Professional Documents
Culture Documents
Design speed (VD) 35 mph Must be multiples of 5 in this spreadsheet, 15 mph to 80 mph (15 to 60 mph when emax = 4%).
Normal crown slope (eNC) 0.020 ft/ft Alaska Preconstruction Manual page 1130-1 section 1130.1.2 (January 1, 2005). 2001 AASHTO GB p 166
Max. Superelevation (emax) 0.06 ft/ft 0.06 = Alaska Preconstruction Manual page 1160-22 section 1160.5.6 (January 1, 2005).
Lane width (w) 12 ft Minimum runout and runoff may not be correct in this spreadsheet for lane widths other than 12 ft. See the last
paragraph on page 172 in the AASHTO 2001 "green book" (GB), and see the bw column below.
Note-2: Tangent runout (Lt) is the length of roadway needed to accomplish a change in outside-lane cross slope from the normal cross slope rate to zero (flat), or vice
versa, AASHTO 2001 "green book" page 168. This spreadsheet value is calculated from the formula on page 173 of the AASHTO 2001 "green book." At reverse and
compound curve transitions, runout may be a little as Lt = 0 at the transitions between both curves involved (also see note 4 and 8 and AASHTO 2001 GB p 234 and p 184).
Note-3: Superelevation runoff (Lr) is the length of roadway needed to accomplish a change in outside-lane cross slope from zero (flat) to full superelevation, or
vice versa, AASHTO 2001 "green book" page 168. This spreadsheet value is calculated from the formula on page 171 of AASHTO 2001 "green book." Also see note-4.
Note-4: % runoff before the curve is taken from the 2001 AASHTO "green book" page 175, exhibit 3-30. For reverse and compound curves, see note 2 and 8.
Note-5: "Suggested advisory speed" will appear when entered R is less than Rmin. This speed is for signage if realignment is not done. Correct superelevation should be
recalculated using the advisory speed as the design speed for this curve. The same emax value must be used or this speed may not be valid. "Suggested advisory speed"
is determined by comparing R with Rmin values at speed thresholds at the specified emax value. For threshold Rmin values, see the 2001 AASHTO GB table on p 145 (156
to 165) or the formula on p 143 (spreadsheet uses the p 143 formula values unrounded). The only input variables that affect the speed value in this column are emax and R.
Note-6: The fmax value was extracted from Exhibit 3-14 page 145 of the AASHTO 2001 "green book." The fmax values for emax = 4, 6, 8, 10, and 12% all appear to match at a
given speed except the 4% values are not given for speeds higher than 60 mph and the fmax value for 25 mph at emax = 8% appears to be a misprint (the AASHTO "green
book" says fmax = 0.185 but the number likely should be 0.165). This spreadsheet was tested using fmax = 0.165 with emax = 8% at 25 mph. Calculated ed matched the
e values in the AASHTO table on page 161 (meaning the fmax value on page 145 is indeed a misprint). This spreadsheet therefore uses 0.165 (not 0.185) in that case.
Note-7: "Transition on tangent" is useful for determining if the alignment has enough tangent before a normally crowned fixed part of the roadway (such as a bridge).
Note-8: "Runoff on tangent" is useful to find minimum tangent length (the sum of "Runoff on tangent" of two successive curves). Tmin = (Lr * %runoof)1 + (Lr * %runoff)2.
This applies in both cases, reverse or compound. Refer to the 2001 AASHTO "Green book" page 234 (third bullet) and p 184 for more about reverse & compound curves.
Note-9: The calculation for ed is derived as in the example on page 155 of the AASHTO 2001 "green book." RC = Remove adverse crown section, superelevate at normal
crown slope (0.75*eNC < ed_preliminary </= eNC). NC = Normal crown section (ed_preliminary </= 0.75*eNC). Example: If RC is displayed and eNC = 0.02, then ed = 0.02 (use
0.02 even though RC is shown in the ed cell). If RC or NC are not displayed then ed = ed_preliminary.
Note-10: Various rounding methods may be used in calculations. The "Rounding method used" box shows what method the spreadsheet is actually using. If "Auto
select" is shown in the "Rounding method select" box then the spreadsheet will select 1, 2, 3, or 4 automatically to make the calculations match the AASHTO tables most
closely. A rounding method number or "No rounding" in the "Rounding method select" box forces rounding of that method. The list below describes the different rounding
methods.
Auto select (in "select" box only) = Automatic rounding method selection (based on VD and emax) to most closely match 2001 AASHTO GB tables p 156 to 165.
1 = The fraction 1/15 is used instead of 0.067 where found in formulas on page 152 and 155 in the 2001 AASHTO "green book" (see page 143). In addition,
rounding is done within the Lt and Lr calculation on ed_preliminary. Otherwise the formulas used are exactly the same as found on p 152 to 155, 171, & 173.
2 = Like "No rounding" below, except rounding is done within the Lt and Lr calculation on ed_preliminary.
3 = Like 1 above, except the formula for Rmin is as found on page 152 of the 2001 AASHTO "green book" (0.067 used).
4 = The only rounding is within the Lt calculation on ed_preliminary.
No rounding = Uses the formulas found on pages 152 to 155, 171, and 173 in the 2001 AASHTO "green book" without rounding.
Note-11: Entered R values must be equal to or higher than Rmin as calculated using the formula on page 143 in the 2001 AASHTO "green book." The viewable Rmin cell will
467961728.xls Page 2 of 19 printed 04/02/2020 04:04:06
not agree with that Rmin value unless rounding method 1 is used. Thus it may be possible to enter an R value slightly lower than displayed Rmin for all but method 1.
Note-12: "Running speed" (VR) was extracted from Exhibit 3-26 on page 168 of the AASHTO 2001 "green book" (called "Average running speed") under the assumption
that "running speed" (VR) is the same for all emax values. This appears to be what the writers of the AASHTO book were using when calculating the tables on pages 156
to 165 based on tests of this spreadsheet.
VD = 50
emax = 10
fmax = 0.14 this can be made to use table in Exhibit 3.14 on p
VR = 44
Rmin = 697.9167
RPI = 1297.12 this appears to be the desired radius value
hPI = 0.029132 this value turns negative with high R values
S1 = 0.006595
S2 = 0.029234
MO = 0.023097
(0.01e + f)D = 0.067(VD)2/R = 0.129132
f1 = 0.05223 use this not f2 since 1/R = 1/RPI in this example
Subtract the line above from the line above it = ed = 0.076903 This equals the value on page 155 and also agree
This example uses the exact AASHTO formulas found on pages 152 to 155 without rounding.
Shaded blocks are input variables
Calculations for rounout and runoff (these reference the cells above)
Table Interpolator
To calculate exact value, enter values from
published table and needed value in shaded cells.
Calculated value is in non-shaded block.
Enter table values Needed
R 2500 3000 2473.526
e (%) 3.8 3.4 3.8211792
Table Interpolator
To calculate exact value, enter values from
published table and needed value in shaded cells.
Calculated value is in non-shaded block.
Enter table values Needed
R 1800 2000 1850
e (%) 4.6 4.3 4.525
Table Interpolator
To calculate exact value, enter values from
published table and needed value in shaded cells.
Calculated value is in non-shaded block.
Enter table values Needed
R 4000 5000 4600
e (%) 2.7 2.2 2.4
use table in Exhibit 3.14 on p 145
Lr =(wnl)ed(bw)/Δ
Lt =eNCLr/ed
Note C: The calculation for ed is derived as in the example on page 155 of the AASHTO 2001 "green book."
The ed_preliminary cell value (rounded) will equal the ed cell, except in RC or NC situations. If rounded ed_preliminary is greater than 75% of normal crown and less
than or equal to 100% of normal crown, then the ed cell will display "RC." If 75% or less than normal crown the cell will display "NC."
Note D: This spreadsheet uses the Rmin formula on page 143 (fraction 1/15 rather than 0.067) for comparison with entered R to determine if the entered R value is belo
it. The reason for this is calculated Rmin was always smaller than when using the formula on page 152 and thus allowed the spreadsheet to accept the AASHTO table
Rmin in all cases.
Note E: Some of the cells restrict the entered data to values the spreadsheet can use (see the Excel menu: DATA > VALIDATION…).
Note F:
In order to verify the calculations using the AASHTO tables on pages 156 to 165, an attempt was made to find one single rounding method that made the
spreadsheet calculations match the tables in every (test) case. Initially no-rounding was used but the tables were not matched in every (test) case. In tests
of this spreadsheet it was found that the AASHTO tables on pages 156 to 165 do not round in a totally consistent way. The biggest difficulty seemed to be
with Rmin rounding. Since Rmin is the first calculation in the chain, it has a domino effect on the rest of the numbers. When it was discovered that no single
method matched the tables in every test case (including no rounding), the methods that came the closest (1and 2) were included in this spreadsheet with
the ability to select between them. A few more methods (3 and 4) were later added as necessary when the spreadsheet was more thoroughly tested (at
table extremes only). Finally, the "No rounding" option was added. Through all this the table below was added.
The table below was developed to "program" the rounding method the spreadsheet will use in a given case. The selected method depends on emax and
design speed (VD). The method selected from the table is shown in the "Rounding method used" box (the one in a hidden row of the "Main sheet"). See
note-10 on the "Main sheet" for descriptions of the different rounding methods. Method 4 will appear in the hidden "Rounding method used" box when "No
rounding" is shown in the "Rounding method select" box. This is because the only difference between method 4 and "No rounding" applies to Lt (runout) so
the switch is accomplished using an" "IF" function in the Lt cell rather than using a table entry (which would require making a lot of other cell formulas even
longer than they already are).
The "Rounding method selector table" back-up (below) contains values that make the spreadsheet match the 2001 AASHTO tables on pages 156 to 165
(tested only at extremes). The table used by the spreadsheet is found in hidden rows on the "Main sheet."
BACK UP (the table actually used is in a hidden area of the Main sheet)
When "Auto select" appears in the "Rounding method select" box, the spreadsheet will use the hidden "Rounding method selector table" to
decide what rounding method to use in order to most closely match the AASHTO tables on pages 156 to 165. The decision making is accomplished using
"IF" functions in columns E, F, G, H, J, and L in the lower table of the first page. The cells look for a 1, 2, 3, or 4 in the "Rounding method used" box in a
hidden area of the Main sheet. The selected number is also shown in an unhidden "Rounding method used" cell to show what method is actually being
used by the spreadsheet.
The number selected by the spreadsheet was determined by testing the spreadsheet (at AASHTO table extremes only). The "Rounding method selector
table" entries can be changed by unprotecting the "Main sheet" and then unhiding the table rows. The "IF" statements mentioned earlier also
reference one of the three rows in the upper table on page one of the "Main sheet," depending on which method is selected (the unused rows in the table
will appear blank, determined using other IF statements that refer to the hidden "Rounding method used" box).
Note G: Rounding for decision making purposes is performed within the ed cell, to determine if RC or NC should be displayed. This rounding is done even when "No
rounding" is specified, however, when a number is displayed in the ed cell the numerical value is not rounded.
Note H: The hidden rows on the "Main sheet" would have been moved to another sheet but "Data validation" of Excel will not reference other sheets.
Note X: See the hidden column "Q" on the main sheet concerning the outdated method formerly used in Alaska for % runoff before the curve (2/3 of total transition
length). This column calculates the % runoff before the curve using the old method for comparison. Tests of this show that the difference from the AASHTO method
can be more than 50%. The old method was used until June 16, 2003 when the Alaska Preconstruction Manual was changed to use the AASHTO method. The
difference between the old Alaska method and the AASHTO method is that the old Alaska method used 2/3 of total transition length (runout plus runoff) rather than the
AASHTO method of using a percentage of runoff only. Page 175 of the 2001 AASHTO "green book" (first paragraph) talks about a majority of agencies using 0.67 of runoff on the
tangent. If this sounds like the old Alaska method, a careful re-read shows it isn't. Again, the outdated Alaska method used 0.67 (2/3) of TOTAL TRANSITION length (runout plus
runoff) before the curve, not 2/3 of runoff. Therefore beware of this when referencing Exhibit 3-30 on the same page and the paragraph below it.
Note-Y: Apply this note to column "R" hidden on the main sheet. This minimum transition length is not valid at reverse or compound curve transitions.
Note Z: This spreadsheet was created by Chris Pillar, Alaska Department of Transportation, Anchorage, Alaska.
Version History
The idea for this spreadsheet originated with a metric spreadsheet obtained from John Linnell. That spreadsheet dates to as far
back as 1998, perhaps earlier. It was used between 1998 and 2003. It required looking up the superelevation rate in the AASHTO
Green Book tables for each curve radius. That required some interpolation work because the tables only have certain radiuses in
them. From the entered radius and other input, the spreadsheet calculated runout, runoff, the entire transition length, and the
percent runoff before the curve for use in Land Desktop (and previous Softdesk-8) software. These calculations had to be done to
accommodate the long used Alaska Preconstruction manual method of positioning two thirds of the entire transition outside of the
curve (not the same as % runoff before the curve). In 2003 a change was made to the Alaska Preconstruction manual requiring
total use of the AASHTO Green Book for superelevation, rather than specifying the long used two thirds method. An update to the
spreadsheet was therefore needed.
As it turned out, the spreadsheet had to be totally rewritten for two reasons. First the AASHTO Green Book method of positioning
the transition is different. Second the spreadsheet had to be converted to English since the DOT converted back to English after a
few years of producing plans in metric units. As it ended up, nothing in the spreadsheet went unchanged.
The initial rewrite was done in the second week of January 2004. It still required looking up the superelevation rates in the AASHT
Green Book tables. In the January 13, 2004 design meeting, Rick Oldford mentioned that the method for positioning superelevatio
had recently changed. Since the change was incorporated in the new spreadsheet, it was sent to him in an EMAIL attachment. He
responded by suggesting the spreadsheet be made to automatically look up the superelevation rate so the user didn't have to.
That work was done between mid January and the beginning of March 2004. Rather than look up superelevation rate, the
spreadsheet was made to calculate it. Test (beta) versions were sent out to Rick Oldford, Gary Steffens, and John Linnell. Some
their suggestions were incorporated.
The main reason for the update was version 4.1 had unintentional password protection.
Version 4.2 has no password protection.
Two other changes were made to make the formulas more efficient.
An error was corrected in a note on the "Spreadsheet Info" sheet (this sheet).
lue when RC is
a used ed_preliminary
was fixed by adding