ITEM H2S DETECTION EQUIPMENT AND SERVICES SPECIFICATIONS CONTRACTOR’S RESPONSE

1 PERSONNEL
Contractor shall provide qualified and experienced personnel Contractor shall provide qualified and experienced personnel
sufficient in number and with appropriate qualifications to sufficient in number and with appropriate qualifications to
maintain and operate the H2S Detection Equipment and maintain and operate the H2S Detection Equipment and
Services on site, and process and interpret data as required. A Services on site, and process and interpret data as required. A
standard crew will comprise one (1) H2S Safety Engineer. For 24 standard crew will comprise one (1) H2S Safety Engineer. For 24
hour operations two (2) crews will be required. hour operations two (2) crews will be required.
a. H2S Safety Engineer shall have minimum 5 (five) years a. H2S Safety Engineer shall have minimum 5 (five) years
of oil industry H2S Safety, plus a minimum of 2 (two) of oil industry H2S Safety, plus a minimum of 2 (two)
years of geothermal drilling operations experience. years of geothermal drilling operations experience.
H2S Safety Engineer shall also have extensive H2S Safety Engineer shall also have extensive
knowledge of H2S safety equipment operations, knowledge of H2S safety equipment operations,
materials and products procedures; and experience in materials and products procedures; and experience in
conducting H2S and SCBA training and emergency conducting H2S and SCBA training and emergency
drills. drills.
(see Document CV engineer)

2 EQUIPMENT
Contractor shall provide the required H2S Detection System Contractor shall provide the required H2S Detection System
equipment on an as required basis, and shall be responsible for equipment on an as required basis, and shall be responsible for
mobilisation and demobilisation of this equipment to and from mobilisation and demobilisation of this equipment to and from
the drilling site as required. The list of H2S Detection Equipment the drilling site as required. The list of H2S Detection Equipment
to be provided, as a minimum: to be provided, as a minimum:
a. 1 set of Fixed Point Electronic H2S Gas Detection a. Schneider Electronic Inc. Fixed Point Electronic H2S
System detection/monitoring system w/ capabilities of
monitoring 4-6 areas around the location.
(see Fergaco Equipment Spec. Page 1)

b. 6 sets for 4 areas of Hydrogen Sulphide Sensor b. Industrial Scientific Inc. iTrans-Explosion proof H2S fix
(measuring range: 0-100 ppm, explosion proof, and sensor (Toxic Electrochemical) measuring ranges : 0-
impervious to high moisture environments.) 500 ppm in 1 ppm increments
(see Fergaco Equipment Spec. Page 2-3)
ITEM H2S DETECTION EQUIPMENT AND SERVICES SPECIFICATIONS CONTRACTOR’S RESPONSE

c. Hydrogen Sulphide Calibration System c. Industrial Scientific Inc. CAL-Gaz Complete set Gas
cylinder for calibration kit contains of mixing gases :
H2S, LEL, CO, O2 c/w regulator.
(see Fergaco Equipment Spec. Page 4 )

d. 3 sets of Strobe Light and Siren System d. Tomar Electronic Inc. Explosion proof H2S alarm
consisting of mounting frame, pole, one amber strobe
light and one alternating yelp tone siren.
(see Fergaco Equipment Spec. Page 5-6 )

e. 8 sets of 30-minute positive Self-Contained Breathing e. Scott Industrial Inc. AP-50 Self Contained Breathing
Apparatus (SCBA) for rescue unit rated to NIOSH Apparatus (SCBA) c/w hose line attachment,
standard. w/cylinder pressure 2216 psi, NIOSH/MSHA approval
(see Fergaco Equipment Spec. Page 7 )

f. 8 sets of Emergency Escape Breathing Apparatus f. International Safety Instrument (ISI),Emergency


(EEBA) with minimum 10-minute escape unit rated to Escape Breathing Apparatus (EEBA) 10 minute
NIOSH standard. duration, cylinder pressure 3000 psi, c/w face hood.
NIOSH standard.
(see Fergaco Equipment Spec. Page 8 )

g. 8 sets of Workline Unit Complete Cascade System g. Scott Industrial Inc. Ska Pak 5 minute entry/egress
cylinder Supplied Air Breathing Apparatus (SABA) c/w
weather proof storage stainless steel box. These air
packs are NIOSH/MSHA Approval. Complete Cascade
System
(see Fergaco Equipment Spec. Page 9-10 )
h. 1 ea of Oxygen Powered Resuscitators
h. Life Support Products Inc. Oxygen Powered
Resuscitators
(see Fergaco Equipment Spec. Page 11)
ITEM H2S DETECTION EQUIPMENT AND SERVICES SPECIFICATIONS CONTRACTOR’S RESPONSE

i. 2 sets of Electronic Multiple Gas Detector with


independent sensors for detection of oxygen, i. Industrial Scientific, VENTIS Multigas Monitor c/w
combustible gases and vapours, carbon monoxide and H2S, CO, LEL, O2 sensor.
hydrogen sulphide. (see Fergaco Equipment Spec. Page 12)

j. Recharge Breathing Air Compressor, One (1) unit of


Electric and one (1) unit of Diesel Breathing Air j. COLTRI-Komba Kompressor, Breathing Air Compressor
Compressor (Electric or Diesel motor driven), min out put of 9.2
Cfm, w/ volume capacity of 260 ltr/minute.
(see Fergaco Equipment Spec. Page 13-14)
k. 1 set of Pelican Rack, minimum 6 cylinders of 45 cubic-
feet for use of 30-minutes SCBA k. Fergaco Custom, Pelican Rack, minimum 6 cylinders of
45 cubic-feet for use of 30-minutes SCBA
(see Fergaco Equipment Spec. Page 15)
l. 3 ea of Windsock
l. Fergaco Custom, Windsock completed by frame and
pole.
(see Fergaco Equipment Spec. Page 16)
m. H2S danger Warning Signs
m. Fergaco Custom, H2S Safety Sign board, i.e : Poison
Caution Gas sign, Safe Briefing Area sign, and Well
Condition sign.
(see Fergaco Equipment Spec. Page 17)
n. 4 ea of Bug Blower (explosion proof), with min 32”
diameter fan n. Euromotori, Explosion proof Bug Blower, w/ out put of
20,000 Cfm capacity, w/ Explosion proof electric
contactor, 220-480 VAC, 50-60 Hz, w/ Electric Power
Motor 5,5 HP, and 36" blade diameter.
(see Fergaco Equipment Spec. Page 18)
o. 1 ea of 20 Foot Container, fully equipped office,
briefing room and spare parts container. Complete o. Fergaco Custom, 20 ft H2S Container, fully equipped
with all wiring, cables, junction box’s and other office, briefing room and spare parts container.
ITEM H2S DETECTION EQUIPMENT AND SERVICES SPECIFICATIONS CONTRACTOR’S RESPONSE
supplies required to support the above equipment Complete with all wiring, cables, junction box’s and
during operation and rig up. Spare parts to sustain other supplies required to support the above
>99% equipment availability. equipment during operation and rig up. Spare parts to
sustain >99% equipment availability.
(see Fergaco Equipment Spec. Page 19-20)
p. 1 ea of Hand held battery powered Megaphone
p. Toa Megaphone, Hand held battery powered
Megaphone
(see Fergaco Equipment Spec. Page 21)
q. 6 ea minimum of Handy talky
q. Motorolla GP-328, Radio HT, two way communication
Radio
(see Fergaco Equipment Spec. Page 22)