TỔNG CÔNG TY XÂY DỰNG SỐ 1 - CTCP

BAN ĐIỀU HÀNH DỰ ÁN CC1 - NGHI SƠN 2

Subcon Subcon.
No. Sub-con Location(Plot Plan) Remarks 1 Descriptions
Target Date Status

1 CC1 ESP unit 2 Closed Closed: Đã đóng hồ sơ - 2/49 ~ 4%

2 CC1 FDF (Forced Draft Fan) - A&B in Boiler 1 Closed

3 CC1 Boiler #1 4-May-20 Work done Missing ITP form no.1 Work done: Đã thi công xong - chưa đóng
hồ sơ - 25/49 ~ 51%

4 CC1 Pulverizer in Boiler 1 22-Apr-20 Work Done Missing ITP form no.1

5 CC1 PAF (Primary Air Fan) - A&B in Boiler 1 15-Apr-20 Work Done Missing ITP form no.1

6 CC1 Blowdown Pit in Boiler 1 15-Apr-20 Work done Missing ITP form no.1

7 CC1 Boiler #2 18-May-20 Work Done Missing ITP form no.1

8 CC1 Pulverizer in Boiler 2 18-May-20 Work Done Missing ITP form no.1

9 CC1 FDF (Forced Draft Fan) - A&B in Boiler 2 11-May-20 Work done Missing ITP form no.1

10 CC1 PAF (Primary Air Fan) - A&B in Boiler 2 11-May-20 Work Done Missing ITP form no.1

11 CC1 Blowdown Pit in Boiler 2 11-May-20 Work Done Missing ITP form no.1

12 CC1 ESP unit 1 22-Apr-20 Work Done Missing ITP form no.1

13 CC1 Duct Support unit 1 (ESP 1 ~ FGD 1) 25-May-20 Work Done Missing ITP form no.1

14 CC1 Duct Support unit 2 (ESP 2 ~ FGD 2) 25-May-20 Work Done Missing ITP form no.1

15 CC1 ID Fan unit 1 15-Apr-20 Work done Missing ITP form no.1
Subcon Subcon.
No. Sub-con Location(Plot Plan) Target Date Status Remarks 1 Descriptions

16 CC1 ID Fan unit 2 11-May-20 Work done Missing ITP form no.1

17 CC1 Plant and Fire Water Storage Tank A & B 25-Mar-20 Work done Missing ITP form no.1

18 CC1 Demi. Water Storage Tank A & B 25-Mar-20 Work done Missing ITP form no.1

19 CC1 LDO Storage Tank A & B 8-Apr-20 Work done Missing ITP form no.1 - Test report

20 CC1 Portable Water Storage Tank 1-Apr-20 Work done Missing ITP form no.1 - Test report

21 CC1 Pressurized Service Water Tank 1-Apr-20 Work done Missing ITP form no.1 - Test report

22 CC1 LDO Truck Unloading Station 8-Jun-20 Work Done Not submitted yet

23 CC1 Water Treatment Building 15-Jul-20 Work done Not submitted yet

24 CC1 Pretreatment Area Pump Shelter 8-Jun-20 Work done Not submitted yet

Waste Water Treatment Plant (Cake Hopper) - Concrete


25 CC1 15-Jun-20 Work Done Not submitted yet
work

26 CC1 Fire Fighting Pump House - Concrete work 30-May-20 Work Done Not submitted yet

27 CC1 Coal Electrical BLGD (South of Coal Area) 22-Jun-20 Work Done Not submitted yet

28 CC1 Ash Pipe Rack unit 1 Open Open: Chưa thi công xong - 22/49 ~ 45%

29 CC1 Ash Pipe Rack unit 2 Open

30 CC1 Duct Support unit 1 (Boiler 1 ~ ESP 1) Open

31 CC1 Duct Support unit 2 (Boiler 2 ~ ESP 2) Open

32 CC1 Foam Station Open

33 CC1 Water Treatment Building - Finishing work Open


Subcon Subcon.
No. Sub-con Location(Plot Plan) Target Date Status Remarks 1 Descriptions

34 CC1 Waste Water Treatment Plant Open

Waste Water Treatment Plant (Cake Hopper) - Finishing


35 CC1 work Open

36 CC1 Waste Water Treatment Plant (Tank Shelter) Open

37 CC1 Waste Water Treatment Plant (Tank Shelter) - Finishing Open


work

38 CC1 Fire Fighting Pump House - Finishing work Open

39 CC1 Clarified Water Holding Reservior Open

40 CC1 Coal Electrical BLGD (South of Coal Area) - Finishing work Open

41 CC1 CHS Electrical building Open

42 CC1 CHS Electrical building - Finhishin g work Open

43 CC1 Ammonia Storage Shelter Open

44 CC1 Bottom Ash Silo unit 1 Open

45 CC1 Bottom Ash Silo unit 2 Open

Oily & Waste Water Drainage


46 CC1 (NS2-XB02-P0UZT-165806) Open

Sanitary Waste Water


47 CC1 Open
[Sewage Sump (SP-01) + Septic Tank (ST-01)]

48 CC1 Electrical Duct Bank Open

49 CC1 Fly Ash Transfer Compressor Shelter Open


Pile Head
No Work Done Area Subcon. Pile work Treatment work

1 Boiler Unit 1 CC1

2 Boiler Unit 2 CC1

3 Admin. & Canteen Building BD234

4 ESP (except Paving) CC1

5 Dmei. Water Storage Tank A&B CC1

6 Plant & Fire Water Storage Tank A&B CC1

7 Ash Pipe Rack Foundation CC1

8 ID Fan Foundation unit 1 CC1

9 ID Fan Foundation unit 2 CC1

10 Duct Support Foundation Unit 2 CC1

11 Gas Gas Heater Foundation unit 1 BD234

12 Gas Gas Heater Foundation unit 2 BD234

13 Absorber Foundation unit 1 BD234

14 Absorber Foundation unit 2 BD234

15 Emer. Storage Tank BD234

16 Bridge No.1 CC1

17 Bridge No.5 CC1

18 IPB Foundation unit 1 BD234

19 IPB Foundation unit 2 BD234


MAR로 대체

Waterproofing Excavation & Filling in Tank


Concrete work Repair work work Backfilling work Foundation work
Legend
Open Document & Site work are in progress
Closed Document & Site work are completed
Work Done Site work are completed
N/A Not applicable.