Professional Documents
Culture Documents
Introduction to
Learning Objectives the Power
Distribution
After studying this unit, you should be able to: System
describe the important features of the power
distribution system;
In Unit 1 of Block 1, you have been very briefly introduced to the power supply
system. You have also learnt in Unit 1 that the demand for electrical power in
India is enormous and growing steadily. Units 2 and 3 have provided you an
overview of the power sector with a special focus on the power distribution
sector, which is responsible for covering the last mile in reaching power to the
consumers.
In this Unit, we give a description of the power distribution system and its
components. We acquaint you with the concept of distribution system
planning, which forms the basis for the smooth operation of the power
distribution system. We also present the general principles and practices
underlying the operation and maintenance of the system. In the next Unit, we
deal specifically with the operation of substation equipment, distribution lines
and their maintenance requirements.
You are familiar with the power supply system. You know that electricity is
generated at 11 kV by electrical generators which utilise the energy from
thermal, hydro, nuclear, and renewable energy resources. To transmit
electricity over long distances, the supply voltage is stepped up to 132/220/
400/800 kV, as required. Electricity is carried through a transmission
network of high voltage lines. Usually, these lines run into hundreds of
kilometres and deliver the power into a common power pool called the grid.
The grid is connected to load centres (cities) through a sub-transmission
network of usually 33 kV (or sometimes 66 kV) lines. These lines terminate
into a 33 kV (or 66 kV) substation, where the voltage is stepped-down to 11 kV
for power distribution to load points through a distribution network of lines at
11 kV and lower.
The power network of concern to the end-user is the distribution network of
11 kV lines or feeders downstream of the 33 kV substations. Each 11 kV
feeder which emanates from the 33 kV substation branches further into
several subsidiary 11 kV feeders to carry power close to the load points
(localities, industrial areas, villages, etc.). At these load points, a transformer
further reduces the voltage from 11 kV to 415 V to provide the last-mile
connection through 415 V feeders (also called Low Tension (LT) feeders) to
individual customers, either at 240 V (as single-phase supply) or at 415 V (as
three-phase supply). The utility voltage of 415 V, 3-phase is used for running
the motors for industry and agricultural pump sets and 240 V, single phase is
used for lighting in houses, schools, hospitals and for running industries,
commercial establishments, etc.
A feeder could be either an overhead line or an underground cable. In urban
areas, owing to the density of customers, the length of an 11 kV feeder is
8 generally up to 3 km. On the other hand, in rural areas, the feeder length is
much larger (up to 20 km). A 415 V feeder should normally be restricted to Introduction to
the Power
about 0.5 −1.0 km. Unduly long feeders lead to low voltage at the consumer Distribution
end. The power supply system, including the distribution network, is depicted System
in Fig. 4.1.
Fig. 4.1: Typical Electric Power Supply System with Distribution Network
The main components of the power distribution system and their brief
descriptions are given in Table 4.1.
Component Description
High voltage primary distribution or 3.3 kV, 6.6 kV, 11 kV, 22 kV, 33 kV,
sub-transmission 66 kV
Higher voltages are used for 3-phase, 3-wire supply to large consumers. Low
voltage distribution of generally 415 V, 3-phase 4-wire system and 240 V
single phase, two wire, phase to neutral system is used for small and medium
consumers. The size and, hence, voltage of supply to a consumer is decided
by the load of the consumer.
4.2.2 Conductors
The 11 kV feeders carry comparatively bulk power from secondary substation
(33/11 kV) to distribution substation transformers (DTRs). Distributors (or
secondary network) carry power from DTRs through service lines (or LT
feeders) which deliver power from the supplier’s nearest support to
consumer’s premises up to the energy meter, through a weather-proof
service wire.
• The current that the distributor has to carry is calculated on the basis of
the load incident on the conductor (including anticipated load growth).
ACSR and AAAC conductors are used for secondary distribution systems.
ACSR conductors are preferred to AAC conductors for long spans owing to
their greater tensile strength. The current carrying capacity of ACSR
conductors is as follows:
In this system, the secondary distribution system with long LT feeders running
up to consumer premises from the distribution substation is totally absent.
The primary distribution system at HT level (11 or 33 kV) is used to
reach the nearest point for a group of small number of consumers. The
consumers are then connected to the HT Distribution System at these
points through small pole mounted transformers used for supplying
power to them through LT service lines. 11
Operation and We now describe the advantages of HT distribution compared to conventional
Maintenance
LT distribution system.
The comparison of current, losses and voltage drop for the distribution of
the same power through HT and LT systems is presented in Table 4.3.
We have considered 100 as the base value for LT system. From the table,
you can see that for the distribution of the same power, technical losses
and voltage drop are much less in HT distribution system when compared
to LT distribution systems.
Table 4.3: Comparison of Current, Voltage Drop and Power Losses for Power
Distribution through HT and LT Distribution Systems
……………………………………………………………………………….
……………………………………………………………………………….
b) What is HVDS? Outline its advantages over the LT system.
……………………………………………………………………………….
……………………………………………………………………………….
4.3.1 Substation
A substation is the meeting point between the transmission grid and the
distribution feeder system. This is where a fundamental change takes place
within most T&D systems. The transmission and sub-transmission systems
above the substation level usually form a network (about which you will study
in the next section). But arranging a network configuration from the substation
to the customer would simply be prohibitively expensive. Hence, most
distribution systems are radial (also described in the next section), i.e., there
is only one path through the other levels of the system.
Typically, a substation consists of high and low voltage racks and buses for 13
Operation and power flow, circuit breakers at the transmission and distribution level,
Maintenance
metering equipment and the control house, where the relaying,
measurement and control equipment is located. But the most important
piece of equipment that gives the substation its capacity rating is the
substation transformer. It converts the incoming power from transmission
voltage levels to the lower primary voltage for distribution. Very often, a
substation has more than one transformer.
4.3.2 Transformer
A transformer is an electrical device that transfers power from one circuit to
another without change in frequency. The purpose of a transformer is to
convert one AC voltage to another AC voltage. A transformer comprises
two or more coupled conducting coils (windings), which are wound on
common laminated core of a magnetic material such as iron or iron-nickel
alloy (Fig. 4.4). These are called primary and secondary windings.
If the primary and secondary windings have the same number of turns, the
14 primary and secondary voltages will be the same. For step-down
transformers, the secondary winding has lesser number of turns than the Introduction to
the Power
primary. For example, to step-down voltages from 240 V at the mains to 6 V, Distribution
there needs to be 40 times more turns in the primary than in the secondary. In System
case of step-up transformers, the number of turns in the secondary winding
is more than those in the primary winding.
The transformer is one of the simplest of electrical devices, yet transformer NOTE
designs and materials continue to be improved every day.
The relation between
the voltages, currents
and number of turns in
the primary and
secondary coils is
given by
V2 I N
= 1 = 2
V1 I 2 N1
Specifications of Transformer
A transformer should be provided with more than one primary winding or with
taps on the winding if it is to be used for several nominal voltages. The Rated
Power of the transformer is the sum of the VA (Volts x Amps) for all the
secondary windings. The important specifications for a transformer are:
primary frequency of incoming voltage (50 Hz), maximum primary
voltage rating, maximum secondary voltage rating, maximum secondary
current rating, maximum power rating, efficiency, voltage regulation and
output type (3 wire or 4 wire).
Types of Transformer
4.3.3 Feeders
Feeders route the power from the substation throughout the service area.
They are typically either overhead distribution lines mounted on wooden
poles, or underground buried or ducted cable sets. Feeders operate at the
primary distribution voltage in primary distribution system and secondary
16 distribution voltage in the secondary distribution system.
Introduction to
the Power
Distribution
System
Definition of a feeder
By definition, the feeder consists of all primary or secondary
voltage level segments of distribution lines between two
substations or between a substation and an open point (switch).
The most common primary distribution voltages in use are 11 kV, 22 kV and
33 kV. The main feeder, which consists of three phases, may branch into
several main routes.
The main branches end at open points where the feeder meets the ends of
other feeders – points at which a normally open switch serves as an
emergency tie between two feeders. 17
Operation and Feeders are connected in a configuration, which depends on the type of
Maintenance
network required in the distribution system. Three types of network are
normally available in the electrical distribution system:
• radial;
• loop; and
• cross-loop network.
Since the radial feeder emanates from one point and ends at the other in the
radial network, load transfer in the case of breakdown is not possible.
Although a radial feeder can be loaded to its maximum capacity, in the case of
breakdown, quite a large area may remain in dark until the fault is detected
and repaired.
In loop arrangement, two feeders are connected to each other so that in the
case of breakdown, the faulty section can be isolated and the rest of the
portion can be switched on. In this type of system, the feeder is normally
loaded to 70% of its capacity so that in the event of breakdown it can share
the load of other feeders also.
Fig. 4.8: Alternative Layouts for Primary and Secondary Network, 33 and 11 kV
In big cities, the concept of 33 kV ring main is very popular and two ring
mains are laid: one outer and one inner. The outer ring main is laid using the
panther conductor and the inner ring main is laid using the dog conductor.
The use of these two types of ring mains provides excellent flexibility to the
system and at the time of breakdown, supply can be immediately switched on
from another 132 kV substation. While making any distribution planning
18 (discussed in Sec. 4.4) for metros, the aspect of outer and inner 33 kV ring
mains is extremely essential and should be included for providing Introduction to
the Power
uninterrupted supply. Distribution
System
Table 4.5 gives a comparison of the three types of network configurations.
§ Interface meter,
It is important to note that these regulations make the use of static meters
mandatory for new consumers. 19
Operation and
Maintenance SAQ 2: Components of power distribution system
……………………………………………………………………………….
……………………………………………………………………………….
………………………………………………………………………………
………………………………………………………………………………
The need for electrical power is growing at a rapid pace on account of rapid
growth of population, industrialisation and urbanisation resulting in high load
density pockets with multi storied complexes. This is coupled with manifold
increase of deep tube wells on account of low ground water level and huge
number of electric pumps connected to the system during the agricultural
season in rural areas. In order to meet the future power needs of the nation,
it is essential to upgrade the existing distribution system and increase its
efficiency and at the same time reduce the technical losses. This requires
proper planning: Utilities have to plan much ahead to meet the present
as well as the projected future demand for quality power supply.
In the context of the current chronic power shortage, the shooting prices of
fuel and the need for conservation of available fossil fuel resources, you can
well understand the urgency of eliminating high losses in the transmission and
distribution system. The high percentage of losses in our country is a matter
of national concern. The main cause of these high losses is laying of
unplanned distribution system in the country. Proper distribution system
planning, financial support and implementation of the plans should be
able to bring down the losses and provide uninterrupted quality supply to the
consumers.
• spelling out the specific activities required in the planning process, and
• implementation of plans.
v Medium/Long-term Planning
v Short-term Planning
For proper distribution planning, we first need to study the existing system,
ascertain loss level and decide on immediate action to be taken to meet
the requirement of consumers and provide them uninterrupted quality
power supply. In the present scenario, it has been found that 11 kV and
33 kV feeders are loaded more than 100% of their rated current carrying
capacity. This results in very high technical losses and needs to be
immediately relieved through short-term planning.
……………………………………………………………………………….......
……………………………………………………………………………….......
……………………………………………………………………………….......
……………………………………………………………………………….......
……………………………………………………………………………….......
• Existing Load Data Study: The study of the existing system forms a
critical input to distribution planning and includes activities such as
− updating all distribution system statistics;
− evaluating changes in technic and economic planning criteria; and
− evaluating and updating load forecasts, voltages and consumers
category-wise with a time horizon of 10 to 15 years.
We now present a case study to illustrate how utilities can take advantage of
distribution planning.
The number of 33 kV rural feeders in the Discom is 282. These have been
strung with Racoon conductors having current carrying capacity of 200 A.
The Discom selected all the 33 kV feeders having loading more than150 A for
study and analysis.
As the National Tariff Policy has made it mandatory for power utilities to
segregate technical and commercial losses within one year, a detailed study 23
Operation and was conducted through CYMDIST software, which is a proven tool for finding
Maintenance
technical losses at each voltage level of the distribution system.
The study was initially conducted on 20 select feeders but later it was
extended to the heavily loaded 224 rural feeders. It was found that 49 feeders
had losses amounting to more than 10% and 52 feeders had losses between
5 -10%. An analysis of the data revealed that for some feeders, voltage
regulation could not be brought within permissible limits even after the
placement of Capacitor Bank, proposing a new 33 kV feeder and augmenting
the conductor size. Further studies were carried out and locations were
identified for putting up 132/33 kV substations. Through short term studies,
the Discom identified 5 such locations.
Between 250−
−300 A 25
Between 200−
−250 A 56
Between 150−
−200 A 28
The number of 11 kV feeders in the Central Discom is 1749, of which 358 are
urban feeders and 1391 rural. In the first phase, a study of all 11 kV urban
feeders was conducted through the CYMDIST software and action was taken
for bifurcation of feeders, augmentation of conductor capacity and putting up
new 33/11 kV substations. All 11 kV feeders of urban areas now have Racoon
conductor and the load of each feeder is within 100 A. The voltage regulations
are also within permissible limits.
In the second phase, a study of 11 KV rural feeders is being carried out. All the
existing feeders are laid on ACSR weasel conductor. The length of the feeders
ranges from 4 km − 100 km and voltage regulation varies from 3% to 24%.
The break-up of the rural feeders on the basis of load is given in Table 4.7.
Between 150−
−200 A 170
Between 100−
−150 A 790
Between 75−
−100 A 172
Less than 75 A 79
The number of 11 kV feeders having load more than 200 A is 180 and a study
is being conducted on them in the first phase through the CYMDIST software.
• Future Load Growth Study: Historical load growth data was the major
basis in anticipating the future load growth.
• Power Factor and Reactive Load Study: A thorough study was made on
the existing power factor and existing load on the system and as per the
data obtained from CYMDIST software study, necessary compensation
was provided by installation of 11 kV capacitor bank on 33/11 kV
substations. 25
Operation and • Thermal Capability of Conductor: Operating data was used to check
Maintenance
whether the conductors were being operated within thermal capability
limits.
You may like to review this information in your own context. Attempt the
following SAQ!
Suggest ways in which your utility can benefit from distribution system
planning.
………………………………………………………………………………......
………………………………………………………………………………......
In this section, we discuss the general O&M objectives and activities for the
power distribution system.
v Increasing the availability and reliability of plant and equipment with NOTE
effective maintenance planning.
Source: Special report
v Improving spares planning and reducing spares inventories. on CEA website
“Guidelines for Project
v Standardising work procedures. Management and
Performance Evaluation
v Ensuring the safety of maintenance personnel.
of Sub-transmission and
v Providing a mechanism for making estimates and controlling Distribution Project”.
maintenance expenses.
v Reduction in
− T&D losses,
− overloading of feeders and transformers,
− consumer interruption
− cost per consumer
− number of trippings due to overloading.
v Degree of improvement in voltage profile vis-à-vis voltage regulation.
v Increase in revenue.
Utilities should have manuals for O&M to ensure efficient and trouble free
operation of the system/equipment. These manuals should contain the
following information:
• factory and site test certificates for each item of the system with reference
to relevant design calculation and quality assurance standards;
• maintenance instructions for all plants and other preventive and corrective
maintenance procedures;
• maintenance and inspection schedules for all items/equipment giving type
of works required on a weekly, monthly, annual basis; and
• proforma of the required maintenance record sheets for all the
component/equipment.
Outline the O&M objectives of your distribution utility. What activities are
undertaken by it to fulfil these objectives?
………………………………………………………………………………
………………………………………………………………………………
………………………………………………………………………………
………………………………………………………………………………
………………………………………………………………………………
………………………………………………………………………………
………………………………………………………………………………
LOCAL
DISTRIBUTION SYSTEM
Definition of a grid
Grid is defined in the Electricity Act, 2003, as : “the high voltage
backbone system of inter-connected transmission lines,
substations and generating plants.”
CUSTOMERS
There are many advantages of having a grid.
ADVANTAGES OF A GRID
The real time operation of the grid is looked after by the Load Dispatch
Centre, which is basically a round-the-clock control room manned by grid
operators or load dispatchers, who operate the grid by giving instructions to
the personnel of the concerned generators and substations.
♦ the voltage profile at all points of the grid remains within acceptable limits;
♦ the grid operates in a stable manner, i.e., there are no power swings.
The Grid Management in our country is done by the Regional Load Dispatch
Centre (RLDC) at the Regional Level and by the State Load Dispatch Centre
(SLDC) at the State Level. Each State, Central Generating Stations and
Independent Power Producers (IPPs) are treated as constituents of the
Region.
v Grid security,
v Economy, and
Besides this, there are also other voltage phenomena like unbalanced voltage
in the three phases, voltage dip, etc. Voltage unbalance in the grid could be
caused due to the tripping of one of the phases of a transmission line or due
to unbalanced load in the three phases emanating from the distribution
systems or bulk loads. Voltage dip, on the other hand, is a transient
phenomenon caused by a transient fault or tripping of an element at a remote
location of the grid. Stormy weather could also cause flashover between
arcing horns, resulting in voltage dip.
• real time operation and control for optimal utilization of available resources
in the grid, which involves
− scheduling,
− monitoring, and
− restoration of grid;
The load dispatch centre is primarily responsible for management of the grid.
Its various functions: ex-ante (a Latin term meaning before-hand), real-time
34 and post-facto (meaning after the fact) are given in Table 4.8.
Table 4.8: Grid Management Functions Introduction to
the Power
Distribution
EX-ANTE REAL-TIME POST-FACTO System
• Ensuring proper
power quality
• Minimizing losses
and optimizing
resource utilization
• Tackling
emergencies
effectively and
efficiently.
The SLDCs then convey to the RLDC their schedule of power drawal from the
Central stations (limited to their entitlement for the day). The RLDC
aggregates these requisitions and determines the dispatch schedules for the
Central generating stations and the drawal schedules for the beneficiaries
(State as a whole) duly incorporating any bilateral agreements and adjusting
for transmission losses. These schedules are then issued by the RLDC to all
concerned and become the operational as well as commercial datum for
inter-State and CGS transactions.
While the schedules so finalized become the operational datum, and the
regional constituents are expected to regulate their generation and consumer
load in a way that the actual generation and drawals generally follow these
schedules, deviations are allowed as long as they do not endanger the system
security.
Load Shedding
During the normal operation of a grid, it is possible that the load exceeds the
generation. If this happens the frequency of the system goes down. The
standard frequency is 50 Hz. But the frequency can go down to about 49.0 Hz.
After this value, it is not advisable to allow it to reduce it any further since it can
cause the system to lose synchronism and lead to ultimate collapse of the
system. As a result, we go for purposeful shedding of load, known as load
shedding. The load shedding is a process of reducing load on the grid so as
to save the grid as a whole.
You have studied in Sec. 4.6.1 that off-line operational planning involves
• load generation balance planning in respect of active power for the next
year, which is reviewed on a quarterly and then monthly basis, in order to
ensure that the frequency stays at the nominal level;
• protection coordination;
The pricing for UI is linked to system frequency such that the constituent
causing the grid frequency to improve/worsen in worst conditions gets
rewarded/penalised at higher price and vice versa. Further, the UI pool account
is zero sum account, i.e., the amounts received from constituents are
distributed amongst the other constituents. As long as the actual generation/
drawal is equal to the given schedule, UI is zero and the payment on account
of the third component of Availability Tariff is zero. In case of under-drawal, a
beneficiary is paid back to that extent according to the frequency dependent
rate specified for deviations from schedule.
Apart from natural unbalancing, unbalanced load may also result from load
shedding of one phase in each of the LT feeders emanating from a
distribution substation. Even though the system may have been balanced
initially, it is difficult to have similarly loaded outgoing feeders and achieve
equal load shedding in the three phases. In some cases, due to constraints on
availability of proper switching facility on each feeder, it is difficult to shed
equal load from each phase.
• Consumer Satisfaction.
On this note, we bring the discussion in this unit to an end. In this unit, you
have learnt about the Power Distribution System, and the general goals and
practices for its maintenance. We now summarise the contents of the unit.
4.7 SUMMARY
5. Does your utility have written O&M practices? If yes, study those and
suggest improvements in the same. If not, what practices are followed
in the field?
42
Introduction to
the Power
APPENDIX 1: REACTIVE POWER CONTROL Distribution
System
IN DISTRIBUTION SYSTEMS
Reactive power (kVAR) control represents an efficient method of reducing
the cost of utility operation. The savings brought about by kVAR/voltage
control are not confined to the monetary value of the energy saved; the
released system capacity can serve to delay a costly expansion and reduce
the ageing of components. kVAR control provides appropriate placement
of compensation devices to ensure a satisfactory voltage profile while
minimizing the power losses and the cost of compensation.
The flow of vars, or reactive power, through a watt-hour meter will not affect
the meter reading, but the flow of vars through the power system will
result in energy losses on both the utility and the industrial facility.
Some utilities charge for these vars in the form of a penalty, or kVA demand
charge, to justify the cost for lost energy and the additional conductor and
transformer capacity required to carry the vars. In addition to energy losses,
var flow can also cause excessive voltage drop, which may have to be
corrected by either the application of shunt capacitors, or other more
expensive equipment, such as load-tap changing transformers,
synchronous motors, and synchronous condensers.
The power factor triangle shown in Fig. 1 is the simplest way to understand
the effects of reactive power. The longest leg of the triangle (on the upper or
lower triangle), labelled total power, represents the vector sum of the reactive
power and real power components. Mathematically,
The angle Φ in the power triangle is called the power factor angle and is
mathematically equal to:
43
Operation and
Maintenance
The ratio of the real power to the total power in the equation above (or the cos
of Φ) is called the power factor.
A high power factor eliminates penalty charges imposed when operating with a
low power factor. Investment on system facilities such as transformers,
cables, switchgears, etc. for delivering load is reduced.
Work Specification
− Standardising work specifications.
− Maintaining notes on work specifications.
Preventive Maintenance and Overhaul
− Generate preventive maintenance plans.
− Listing of locations, equipment and tasks to be included in the plan.
− Allocation of tasks to specific groups.
− Recording the material required.
− Generating work orders.
− Overhauling equipment as per requirement.
Breakdown Maintenance
− Noting the time of fault and the priority status.
− Processing the request.
− Enabling maintenance work.
Condition-based Maintenance
− Predicting potential machine failures.
− Recording data about malfunctioning equipment.
Signature Analysis
− Identifying parameters to be monitored for each class of equipment. 45
Operation and − Identifying test point for measuring the above.
Maintenance
− Entering a target or optimum value, and limits for the parameter.
− Determining the frequency of measurements to be made at each test
point.
− Generating schedules for taking readings.
− Capturing readings at each test point.
− Analysing readings and generating alarm / warning signals.
− Displaying message to generate work order if required.
Maintenance Requests
− Issuing maintenance requests.
− Closing maintenance requests.
Spares Planning
− Identifying spares required for equipment.
− Viewing the updated stock positions.
− Generating lists of spares featuring quantity required and criticality.
Maintenance History
− Recording detailed maintenance history.
− Recording breakdown details / cause of failure / action taken /
downtime.
− Generating reports for equipment failures.
Document Management
− Maintaining document master.
− Generating document register.
47
Operation and
Maintenance
48