You are on page 1of 13

DENAI CONCEPT SDN BHD

Appendix 1
BILL OF QUANTITIES

PROJECT: Civil Works of the Rest Construction Area of the New CH138 Camp

NO DESCRIPTION UNIT PROV. QTY UNIT RATE (RM) TOTAL (RM) Remarks

A Preliminary
Mobilization and Demobilization
1 LS 1 -
Payment shall be paid in accordance with the actual progress rate
HSE Management

Including but not limited to holding the safety meeting before work every day, traffic
control, spraying water to prevent dust pollution, waste collection and dispose, cleaning
2 LS 1 -
lorry that is leaving the site and complying with all the other HSE requirements of Main
Contractor.

Payment shall be paid in accordance with the actual progress rate

Surveying Work

3 Including but not limited to setting out etc. LS 1 -

Payment shall be paid in accordance with the actual progress rate

Accomodation & Transportation


4 LS 1 -
Payment shall be paid in accordance with the actual progress rate

Temporary power & water supply


5 LS 1 -
Payment shall be paid in accordance with the actual progress rate

TOTAL SUB-AMOUNT (PRELIMINARIES): -

B Construction Items

1 Wall and Main Gate

1.1 Brick Wall

Wall and Column

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out; excavation; formwork installation, dismantlement
and reshipment; pouring and curing of C15 concrete cushion; damp proof course; brick
foundation; brick wall; steel bar processing and installation; backfill; rolling and
compacting, compactness not less than 95% etc.

1.1.1 Main Contractor shall supply the steel bar, allowing wastage not exceeding more than ㎡ 636.93 -
1.5%, the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted
from any due to or becoming due to payment of Subcontractor based on the provided rate
schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by area in accordance with the joint surveying upon
completion.

C25 Concrete Ring Beam

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out; formwork installation, dismantlement and
reshipment; steel bar processing and installation, concrete pouring and curing etc.

Main Contractor shall supply the steel bar, allowing wastage not exceeding more than
1.1.2 1.5%, the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted m 303.30 -
from any due to or becoming due to payment of Subcontractor based on the provided rate
schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by length in accordance with the joint surveying upon
completion.

Column Cap

Detailed technical requirements refer to the Drawing.

Including but not limited to brick masonry, plastering mortar etc.


1.1.3 NOS 72 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by number in accordance with the joint surveying upon
completion.

Plastering Mortar and Normal White Painting for Both Sides of the Wall and
Column

Detailed technical requirements refer to the Drawing.

Including but not limited to plastering mortar and normal white painting etc.
1.1.4 ㎡ 1,273.86 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by area (inner and outer surface) in accordance with the joint
surveying upon completion.
DENAI CONCEPT SDN BHD
Appendix 1
BILL OF QUANTITIES

PROJECT: Civil Works of the Rest Construction Area of the New CH138 Camp

NO DESCRIPTION UNIT PROV. QTY UNIT RATE (RM) TOTAL (RM) Remarks

1.2 Hoarding - Sandwich Panel with Color Steel

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out; excavation; formwork installation, dismantlement
and reshipment; pouring and curing of C25 concrete foundation; installation of sandwich
panel with color steel; backfill; rolling and compacting compactness not less than 95%
etc.

Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%,
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
1.2.1 m 928.40 -
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Main Contractor to supply the sandwich panel with color steel.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by length in accordance with the joint surveying upon
completion.

1.3 Hoarding - Color Steel Plate

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out; excavation; formwork installation, dismantlement
and reshipment; pouring and curing of C25 concrete foundation; installation of color steel
plate; backfill; rolling and compacting compactness not less than 95% etc.

Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%,
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
1.3.1 due to or becoming due to payment of Subcontractor based on the provided rate schedule. m 598.80 -

Main Contractor shall supply the color steel plate.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by length in accordance with the joint surveying upon
completion.

1.4 Concrete Column (C1)

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out; excavation; formwork installation, dismantlement
and reshipment; pouring and curing of C25 concrete column and C15 concrete cushion;
steel bar processing and installation; backfill; rolling and compacting compactness not
less than 95% etc.

Main Contractor shall supply the steel bar, allowing wastage not exceeding more than
1.4.1 1.5%, the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted NOS 8 -
from any due to or becoming due to payment of Subcontractor based on the provided rate
schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by number in accordance with the joint surveying upon
completion.

1.5 Main Gate Construction

Excavation

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out; excavation etc.


1.5.1 m³ 16.00 -
Subcontractor to supply all the manpower, material, machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by nature volume in accordance with the joint surveying
upon completion.

C15 Cushion

Detailed technical requirements refer to the Drawing.

Including but not limited to formwork installation, dismantlement and reshipment,


concrete pouring and curing etc.

Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%,
1.5.2 the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any m3 10.80 -
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.

Brick Masonry

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out, brick masonry etc.


1.5.3 m3 26.00 -
Subcontractor to supply all the manpower, material, machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.
DENAI CONCEPT SDN BHD
Appendix 1
BILL OF QUANTITIES

PROJECT: Civil Works of the Rest Construction Area of the New CH138 Camp

NO DESCRIPTION UNIT PROV. QTY UNIT RATE (RM) TOTAL (RM) Remarks

M10 Mortar Surface

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out, brick masonry etc.


1.5.4 ㎡ 87.00 -
Subcontractor to supply all the manpower, material, machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by area in accordance with the joint surveying upon
completion.

Marble Installation (600mm*600mm)

Detailed technical requirements refer to the Drawing.

Including but not limited to marble installation etc.

1.5.5 Main Contractor shall supply the marble. ㎡ 87.00 -

Subcontractor shall supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by area in accordance with the joint surveying upon
completion.

Gate Installation

Detailed technical requirements refer to the Drawing.

Including but not limited to gate installation etc.

1.5.6 Main Contractor shall supply the gate. NOS 1.00 -

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by number in accordance with the joint surveying upon
completion.

TOTAL SUB-AMOUNT (WALL AND MAIN GATES): -

2 Civil Work for Steel Bar Processing Shed

2.1 Foundation of Steel Bar Processing Shed

Earth Excavation

Detailed technical requirements refer to the Drawing.

Including but not limited to excavation, pumping water of the pit (if any),
2.1.1 m3 108.00 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by natural volume in accordance with the joint surveying
upon completion.

Crusher Run Replacement Filling

The work shall be conducted in accordance with the instruction of the Main Contractor.
2.1.2 m3 27.00 -
Subcontractor to supply all the manpower, material, machinery and equipment, tools,
hardware, instrument.

The volume shall be measured as in the transport vehicle at the place of deposition.

C15 Cushion for Foundation

Detailed technical requirements refer to the Drawing.

Including but not limited to excavation, setting out, formwork installation and
dismantlement, concrete pouring and curing etc.

Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%,
2.1.3 m3 3.60 -
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.

C30 Concrete Foundation

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out, formwork installation and dismantlement,
concrete pouring, vibration and curing etc.

Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%,
2.1.4 m3 16.00 -
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.
DENAI CONCEPT SDN BHD
Appendix 1
BILL OF QUANTITIES

PROJECT: Civil Works of the Rest Construction Area of the New CH138 Camp

NO DESCRIPTION UNIT PROV. QTY UNIT RATE (RM) TOTAL (RM) Remarks

Steel Bar for Foundation

Detailed technical requirements refer to the Drawing.

Including but not limited to steel bar processing, binding, installation and reshipment
within the site etc.

Main Contractor shall supply the steel bar, allowing wastage not exceeding more than
2.1.5 1.5%, the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted t 1.800 -
from any due to or becoming due to payment of Subcontractor based on the provided rate
schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by weight in accordance with the joint surveying upon
completion.

Iron Build-In Fitting Installation

Detailed technical requirements refer to the Drawing.

Including but not limited to the Iron Build-In Fitting installation etc.

2.1.6 Main Contractor shall supply the Iron Build-In Fitting. NOS 18 -

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by number in accordance with the joint surveying upon
completion.

Backfill

Including but not limited to the backfill, compacting and rolling, and leveling the
additional earth. The compactness shall be not less than 95%.
2.1.7 m3 61.40 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by compacted volume in accordance with the joint surveying
upon completion.

2.2 Foundation of Gantry Crane

Earth Excavation

Detailed technical requirements refer to the Drawing.

Including but not limited to excavation, pumping water of the pit (if any),
2.2.1 m3 268.80 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by natural volume in accordance with the joint surveying
upon completion.

Crusher Run Replacement Filling

The work shall be conducted in accordance with the instruction of the Main Contractor.
2.2.2 m3 108.00 -
Subcontractor to supply all the manpower, material, machinery and equipment, tools,
hardware, instrument.

The volume shall be measured as in the transport vehicle at the place of deposition.

C15 Cushion for Foundation

Detailed technical requirements refer to the Drawing.

Including but not limited to excavation, setting out, formwork installation and
dismantlement, concrete pouring and curing etc.

Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%,
2.2.3 m3 15.40 -
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.

C30 Concrete Foundation

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out, formwork installation and dismantlement,
concrete pouring, vibration and curing etc.

Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%,
2.2.4 m3 46.00 -
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.
DENAI CONCEPT SDN BHD
Appendix 1
BILL OF QUANTITIES

PROJECT: Civil Works of the Rest Construction Area of the New CH138 Camp

NO DESCRIPTION UNIT PROV. QTY UNIT RATE (RM) TOTAL (RM) Remarks

Steel Bar for Foundation

Detailed technical requirements refer to the Drawing.

Including but not limited to steel bar processing, binding, installation and reshipment
within the site etc.

Main Contractor shall supply the steel bar, the loss rate 1.5% shall be complied with by
2.2.5 t 10.452 -
Subcontractor, otherwise the amount for extra quantities shall be deducted from any due
to or becoming due to payment of Subcontractor based on the market price.

Subcontractor shall supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by weight in accordance with the joint surveying upon
completion.

Backfill

Including but not limited to the backfill, compacting and rolling, and leveling the
additional earth. The compactness shall be not less than 95%.
2.2.6 m3 99.40 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by compacted volume in accordance with the joint surveying
upon completion.

2.3 C25 Ground Hardening for Steel Bar Processing Shed

Ground Hardening

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out, original ground leveling, compacting and rolling,
formwork installation and dismantlement, concrete pouring, vibration and surface
troweling, roughening, geotextile curing, etc.

2.3.1 Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%, m3 620.00 -
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.

Sawcut Control Joint

Detailed technical requirements refer to the Drawing.

The work shall not be conducted until the final setting time of the concrete at least reach
to 4-6 hours and follow the instruction of Main Contractor.
2.3.2 m 620.00 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by length in accordance with the joint surveying upon
completion.

TOTAL SUB-AMOUNT (STEEL BAR PROCESSING SHED): -

3 Civil Work for Maintenance Shop


3.1 Foundation of Maintenance Shop

Earth Excavation

Detailed technical requirements refer to the Drawing.

Including but not limited to excavation, pumping water of the pit (if any),
3.1.1 m3 28.22 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by natural volume in accordance with the joint surveying
upon completion.

C15 Cushion for Foundation

Detailed technical requirements refer to the Drawing.

Including but not limited to excavation, setting out, formwork installation and
dismantlement, concrete pouring and curing etc.

Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%,
3.1.2 m3 2.35 -
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.
DENAI CONCEPT SDN BHD
Appendix 1
BILL OF QUANTITIES

PROJECT: Civil Works of the Rest Construction Area of the New CH138 Camp

NO DESCRIPTION UNIT PROV. QTY UNIT RATE (RM) TOTAL (RM) Remarks

C30 Concrete Foundation

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out, formwork installation and dismantlement,
concrete pouring, vibration and curing etc.

Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%,
3.1.3 m3 10.44 -
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.

Steel Bar for Foundation

Detailed technical requirements refer to the Drawing.

Including but not limited to steel bar processing, binding, installation and reshipment
within the site etc.

Main Contractor shall supply the steel bar, allowing wastage not exceeding more than
3.1.4 1.5%, the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted t 5.409 -
from any due to or becoming due to payment of Subcontractor based on the provided rate
schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by weight in accordance with the joint surveying upon
completion.

Iron Build-In Fitting Installation

Detailed technical requirements refer to the Drawing.

Including but not limited to the Iron Build-In Fitting installation etc.

3.1.5 Main Contractor shall supply the Iron Build-In Fitting. NOS 12.00 -

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by number in accordance with the joint surveying upon
completion.

Backfill

Including but not limited to the backfill, compacting and rolling, and leveling the
additional earth. The compactness shall be not less than 95%.
3.1.6 m3 15.43 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by compacted volume in accordance with the joint surveying
upon completion.

3.2 Service Pit

Earth Excavation

Detailed technical requirements refer to the Drawing.

Including but not limited to excavation, pumping water of the pit (if any),
3.2.1 m3 106.80 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by natural volume in accordance with the joint surveying
upon completion.

C30 Concrete for Service Pit Baseplate

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out, formwork installation and dismantlement,
concrete pouring, vibration and curing etc.

Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%,
3.2.2 m3 7.60 -
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.
DENAI CONCEPT SDN BHD
Appendix 1
BILL OF QUANTITIES

PROJECT: Civil Works of the Rest Construction Area of the New CH138 Camp

NO DESCRIPTION UNIT PROV. QTY UNIT RATE (RM) TOTAL (RM) Remarks

Steel Bar for for Service Pit Baseplate

Detailed technical requirements refer to the Drawing.

Including but not limited to steel bar processing, binding, installation and reshipment
within the site etc.

Main Contractor shall supply the steel bar, allowing wastage not exceeding more than 2%,
3.2.3 t 0.381 -
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by weight in accordance with the joint surveying upon
completion.

C30 Concrete for Service Pit Wall

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out, formwork installation and dismantlement,
concrete pouring, vibration and curing etc.

Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%,
3.2.4 m3 12.10 -
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.

Steel Bar for Service Pit Wall

Detailed technical requirements refer to the Drawing.

Including but not limited to steel bar processing, binding, installation and reshipment
within the site etc.

Main Contractor shall supply the steel bar, allowing wastage not exceeding more than
3.2.5 1.5%, the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted t 0.886 -
from any due to or becoming due to payment of Subcontractor based on the provided rate
schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by weight in accordance with the joint surveying upon
completion.

Clay Brick Staircase

Detailed technical requirements refer to the Drawing.

Including but not limited to the brick masonry, plastering mortar etc.
3.2.6 m3 2.40 -
Subcontractor to supply all the manpower, all the material and machinery and equipment,
tools, hardware, instrument.

Quantities shall be measured by valume in accordance with the joint surveying upon
completion.

Backfill of Service Pit

Including but not limited to the backfill, compacting and rolling, and leveling the
additional earth. The compactness shall be not less than 95%.
3.2.7 m3 70.60 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by compacted volume in accordance with the joint surveying
upon completion.

3.3 C25 Ground Hardening for Maintenance Shop

Ground Hardening

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out, original ground leveling, compacting and rolling,
formwork installation and dismantlement, concrete pouring, vibration and surface
troweling, roughening, geotextile curing, etc.

3.3.1 Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%, m3 60.00 -
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.
DENAI CONCEPT SDN BHD
Appendix 1
BILL OF QUANTITIES

PROJECT: Civil Works of the Rest Construction Area of the New CH138 Camp

NO DESCRIPTION UNIT PROV. QTY UNIT RATE (RM) TOTAL (RM) Remarks

Steel Bar

Detailed technical requirements refer to the Drawing.

Including but not limited to steel bar processing, binding, installation and reshipment
within the site etc.

Main Contractor shall supply the steel bar, allowing wastage not exceeding more than
3.3.2 1.5%, the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted t 0.174 -
from any due to or becoming due to payment of Subcontractor based on the provided rate
schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by weight in accordance with the joint surveying upon
completion.

Sawcut Control Joint

Detailed technical requirements refer to the Drawing.

The work shall not be conducted until the final setting time of the concrete at least reach
to 4-6 hours and follow the instruction of Main Contractor.
3.3.3 m 77.10 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by length in accordance with the joint surveying upon
completion.

TOTAL SUB-AMOUNT (MAINTENANCE SHOP): -

4 Civil Work for Material Storage


4.1 Foundation of Material Storage

Earth Excavation

Detailed technical requirements refer to the Drawing.

Including but not limited to excavation, pumping water of the pit (if any),
4.1.1 m3 70.56 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by natural volume in accordance with the joint surveying
upon completion.

C15 Cushion for Foundation

Detailed technical requirements refer to the Drawing.

Including but not limited to excavation, setting out, formwork installation and
dismantlement, concrete pouring and curing etc.

Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%,
4.1.2 m3 5.88 -
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.

C30 Concrete Foundation

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out, formwork installation and dismantlement,
concrete pouring, vibration and curing etc.

Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%,
4.1.3 m3 26.10 -
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.

Steel Bar for Foundation

Detailed technical requirements refer to the Drawing.

Including but not limited to steel bar processing, binding, installation and reshipment
within the site etc.

Main Contractor shall supply the steel bar, allowing wastage not exceeding more than
4.1.4 1.5%, the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted t 13.522 -
from any due to or becoming due to payment of Subcontractor based on the provided rate
schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by weight in accordance with the joint surveying upon
completion.
DENAI CONCEPT SDN BHD
Appendix 1
BILL OF QUANTITIES

PROJECT: Civil Works of the Rest Construction Area of the New CH138 Camp

NO DESCRIPTION UNIT PROV. QTY UNIT RATE (RM) TOTAL (RM) Remarks

Iron Build-In Fitting Installation

Detailed technical requirements refer to the Drawing.

Including but not limited to the Iron Build-In Fitting installation etc.

4.1.5 Main Contractor shall supply the Iron Build-In Fitting. NOS 22 -

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by number in accordance with the joint surveying upon
completion.

Backfill

Including but not limited to the backfill, compacting and rolling, and leveling the
additional earth. The compactness shall be not less than 95%.
4.1.6 m3 38.58 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by compacted volume in accordance with the joint surveying
upon completion.

4.2 C25 Ground Hardening for Material Storage

Ground Hardening

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out, original ground leveling, compacting and rolling,
formwork installation and dismantlement, concrete pouring, vibration and surface
troweling, roughening, geotextile curing, etc.

4.2.1 Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%, m3 213.84 -
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by volume in accordance with the dimension on the


Construction Drawing.

Sawcut Control Joint

Detailed technical requirements refer to the Drawing.

The work shall not be conducted until the final setting time of the concrete at least reach
to 4-6 hours and follow the instruction of Main Contractor.
4.2.2 m 240.00 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by meter in accordance with the joint surveying upon
completion.

TOTAL SUB-AMOUNT (MATERIAL STORAGE): -

5 Civil Work for Oil Storage Tank

C25 Concrete for Foundation

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out, formwork installation and dismantlement,
concrete pouring, vibration and curing etc.

Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%,
5.1 m3 22.08 -
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.

Steel Bar for Bottom Slab

Detailed technical requirements refer to the Drawing.

Including but not limited to steel bar processing, binding, installation and reshipment
within the site etc.

Main Contractor shall supply the steel bar, allowing wastage not exceeding more than
5.2 1.5%, the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted t 0.110 -
from any due to or becoming due to payment of Subcontractor based on the provided rate
schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by weight in accordance with the joint surveying upon
completion.
DENAI CONCEPT SDN BHD
Appendix 1
BILL OF QUANTITIES

PROJECT: Civil Works of the Rest Construction Area of the New CH138 Camp

NO DESCRIPTION UNIT PROV. QTY UNIT RATE (RM) TOTAL (RM) Remarks

Brick Masonry for the Wall

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out; brick wall masonry etc.
5.3 m3 10.50 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.

M10 Mortar on the Wall Surface (Both Sides)

Detailed technical requirements refer to the Drawing.

Including but not limited to plastering M10 Mortar on the wall surface (both sides) etc.
5.4 ㎡ 93.72 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by area in accordance with the joint surveying upon
completion.

Normal Yellow and Black Paint on the Wall Surface (Both Sides)

Detailed technical requirements refer to the Drawing. Detailed method statement refer to
the instruction of Main Contractor.

Including but not limited to plastering paint on the wall surface (both sides) etc.
5.5 ㎡ 93.72 -
Subcontractor shall supply all the manpower, material and machinery and equipment,
tools, hardware, instrument.

Quantities shall be measured by area in accordance with the joint surveying upon
completion.

Brick Masonry for the Staircases

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out; brick wall masonry etc.
5.6 m3 1.00 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.

M10 Mortar on the Staircase Surface

Detailed technical requirements refer to the Drawing.

Including but not limited to plastering M10 Mortar on the staircase surface etc.
5.7 ㎡ 4.75 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by area in accordance with the joint surveying upon
completion.

Normal Yellow and Black Paint on the Staircases

Detailed technical requirements refer to the Drawing. Detailed method statement refer to
the instruction of Main Contractor.

Including but not limited to plastering normal white paint on the staircases surface etc.
5.8 ㎡ 4.75 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by area in accordance with the joint surveying upon
completion.

Brick Masonry for the Oil Interceptor

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out; brick wall masonry etc.
5.9 m3 1.48 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.
DENAI CONCEPT SDN BHD
Appendix 1
BILL OF QUANTITIES

PROJECT: Civil Works of the Rest Construction Area of the New CH138 Camp

NO DESCRIPTION UNIT PROV. QTY UNIT RATE (RM) TOTAL (RM) Remarks

M10 Mortar on the Oil Interceptor Wall Surface

Detailed technical requirements refer to the Drawing.

Including but not limited to plastering M10 Mortar on the wall surface etc.
5.10 ㎡ 5.95 -
Subcontractor shall supply all the manpower, material and machinery and equipment,
tools, hardware, instrument.

Quantities shall be measured by area in accordance with the joint surveying upon
completion.

Oil Tank Installation

Detailed technical requirements refer to the Drawing.

Including but not limited to lifting, installation etc.


5.11 NOS 2 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by number in accordance with the joint surveying upon
completion.

TOTAL SUB-AMOUNT (OIL STORAGE TANK): -

6 Civil Work for Wash Trough

Earth Excavation

Detailed technical requirements refer to the Drawing.

Including but not limited to excavation, pumping water of the pit (if any),
6.1 m3 11.38 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by natural volume in accordance with the joint surveying
upon completion.

Hardcore Replacement Filling

Detailed technical requirements refer to the Drawing.

6.2 Subcontractor to supply all the manpower, material, machinery and equipment, tools, m3 20.00 -
hardware, instrument.

Quantities shall be measured by compacted volume in accordance with the joint surveying
upon completion.

C25 Concrete for Bottom Baseplate

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out, formwork installation and dismantlement,
concrete pouring, vibration and curing etc.

Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%,
6.3 m3 10.20 -
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.

Steel Bar

Detailed technical requirements refer to the Drawing.

Including but not limited to steel bar processing, binding, installation and reshipment
within the site etc.

Main Contractor shall supply the steel bar, the loss rate 1.5% shall be complied with by
6.4 t 0.167 -
Subcontractor, otherwise the amount for extra quantities shall be deducted from any due
to or becoming due to payment of Subcontractor based on the market price.

Subcontractor shall supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by weight in accordance with the joint surveying upon
completion.

Iron Build-In Fitting (Angle Steel with Steel Bar Holder) Installation

Detailed technical requirements refer to the Drawing.

Including but not limited to the Iron Build-In Fitting processing and installation etc.

6.5 Main Contractor shall supply the Iron Build-In Fitting. NOS 5 -

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by number in accordance with the joint surveying upon
completion.
DENAI CONCEPT SDN BHD
Appendix 1
BILL OF QUANTITIES

PROJECT: Civil Works of the Rest Construction Area of the New CH138 Camp

NO DESCRIPTION UNIT PROV. QTY UNIT RATE (RM) TOTAL (RM) Remarks

C25 Concrete for Sedimentation Basin

Detailed technical requirements refer to the Drawing.

Including but not limited to setting out, formwork installation and dismantlement,
concrete pouring and curing etc.
6.6 m3 0.32 -
Subcontractor to supply all the manpower, material, machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.

Backfill

Including but not limited to the backfill, compacting and rolling, and leveling the
additional earth. The compactness shall be not less than 95%.
6.7 m3 5.00 -
Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by compacted volume in accordance with the joint surveying
upon completion.

Φ225 PVC Pipe Installation

Detailed technical requirements refer to the Drawing.


6.8 m 1.00 -
Quantities shall be measured by length in accordance with the joint surveying upon
completion.

TOTAL SUB-AMOUNT (WASH TROUGH): -

7 Ground Hardening

C25 Concrete Hardening, 20cm Thickness

Detailed technical requirements refer to the Drawing.

Including but not limited to original ground rolling and compacting, the compactness shall
not be less than 95%; formwork installation and dismantlement; concrete pouring,
vibration, curing and roughing etc.

7.1 Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%, m³ 800.00 -
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.

Sawcut Control Joint Cutting

Detailed technical requirements of the joint cutting refer to the TENDER DRAWING and
follow the instructions of the Main Contractor.

The work shall not be conducted until the final setting time of the concrete at least reach
7.1.1 m 800.00 -
to 4-6 hours and follow the instruction of Main Contractor.

Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by meter in accordance with the result of the joint surveying.

C30 Hardening for Aggregate Warehouse Field Area, C25 Concrete Hardening,
20cm Thickness

Detailed technical requirements refer to the Drawing.

Including but not limited to original ground rolling and compacting, the compactness shall
not be less than 95%; formwork installation and dismantlement; concrete pouring,
vibration, curing and roughing etc.
7.2 m³ 650.00 -
Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%,
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.

Sawcut Control Joint Cutting

Detailed technical requirements of the joint cutting refer to the TENDER DRAWING and
follow the instructions of the Main Contractor.

The work shall not be conducted until the final setting time of the concrete at least reach
7.2.1 m 650.00 -
to 4-6 hours and follow the instruction of Main Contractor.

Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by meter in accordance with the result of the joint surveying.
DENAI CONCEPT SDN BHD
Appendix 1
BILL OF QUANTITIES

PROJECT: Civil Works of the Rest Construction Area of the New CH138 Camp

NO DESCRIPTION UNIT PROV. QTY UNIT RATE (RM) TOTAL (RM) Remarks

C30 Hardening for Batching Plant Field Area, C25 Concrete Hardening, 20cm
Thickness

Detailed technical requirements refer to the Drawing.

Including but not limited to original ground rolling and compacting, the compactness shall
not be less than 95%; formwork installation and dismantlement; concrete pouring,
vibration, curing and roughing etc.
7.3 m³ 1,300.00 -
Main Contractor shall supply the concrete, allowing wastage not exceeding more than 2%,
the loss shall be absorbed by Subcontractor own cost, otherwise to be deducted from any
due to or becoming due to payment of Subcontractor based on the provided rate schedule.

Subcontractor to supply all the manpower, all the other material and machinery and
equipment, tools, hardware, instrument.

Quantities shall be measured by volume in accordance with the joint surveying upon
completion.

Sawcut Control Joint Cutting

Detailed technical requirements of the joint cutting refer to the TENDER DRAWING and
follow the instructions of the Main Contractor.

The work shall not be conducted until the final setting time of the concrete at least reach
7.3.1 m 1,300.00 -
to 4-6 hours and follow the instruction of Main Contractor.

Subcontractor to supply all the manpower, material and machinery and equipment, tools,
hardware, instrument.

Quantities shall be measured by meter in accordance with the result of the joint surveying.

TOTAL SUB-AMOUNT (GROUND HARDENING): -


C Provisional Sum
1 Excavator DAY (8 HOURS) 10 -
2 Lorry DAY (8 HOURS) 10 -
3 Loader DAY (8 HOURS) 10 -
4 Backhoe Loader DAY (8 HOURS) 10 -
5 Bulldozer DAY (8 HOURS) 10 -
6 Compactor DAY (8 HOURS) 10 -
7 General Worker DAY (8 HOURS) 10 -
8 skill worker DAY (8 HOURS) 10 -

TOTAL SUB-AMOUNT (PROVISIONAL SUM): -

TOTAL AMOUNT (RM) : -