Professional Documents
Culture Documents
1 of 98
Name of Project : Construction of Aqueduct
Procurement an Transportation of Tools
For Schemes For Schemes with For Schemes with For Schemes with For Schemes with more
S.No. Type of Tools Unit Unit Rate Unit wt upto 3 km pipeline 3 to 5 km pipeline 5 to 8 km pipeline 8 to 15 km pipeline than 15 km pipeline
( Rs.) ( kg) Qtty. Cost Rs. Qtty. Cost Rs. Qtty. Cost Rs. Qtty. Cost Rs. Qtty. Cost Rs.
S.WELL Page 4
Sump Well Under FC RVT
3 Dry stone soling 1 1.40 1.40 0.15 0.29 m³ 9,812.88 2845.74 11,284.81 3272.59
4 Plain Cement Concrete (1:2:4) 0 0
Side wall 1 4.80 0.20 1.00 0.960 0 0
base 1 1.40 1.40 0.20 0.392 0 0
Total 1.352 m³ 32,210.67 43548.83 37,042.27 50081.15
6 Centering & shuttering work for PCC/RCC 0 0
Inner sides 4 1.00 1.00 4.00 0 0
-Outer side 4 1.40 - 1.00 5.60 0 0
Total form work 9.60 m² 2,420.74 23239.1 2,783.85 26724.96
0 0
7 Steel reinforcement 0 0
8 mm ø @ 100 mm c/c bothways 24 4.00 @ 0.395 kg/m 37.92 0 0
54 1.00 @ 0.395 kg/m 21.33 0 0
Total reinforcement 59.25 kg 126.14 7473.8 145.06 8594.81
0 0
8 12.5 mm thick 1:2 c-s plaster 0 0
floor 1 1.00 1.00 1.00 0 0
Inner sides 4 1.00 - 1.00 4.00 0 0
Total 5.00 m² 683.08 3415.4 785.54 3927.7
C.WELL Page 5
Barbed Wire Fencing & Gate
Mesh Wire Fencing ( Type - A)
Construction of Aqueduct
Total length of fencing = 30 m
S.N. Description No. Length Breadth Height Quantity Unit UC Contract
Rate Amount Rate
1 Earthwork in excavation for foundation work in hard soil
19 0.20 0.20 0.50 0.38 m³ 920.56 349.81 1,058.64
2 Plain Cement Concrete (1:3:6)
For anchoring blocks 19 0.15 0.15 0.50 0.21 m³ 29,515.20 6,198.19 33,942.48
3 Plain Cement Concrete (1:2:4) for wall top 1 22.00 0.35 0.10 0.77 m³ 32,210.67 24,802.22 37,042.27
4 Stone masonry (1:6) cement mortar for wall 1 22.00 0.35 0.50 3.85 m³ 18,422.07 70,924.97 21,185.38
5 MS angle post(ISA 40×40×3 - 2.1m long) 19 2.10 @ 1.80 kg/m 71.82 kg 110.03 7,902.35 126.53
MS angle post(ISA 25×25×3 - 1.5m long) 19 1.50 @ 1.10 kg/m 31.35 kg 110.03 3,449.44 126.53
6 Mesh wire fencing work 1 30.00 30.00 m 926.91 27,807.30 1,065.95
7 Two (primary, first & second)coats of
readymade enamel painting work 19 1.50 0.16 4.56 m² 295.76 1,348.67 340.12
Entrance Gate
For Mesh wire fencing Type-A
UC Contract
S.N. Description No. Length Breadth Height Quantity Unit Rate Amount Rate
Contract
Amount
402.28
-
7,127.92
28,522.55
81,563.71
9,087.38
3,966.72
31,978.50
1,550.95
164,200.01
164,200.01
6,841.67
Entrance Gate
For Mesh wire fencing Type-A
Contract
Amount
455.22
1,241.33
-
-
-
22,880.21
-
-
-
2,002.61
-
-
-
2,547.45
5,501.50
486.37
35,114.69
35,114.69
Mesh Wire Fencing ( Type - B )
(Total Fencing Length 24 m)
Contract
Amount
275.25
-
-
-
5,091.37
28,511.68
71,182.88
12,435.37
30,699.36
1,898.02
1,044.17
151,138.10
151,138.10
6,297.42
Electrification Works
Ground Dist. from E.Main line to OHT compound 4000 m Nos of Pole 80
2 pole extra for Tranformer Installation Total no of pole 82
Quantit Unit Rate Amount Unit weight
S.N. Description of Items Unit Remarks
y (NRs.) (NRs.) (kg)
Ground Distance 4000 m
I Eletrification Works
A Material Cost
A1 11 KV Line
1 PSC electrical pole 9m long
82.00 nos 25000.00 2050000.00 147.00 Keeping 50 m pole to pole distance in average
2
PSC electrical pole 11 m long(As per NEA
Specification) ; (Single upto OHT area &
Double in last station for Transformer) nos 27000.00 0.00 175.00
17 0.03 Sq. Inch A.C.S.R. Conductor 12.600 Km 35000.00 441000.00 128.00 Adding 5 % Extra for slag
18 11KV disc insulator set 246 sets 1000.00 246000.00 3 nos for each pole
19 Suspension Clamp(Tension set) 83 nos 450.00 37350.00 1 for 3 Disk Insulator=16/3=6nos
20 Stay assembly complete set 164 sets 2000.00 328000.00 2 nos for single pole
21 Stay wire 7/12 984 kg 275.00 270600.00 6 kg per each stay set
22 Fabricated Chanel 2"*4"*8' 80 nos 5750.00 460000.00
23 Nuts & Bolts with washer full threaded 2 kg 250.00 500.00 1.00
Sub Total 3833450.00
Vat @13 % 498348.50
Grand Total A1 4331798.50
A2 Transformer & Accessories
Calculation of tranformer Capacity
For 1 HP motor 750 watt transformer
937.5 VA VA= Volt Ampere
0.9375 KVA KVA= Kilo Volt Ampere
For 17 HP motor 15.94 KVA 25 KVA Recommended
Ground Dist. from E.Main line to OHT compound 4000 m Nos of Pole 80
2 pole extra for Tranformer Installation Total no of pole 82
Quantit Unit Rate Amount Unit weight
S.N. Description of Items Unit Remarks
y (NRs.) (NRs.) (kg)
Vat @13 % 0.00
Grand Total A3 0.00
Electrification Works
Ground Dist. from E.Main line to OHT compound 4000 m Nos of Pole 80
2 pole extra for Tranformer Installation Total no of pole 82
Quantit Unit Rate Amount Unit weight
S.N. Description of Items Unit Remarks
y (NRs.) (NRs.) (kg)
A4 Procurement of energy meter & other accessories Note-
1 Metallic TOD Meter box 1 no 28000 28000.00 Main Switch(TOD=Time of day)
2 4 core, 70 mm2 Al Armored Power cable, 20 m 1850.00 37000.00 25kva Transformer-50/5 Amp
3 Main Switch, TOD Meter (100/5Amp,)LS 1 no 17500 17500.00 50 kva Transformer-100/5 Amp
4 CT 3 sets 3000 9000.00
5 7/18 wire 1 coil 5500 5500.00 100 kva Transformer-150/5 Amp
Sub Total 97000.00
Vat @13 % 12610.00
Grand Total A4 109610.00
B Labour Cost
1 Poling work 82.00 nos 0.00 0.00
2 0.03 Sq. Inch A.C.S.R. Conductor stringing-
12.600 Km 0.00 0.00
33 KV HT/LT
3 Stay installation 164 sets 1090.00 178760.00 "
4 Installation of 9 KV Lightning arrestor 3 set 4835.00 14505.00
5 Earthing work 2 job 4420.00 8840.00
6 Installation of 11 KV D/O Fuse set 2 job 4420.00 8840.00
7 Tr post & trasformer installation 1 job 32000.00 32000.00
8 Installation of MCCB 100Amp. 1 job 3625.00 3625.00
9 Cable laying 20 m 360.00 7200.00
10 Installation of 11 KV GOAB Switch 2 job 7120.00 14240.00
11 Transportation from source to site &
Installation 2 job 50000.00 100000.00
3 Dry stone soling 1 4.10 1.70 0.15 1.05 m³ 9,812.88 10303.52 11,284.81 11849.05
4 Plain Cement Concrete (1:2:4) 0 0
in foundation 1 4.10 1.70 0.10 0.697 0 0
Pipe embeddment block 3 0.35 0.20 0.20 0.042 0 0
top of baffle wall 1 0.80 0.35 0.10 0.028 0 0
Cover slab 1 4.10 1.70 0.10 0.697 0 0
Deduct: 0 0
-Manhole cover 1 0.60 0.60 0.05 -0.057 0 0
Total 1.407 m³ 32,210.67 45320.41 37,042.27 52118.47
5 Stone masonry work in 1:4 c-s mortar 0 0
Settler portion 1 9.40 0.45 1.75 7.40 0 0
middle wall 1 0.80 0.35 1.10 0.31 0 0
Total 7.71 m³ 19,752.01 152288 22,714.81 175131.19
6 Centering & shuttering work for PCC/RCC 0 0
Bottom of cover slab - CC portion 1 3.20 0.80 2.56 0 0
-Outer edge of cover slab 1 11.60 - 0.10 1.16 0 0
Total form work 3.72 m² 530.90 1974.95 610.54 2271.21
0 0
7 Steel reinforcement 0 0
8 mm ø @ 150 mm c/c bothways 20 1.70 @ 0.395 kg/m 13.43 0 0
12 2.90 @ 0.395 kg/m 13.75 0 0
Total reinforcement 27.18 kg 126.14 3428.49 145.06 3942.73
0 0
8 12.5 mm thick 1:4 c-s plaster 0 0
floor of CC 1 2.85 0.80 2.28 0 0
Inner sides of Walls of CC 2 2.85 - 1.75 9.98 0 0
2 0.80 - 1.75 2.80 0 0
Side of baffle wall 2 0.80 0.60 0.96 0 0
top of baffle wall 1 0.80 0.35 0.28 0 0
Outer portion of all walls above GL 1 11.60 - 0.30 3.48 0 0
Total 19.78 m² 607.41 12014.57 698.52 13816.73
9 3 mm thick 1:1 c-s punning 0 0
as per plaster 19.78 0 0
Deduct for outer portion -3.48 0 0
Total 16.30 m² 329.45 5370.04 378.87 6175.58
10
Supply and installation of standard
man hole cover - 600×600 mm² 1 1 set 2,090.57 2090.57 2,404.16 2404.16
11 Installation of pipes and fittings 1 job 500 1000 500 500
12 Mesh wire fencing (type A) 15 m 5949.29 89239.35 6841.67 102625.05
12 Entrance gate in fencing (Type-A) 1 Nos 31411.15 31411.15 35114.69 35114.69
Total amount 369942.26 423775.18
Vat13% 55090.77
Total amount 369942.26 478865.95
3.Very Difficult Load(Inconvenient materials & HDPE Pipes Above 40 mm Dia & above 25 mm dia GI pipe)
Black Top Earthen Road Loading/Unloading Total of Head load Total
From To Km Rate Total From To Km Rate Total Times Rate Total vehicle From To Km Rate Total Rate/Kg
Khalanga Phera Bazar 21 0.077 1.617 Phera Bazar Ghorneta 10 0.1485 1.485 2 0.132 0.264 3.366 Ghorneta Site 3 3.465 10.395 13.76
Rates for Analysis
Name of Project : Construction of Aqueduct
Local materials
1 Block Stone m3 2,981.00
2 Bond Stone m3 2,981.00
3 10 - 20 mm Aggregate m3 16,956.50
4 20 - 40 mm Aggregate m3 12,309.00
5 Sand m3 14,672.75
6 Mud ( 1.5md of coolie) m3 1,072.50
7 Sal Wood m 3
187,143.00
8 Local Wood m3 87,947.32
9 Bamboo no 400.00
10 Brick 1st class no 17.00
Labours
2 Stone for 1 m³
If it is to be purchased, cost/m³ = 0.00 Rs./cum
Labour required for collection and stacking of 1 m³ of stone = 1.40 nos
Cost of labour for collection and stacking of 1 m³ of stone = 1001.00 Rs.
Total Cost of transportation 1980.00 Rs.
Rate of 1 m³ of Stone at site = 2981.00 Rs.
1 Surface clearance
Trimming projections, filling
1 (1-7) depressions to level the surface etc. Labour 0.01 715.00 7.15
(including service roads etc.) for 1 m2 1 Sq.m. Total 7.15 Total - 7.15 1.07
Top Soil Excavation : Excavating
2 (1-8) 15-2 cm of the top soil including Labour 0.16 715.00 114.40
disposal outside of the constr. site 1 Sq.m. Total 114.40 Total - 114.40 17.16
3 Site clearance Unskilled 0.17 715.00 121.55 -
1 Sqm Total 121.55 Total - 121.55 18.23
2 Excavation Work
4 (2-9) Earthwork in Excavation in Soft Soil/Ordinary 1 Cum Labour 1 715.00 715.00 T & P @3% of Labour Cost 21.45 736.45 110.47
5 2 (12) Earthwork in Excavation in Hard Soil 1 Cum Labour 1.25 715.00 893.75 T & P @3% of Labour Cost 26.81 920.56 138.08
6 2 (14) Earthwork in Excavation in BMS 1 Cum Labour 1.59 715.00 1,136.85 T & P @3% of Labour Cost 34.11 1,170.96 175.64
7 (2-15Ka) Soft rock cutting in foundation, Drain 1 Cum Labour 3.00 715.00 2,145.00 T & P @3% of Labour Cost 64.35 2,209.35 331.40
8 (2-15Ka) Medium rock cutting 1 Cum Labour 4.50 715.00 3,217.50 T & P @3% of Labour Cost 96.53 3,314.03 497.10
9 2 (15-Kha) Hard rock cutting 1 Cum Labour 25.20 715.00 18018.00 T & P @3% of Labour Cost 540.54 18,558.54 2,783.78
3 Back Filling
9 (2-39Ka) with soft /ordinary Soil 1 Cum Labour 0.50 715.00 357.50 T & P @3% of Labour Cost 10.73 368.23 55.23
10 2 (39-Ga) Backfilling with Hard Soil 1 Cum Labour 0.63 715.00 450.45 T & P @3% of Labour Cost 13.51 463.96 69.59
11 2 (39-Gha) Earthwork in Backfilling with BMS 1 Cum Labour 0.60 715.00 429.00 T & P @3% of Labour Cost 12.87 441.87 66.28
12 2 (39-Na) Backfilling with Soft Rock 1 Cum Labour 1.10 715.00 786.50 T & P @3% of Labour Cost 23.60 810.10 121.52
4 Brick Works
13 5-1Ka1 Brick masonry in 1:3 cement mortar Mason 1.50 950.00 1425.00 Brick 530.0 Nos 17.00 9,010.00
Labour 2.20 715.00 1573.00 Cement 2.60 Bag 1,531.50 3,981.90
Sand 0.27 Cum 14,672.75 3,961.64
1 Cum Total 2998.00 Total 16,953.54 19,951.54 2,992.73
14 5-1Ka2 Brick masonry in 1:4 cement mortar Mason 1.50 950.00 1425.00 Brick 530.0 Nos 17.00 9,010.00
Labour 2.20 715.00 1573.00 Cement 2.00 Bag 1,531.50 3,063.00
Sand 0.27 Cum 14,672.75 3,961.64
1 Cum Total 2998.00 Total 16,034.64 19,032.64 2,854.90
Analysis of Labour & Material
Sub-Project : Construction of Aqueduct
Labour (A) Materials (B)
Analyzed Man Rate Amount Type of Unit Total Sub-Total Contract.
Sr. Norms Desciption of works for Category Days Rs. Rs. Materials Quantity Unit Rate Amount (A+B) O / head
No. No. used Rs. Rs. 15%
1 2 3 4 5 6 7 8 9 10 11 12
1x2 4x5 11*0.15
15 5-1Ka3 Brick masonry in 1:6 cement mortar Mason 1.50 950.00 1425.00 Brick 530.0 Nos 17.00 9,010.00
Labour 2.20 715.00 1573.00 Cement 1.80 Bag 1,531.50 2,756.70
Sand 0.31 Cum 14,672.75 4,548.55
1 Cum Total 2998.00 Total 16,315.25 19,313.25 2,896.99
16 5-1Ka3 Dry Brick masonry Mason 1.50 950.00 1425.00 Brick 530.0 Nos 17.00 9,010.00
Labour 2.20 715.00 1573.00
4 Stone Works
17 6-2 (2) R.R. Masonry in mud mortar Mason 1.00 950.00 950.00 Block Stone 1.10 Cum 2,981.00 3,279.10
18 6-2 (2) Dry stone masonry work Mason 1.00 950.00 950.00
Labour 2.00 715.00 1430.00 Block Stone 1.10 Cum 2,981.00 3,279.10
19 6 (5) Dry boulder packing work 1 Cum Labour 1.50 715.00 1072.50 Block Stone 1.20 Cum 2,981.00 3,577.20 4,649.70 697.46
20 11-16 Boulder soling with sand Mason 1.00 950.00 950.00 Block Stone 1.10 Cum 2,981.00 3,279.10
21 6-1 (2) R.R. masonry in 1:4 cement mortar Mason 1.50 950.00 1425.00 Block Stone 1.10 Cum 2,981.00 3,279.10
Labour 5.00 715.00 3575.00 Cement 3.18 Bag 1,531.50 4,870.17
Sand 0.45 Cum 14,672.75 6,602.74
1 Cum Total 5000.00 Total 14,752.01 19,752.01 2,962.80
22 6-1 (3) R.R. masonry in 1:6 cement mortar Mason 1.50 950.00 1425.00 Block Stone 1.10 Cum 2,981.00 3,279.10
Labour 5.00 715.00 3575.00 Cement 2.12 Bag 1,531.50 3,246.78
Sand 0.47 Cum 14,672.75 6,896.19
1 Cum Total 5000.00 Total 13,422.07 18,422.07 2,763.31
23 R.R. masonry in 1:3 cement mortar Mason 1.50 950.00 1425.00 Block Stone 1.10 Cum 2,981.00 3,279.10
Labour 5.00 715.00 3575.00 Cement 3.88 Bag 1,531.50 5,942.22
Sand 0.42 Cum 14,672.75 6,162.56
1 Cum Total 5000.00 Total 15,383.88 20,383.88 3,057.58
24 Gravel packing 20,25 mm dia Skilled 1.00 950.00 950.00 Aggregate
Analysis of Labour & Material
Sub-Project : Construction of Aqueduct
Labour (A) Materials (B)
Analyzed Man Rate Amount Type of Unit Total Sub-Total Contract.
Sr. Norms Desciption of works for Category Days Rs. Rs. Materials Quantity Unit Rate Amount (A+B) O / head
No. No. used Rs. Rs. 15%
1 2 3 4 5 6 7 8 9 10 11 12
1x2 4x5 11*0.15
Unskilled 3.50 715.00 2502.50 - 40 mm 1.10 Cum 12,309.00 13,539.90
1 Cum Total 3452.50 Total 13,539.90 16,992.40 2,548.86
5 Cement Concret Works
25 7-4 Kha Plain cement concrete (1:1:5:3) Mason 1.00 950.00 950.00 Cement 8.00 Bag 1,531.50 12,252.00
Sub structure Labour 4.00 715.00 2860.00 Sand 0.43 Cum 14,672.75 6,309.28
Aggregate
- 10mm 0.29 Cum 16,956.50 4,917.39
- 20mm 0.57 Cum 16,956.50 9,665.21
1 Cum Total 3810.00 Total 33,143.88 36,953.88 5,543.08
26 7-2 Gha Plain cement concrete (1:2:4) Mason 1.00 950.00 950.00 Cement 6.40 Bag 1,531.50 9,801.60
Sub structure Labour 4.00 715.00 2860.00 Sand 0.45 Cum 14,672.75 6,602.74
Aggregate
- 10mm 0.11 Cum 16,956.50 1,865.22
- 20mm 0.22 Cum 16,956.50 3,730.43
- 40mm 0.52 Cum 12,309.00 6,400.68
1 Cum Total 3810.00 Total 28,400.67 32,210.67 4,831.60
27 7-2 ga Plain cement concrete (1:3:6) Mason 1.00 950.00 950.00 Cement 4.40 Bag 1,531.50 6,738.60
Sub structure Labour 4.00 715.00 2860.00 Sand 0.47 Cum 14,672.75 6,896.19
Aggregate
- 20mm 0.24 Cum 16,956.50 4,069.56
- 40mm 0.65 Cum 12,309.00 8,000.85
1 Cum Total 3810.00 Total 25,705.20 29,515.20 4,427.28
N 7-4b Plain cement concrete (1:1:5:3) Mason 0.80 950.00 760.00 Cement 8.00 Bag 1,531.50 12,252.00
Superstructure Labour 7.00 715.00 5005.00 Sand 0.430 Cum 14,672.75 6,309.28
Aggregate
- 10mm 0.29 Cum 16,956.50 4,917.39
- 20mm 0.57 Cum 16,956.50 9,665.21
1 Cum Total 5765.00 Total 33,143.88 38,908.88 5,836.33
N 7-4a Plain cement concrete (1:2:4) Mason 0.80 950.00 760.00 Cement 6.40 Bag 1,531.50 9,801.60
Superstructure Labour 7.00 715.00 5005.00 Sand 0.45 Cum 14,672.75 6,602.74
Aggregate
- 10mm 0.11 Cum 16,956.50 1,865.22
- 20mm 0.22 Cum 16,956.50 3,730.43
- 40mm 0.52 Cum 12,309.00 6,400.68
1 Cum Total 5765.00 Total 28,400.67 34,165.67 5,124.85
Analysis of Labour & Material
Sub-Project : Construction of Aqueduct
Labour (A) Materials (B)
Analyzed Man Rate Amount Type of Unit Total Sub-Total Contract.
Sr. Norms Desciption of works for Category Days Rs. Rs. Materials Quantity Unit Rate Amount (A+B) O / head
No. No. used Rs. Rs. 15%
1 2 3 4 5 6 7 8 9 10 11 12
1x2 4x5 11*0.15
(N 7-2d) Mason 1.00 950.00 950.00 Cement 6.40 Bag 1,531.50 9,801.60
P.C.C (1:2:4) work in sub structure with 2%
W.P.C Labour 4.00 715.00 2860.00 Sand 0.45 Cum 14,672.75 6,602.74
Aggregate
- 20mm 0.33 Cum 16,956.50 5,595.65
- 40mm 0.52 Cum 12,309.00 6,400.68
Silica admixer @2% 6.40 kg 335.03 2,144.19
1 Cum Total 3810.00 Total 30,544.86 34,354.86 5,153.23
( N7-2d +N7-4b Mason 1.00 950.00 950.00 Cement 8.00 Bag 1,531.50 12,252.00
P.C.C(1:1.5:3) work in sub structure with 2%
W.P.C Labour 4.00 715.00 2860.00 Sand 0.43 Cum 14,672.75 6,309.28
Aggregate
- 20mm 0.86 Cum 16,956.50 14,582.59
Silica admixer @2% 8.00 kg 335.03 2,680.24
1 Cum Total 3810.00 Total 35,824.11 39,634.11 5,945.12
Plain cement concrete (1:1.5:3) upto 4m
7-2 ga inOHT Mason 0.80 950.00 760.00 Cement 8.00 Bag 1,531.50 12,252.00
Labour 8.00 715.00 5720.00 Sand 0.425 Cum 14,672.75 6,235.92
Aggregate
- 20mm 0.86 Cum 16,956.50 14,582.59
-
8-2-c 4.6 Formwork from 20m to 22m Skilled 1.0200 950.00 969.00 Timber 0.2290 cu.m 14,657.90 419.58
Locking set
79 17-4-ka DI pipe jointing works Plumber 2.00 950.00 1900.00 Others etc @10% 1,048.00
96 2-24b with 10 m lead and 4 m lift depth of 1 Cum Labour 3.6 715.00 2574.00 T & P @3% of Labour Cost 77.22 2,651.22 397.68
excavation: depth of excavation 2 m
97 2-24c with 10 m lead and 4 m lift depth of 1 Cum Labour 3.7 715.00 2645.50 T & P @3% of Labour Cost 79.37 2,724.87 408.73
excavation: depth of excavation 3 m
98 2-24d with 10 m lead and 4 m lift depth of 1 Cum Labour 3.8 715.00 2717.00 T & P @3% of Labour Cost 81.51 2,798.51 419.78
excavation: depth of excavation 4 m
99 2-24e with 10 m lead and 7.5 m lift depth 1 Cum Labour 4.2 715.00 3003.00 T & P @3% of Labour Cost 90.09 3,093.09 463.96
of excavation: depth of excavation 5
m
### 2-24f with 10 m lead and 7.5 m lift depth 1 Cum Labour 4.3 715.00 3074.50 T & P @3% of Labour Cost 92.24 3,166.74 475.01
of excavation: depth of excavation 6
m
### 2-24f+ with 10 m lead and 7.5 m lift depth 1 Cum Labour 4.5 715.00 3217.50 T & P @3% of Labour Cost 96.53 3,314.03 497.10
of excavation: depth of excavation 7
m
### 2-24f+ with 10 m lead and 9 m lift depth of 1 Cum Labour 4.7 715.00 3360.50 T & P @3% of Labour Cost 100.82 3,461.32 519.20
excavation: depth of excavation 8 m
### 2-24f+ with 10 m lead and 9 m lift depth of 1 Cum Labour 4.9 715.00 3503.50 T & P @3% of Labour Cost 105.11 3,608.61 541.29
excavation: depth of excavation 9 m
### 2-24f+ with 10 m lead and 10 m lift depth 1 Cum Labour 5.1 715.00 3646.50 T & P @3% of Labour Cost 109.40 3,755.90 563.39
of excavation: depth of excavation
10 m
Analysis of Labour & Material
Sub-Project : Construction of Aqueduct
Labour (A) Materials (B)
Analyzed Man Rate Amount Type of Unit Total Sub-Total Contract.
Sr. Norms Desciption of works for Category Days Rs. Rs. Materials Quantity Unit Rate Amount (A+B) O / head
No. No. used Rs. Rs. 15%
1 2 3 4 5 6 7 8 9 10 11 12
1x2 4x5 11*0.15
RA N 34
Description of item :Providing, laying and fixing of Geo-textile (filter fabrics), lead 30m
Unit: 1.00
Nor Resources
ms Specification
Labour (A) Materials (B) Equipment (C)
acti Clause
vity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate
24 2404 Unskilled md 0.017 715.00 14.96 Geotextile sq.m. 1.2000 421.00 505.20
Sub - total (A) 14.96 Sub - total (B) 505.20 Sub total (c)
Direct Cost (A+B+C) = NRs.
Contractor's Overhead @ 15 % of (A+B+C) = NRs.
Total Item Rate = NRs.
Say NRs. per sq.m. 598.00
Description of item Providing and laying Reinforcement including cutting, bending, binding, fixing in position and lead 30m. etc. all complete as per specification and drawing.
Diameter above 8mm and 16mm ii and iii average Unit: 1.00
Nor Resources
ms Specification
Labour (A) Materials (B) Equipment (C)
acti Clause
vity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate
Materials (B)
Total Amount
with O/H
without VAT
13
11+12
8.22
131.56
139.78
846.92
1,058.64
1,346.60
2,540.75
3,811.13
21,342.32
423.46
533.55
508.15
931.62
22,944.27
21,887.54
nalysis of Labour & Material
Materials (B)
Total Amount
with O/H
without VAT
13
11+12
22,210.24
13,809.20
7,437.11
6,507.97
5,347.16
11,284.81
22,714.81
21,185.38
23,441.46
nalysis of Labour & Material
Materials (B)
Total Amount
with O/H
without VAT
13
11+12
19,541.26
42,496.96
37,042.27
33,942.48
44,745.21
39,290.52
nalysis of Labour & Material
Materials (B)
Total Amount
with O/H
without VAT
13
11+12
39,508.09
45,579.23
45,483.09
46,305.34
nalysis of Labour & Material
Materials (B)
Total Amount
with O/H
without VAT
13
11+12
49,594.34
57,451.08
51,238.84
52,883.34
54,527.84
nalysis of Labour & Material
Materials (B)
Total Amount
with O/H
without VAT
13
11+12
56,172.34
145.06
1,341.66
610.54
439.17
763.07
1,068.17
1,858.94
nalysis of Labour & Material
Materials (B)
Total Amount
with O/H
without VAT
13
11+12
2,173.73
2,486.40
2,802.25
472.47
1,332.24
2,139.26
2,463.54
3,255.39
1,012.40
2,783.85
nalysis of Labour & Material
Materials (B)
Total Amount
with O/H
without VAT
13
11+12
1,119.34
1,427.60
2,221.54
2,539.49
2,855.34
3,088.96
1,318.22
1,527.61
nalysis of Labour & Material
Materials (B)
Total Amount
with O/H
without VAT
13
11+12
11,375.00
279,976.45
14,667.08
5,729.75
nalysis of Labour & Material
Materials (B)
Total Amount
with O/H
without VAT
13
11+12
10,124.12
126,926.16
957.38
3,224.11
1,211.51
3,032.70
1,815.34
2,887.90
3,040.76
2,155.99
nalysis of Labour & Material
Materials (B)
Total Amount
with O/H
without VAT
13
11+12
20,093.41
2,449.21
785.54
698.80
698.52
1,050.34
976.37
965.71
906.49
438.46
378.87
nalysis of Labour & Material
Materials (B)
Total Amount
with O/H
without VAT
13
11+12
204.79
340.12
83.31
234.88
159.18
4,658.66
6,678.56
3,184.49
3,230.01
4,182.09
nalysis of Labour & Material
Materials (B)
Total Amount
with O/H
without VAT
13
11+12
3.80
4.68
5.69
75.26
110.85
146.44
184.74
82.16
nalysis of Labour & Material
Materials (B)
Total Amount
with O/H
without VAT
13
11+12
112.99
154.07
205.38
256.70
313.19
225.98
282.47
nalysis of Labour & Material
Materials (B)
Total Amount
with O/H
without VAT
13
11+12
338.96
451.95
205.94
264.79
nalysis of Labour & Material
Materials (B)
Total Amount
with O/H
without VAT
13
11+12
368.63
460.15
554.85
744.66
2,134.95
nalysis of Labour & Material
Materials (B)
Total Amount
with O/H
without VAT
13
11+12
1,065.95
215.53
2,563.93
15,136.82
20,748.68
17,991.11
829.29
nalysis of Labour & Material
Materials (B)
Total Amount
with O/H
without VAT
13
11+12
12,507.06
2,972.68
3,048.90
3,133.60
3,218.29
3,557.05
3,641.75
3,811.13
3,980.52
4,149.90
4,319.29
nalysis of Labour & Material
Materials (B)
Total Amount
with O/H
without VAT
13
11+12
sq.m.
Resources
Equipment (C)
Amount
0.00
520.16
78.02
598.18
ton
Resources
Equipment (C)
Amount
0.00
18460.30
2769.05
21229.35
DIAMETER (d) = 3.50 m
SMALL CHAMBER DIAMETER (d) = 1.50 m CAPACITY =Type II
QUANTITY ESTIMATE
Page No. 1 of 3
Ref. No.: QNT-FER-SED-II Drawing No. G-09
S.N. Description No. Radius Length Breadth Height Quantity Unit Rate Amount
1 Site Clearance 1 8.1 8.1 0.71 23.29 m³ #REF! #REF!
(Q = ½ x 11.10 x 2.35 x 7) Assuming Slope = 5°
7 Plain Cement Concrete (1:1.5:3) for tank base 1.00 1.90 0.13 1.47 m³ #REF! #REF!
(Q = x r² x h, r = d/2+0.05+0.10 d = 4.0 m)
14 Bitumen paint on the buried surface of sedimentation tank 1.00 1.80 0.80 9.05 m² #REF! #REF!
(Q = 2 x x r x h, r = d/2+0.05, d = 4.0 m)
17 Polythene sheet 500 gauge for tank base 1.00 1.90 11.35 m² #REF! #REF!
(Q = x r², r = d/2+0.05+0.1, d = 4.0 m)
18 Formwork for ferrocement 1.00 1.75 1.25 13.75
- Wall portion (Q = 2 x x r x h, r = d/2, d = 4.0 m)
- Wall portion (small chamber) 1.00 0.75 1.05 4.95
(Q = 2 x x r x h, r = d/2, d = 2.0 m)
- Roof portion (Q = 4 x 2 x x R x h) (R = D² +4h²)/8h) 1.00 2.68 0.65 10.95
(D = d+0.05, h= d/5-0.05/2, d = 4.0 m)
- Dividing wall 1.00 0.95 1.05 1.00
- Deduction for manhole opening (Q = 4..r², r=0.30 m) 1.00 0.30 -0.28
30.37 m² #REF! #REF!
19 Reinforcement, including Chicken Wire Mesh,
MS Rods, GI Wire etc.
- Wall portion of sedimentation tank 1.00 1.78 1.25 13.99
(Q = 2 x x r x h, r = d/2+0.005/2, d = 4.0 m)
- Wall portion (small chamber) 1.00 0.78 1.00 4.90
(Q = 4 x 2 x x r x h, r = d/2+0.05/2, d = 2.0 m)
- Roof portion (Q = 4 x 2 x x R x h) (R = D² +4h²)/8h) 1.00 2.66 0.68 11.37
(D = d+0.05, h= d/5-0.05/2, d = 4.0 m)
- Dividing wall 1.00 0.95 1.05 1.00
- Deduction for manhole opening (Q=.r², r = 0.30 m) 1.00 0.30 -0.28
30.98 m² #REF! #REF!
20 Mesh wire fencing with masonry wall (Type A) 20.00 m #REF! #REF!
(Q = 2 x ((d + 3) + (d + 4.5)), d = 4.0 m)
21 Entrancce gate in barbed wire fencing (Type A) 1.00 1.00 No. 31411.15 31411.15
22 600 m circular metal manhole cver for ferrocement 2.00 2.00 Set 2640.72 5281.44
tank as per standard details
Sub total Amount #REF!
Vat 13% #REF!
Total Amount #REF!
Chandanpur Terai Madhes WSIPGadhawa-9, Dang
4 100 mm thick Sand filling in foundation 1 12.566 1.400 0.100 1.76 Cu.m. 20,093.41 35,364.40
c. Bracing beams
Bracing beam at 0m height 6 2.150 2.200 28.38
Bracing beam at 4m height 6 2.150 2.200 28.38
Bracing beam at 8m height 6 2.150 2.200 28.38
Bracing beam at 12m height 6 2.150 2.200 28.38
Bracing beam at 16m height 6 2.150 2.200 28.38
Total 141.90 Sq.m. 2,139.26 303,560.99
d. Tank from height from 20 to 26m
Bottom Circular Girder 1 PI()*7.0 - 2.200 48.38
Bottom spherical dome 1 Area = Pi()*(c2/4+h2) 39.79 h=1.45m, c=6.50m
Inclined Conical dome 1 PI()*9.85 - 3.300 102.12
Bottom Ring Beam 1 PI()*12.50 - 1.100 43.20
10 Reinfocement bar binding work for RCC work As per Bar Schedule 14947.77 Kg 145.06 2,168,323.52
f. Cement Punning of 3mm Thick Same As Cement Plaster 70.62 Sq.m. 378.87 26,755.80
h. Earth Work in Back Filling 50% of Excavation 15.23 Cu.m. 423.46 6,449.30
21 Fitting electric bulb and wiring at top of the dome 1.00 Set L/S 10000
23 Filling of soil in Over Head Tank Area 1 Area = 78.54 0.3 23.56 Cu.m. 423.46 9,976.72
4 100 mm thick Sand filling in foundation 1 9.425 1.000 0.100 0.94 Cu.m. #REF! #REF!
c. Bracing beams
Bracing beam at 0m height 6 2.150 2.200 28.38
Bracing beam at 4m height 6 2.150 2.200 28.38
Bracing beam at 8m height 6 2.150 2.200 28.38
Bracing beam at 12m height 0 2.150 2.200 0.00
Bracing beam at 16m height 0 2.150 2.200 0.00
Total 85.14 Sq.m. -
d. Tank from height from 20 to 26m
Bottom Circular Girder 1 PI()*7.0 - 2.200 48.38
Bottom spherical dome 1 Area = Pi()*(c2/4+h2) 39.79 h=1.45m, c=6.50m
Inclined Conical dome 1 PI()*9.85 - 3.300 102.12
Bottom Ring Beam 1 PI()*12.50 - 1.100 43.20
10 Reinfocement bar binding work for RCC work As per Bar Schedule 6054.71 Kg #REF! #REF!
13 Water proof cement paint Total area of outside plaster 1165.14 Sq.m. #REF! #REF!
b. stone Soling
In Drain 1 50.00 0.90 0.15 6.75
For Chamber 1 1.10 1.10 0.15 0.18
Total 6.93 Cu.m. #REF! #REF!
f. Cement Punning of 3mm Thick Same As Cement Plaster 70.83 Sq.m. #REF! #REF!
h. Earth Work in Back Filling 50% of Excavation 15.23 Cu.m. #REF! #REF!
21 Fitting electric bulb and wiring at top of the dome 1.00 Set L/S 10000
23 Filling of soil in Over Head Tank Area 1 Area = 78.54 0.3 23.56 Cu.m. #REF! #REF!
S.No. Description of items Unit Rate Quantity Amount unit weight Total weight
1 GI Pipe (Medium class) in pumping main -80mm dia. m 976.00 0 0 8.85 0.00
4 Butterfly Valve (80 mmØ)/(GM/Cast steel gate valve) no 14300 0 0 3 0.00
9 Nonreturn Valve(dual plate) 80 mmØ with flange set(swing type) set 14300 0 0 10 0.00
11 Pressure gauge( upto 250 m head) no 3000 1 3000 2 2.00
13 GI Blind flange set (150 mmØ) with 6-8 nut bolts set 5850 0 0 6 0.00
15 GI pipe 150 mmØ medium duty m 2782 0 0 2.25 0.00
20 GI Equal Tee (80 mmØ) no #REF! 0 #REF! 1.75 0.00
25 GI-GI flange set (80 mmØ) set 2352 0 0 2.5 0.00
30 GI bend 80 mmØ - 120° internal angle set 5590 0 0 2 0.00
35 GI Nipple (80 mmØ) - 6" long no 495 0 0 1.75 0.00
42 GI Reducer Socket (80x50 mmØ) 860 0 0 0.65 0.00
43 3 core flat PVC 10 mm sq submersible cable m 730 25 18250 0.00
23 Diesel Generator:
CI/DI Pipe(Both Side flanged joint) required for Vcs
Procurement and Installation of Sound proof 100kVA; 3 m 12600 0.00
150mm
Phase; 415/0.23 volts; 50 Hz and water cooled four stroke set 1477000 0.00
56
Diesel Generator set complete with control panel,
57 Installation
interconnections&ofJointing works
cable to MSB for Standby use all 0.00
57.1 complete.
Cutting of 125 mm dia.GI MC riser pipe into the required length &
job 2 0.00
Welding GI flange to both ends
57.2 Installation of Submerssible pump into the borehole all complete job 20000 1 20000.00
57.3 Testing Commissining of pump and panel board all complete job 10000 1 10000.00
57.4 100 mm double flanged CI/DI tail piece no 0 0 0.00
57.5 100 mm CI/DI all flanged Equal Tee no 0 0 0.00
57.6 100 mm CI/DI double flanged Non Return Valve no 0 0 0.00
57.7 100 mm CI/DI 90 degree double flanged bend no 0
57.8 125 mm CI/DI 90 degree double flanged bend no 0 #REF! #REF!
57.9 150 mm CI /DI 90 degree double flanged bend no 0 #REF! #REF!
58 200 mm CI /DI 90 degree double flanged bend no 0 #REF! #REF!
58.1 100 mm CI/DI all flanged equal tee no 0
13 of 98
Quantity/Cost Estimate
of
Electromechanical Materials
(Supply & Installation of pump and its accessories,RT outlet fittings,housing structure fittings)
14 of 98
Chandanpur Terai Madhes WSIPGadhawa-9, Dang