BITUMIN ROAD

BILL OF QUANTITIES FOR BITUMIN ROAD FOR PROPOSED FACTORY


PROJECT FOR J B SPICES AT KURALI.
APPROX ROAD AREA = 32077 SQ.FT.
Sr.NO Description Quantity Unit Rate Total Amount
1 Excavation in all sorts of soils except soft
or hard rock for the foundation or other
works including shoring, strutting and de-
watering if required, dressing of sides and
ramming bottom, and also inclusive of
depositing the excavated earth category
wise within the plot as directed.
a. Up to 1.5mt. Lvl. (Mass Excavation) 1,327.83 M3 110 146,061.30

2 Preparation and Consolidation of subgrade


with power road roller of 8 to 12 tonne
capacity after excavation earth to an
average of 22.5 cm depth, dressing to
camber and consolidating with road roller
including making good the undulations etc.
and rerolling the sub grade and disposal of
surplus earth lead upto 50 m. 9375.0 M2 25 234,375.00

3 Providing and laying 60=80 mm size


metalling in two layers below WBM in
filling voids with Quarry Dust and rolling
individual layers with roller and compacting
etc. complete as per directed by engineer
in charge. 2343.75 M3 1750 4,101,562.50

PAGE NO:1
BITUMIN ROAD

4 Laying, spreading and compacting stone


aggregate of specified sizes to WBM
specifications including spreading in
uniform thickness, hand picking, rolling with
3 wheeled raod / vibratory roller 8 to 10
tonne capacity in stages proper grade and
camber, applying and broming requisite
type of screening / binding material to fill up
the interstices of coarse aggregate
watering and compacting to required
density.

a. Subbase 100 mm with stone aggreagte


63mm to 90mm including stone screening
13.2 mm size. 937.50 M3 1,680.00 1,575,000.00

b. Base course 100 mm with 63mm to 40 mm


size including stone screening 13.2 mm
size 937.50 M3 1,750.00 1,640,625.00
TOP LAYERS FOR CARPETS.
5 Providing and applying 25mm SEMI
GROUT with 15kg/10sq.mt of
bitumincomplete in all respect as directed
by Engineer IN charge
On W.B.M @ 1.5kg / sqm 9,375.00 M2 150.00 1,406,250.00

6 Providing and applying 25mm PREMIX


SEAL COAT with 7.5kg/10sq.mt of bitumin
complete in all respect as directed by
Engineer IN charge 9,375.00 M2 350 3,281,250.00

7 Providing and applying 20mm PREMIX


CARPET COURSE with surface road
aboveabove with 20kg/10sq.mt of bitumin
complete in all respect as directed by
Engineer IN charge 9,375.00 M2 275 2,578,125.00

8 Providing ,supplying & Pre-Cast KERB


STONE in Grade M20, on respect to level
as on site ,maintaining the longitudinal
slope, ...complete as per instruction of
incharge... 2,238.00 Rmt 850.00 1902300

Total Amount For Bituminouse Road. 16865548.8


Per sq.ft. 525.80

PAGE NO:2
BITUMIN ROAD

9167925.00 TOATAL FOR TOP CARPET


285.82

PAGE NO:3
RCC ROAD.

BILL OF QUANTITIES FOR RCC ROAD FOR PROPOSED FACTORY PROJECT


FOR J B SPICES AT KURALI.
APPROX ROAD AREA = 32077 SQ.FT.
Sr.NO Description Quantity Unit Rate Total Amount
1 Excavation in all sorts of soils except soft
or hard rock for the foundation or other
works including shoring, strutting and de-
watering if required, dressing of sides and
ramming bottom,
a. Up to 1.5mt. Lvl. (Mass Excavation) 930.85 M3 210 195,478.05

2 Transporting and dumping the excavated


excess earth in the plot premises up to 500
mt. lead 685.64 M3 75 51,423.33
3 Preparation and Consolidation of subgrade
with power road roller of 8 to 12 tonne
capacity after excavation earth to an
average of 22.5 cm depth, dressing to
camber and consolidating with road roller
including making good the undulations etc.
and rerolling the sub grade and disposal of
surplus earth lead upto 50 m. 2981.1 M2 35 104,337.19

3 Providing and laying metal solling of 230


thick layer and filling the voids with hand
broken metals and Quarry Dust and rolling
with roller and compacting etc. complete
as per directed by engineer in charge. 685.64 M3 1950 1,337,006.53

PAGE NO:4
RCC ROAD.

4 Laying, spreading and compacting stone


aggregate of specified sizes to WBM
specifications including spreading in
uniform thickness, hand picking, rolling with
3 wheeled raod / vibratory roller 8 to 10
tonne capacity in stages proper grade and
camber, applying and broming requisite
type of screening / binding material to fill up
the interstices of coarse aggregate
watering and compacting to required
density.

a. Subbase 100 mm with stone aggreagte


63mm to 90mm including stone screening
13.2 mm size. 298.11 M3 2,200.00 655,833.75

5 Providing ,supplying & fixing LDPE sheet


400micron, on respect to level as on
site ,maintaining the longitudinal slope,
...complete as per instruction of incharge...

On W.B.M … 2,981.06 M2 130.00 387,538.13

6 Providing and laying controlled cement


concrete M-200, 150mm thick, in alternate
panels for flooring. Panels shall be formed
by MS channel 100 mm depth on all four
sides and bolted adequately to make the
panel size as required. Entire concrete
mass shall be vibrated with skin vibrators
and smooth finished with power trowel,
after the concrete has been worked upon
by vacuum dewatering system / Tri mix
system, vertical sides of cast panels shall
be made smooth by putting plastic film
prior to concreting. Expansion joint
between two panels shall be groove cut to
size 4 X 60 mm and filled with poly
sulphide sealant filler and top surface shall
be smoothened in level with cast floor
panel including the cost of from work
excluding cost of reinforcement, and curing
by pounding the surface of concrete,
complete as directed by Engineer IN
charge.

372.63 M3 6200 2,310,323.44

PAGE NO:5
RCC ROAD.

7 Providing & Supplying & fixing in position


High yield deformed bar reinforcement
confirming to IS – 1139 or cold Twisted
bars, TOR steel / TMT / or Equivalent
Reinforcement bars confirming to IS –
1786 for RCC construction including
transporting (i.e. loading & unloading) the
steel from store/issue points to site of
works including unloading from
Trucks/Trailers, cleaning, de coiling,
cutting, bending to required shape and
lengths as per detailed drawing, binding
with 16 SWG black soft annealed binding
wire, placing with proper cover block,
support chairs, overlap, spacers, etc.
complete in all respect as directed by
Engineer IN charge in foundation and up to
Plinth level.

37,000.00 Kg. 55 2035000

8 Providing ,supplying & Pre-Cast KERB


STONE in Grade M20, on respect to level
as on site ,maintaining the longitudinal
slope, ...complete as per instruction of
incharge... 794.95 Rmt 550.00 437222.5

Total Amount For Road. 7514162.913125

PAGE NO:6
RCC ROAD.

PAGE NO:7
MESURMENT SHEET FOR 1 M2

SR.NO DES. NOS L B H QTY UNIT.


1 EXCAVATION 1.00 1.00 1.00 0.43 0.43 M3

2 RUBLE SOLING 1.00 1.00 1.00 0.23 0.23 M3

3 WBM 63-90 1.00 1.00 1.00 0.10 0.10 M3

4 WBM 40-63 1.00 1.00 1.00 0.00 0.00 M3

5 25MM SEMI GROUT WITH


15KG/10SMT OF BITUMIN 1.00 1.00 1.00 - 1.00 M2

6 25MM PREMIX WITH


7.5KG/10SMT OF BITUMIN 1.00 1.00 1.00 - 1.00 M2

7 20MM PREMIX CARPET


COURSE WITH SURFACE
ROAD ABOVE 15KG/10SMT
OF BITUMIN 1.00 1.00 1.00 - 1.00 M2

8 PRE CAST KERBING STONE 2.00 1.00 - - 2.00 RMT

9 EXCAVATION 2 160 7 0.43 963.2 M3


1 160 7 0.43 481.6 M3
2 32 7 0.43 192.64 M3
1 110 7 0.43 331.1 M3
1 102 7 0.43 307.02 M3
1 220 12 0.43 1135.2 M3
1 26 24 0.43 268.32 M3

1 67 7 0.43 201.67 M3
1 50 7 0.43 150.5 M3
4031.25 M3
AREA TABLE.
DESC. nos L B AREA.
MAIN ENTRY TO END 1 169.265 7.5 1269.488
AREA. QTY. NOTE 1 119.37 7.5 895.275
2164.763 930.8479 2 54.42 7.5 816.3

2981.063 685.6444

2981.063 298.1063

2981.063 0

2981.063 2981.063 397.475 2981.06

2981.063 2981.063 Total Road length. 397.475 Rmt. 32076.23


Avg. Road width.. 7.5
2981.063 32076.23

2981.063 2981.063

397.475 794.95

4031.25
169.265
119.37
108.84
397.475

SMT

SFT

SFT