Professional Documents
Culture Documents
INTRODUCTION
Deterioration and collapse of highway bridges has been a crucial problem across the
globe. Statistics from National Bridge Inspection Program in the US unfolded that
41% bridges in states are structurally inadequate and dangerous to use, and after
every two days a bridge sags, buckles or collapse (FHWA proposes Certification of
Bridge inspector, National Society of Professional Engineers, 1987). Inadequate sign
boards, poor alignment and approaches annually kill 1000 American (White et al.,
1992). To resolve this problem, National Bridge Inspection program in the US
developed a bridge rating and inspection system to maintain existing bridges and to
optimize their remaining service life. (White et al., 1992)
1
grim that not even a single highway authority has developed inspection manuals or
acquired bridge inspection equipment.
Fig. 1.1 highlights the poor maintenance practices across the country. The expansion
joint has been worn out with the passage of time, and in the absence of any
scheduled maintenance, the deck slab at the edges of joint deteriorated and locally
repaired several times. To avoid any mishap bricks have been inserted in the joint,
which is an improper way of maintenance.
Fig. 1.2 shows false construction practices in Pakistan. An under construction slab
bridge in Gujranwala city presenting inadequate provision of cover and improper
concrete mix (honey combed concrete). With the passage of time in the presence of
environmental agents, reinforcement will starts corroding and oxiding.
The recently constructed BRTS (Bus Rapid Transit System) Bridge has also started
deteriorating showing signs of improper construction practices. Within few months
after the inaugural, wearing surface has developed pot holes, drain pipes started
choking or leaking as shown in Fig. 1.3, emphasizing the need of bridge rating and
management system in Pakistan.
2
Improper
Drainage
(a) (b)
Figure 1.3: Condition of recently constructed BRTS Bridge, a) Pot Holes in wearing
surface, (b) Drain Leaking/Choking
1.3 OBJECTIVES
Scope of this research work was to carry out condition and load rating of following
two bridges:
“Mian Meer Bridge over railway track near Fortress Stadium, Lahore Cantt”
“Sherpao Bridge over railway Track near Lahore Cantt Station.”
There are five chapters in this thesis consisting of the following information.
3
Chapter 1 includes introduction of the research work, objectives, scope of work
and thesis organization.
Chapter 3 describes the details of field work and in depth inspection procedures,
sample formats for condition evaluation of bridge components.
Chapter 4 includes load analysis and ratings of both bridges. It also explains the
development of a new analytical tool “Bridge Performance Index” (BPI).
4
2. LITERATURE REVIEW
Bridge condition evaluation and rating system was mainly started in 1967, when
Silver Bridge (Suspension bridge) on Ohio River failed and collapsed in West
Virginia, USA with loss of 46 lives. The incident set a record of twentieth century
causalities in a bridge collapse. As a result National Bridge Inspection Program was
started to pinpoint a bridge network, abolish potential hazards in it, and also to
address present and future needs (Wiley Structure Condition Assessment, 2010). It also
acknowledged the demand for recurrent & uniform bridge inspection program
(Texas DOT 2002).The first AASHTO inspection manual was issued in 1970, modified
in 1974, which provides the minimum information requisite for recording, rating and
assessing load capacity of bridges (Texas DOT 2002).
5
2.2 BRIDGE RATING AND MANAGEMENT SYSTEMS
There are well established electronic bridge management systems in the world. With
the development of such system, a bridge manager can remain informed about the
maintenance and health of a bridge at all the times. A manager can take better
decisions and control of bridge structures.
Following are the basic stages in the life of a bridge (Ryall., 2001)
Concept
Analysis
Design
Construction
Service
Collapse
The most widely used Bridge management system in UK developed by High Point
Rendel(HPR) is called Highway Structures Management Information System
HiSMIS (Ryall.2001). Basic modules have been shown in Fig. 2.2. It is a very
comprehensive and user friendly system, it have adequate data storage capacity. Its
scope is not only limited to bridges, but is applicable to tunnels, culverts, etc. Actual
database is composed of 05 modules for INPUT; OUTPUT is dependent on the
enquiry and information of 06 modules.
HISMIS
Bridge record
cards
2.4.2 USA
PONTIS is the primary BMS system adopted by various states in USA. It is very
good in transforming engineering decisions into meaningful and beneficial
maintenance costs. Bridge inspectors have 120 basic bridge elements to which they
7
assign condition state (Ryall.2001). After condition rating, deterioration models are
developed. It can also be used to calculate expected annual cost of a bridge
compared to alternative bridges designs for new crossings. In the end full life cycle
cost can be estimated which helps in choosing the final decision.
2.5 INSEPCTION
Following are the five types of inspection which permit a bridge owner to establish
an inspection type even and consistent with the structure. (White et al. 1992)
I. Inventory Inspection
This is very first inspection of a bridge, which becomes a record in the bridge
file. It helps in adaptation and alteration of a bridge later on.
8
independently scheduled or it may follow up for damage or inventory
inspection.
V. Special Inspection
Special inspection is scheduled at the choice of a bridge owner. It is used to
monitor some particular deficiencies in a bridge element.
2.5.2 Inspection Frequency
A team usually comprises of 5 to 6 personnel are required for this research work.
Team lead should be an experienced (ten years) bridge engineer and he should be
present all the time during inspection of a bridge. Rest of the team members should
have undertaken the training of bridge inspectors.
2.5.3.2 Safety
Safety of both public and inspection team is to be ensured by inspection plans. All
the tools, equipments and operations should be planned keeping in view the safety
concerns and local codes.
9
Bridge inspection is a special task which requires more advanced machinery and
skilled labor as shown in Fig. 2.3. It is dilemma of this nation that none of the
Highway Authorities have bridge inspection equipment in Pakistan. Cherry Picker is
a movable single arm truck mounted inspection platform used worldwide. Snooper
type truck mounted platform which allows inspecting Bridge from existing
infrastructure. This costs about Rs.70.00 million
2.6.1 General
Each department or bridge owner should develop and maintain an up-to-date and
precise record of bridges under its administration. Condition evaluation forms
should be prepared keeping in view the requirements of the location and type of
bridge.
Bridge record should contain as-built drawings showing the condition of bridge
with signature of team lead that has been responsible for recording the as-built
condition of bridge.
2.6.3 Specifications
10
Technical specification and designation under which the bridge was constructed
should be a part of bridge documentation and file record. The published version of
some general technical specification should also be mentioned with date and
signature of authority.
2.6.4 Correspondence
2.6.5 Photographs
At least two photographs one plan and one elevation of the bridge are to be included
in the file record. However the defects and deficiencies in the bridge should also be
endorsed with the related photographs.
Maintenance and repair history since the initial construction of the bridge should be
included in details with date and description.
Record of the most significant single trip permit along with calculations should be
included in bridge file. A summary of posting actions taken with signage used
should also be included.
The history of a vehicle using the bridge with its variation over a year should be
available .ADT is an important parameter to assess the traffic on the bridge.
11
Structures over waterways should include history of major floods, with water marks,
scour depth and other critical features.
The criterion governing the rating to be assigned is “how well the element is
fulfilling its intended function”. In general, it can be said that conditional rating is
actually comparing the component with itself when it was new. FHWA condition
rating will be used.
Good: A rating of “good” corresponds to the FHWA rating of (7, 8, 9), that is the
element is free from section lost, spalling and it is as it was designed.
12
Fair: A rating of “fair” corresponds to the FHWA rating of (5, 6), that is the element
is at worst condition show minor section loss, cracking, but is not structurally
dangerous.
Poor: A rating of “poor” corresponds to the FHWA rating of (3, 4), that is the
element is seriously affected and it is no more structurally sound. This condition
show local failure.
Critical: A rating of “critical” corresponds to the FHWA rating of (0, 1), that is the
element is seriously deteriorated and it cannot perform its intended function & is
dangerous to use in future.
To ensure safety and adequacy of structures, analytical techniques along with field
inspections are required (AASHTO 1972). In order to evaluate a bridge regarding its
structural adequacy, capacity/load rating of bridges is required to be done at two
levels (White et al. 1992). For this purpose structural & construction drawings of the
bridge are required. Load rating in current research was carried out by allowable
stress method/design (ASD), because both these bridges were designed on using
ASD.
13
a) Inventory Rating Level:
The lower load level rating is called inventory rating. It corresponds to customary
design level of stresses but reflects the existing bridge and material conditions with
regards to deterioration and loss of section. It indicates the load level which a
structure can safely utilize for an indefinite period of time. (AASHTO 2000, White et
al. 1992)
The upper load level rating is called operating rating. It will result in absolute
maximum load permissible to which the structure may be subjected. The operating
rating may be considered as the maximum load that should be allowed on a bridge
under any circumstances. Allowing unlimited number of vehicles to use the bridge
at operating level may shorten the life of the bridge. (AASHTO 2000, White et al.
1992)
Eq 2.1
Eq 2.2
Where,
RF = Rating factor
RT = Rating of bridge member in Tons
C = Capacity of member
D = Deal load effect
L = Live load effect
A1 = Factor for dead load
14
A2 = Factor for live load
W = Live load on member
I = Impact Factor
Rating of a bridge will be controlled by the member with lowest rating level
(AASHTO 2000). Since the entire old highway bridges were designed on allowable
stress method, therefore main focus of this study will be on allowable stress method.
15
. CONDITAT
3. CONDITION RATINGS
Rating of Mian Meer bridge and Sherpao bridge near Lahore Cantonment has been
undertaken in this research work. The objective was to explore the rate and level of
deteriorations in both these bridges which have consumed half of their service lives.
Both of these bridges were designed and constructed by Punjab Highway
Department to reduce the traffic jams at the railway crossings in Lahore
Cantonment.
The first step was to have reconnaissance survey of the bridge, taking the crew and
verifying the dimensions of the bridge in full length and across its width as shown in
Fig. 3.5. Rating a bridge is primarily dependent on the accuracy of its physical
record, that’s why dimensional verification is a very important step. The tender
drawings of Mian Meer Bridge available in Punjab Highway Department record are
50% different from the structure on ground; it may be due to the practice of more
than one proposal of a bridge at that time and later on construction drawings would
be of final proposal. The most important aspect of bridge rating is to optimize the
service life of the bridge, and it cannot be achieved without knowing the actual
condition and requirements of a bridge.
3.2 INVENTORY
Table 3.1 and 3.2 present the Inventory record of both the bridges:
16
Table 3.1: Mian Meer Bridge Inventory
TECHNICAL DATA
Type Of Bridge Slab on Girder Bridge
No of Spans 59 Each Carriageway
Materials Used RCC primary members 8 No RCC T-Girders 36”
deep
Type Of Piers Rectangular piers 3 ft X 2ft
Type Of Pier Cap Non-Prismatic 3.5 ft X 2ft
Type of Railing RCC Railing 4’-2” high
Type of Wearing Surface Asphalt Concrete
Type of Expansion Joints Concealed
Type of Bearings Concealed
Drain Open Drains
GEOMETRIC DATA
Metalled Width 28 ft
Max / -Min Span 95’ / 15’
Overall Length 1972 ft
Vertical Clearance 22 ft
Approach Roadway Width 28 ft
Bridge Width(Kerb to Kerb) 35’-3”
Bridge sidewalk width 5 ft
Vertical Kerb Height 5”
Bridge Median Width 2’-3”
Bridge Curved Y/N N
Skew Angle 38.25 Degree
17
Figure 3.1: Mian Meer Bridge over Railway Track on Mall Road, Lahore Cantt
Figure 3.2: Another view of Mian Meer Bridge over Railway Track on Mall Road,
Lahore Cantt
18
Table 3.2: Sherpao Bridge Inventory
TECHNICAL DATA
Type Of Bridge Arch Bridge Slab on Girder Bridge
No of Spans 85 33
Materials Used Brick Masonry Prestressed Girders
Type Of Piers Solid Wall/Piers Rectangular Piers
Type Of Pier Cap Spandrel Beam Non-Prismatic
Type of Railing Pipe railing/Guard rail Pipe railing/Guard rail
Type of Wearing Surface Asphalt Concrete
Type of Expansion Joints Not required Concealed
Type of Bearings Not requierd Steel + Elastomeric
Drain Open Drains
GEOMETRIC DATA
Metalled Width 27.25 ft
Max / Min Span 98’ / 23.25’
Overall Length 3000 ft
Vertical Clearance 22 ft
Approach Roadway Width 28 ft
Bridge Width(Kerb to Kerb) 36 ft 23’-6”
Bridge sidewalk width No
Vertical Kerb Height N/A
Bridge Median Width NO
Bridge Curved Y/N Yes Sharp Curvature Radius 597 ft
Skew Angle 36 Degree
19
Fig 3.3: Sherpao Bridge over Railway Track on Jail Road, Lahore Cantt
20
(a) (b)
Figure 3.5: Dimensional Verification of bridges, a)- Mian Meer Bridge, b) Sherpao
Bridge
3.3 CONSTRAINTS
In the absence of any integrated bridge management system, it was very difficult to
coordinate with various public or private agencies to collect data and gather
information required for rating of a bridge. Situation becomes worse when one
needs to gather information, collect drawings and other data for 40 years old bridge.
It has also been realized that some officers may have the record but they hesitate in
providing for a research work. The attitude may be due to lack of trust amongst
engineering community in Pakistan. First 04 months were consumed in arrangement
of necessary documents to kick off the research work. Non-Professional attitude of
officers and staff is another common cause of delaying milestones in Pakistan.
Fig.3.4 show that in the absence of proper equipment required for inspection of
bridges, ordinary ladders can be helpful for bridge inspection and monitoring.
Following are some of the major constraints that were being faced in completing this
research task.
21
Obtaining no objection certificate from Chief Engineer District Government,
Lahore, for undertaking this research work.
Accidents record collection from District Emergency office and Control Room
in-charge of Rescue 1122.
(a) (b)
Figure 3.6: Field work: a) Ladder is being tied for field work; b) crew is setting up
22ft ladder for inspecting Girders of Sherpao bridge
22
3.4 AS-BUILT DRAWINGS
In the absence of any as built drawings, very next step after dimensional verification
is to prepare as built Plan, cross sections and elevation of the bridges. At present, no
highway authority practices to prepare as built drawings of bridges and keep them
in record. Fig. 3.7 and Fig. 3.8 present the As-built cross section of Mian Meer and
Sherpao bridge respectively.
Field visits in Pakistan seldom utilize the literature and pre-visit desk work for
inspection of a bridge. Ultimately the purpose of a visit is not accomplished and the
outcomes have errors and omissions. In order to visualize and assess a bridge it is
prerequisite to go through the literature and available standard manuals, develop a
strategy of inspection, and find out the causes of deterioration or problems in a
bridge component.
Wearing Surface
Expansion Joints
Drainage System
Diaphragms
Deck Slabs
Bearing System
Pier Caps
Pierss
Abutments
Sidewalk
Table 3.3 presents a sample performa for inspecting wearing surface. Ther
performas for other members are presented in the appendix.
24
Table 3.3: CONDITION EVALUATION PERFORMA FOR WEARING SURFACE
(WS):
Physical
Condition
Concrete
Overlays?
Map Cracking Due to Excessive deflection,
drying of asphalt
Edge Cracks Longitudinal Cracks near the
edge, due to lack of lateral
support, drying of asphalt
Lane joint Longitudinal Separation
cracks between Paving lanes
Reflection No set Pattern, Cracks in
Cracks underlying concrete slab
Slippage Lack of Bond b/w slab and
cracks asphalt overlay
Channelized Lateral Movement of Surface
(ruts) under traffic
Depressions Settlement of Concrete Deck
Potholes Bowl shaped holes of various
sizes, localized disintegration
of asphalt
Raveling Separation of Particles, due to
low asphalt content and poor
construction
Condition Rating:
Condition of various bridge components has been assessed and rated out of 9.Then
the average condition has been calculated based on the results of the entire spans.
25
For this purpose, the work was carried out from the top most bridge component
(railing) to the bottom one (piers).
Mian Meer Bridge comprises of 4’-2” RCC railing as shown in Fig. 3.9. The thickness
of the railing is 7”, however in each span, there are three posts, one in the mid and
two at the ends. The thickness of the railing at post is 10”. Railing in most of the
spans is in very good condition. Its soundness was checked with hammer.
Aesthetically railing look appealing due to the application of Graffiti. Highest
condition rating amongst all the spans is 8, and lowest is 6. However the average
condition rating (ACR) is found out to be 7 which mean railing is in good condition.
Following is the extent of deterioration:
ACR = 7
26
3.6.1.2 Sher-Pao Bridge
Sher-Pao Bridge comprises of 3’-0” high New Jersy (NJ) barrier. The thickness of the
barrier is 7” and the width at the base is 1’-4”.Pipe railing/guard rail has been
affixed over it with height of 2’-0”as shown in Fig. 3.10.
%age Deterioration = 3%
ACR = 7
27
3.6.2.1 Mian Meer Bridge:
Mian Meer Bridge has a 5’-0” wide sidewalk. Tuff tiles have been used on the
sidewalk, however in majority of spans the level of the tuff pavers is uneven causing
tension in the tiles, that’s why cracks were observed in the tiles as shown in Fig. 3.11.
Due to unevenness, water has been stagnating causing efflorescence in tiles. Average
condition rating is 6. Following is the extent of deterioration:
ACR = 6
28
3.6.2.2 Sher-Pao Bridge:
There is no sidewalk in Sher-Pao Bridge. Previously the old arch bridge had 4’ wide
sidewalks on either side, however after re-modeling and widening of the bridge,
sidewalks have been omitted.
Wearing Surface of the bridge is in very good condition, seems to be recently laid. It
has also been observed that more than 02 times wearing surface has been laid on the
bridge. Because the vertical face of the curb which should be 11”is now only 5” at the
site. It shows that the older carpet was not scarped and new surface was laid. There
are no potholes, no raveling or patching of the surface as shown in Fig. 3.12. Average
condition rating is 8. Following is the extent of deterioration:
Deterioration = Negligible
ACR = 8
29
3.6.3.2 Sher-Pao Bridge
Wearing Surface of the bridge is also in very good condition, seems to be recently
laid. However at the interface of the old arch structure and widened portion a
longitudinal crack spanning the entire bridge length was observed as shown in Fig.
3.13. Bridge has worn out expansion joints which cause noise when the traffic passes
over them. There are no potholes, no raveling or patching of the surface. Average
condition rating is 8.Following is the extent of deterioration:
Deterioration = Negligible
ACR = 8
3.6.4 Condition Rating of Expansion Joint (E.J):
Mian Meer Bridge has concealed or buried type of expansion joints which are mostly
employed for short spans bridge as shown in Fig. 3.14. Due to poor maintenance
most of the joints have been worn out with the passage of time. Water has been
30
penetrating through them to the structural components beneath. Average condition
rating of Expansion joints is 6.Following is the extent of deterioration:
(a) (b)
Figure 3.14: Expansion Joint Mian Meer Bridge a)- Concealed Exp. Joint, b)-Water
peneteration from expansion joint
ACR = 6
Carriageway from Lahore cantt to City is an arch bridge which does not have any
expansion joint except in railway spans, and provides a very smooth surface to the
commuters. Carriageway from city to Cantt has expansion joints as shown in Fig.
3.15 that have been worn out severely only in 14 years. Almost 4” deep deterioration
was observed in the joint space. Water has been penetrating into the structure.
Average condition rating is 5. Following is the extent of deterioration:
Total Joints = 35
% Deterioration = 20 (55 %)
31
(a) (b)
Figure 3.15: Expansion Joint SherPao Bridge, a)-Worn out expansion joint , b)- Water
penetration from expansion joint
ACR= 5
Mian Meer Bridge has 2” diameter drain pipes as shown in Fig. 3.16. It was observed
that the poor maintenance of the bridge has lead to clogging of drain pipes.
Additional wearing surfaces have also blocked some of the drains. One of the most
critical causes of efflorescence in the structure is due to full or partial clogging of
drain pipes. Following is the extent of deterioration:
Deteriorated = 60
ACR = 5 32
3.6.5.2 Sher-Pao Bridge
Drainage condition in case of Sher-pao Bridge is no more different from Mian Meer
Bridge. Water remains stagnant on sharp curvature on carriageway from cantt to city
due to clogging of drain pipes as shown in Fig. 3.17. Old arch spans are severely
damp due to improper drainage created after remodeling of the bridge as shown in
Fig. 3.17. The condition is worse in arch rings near railway spans. Establishment of
Parking lots by private companies is also creating a hazardous situation. The water
coming down from drain pipes remains stagnant in parking lots. It can harm the
shallow footing of old arch bridge. Following is the extent of deterioration:
(a) (b)
ACR = 6
33
3.6.6 Condition Rating of Deck Slab (DS)
Deck slab is in good condition, except the edges of the slab near the expansion joints,
which have been damped, and deteriorated as shown in Fig. 3.18. It is due to water
penetration from the joint causing efflorescence and delamination of concrete
adjacent to the expansion joint. Span 6 of carriageway from Cantt to City is the most
critical portion. Oxidation of reinforcement has started near edges. When an edge
was hammered, concrete spalled off showing rust marks of steel and showing that
the bond between reinforcement and concrete has already been lost.
(a) (b)
(c)
Figure 3.18 Condition Rating Deck Slab Mian Meer Bridge, a)-Deteriorated Edge of
deck slab near expansion joint, b)-unsound concrete when hammered spalled off, c)-
Oxidation marks on the broken part of slab
ACR = 6
34
3.6.6.2 Sher-Pao Bridge:
The condition of Deck slab is better compared to Mian Meer Bridge. Light to
moderate dampness was observed in some spans as shown in Fig. 3.19. Average
condition rating is 7. Following is the extent of deterioration:
Primary member of Mian Meer Bridge are in very good condition as shown in Fig.
3.20 (a). Each carriageway is composed of 8 no RCC T-Girders which are in good
condition. Concrete quality is good as well as no structural cracks encountered. ACR
is 7. Main railway span is of pre-stressed post-tensioned girders as shown in Fig.3.19
(b). Fressynet system of stressing was used in design as verified by visual hands on
inspection of the end zone of the exterior girder. Exterior girder of carriageway from
city to cantt shows the cover to the pre-stressing wires at the end has not been
35
provided. Although girders are in good condition, yet it is expected that, pre-
stressing wires may get corroded with time. ACR of Pre-stress Girders is 7.
(a) (b)
Figure 3.20: Condition Rating of Mian Meer Bridge, a)-RCC Girders, b) - Prestress
Girders
ACR = 7
3.6.7.2 Sher-Pao Bridge:
Primary member of Sherpao Bridge are in very good condition as shown in Fig. 3.21.
Each carriageway is composed of 3 no post-tensioned girders on widened portion of
carriageway from city to cantt. Main railway span is of pre-stressed girders; however
side spans are RCC T-Girders which are in good condition. Concrete quality is good
as well as no structural cracks encountered. Average condition rating is 7.
(a)
(a) (b)
Figure 3.21: Condition Rating of Girders SherPao Bridge, a)- Prestress ,b)- RCC
ACR = 7
36
3.6.8 Condition Rating of Diaphragms:
Mian Meer Bridge has typical 35’-0” RCC T-Girders. Each deck has 03 no of RCC
diaphragms, one at the mid and two at the ends. The diaphragms are in good
condition, however light to moderate efflorescence and delamination was found out
in end diaphragms due to percolation of water from expansion joints as shown in
Fig. 3.22. ACR of diaphragms is 6. Main railway span is composed of composite
section; there are 05 no of RCC diaphragms in skew direction for supporting the
deck. Diaphragms are in good condition. ACR is 7.
(a) (b)
Figure 3.22: Condition Rating of Diaphragms Mian Meer Bridge, a)- End diaphragm,
b)- Closer View of dampness in diaphragms
ACR = 6
Carriageway from city to cantt is comprises of widened portion of the bridge, except
04 feet wide part from arch bridge. Widened portion has 71’-3” typical pre-stressed
spans, each spans has 03 no of diaphragms with one at mid and two at ends as
shown in Fig. 3.23. All the diaphragms are RCC. Diaphragms are in good condition.
Average condition rating is 7.
37
(a) (b)
Bearing system is one of the most critical components of Mian Meer Bridge. Most of
the bearings have been jammed particularly on carriageway from cantt to city. Due
to jamming of bearing, the stresses have been transferred to pier cap as shown in Fig.
3.24. ACR is 5. Following is the extent of deterioration
(a) (b)
Figure 3.24: Condition Rating of Bearings Mian Meer Bridge, a) End girder
bearing jammed, b) - Multi-girder bearings jammed
38
ACR = 5
3.6.9.2 Sher-Pao Bridge:
Bearing system of Sher-pao bridge is working better compared to Mian Meer bridge.
Arch bridge does not require any bearing system. For RCC spans, steel plate bearing
system was installed which shows slight rusting of plate in some spans. Wooden
wedges used to launch a girder have not been removed in some spans.For Pre-stress
girders, Elastomeric neoprene bearing 2” thick were incorporated for pre-stressed
girders as shown in Fig. 3.25.
Bearings are performing well, however some cracks were observed underneath
girder no 4 from exterior side in railway span of carriageway from city to cantt.
Average condition rating is 7.
(a) (b)
Figure 3.25: Condition Rating of Bearings SherPao Bridge, a)- Steel Bearing, b)-
Elastomeric
ACR = 7
Old arch bridge is a masonry structure with 23’-9” typical spans. Arch ring has been
in good condition despite lapse of 40 years life. Collision scratch marks were
observed in spans where provision of u-turns for movement of traffic is provided.
Some of the arch spans have been severely damp as shown in Fig. 3.26. Average
condition rating is 7.
39
Figure 3.26: Severe dampness in arch ring SherPao Bridge
ACR = 7
(a) (b)
Figure 3.27: Condition Rating of Arch spans SherPao Bridge, a) - Spandrel Beam,
b) - another of spandrel beam showing rusting of bars within the concrete
ACR = 6
40
3.6.11 Condition Rating of Piers:
3.6.11.1 Mian Meer Bridge:
Each carriageway of Mian Meer bridge has been supported on rectangular piers of 3’
x 2’. Piers are in very good condition. Except light to moderate scaling was observed
in railway side spans as shown in Fig. 3.28. It may be due to weathering action,
water remain stagnant and then evaporates. It leads to separation of mortar from the
mix. It may be given top priority in maintenance plan. Rest of the piers is in very
good condition. Average condition rating is 7. Following is the extent of
deterioration:
Total Area inspected= 2160 sft
Deteriorated = 54 sft (2.5%)
ACR = 7
3.6.12 Sher-Pao Bridge:
3.6.12.1 RCC Piers:
Widened portion of the bridge comprises of square pier of 5 ft x 5 ft and in very
good condition as shown in Fig. 3.29. Railway spans and side spans in both
carriageways have Square piers of 2ftx 2ft size. Each carriageway of old structure is
supported on 04 rectangular piers in railway spans. Widened portion of railway
span is supported on 03 no of rectangular piers. Piers are in very good condition. No
mortar loss or structural crack was observed in the inspection of piers that’s why
Average condition rating is 8.
41
Figure 3.29: Condition Rating of Piers Widened portion SherPao Bridge
ACR = 8
-
(a) (b)
Figure 3.30: Condition Rating of Brick Piers & Abutments SherPao Bridge, a)- Brick
Pier and abutment, b)- closer view of abutment
42
3.6.13 Condition Rating of Retaining walls:
3.6.13.1 Mian Meer Bridge.
Initial spans of this bridge has been started just at the NSL, that’s why the retaining
walls are not required. Masonry wall has been constructed on both ends but it does
not suits to be considered as retaining wall as shown in Fig. 3.31. Because structure
beneath is visible from broken area of brick wall. These walls have been constructed
to protect the structure from debris of nearby locality like Basti Syedan Shah as well
as from direct collision of any vehicle into the structure.
Figure 3.31: Temporary Brick wall constructed in end Spans of Mian Meer Bridge
43
(a) (b)
Figure 3.32: Condition Rating of RCC Retaining wall SherPao Bridge, a) - City
Side, b)- Cannt side
ACR = 7
3.6.13.2.2 Masonry retaining wall:
Old Arch Bridge has brick masonry retaining walls. Mortar has been lost at some
places as well as it has some collision marks as shown in Fig. 3.33. Maintenance of
masonry wall should be given priority level in developing maintenance plan of this
bridge. Average condition rating is 6. Following is the extent of deterioration:
Total Length = 772 ft
(a) (b)
Figure 3.33: Condition Rating of Brick Masonry Retaining Wall SherPao Bridge, a) -
Mortar loss, b)- Another view of Masonry wall
ACR = 6 44
3.7 Cumulative Deterioration Trends
Based on the condition rating of different bridge components, following graph has
been developed which shows cumulative deterioration trend in both these bridges.
Expansion Joint, drainage, deck Slab, diaphragm, bearings, masonry abutment, and
arch ring are more vulnerable to deterioration compared to other bridge components
as shown in Fig. 3.34. It also underlines that the expansion joint and drainage system
are directly affecting the condition of five other bridge components likewise deck
slab, diaphragm, pier cap, and arch ring as highlighted with circle.
45
4. LOAD RATINGS & BRIDGE PERFORMANCE INDEX
4. LOAD RATINGS AND BRIDGE
PERFORMANCE INDEX
Load ratings have already been defined in the definitions. Primary purpose of this
rating is to ensure structural safety for load actually plying on a bridge (AASHTO
2000). It requires engineering judgment in determining a level of rating that is
important to maintain safe utilization of a bridge, and then to decide posting and
weight limitations and permit decisions to vehicles. Load rating of a Girder should not
be less than 3 Tons in any Case. Otherwise the bridge should be closed. (AASHTO 2000).
Bridge load ratings are dependent on the information provided in a bridge file
record, which in turn utilizes the outcomes of a recent bridge inspection.
4.1.1 Legal Loads:
Following are practical truck manufactures in United States as shown in Fig.4.1. It
has been conceptual to utilize a structure for practical load utilizing it, rather than
hypothetical design loads (AASHTO 2000, White.et.al 1992). In Pakistan there is no
standard dimensions of trucks, that is why the analysis in load ratings have been
done based on legal loads of states and standard design loads of Pakistan West Code
of Practice for Highway Bridges 1967.
West code of practice for Highway Bridges 1967 is the standard reference document
used for design of bridges in Pakistan. Bridges under study were also designed as
per the above standard document. It is important to analyze the bridge based on
actual dimension on standard loadings. There three main types of loadings:
Class A loading
Class AA Loading
Class B Loading
Class A loading
Class AA Loading
49
Sectional Properties:
Dead Loads:
Diaphragm Loads:
50
Load of one dipahramg = 0.97 k
Location of N.A
K = 0.25
J = 1 - k/3
= 0.917
Eq 4.6
Mc =
= 959 k-ft
Capacity of Section if Concrete Stresses controls:
Ms = A s fs J d Eq 4.7
= 452 k-ft
51
Live Load Analysis: Class AA Live Loading
CL of loading 11ft
CL of roadway 17.63ft
C.L of Loading = 11 ft
n =number of girders = 8
D.F = 0.253
R.f =
= 0.564
R.f =
= 1.12
Minimum rating should be greater than 3 tons in any case, otherwise bridge should
be closed. (AASHTO 2000)
The above results states that if a military tank weighing 40 tons will utilize this
bridge for indefinite period of time, there will be no harm to the service life of the
bridge. However if military tank weighs 78 ton, it is important to give this vehicle
trip wise special permission, and to lemmatize its passes over the bridge, so as to
optimize its service life.
Bridges are posted for weight limitations when they have been deteriorated from a
certain level of condition. In order to post weight limitation on a bridge, it is
suggested to choose value in between of Inventory and operating level rating. It will
be much feasible compared to posting the bridge on posting level or on inventory
level. For example, if Mian Meer Bridge is to be posted the maximum allowable
weight of a vehicle should be in between of Inventory and operating level weight in
tons (65 Tons).
53
4.4 Load Rating of Pre-Stress Girders
Inventory Rating:
Eq(4.7)
Eq(4.8)
54
If rating factor at operating level is greater than 1, it means the member is already
safe and performing well under prevailing loading condition. For example in the
above calculations, rating factor found out for Class A loading for flexural and shear
at operating level is 1.2, it means the member has 20% more strength than applied
live loading and it is safe to resist Class A loading.
The most critical panel of deck slab is Span 6 of carriageway from cantt to city, Mian
Meer Bridge. Condition rating of this panel is 4, which shows that the member has
undergone serious deterioration.
It is important to check the limitation of maximum axle load on this deck slab panel
and ultimately this axle load controls for axle limitation to the whole bridge
structure.
Table 4.2 explains the load rating outcomes of critical slab panel, the maximum
allowed axle load on Mian Meer bridge should be in between of Inventory and
operating rating ” 10” tons. The data obtained and analyzed as below.
55
Table 4.2: Live Load Rating Deteriorated deck Slab Panel
The above record shows that every 4th day an accident occurred on Sherpao Bridge.
It may be due to sharp curvature on the bridge. Drivers don’t obey the design speed
limits and ultimately these results into more frequent accidents on the bridge.
56
Radius of curvature has been found out from the help of Google earth image as
shown in Fig. 4.5. Based on the deck width already known, it is easier to trace out the
centre of the arc on exact scale, and radius of curvature is found out as 597 ft.
• Super-elevation = 4%
For design speed of 60KM and prevailing road conditions, minimum radius of
curvature required: (AASHTO Geometric design policy- 3.10)
Eq 4.9
v is the velocity of vehicle in miles/hours, and f is the side friction, solving above
equation Rmin is found out to be 537 ft. It means radius of curvature provided is
57
satisfying minimum condition required. But it is important to note that drivers don’t
obey this speed limit, the site condition shows that average speed of vehicles on this
bridge is 75-80 Km/h.
It is very important to post serious consideration to speed limit signage and speed
reducing devices on this bridge. This will help in reduction of traffic accidents on the
bridge.
Structural.
Non- Structural.
In developing BPI, 50% importance has been given to the structural components,
25% to non-structural components and 25% to geometric and safety features of the
bridge. Refer to table 4.4, Item (A) and (B) are qualitative based on the average
condition rating of different bridge components already calculated in chapter 3.
58
Table 4.4: Break up of Bridge Performance Index (BPI)
Items (c) are not qualitative; traffic capacity of a bridge depends on Level of service it
is offering either for ADT or for peak hour traffic. However no traffic counts have
been conducted by any agency in Lahore and in the absence of any traffic count and
traffic growth, it is assumed that the bridge is offering LOS C (Level of Service) to
59
the commuters which show a stable condition. (AASHTO Geometric design policy, 2-
31, 2-32). Engineering judgment is important in assigning importance factor and
weighted number for items (c).
Geometric and safety features includes the alignment of the bridge, preferably it
should be right angle and straight. Vertical clearance should be provided as per
requirements of Railways or Irrigation systems. Proper Signage is important to
address faulty alignments particularly on sharp curves to reduce number of fatalities
and essentially required on Sharpao bridge.
BPI will be very helpful in dictating the funding allocation and financial
requirements of a bridge as under:
60
5. 5.
CONCLUSIONS
CONCLUSIONS &RECOMMENDATIONS
AND FUTURE RECOMMENDATIONS
5.1 CONCLUSIONS:
5. For VVIP movements, new wearing surface is laid without scraping the older
one. This practice may affect the capacity of the structure and the sidewalk
efficiency as well as.
61
5.2 FUTURE RECOMMENDATIONS:
• Drainage System once a year before rainy season ,Roding and flushing
3. Due to less service life and less impact durability of joints in Pakistan,
expansion joints when laid or rehabilitated, they should be provided with a
perforated channel so as to collect water and discharge it into a downpour.
rating. If a structural member have Condition rating <5, Go for load ratings
6. Highway authorities should procure state of the art technology for inspection
(BMS) in Pakistan.
62
REFERENCES
3. AASHTO Manual of Condition Evaluation for Bridges, 2nd ed. (2000 Interim
Revisions), American Association of State Highway and Transportation
Officials (AASHTO), Washington, D.C.
63
13. Ryall, M.J., “Bridge Management”, Butterworth-Heinemann, 2001.
14. White, K.R., Minor, J., Derucer, K.N., “Bridge Maintenance, Inspection, and
Evaluation”, 2nd Edition, Marcel Dekker, Inc, 1992.
64