractor fails to carry out this
instruction then the Employer is
entitled to arrange for other persons
to carry out the work and claim the
Costs under Sub-Clause 11.4 (c)

10 Employers Taking Over 87 Provisional acceptance


Under Clause 10.1 Employers Taking Under sub clause 87.1 states that the works shall
Over be taken over by the Public Body when they have
This clause provides a requirement satisfactorily passed the tests on completion and
to be taken over when completed in a certificate of provisional acceptance has been
accordance with the Contract. The issued or is deemed to have been issued.
requirement includes the matters Under sub clause 87.2 states that the Contractor
described above on Sub-Clause 8.2 may apply, by notice to the Engineer, for a
which are passing the Tests on certificate of provisional acceptance not earlier
Completion and completing all the than 15 days before the works, in the
work as required by the Contract.
Contractor's opinion, are complete and ready for
According to this clause, it is not
provisional acceptance. The Engineer shall within
necessary to complete “any minor
30 days after the receipt of the Contractor's
outstanding work and defects which
application either:
will not substantially affect the use of
the Works or Section for their a). issue the certificate of provisional acceptance
intended purpose (either until or to the Contractor with a copy to the Public Body
whilst this work is completed and stating, where appropriate, his reservations, and,
these defects are remedied” the inter alia, the date on which, in his opinion, the
Contractor decides that the work is works were completed in accordance with the
within 14 days of being ready to be
Contract and ready for provisional acceptance; or
taken over, he issues a notice to
apply to the Engineer for a Taking b). reject the application giving his reasons and
Over Certificate. 2. specifying the action which, in his opinion, is
Within 28 days of receiving the required of the Contractor for the certificate to
Contractors‟ application the
Engineer must issue the Taking-Over
Certificate stating the date when the
Works were completed in accordance
with the contract or reject the
application.

If the Engineer rejects the application


he must give his reasons and specify
the work that must be done by the
Contractor to enable the Taking-Over
Certificate to be issued. The
Contractor must then complete this
work and issue another notice. Under
this clause the procedures follow by
the Employer is 1. When
If the Engineer fails either to issue the
Taking
11.3 Defect notification period, 88 Defect liability period
The contractor is liable for the defects The defect liability period of the contractor shall
not more than two years. be indicated in the SCC
sub-clause 88.7 it shall be 365 days, [Defect
liability].

Under Civil Code 1960


Liability period
The contractor shall be liable for the good quality of the material, Provided by him. Art 2614(1)
[Materials provided by contractor]
Quality control
Administrative authority shall control the quality of the materials used and may refuse them.
Art. 3255 [Personnel of the undertaking and materials]
Period of warranty
The contractor is liable for the defects not less than ten year from its delivery, Civil code 1960,
Art. 3039(1, 2, 3) [Warranty due by contractor]
Remedy Cost
Remedy the defects up to period of warranty is performed by the contractor’s monies only.

You might also like