Professional Documents
Culture Documents
Materials Verification
Precast components Structural defects, dimensional tolerances, surface finishes and physical
damage
Bonding agent, Waterproofing admixtures, Delivered in original packaging, shelf life from date of production and
Liquid applied waterproofing materials, batch reference
and Sealant
20
Measurement of dimensions Inconsistent surface finish
All precast components should be handled in a manner The location of the lifting device should be situated
that avoids excessive stresses, damages and cracks to at the downstand of the joggled profile of panels to
the components, especially during demoulding and prevent excessive stress and cracks around this area
handling in site precast yards. Young immature concrete (see Figure 4.2).
delivery, handling & storage
✗ Lifting device
✓
CP 81:1999 recommends that the following be • method of lifting and type of lifting equipment;
considered when handling precast units on site: and
• minimum concrete strength; • proper supports and support location.
• size and weight of precast unit;
Rigging system selected should ensure safety and equal
• adequacy of reinforcement to resist handling load distribution to all lifting points. Two common
stresses; rigging configurations are the 2 x 1 and 2 x 2
• number, size and location of lifting points; configurations as shown in Figure 4.3.
21
Figure 4.3: Rigging of precast panels
0.5H
Min 2D
2x2
2x1
Precast components should be placed on strong and 4.2 BRICKS, CEMENT, SAND
level supports. The supporting points should be AND OTHERS
positioned such that the precast components are not
subject to excessive stress. Stacking should be done in Proper packaging, delivery, handling and storage of
22
Bricks should not be stacked higher than 2 pallets. wheelbarrow should be avoided, unless absolutely
They should be hoisted in pallets or transported required, such as in narrow spaces.
using a pallet jack. Transportation of bricks using
✗ ✓
delivery, handling & storage
✓ ✓
Aggregates for the mortar mix should be stored with from contamination by other site materials, for
good drainage provision and protected from dirt, example, by providing a containment with proper base
intrusion of foreign matter and excessive high and kerb. A sand pump could be used to transport
temperatures. Sand should be stored in a manner free sand, where needed.
23
Figure 4.7: Transportation and storage of sand
Sand
Provide a good base (eg, plywood or Using sand pump to transport sand to required location
lean concrete) to store sand
Cement and pre-packed mortars should be stored off c) bitumen and other thermoplastic materials should
24