You are on page 1of 7

The official publication of the Tunnelling NORTH AMERICAN EDITION

Association of Canada December ~ January 2016

CSOs

TAC Awards

Risk

CANADA'S BEST TAC bestows accolades in the 2015 awards

001tunNA1215cover.indd 1 25/11/2015 09:40


T E C HNI C A L / RIS K

CONQUERING COBBLY,
BOULDERY GROUND
T
UNNELLING IN ground with
cobbles and boulders involves risks.
Primary risks include: obstruction;
reduced advance rates; steering difficulties;
increased risk of excessive lost ground Steve Hunt
settlements or sinkholes and associated Steve is a senior tunnelling technologist at
damage; impact or vibration damage to CH2M based in Henderson, Nevada
cutter housings or TBM gears; increased
abrasion and wear of cutters, cutterhead
and mucking system; and lower utilization
resulting from intervention time to remove
Properly managing risk of tunnelling in cobbly, bouldery
obstructions and repair worn tunnelling ground can be accomplished using four steps. Steve
components. The importance of these risks
depends on extent of cobbly-bouldery Hunt, of CH2M, explains the relevant investigations,
ground and the tunnelling means and
methods employed. Assessment of risk
baselines and mitigation methods
severity requires specialized subsurface and resulting risks - use a risk register to thoroughly identify
investigation, identification of potential and quantity the risks.
hazards, quantification of probability of 4. Determine mitigation methods – list mitigation options and
occurrence and potential consequences. work with prospective contractors and the owner to determine
Once risk severity has been determined, how best to mitigate the unacceptable risks through prescriptive
mitigation measures can be selected and specifications, baselining, payment items and construction
implemented. administration.
In order to properly manage risks of
tunnelling in ground with cobbles and UNDERSTANDING RISKS
boulders, four steps should be followed: Tunnelling risks are not only dependent on the ground
conditions, but also on the site conditions and tunnelling
1. Understand the risks – identify the methods employed. Site condition factors include: tunnel depth;
ground hazards and associated surface access constraints (land use and easement restrictions);
potential consequences for the utility interferences to potential rescue or obstruction removal
tunnelling methods being considered. shafts; dewatering and ground improvement limits; settlement
2. Characterize and quantify – use special limits; vibration limits and ground contamination. Tunnelling
subsurface investigation methods method factors involve: tunnel size and shape; face stability
to collect ground condition data; control measures (open mode vs. closed and pressurized mode);
characterize the cobble, boulder and required ground improvement; excavation tools (TBM cutters,
matrix conditions; quantify volume spades, backhoes, rotary milling heads, etc.); available power; face
ratios, sizes, shapes, distributions, Below: Figure 1, access; and the mucking system.
abrasivity and rock clast strengths. Risk of boulder In general, cobble and boulder impact risks are less for large
3. List hazards, potential consequences obstruction tunnels with free air (open-mode) access and higher for smaller
tunnels with pressurized face (closed-mode) access. This concept
relative to obstruction risk is illustrated in Figure 1.
Many hazards and potential consequences are listed in
Table 1. Quantification of the potential consequences in terms
of safety, cost or delay is much more difficult and depends on
specific ground and site conditions. Some of the more common
Risk of obstruction

MTBM-TBM with no face


access and no disc cutters severe consequences include: obstructed advance (stuck TBM)
requiring an abandoned tunnel drive or rescue shaft or hyperbaric
MTBM-TBM with face
access intervention; severe cutter, cutterhead, mucking system or gear
damage from impacts or abrasion resulting in a need for a rescue
shaft or hyperbaric intervention to make major repairs; and much
Open face
slower than anticipated advance rates or maintenance delays that
TBM - shield result in much longer tunnelling time and costs.

INVESTIGATE, CHARACTERISE AND BASELINE


0% ~30% ~70% 100% Managing risks of tunnelling in cobbles and boulders requires an
adequate understanding of ground conditions and the geologic
Relative boulder size
setting. Too often, the site and subsurface investigation program

30 | Tunnels | December ~ January 2016 www.tunnelsonline.info

030_035tunNA1215cobble.indd 30 25/11/2015 10:07


RI S K / T E C HNI C A L

Table 1. Boulder encounter hazards and potential consequences for TBM excavated tunnels
Hazard or Condition Potential consequence
Boulder(s) over ~ 20-30 per cent diameter, no face- 46 Stuck TBM, rescue shaft or shaft-tunnel required or TBM-
chamber access or disc cutters tunnel abandoned
Boulders composed of much harder, stronger rock than 38 Severe pump and slurry line wear resulting in pump
expected failure or line rupture
Cobble and boulder quantities much greater than 33 Severe cutter wear, higher tool replacement cost, poten-
expected tial stuck TBM
Matrix ground or cobbles and boulders are much more 33 Severe mucking system wear resulting in stoppages for
abrasive than anticipated repair or replacement
Boulders in weak-loose matrix resulting in plucked boul- Severe cutterhead wear or rock crusher bar wear, reduced
der rolling on cutterhead advance rate, stuck TBM
Mixed face heading weak soil zone adjacent to hard Steering difficulty, TBM shield deflected beyond line or
bouldery ground grade limits
Advance rate higher than allowed for disc cutters causing Broken cutters or cutter housings and or cutter arms or
plucked rock damaged gears from high impact forces
Plucked boulders extending beyond perimeter or at face Perimeter voids, excess lost ground, sinkholes, damaging
result in voids and ground loss settlements
Perimeter boulder(s) not cut by gage cutters or plucked Pipe or lining damage from passed perimeter boulder
from perimeter causing high contact stresses
Attempt to blast or split boulders at heading in free air Face instability and excess ground loss at face resulting
and unstable soil damaging settlements or sinkholes
Large oblong boulders pass through cutterhead opening Boulders jam inside rock crusher or excavation chamber
requiring an intervention to remove
Source: Author

is not customized to provide suitable information on cobble cobble and boulder conditions should
and boulder conditions. In most cases, a routine subsurface be phased and should include multiple
investigation program will not provide the information exploration methods. After each phase,
needed. What is needed is a geologic desk study followed by a the geologic setting should be refined and
customized, phased, subsurface investigation program where remaining uncertainties for the anticipated
each phase is evaluated in a geologic setting and the next phase underground construction methods
is designed to reduce remaining uncertainties. All the relevant identified. The subsequent phase should
collected data should be presented in a geotechnical data report be designed to reduce uncertainties and
(GDR). Key cobble, boulder and matrix ground conditions should improve geologic condition reliability.
be baselined in a geotechnical baseline report (GBR). Conventional 100 to 200mm diameter
rotary wash or hollow stem auger borings
Geologic desk study and setting with split spoon sampling is rarely adequate
An investigation of cobble and boulder conditions should be alone for investigation of cobble and
completed in the context of a geologic setting to be effective. boulder conditions. Conventional borings
The occurrence of cobbles and boulders is dependent on geologic and sampling should be completed and
processes, which affect the character of geologic units. As a result, can be enhanced by drilling observations
different geologic units tend to have characteristic ranges in cobble such as determination of ‘relative drilling
and boulder conditions. Each geologic unit should be specifically resistance’ as defined in Hunt (2014).
baselined and as a result, the subsurface investigation program In most cases, conventional borings
should be designed to help define geologic units. should be supplemented by subsurface
A site reconnaissance and geologic desk study should be investigation methods. The effectiveness
completed to determine to scope of the initial subsurface and relative cost of 10 subsurface
investigation phase. The desk study should obtain and include investigation methods was discussed in
review of available: geologic maps, reports and papers; previous Hunt and Del Nero (2010) and is discussed
subsurface investigation reports from any source in the vicinity; in more detail in Hunt (2014). The most
a Phase 1 Environmental Site Assessment; a geologic site cost-effective additional method is often
reconnaissance, an initial phase subsurface utility study; and a rotosonic coring. It allows continuous
review of reports from previous underground construction projects coring and sampling. Cobble and boulder
in the project vicinity. This information should be evaluated to sizes and quantities can be determined
establish an initial geologic setting and a crude risk register (at by careful logging of core samples and
least a list of potential hazards and risks). The scope of the first extrapolation of sizes from pieces in
phase of subsurface investigation should be designed to verify the the core. A study of various exploration
interpreted geologic conditions, the desk study information and to methods within glacial soils in Columbus,
reduce specific uncertainties. Ohio, (Frank & Chapman 2001) also found
rotosonic coring to be the most cost-
Subsurface investigation effective supplementary method.
A subsurface investigation program that includes assessment of Other methods that should be

www.tunnelsonline.info December ~ January 2016 | Tunnels | 31

030_035tunNA1215cobble.indd 31 25/11/2015 10:07


T E C HNI C A L / RIS K

10%
vs. clustered) for each geologic unit
■ Rock clast mineralogy and rock type descriptions including both
9% native and erratic clasts
Bouldery Ground Length / Lengh Drilled In Borings

■ Rock clast unconfined compressive strength ranges (histogram)


8% ■ Cerchar abrasivity index (CAI) ranges for rock clasts
■ Soil matrix types, strength (including degree cemented), density,
7%
abrasivity and permeability.
6%
Additional conditions to consider baselining include: cobble
5% and boulder angularity and shapes. Cobble and boulder quantities
are generally best baselined as boulders per length of tunnel for
4% each selected size range, however cobble and boulder volume
ratios for geologic units should also be given. Other items require
3% baselining of ranges and mean-averages. When sufficient data
exists, histograms are generally the best method of baselining.
2%
Histograms show both the data range and predominant values.
1% The thoroughness of the subsurface investigation program
(available data) and risks involved should guide decisions on how
0.0% 0.2% 0.4% 0.6% 0.8% 1.0% 1.2% 1.4% 1.6% 1.8% 2.0%
many of these items to baseline. Where data from a site specific
Boulder Volume Ratio subsurface investigation program is lacking, regional typical value
data obtained from the desktop study might be used. For example,
if data from other projects or from geologic studies of similar rock
considered and utilized when practical Above: BVR types indicates typical unconfined compressive strengths range
include: test pits (particularly when the vs. per cent from 135 to 200 MPa, and site specific data is lacking, the typical
tunnel zone geologic unit can be reached); bouldery ground local values should be baselined.
accessible construction excavations, in borings (Hunt, Regarding cobble and boulder quantities, ultimately, bidders
shafts or quarries; Becker percussion 2002) want to know baseline quantities for expected size ranges. If the
borings; and large diameter auger borings. excavated tunnel diameter is known, the quantities for selected
Generally less effective methods include size ranges along each tunnel reach can be baselined. Alternatively,
cone penetrometer probes, cross-hole and cobble volume ratio (CVR) and boulder volume ratio (BVR) can be
surface seismic refraction, and ground baselined for anticipated geologic units or tunnel reaches.
penetrating radar.
Another potentially very effective Volume ratio baselining
method to consider is horizontal directional Volume ratio methods involve analysis of geologic and subsurface
drilling or directional-horizontal boring investigation data to determine CVR and BVR values for specific
with coring capability. This method can geologic units. The data can often include a percentage per length
result in much more sample recovery from drilled in cobbly-bouldery ground within conventional borings and
the proposed tunnel zone and therefore CVR-BVR determinations from a second source such as rotosonic
better baselining of cobble and boulder cores, test pits, or large diameter auger bores.
conditions. To improve interpretation of conventional small diameter
borings, the author developed a BVR correlation chart using cobble
Cobble and boulder baselining and boulder indications such as high Standard Penetration Test
Cobble and boulder conditions can and (STP) blow counts, Relative Drilling Resistance (RDR) - (Hunt
should be baselined for most tunnel & Angulo, 1999; Hunt, 2002; Hunt & Del Nero, 2010; Hunt
projects even where pressurized face 2014). Figure 2 shows the correlation between small diameter
tunnelling results in very little or no access conventional boring indication of boulders and BVR. Tables 2 and
to the heading to determine actual ground 3 provide charts for RDR and STP for use in indicating cobble and
conditions encountered for comparison boulder occurrence.
to baselines. Despite challenges in An interpretation of the data and determination of the ratio
measuring cobble and boulder conditions between CVR and BVR is also needed for each geologic unit. CVRs
encountered, baselines are still essential are generally higher than BVRs. For several Milwaukee projects
to help bidders understand anticipated studied, cobble volume ratios were estimated to be approximately
conditions and better manage risks by one-and-a-half to two times the BVRs, which resulted in much
selecting suitable means and methods, higher cobble quantities due to their smaller sizes. On the
estimating reasonable advance rates and Bradshaw 8 project in Sacramento, California, the CVRs ranged
planning mitigation costs. The primary from 25 to 50 per cent and were much greater than BVRs due to
cobble and boulder (rock clast in soil fluvial sorting – CVRs typically ranged from five to 10 times greater
matrix) related conditions to consider than the BVRs. On two other projects in California, CVRs ranged
baselining include: from three to five times the BVRs. On the Chengdu Metro project
in China, CVRs ranged from 60 to 85 per cent in some geologic
■ Quantities and size ranges for units. On the BWARI project in Columbus, Ohio, a back analysis by
anticipated cobbles the author indicated an approximate CVR of 0.22 per cent and a
■ Quantities and size ranges for BVR of 0.34 per cent - a ratio of 0.65 to 1. Estimated total average
anticipated boulders CVR to BVR ratios for 23 projects studied vary from approximately
■ Cobble, boulder distributions and 0.5 to 10 and average about 2.
concentrations along tunnel (isolated Once a percentage of cobbly and bouldery ground per

32 | Tunnels | December ~ January 2016 www.tunnelsonline.info

030_035tunNA1215cobble.indd 32 25/11/2015 10:07


RI S K / T E C HNI C A L

Table 2. Relative drilling resistance (RDR)


RDR Term Criteria Typical ground conditions
1 Very easy No chatter, very little resistance, very fast and Very soft to soft silts and clays; very loose to loose
steady drill advance rate silts and sands; no gravel, cobbles, boulders or rubble
2 Easy No chatter, some resistance, fast and steady drill Firm to stiff silts and clays; loose to medium dense
advance rate silts and sands; little or no gravel, no to very few cob-
bles, boulders or pieces of rubble
3 Moderate Some chatter, firm drill resistance with moder- Stiff to very stiff silts and clays; dense silts and sands;
ate advance rate medium dense sands and gravel; occasional cobbles or
rubble pieces (2-3 occurrences per 10 ft)
4 Hard Frequent chatter and variable drill resistance, Very stiff to hard silts and clays with some gravel
slow advance rate and cobbles; very dense to extremely dense silts and
sands with some gravel; dense to very dense sands
and gravel; very weathered, soft bedrock; frequent
cobbles and boulders or rubble pieces (3-4 per 10 ft)
5 Very hard Constant chatter, variable Hard to very hard silts and clays with some gravel;
and very slow drill advance, nearly refusal very dense to extremely dense gravelly sand or sandy
gravel; very frequent cobbles and boulders (at least 5
per 10 feet); weathered, very jointed bedrock
Source: Author

unit boring length for each geologic unit is determined from The most extensive study of subsurface
conventional borings, CVRs and BVRs can be estimated for each exploration for tunnelling in bouldery
geologic unit using Figure 2. The resulting estimates should ground and development of an approach
be compared to CVR and BVR date from the other subsurface to predict boulder quantities and sizes
exploration sources as well as data from previous shaft and tunnel for baselining was completed by Frank &
excavations in the same geologic units. Any inconsistencies should Chapman during the early to mid-2000s
be rectified if possible, but ultimately the more reliable and often for the BWARI project in Columbus, Ohio.
the more conservative interpretations are used. They developed an exponential distribution
Specific quantities of cobbles and boulders can be estimated relationship similar to that used for the
for shaft and tunnel excavation volumes in each geologic unit Storebaelt Tunnel. The number of clasts
using a spreadsheet. The size ranges desired and maximum (boulders) expected is computed as N=C/
anticipated boulder size must first be selected. Figure 3 shows BVR 7rEXIFSF/OPDMBTUT 7WPMVNF
data evaluation completed for a tunnel reach using a negative excavated, C is a constant correlated with
exponential distribution function within a spreadsheet. Subsurface sample size data, and d is a constant
investigation data analysis is used to estimate the mean size and correlated with clast size distribution (Frank
standard deviation for each tunnel reach in a geologic unit. An & Chapman, 2005). The method requires
“area factor” calculation is completed to convert computed boulder a significant amount of reliable sample
volumes into boulder quantities for each size range. The result is data from the subsurface investigation.
an estimate of the total number of boulders for the reach being The constant d is evaluated from boulder
analysed. The resulting boulder quantities can then be baselined. sizes found in the investigation. The
constant C is calculated from boulder
Probabilistic methods volume data. The number of clasts for
Attempts to predict boulder quantities using statistical or selected sizes is then computed using the
probabilistic methods date back to at least 1976 when Stoll 1976 formula with these constants. Tunnelling
attempted to use a random probabilistic method. Tang & Quek results indicated that boulder quantities
1986 published the results from a statistical evaluation of the were slightly over-predicted, but accurate
lengths of boulders taken from boreholes in sedimentary deposits estimates of actual boulders encountered
in Singapore. They showed a statistical correlation of lengths in were difficult to make from the broken
boreholes with excavated boulder sizes. Probabilistic methods were rock and very large quantities of muck.
also used for the Storebaelt Tunnel in Denmark (Ditlevsen 1997,
2006) and more recently for a tunnel in Italy (Felletti 2009). Baselining conclusions
Which aspects of cobble and boulder
Table 3. Standard penetration test (STP) conditions to baseline and whether or
not to directly baseline conditions or
Corrected N value indicating
Approximate average relative use functional baselines depends on the
probable cobbles and or boulders
density of soil matrix ground conditions, anticipated methods of
(blows/ft)
construction and project owner’s preference
Loose >25 for risk sharing. The method to use for
Medium dense >50 evaluating data to predict quantities for
baselining should depend on the size of
Dense >75 the project and the quality and quantity
Very dense >100 of data available. When desired to baseline
quantities, the CVR and BVR method is
Source: Author
generally more practical than probabilistic

www.tunnelsonline.info December ~ January 2016 | Tunnels | 33

030_035tunNA1215cobble.indd 33 25/11/2015 10:07


T E C HNI C A L / RIS K

Project Example at BVR =1% Drive 1000 ft of 10 ft ED tunnel

Tunnel excavated volume, Tt = 78500 ft3 ED = 120 in


% boulders by volume, BVR = 1.00% ED = 10.00 ft

L = 1000 ft
Total volume of boulders, VB = 785 ft3
Mean value, = 18 in
Standard deviation, = 10 in

Lower Upper Avg Area Vol. of Single Number 90


bound bound boulder factor boulders boulder of Small Medium Large
[in] [in] size [in] ft3 vol*, ft3 boulders 80
12 14 13 0.141 76 0.890 86 70

No. of boulders
14 16 15 0.152 83 1.367 60 60
16 18 17 0.159 86 1.990 43
18 20 19 0.159 86 2.779 31 50
20 22 21 0.152 83 3.752 22 40
22 24 23 0.141 76 4.929 15
24 26 25 0.125 68 6.330 11 30
26 28 27 0.106 58 7.973 7 20
28 30 29 0.087 47 9.880 5
30 32 31 0.069 37 12.068 3 10
32 36 34 0.090 49 15.922 3 0
36 40 38 0.044 24 22.228 1 13 15 17 19 21 23 25 27 29 31 34 38 42 46
40 44 42 0.018 10 30.013 0 Average boulder size (in)
44 48 46 0.007 4 39.430 0
1.448794 785 Total 288
Avg B/ft = 0.3 Small boulders = 220 r=d/2 Size, d(ft) Boulder volume
Avg B size*,d = 1.5 ft Med boulders = 63 sphere = 1.33 r3 1 0.52 ft3 0.019 yd3
Avg B size*,d = 18 in Large boulders = 5 cube = d3 1 1.00 ft3 0.037 yd3
Avg B vol = 273 ft3 Small boulders = 331 ft3 12.2 yd3 *rd’d cube = 0.7d3 1 0.70 ft3
0.026 yd3
Avg B vol = 0.101 yd3 Med boulders = 368 ft3 13.6 yd3
rd’d cube = 0.8d3 1 0.80 ft3 0.030 yd3
Large boulders = 86 ft3 3.2 yd3
Total voloume = 785 ft3 29 yd3

methods for most projects. Probabilistic Above: Boulder including: cutters, cutterhead, crusher and mucking system. The
methods are viable for larger projects with size distribution occurrence of cobbles and boulders can significantly increase
a significant amount of quality data. In for anticipated the rate of abrasion of components beyond that caused by the
either case, the method should consider the BVR value abrasiveness of the matrix soil (Gharahbagh et. al. 2012). The
geologic setting, geologic variability and increase is dependent on the abrasiveness of the cobble and
local experience. boulder rock clasts and the CVR and BVR magnitudes.

HAZARDS, POTENTIAL Impact risk


CONSEQUENCES AND Excavating and ingesting cobbles and boulders causes impact
RESULTING RISKS forces and vibrations. Impacts tend to cause cutter and cutter
The occurrence of cobbles and boulders housing breakage and may cause cutter bearing or gear-pinion
creates a large variety of hazards that failures. The risk of impact consequences increases with boulder
may result in concernable risk depending size and CVR and BVR magnitudes. Impact forces also tend to be
on the ground conditions, surface more severe when the difference in density and strength between
conditions and tunnelling method. In the rock clasts and matrix are more extreme, such as when cobbles
general, these risks can be grouped into and boulders are in a loose, soft matrix.
three categories: obstruction, abrasion
and impact vibration. Hunt 2014 provides Risk assessment
a detailed discussion of these risks. This is Hazards and potential consequences from encountering
a general overview. anticipated cobble and boulder conditions for each tunnelling
method being considered should be analysed using a risk register.
Obstruction risk This form of risk assessment requires reliable data on cobble
Obstruction risks are those that may and boulder conditions from a thorough, phased subsurface
obstruct or stop the tunnel advance, investigation program and tunnelling experience provided by
significantly slow the rate of advance engineers, contractors and TBM manufacturers. Once risk levels
or result in steering problems. A large have been determined, risk allocation and mitigation measures can
boulder or clusters of cobbles and boulders be determined.
may stop tunnel advance if the energy
required to break and ingest the rock clasts MITIGATION METHODS
exceeds the capabilities of the TBM and When assessment indicates high, unacceptable tunnelling risks
cutters. TBM obstruction and advance rate from cobbles and boulders, they should be avoided, mitigated or
reduction are very common tunnelling risks allocated. Avoidance and mitigation measures generally involve
(Hunt and Mazhar 2004). both planning and design decisions and construction actions
Significant cobble and boulder risk avoidance and mitigation
Abrasion risk may occur during planning and design. Reliable data on
Abrasion risks are related to wear or anticipated cobble and boulder ground conditions and tunnelling
breakage of components that come methods is required. Planning and design phase avoidance and
into contact with the ground and muck mitigation measures may include:

34 | Tunnels | December ~ January 2016 www.tunnelsonline.info

030_035tunNA1215cobble.indd 34 25/11/2015 10:07


RI S K / T E C HNI C A L

■ Vertical and horizontal alignment changes to avoid or minimize mitigation measures to manage cobble
extent of tunnelling in adversarial ground conditions. and boulder risks. Again, reliable data on
■ Horizontal alignment changes to minimize overhead anticipated cobble and boulder ground
interferences and obstructions that would prevent a rescue conditions is essential to allow effective
shaft if needed. construction phase risk mitigation.
■ Tunnel depth changes to avoid zones with high CVRs and Contractors and TBM manufactures have
BVRs or minimize adversarial ground conditions such as high the most control over TBM robustness and
permeability. components to eliminate or resist cobble
■ Spacing and locating shafts to reduce drive lengths and and boulder impacts. These measures
associated wear impacts and to allow for easier repairs and have a cost that must be managed
maintenance of TBM components. through bidding, pay items and contractor
■ Spacing and locating ground improvement ‘safe zones’ to allow controlled risk management. Some of the
open mode interventions for cutter changes and cutterhead contractor and TBM manufacture cobble
repairs. and boulder risk mitigation measure
■ Increasing the allowable or specified tunnel diameter to improve options are:
potential TBM power, face access and intervention options.
■ Use of prescriptive specifications to require bidders-contractors ■ TBM type and component design:
to have minimum essential TBM system components. This cutter types, cutter access, excavation
might involve: cutter types; cutterhead armouring and opening access, cutterhead and mucking system
ratio restrictions; excavation chamber access; requirements for materials and armouring, grizzly bars,
hyperbaric intervention, TBM torque-speed, and or conditioning rock crusher, EPB screw design, face
or slurry to minimize abrasion; TBM type restrictions, purpose- access, air locks, etc.
build TBMs vs. refurbished TBM, advance probing and grouting ■ TBM and mucking system operation
from TBM requirements, and more. measures: advance rates, cutterhead
rotation speed-torque, conditioner use,
Depending on specification requirements, contractors and slurry design, and advance probing and
TBM manufactures have a considerable to full range of potential grouting capability.
■ Shaft spacing and locations affecting
drive lengths including additional shafts
References or safe zones for interventions.
■ Frequency of inspection and
Ditlevsen O. 1997. Probability of boulders. In: Storebaelt East Tunnel, N.J. Gimsing, (Ed). A/S maintenance activities.
Storebæltsforbindelsen, Copenhagen, (1997) 39–41.
Ditlevsen O. 2006. A story about distributions of dimensions and locations of boulders, SUMMARY AND CONCLUSIONS
Probabilistic Engineering Mechanics, Elsevier-Science Direct, (21- 1) (2006), 9-17. During the past 20 years, the tunnelling
Felletti F. & Pietro-Beretta G. 2009. Expectation of boulder frequency when tunnelling in industry has made considerable
glacial till: A statistical approach based on transition probability, Elsevier-Science Direct, improvements in capability to
Engineering Geology, (108) (2009), 43-53. successfully microtunnel and tunnel in
Frank G. and Chapman D. 2001. Geotechnical Investigations for Tunnelling in Glacial Soils, cobbly-bouldery ground. Subsurface
In: Proceedings of 2001 Rapid Excavation and Tunnelling Conference. W.H Hansmire & I.M investigations have gotten more varied
Gowring (Eds), SME, Littleton, Colorado, (2001-26), 309-324. and focused to obtain necessary data. A
Frank G. & Chapman D. 2005. New Model for Characterizing the Cobble and Boulder database of typical cobble and boulder
Fraction for Soft Ground Tunnelling, Hutton J.D. & Rogstad D. (Eds), In: Proceedings 2005 volume ratios for common soil types
Rapid Excavation and Tunnelling Conference., SME, (2005-60), 780-791. has grown. Designers have developed
Gharahbagh, E.A., Frank G., DiPonio M. A., Shinouda. M. M. and Rostami, J. 2012. Cutterhead practical and statistical methods to
Wear Study for EPB TBMs in Glacial Soils. Proceedings of North American Tunnelling predict cobble and boulder occurrences.
Conference. 2012. SME. N2012.13, 100-108. These methods have been used with
Hunt S.W. and Angulo M. 1999. Identifying and Baselining Boulders for Underground reasonable success on many projects.
Construction. In: G. Fernandez & R.A. Bauer (Eds), Geo-Engineering for Underground Baselining and pay items (where
Facilities. ASCE, Reston Virginia, 1999, 255-270. applicable) have helped to significantly
Hunt S.W. 2002. Compensation for Boulder Obstructions. In: Proceedings of The North reduce the contractual and cost risk of
American Tunnelling 2002, Ozdemer L., (Ed), Rotterdam: Balkema, (2002- 3), 23-36. excavating through cobbly-bouldery
Hunt S.W. & Mazhar F.M. 2004. MTBM and Small TBM Experience with Boulders. In: ground. Risk management methods
Proceedings of North American Tunnelling 2004, Ozdemir L. (Ed.), SME, Littleton, Co., (2004- should be used to assess cobble and
6), 47–64. boulder risks along all portions of the
Hunt S.W. & Del Nero, D.E. 2010. Two Decades of Advances Investigating, Baselining and alignment. Where the consequences
Tunnelling in Bouldery Ground. Proceedings of World Tunnelling Congress. Vancouver, ITA- of getting stuck are high or where the
TAC, 2010, 8p. cost of interventions to change cutters
Hunt S.W. 2014. Tunnelling in Cobbles and Boulders. Proceedings of Breakthroughs in is excessive, contract documents might
Tunnelling Short Course. Colorado School of Mines, September 15-17, 2014, 38p. require more robust TBMs or MTBMs
Stoll U.W. 1976. Probability That A Soil Boring Will Encounter Boulders. In: Conference with face access and combination roller
on Better Contracting for Underground Construction, Michigan Section of ASCE, Detroit and scraper cutters. Where conditions
(1976), 34-48. are bad and risks are high, redundancy
Tang W., Quek S.T. 1986. Statistical model of boulder size and fraction. Journal of and backup plans should be designed
Geotechnical and Geoenvironmental Engineering, 112 (1), ASCE (1986) 79–90. with appropriate pay items to manage
uncertainties and risks

www.tunnelsonline.info December ~ January 2016 | Tunnels | 35

030_035tunNA1215cobble.indd 35 25/11/2015 10:07

You might also like