Professional Documents
Culture Documents
net/publication/306467669
CITATIONS READS
0 7,489
2 authors, including:
Nurly Gofar
Universitas Bina Darma
49 PUBLICATIONS 222 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Intelligent prediction for evaluation of single pile bearing cpaacity using Pile Dricving Analyzer (PDA) datas View project
All content following this page was uploaded by Nurly Gofar on 25 August 2016.
GROUND IMPROVEMENT BY
PRELOADING AND VERTICAL DRAIN
Nurly Gofar
Universiti Teknologi Malaysia
Rosdi Mohamed
Universiti Malaysia Pahang
3.1 Introduction
In Malaysia, soft soil deposits are widespread all over the country
and mostly found in the coastal area. In general, soft soil posses
low strength and high compressibility and thus having low bearing
capacity. The soil needs to be improved to avoid excessive
settlement and prevent stability failure that affecting the safety of
the infrastructure.
Preloading is one of the most effective and economical
methods to reduce settlement and improve the bearing capacity of
the soft soil. The application of preloading does help in applying
stress to the existing soil, thus increasing the pore water pressure.
Consolidation happens when the water in soil is squeezed out from
the soil matrix. With the elimination of water from the soil, the soil
strength is increased. However, this method does not have the
advantages of speeding up the process of pore water pressure
dissipation hence settlement might takes years to complete.
The preloading method is usually combined with vertical drain.
The use of prefabricated vertical drain in a soft soil layer can
shorten the treatment time of ground by increasing the rate of
53
54
Figure 3.1 The beneficial effect of preloading and vertical drain (after
Haussmann, (1990)
1.2
1.0
Time Factor, Tv
0.8
0.6
0.4
0.2
0.0
0 10 20 30 40 50 60 70 80 90 100
Percent consolidation (%)
U vh = 1 − (1 − U h )(1 − U v ) (3.3)
F = F (n) + Fs + Fr (3.5)
57
⎛D ⎞
F (n) = ln⎜⎜ e ⎟⎟ − 0.75 (3.6)
⎝ dw ⎠
⎡⎛ k ⎞ ⎤ ⎛ d ⎞
Fs = ⎢⎜⎜ h ⎟⎟ − 1⎥ ln⎜⎜ s ⎟⎟ (3.7)
⎣⎢⎝ k s ⎠ ⎦⎥ ⎝ d w ⎠
⎛k ⎞
Fr = πz ( L − z )⎜⎜ h ⎟⎟ (3.8)
⎝ qw ⎠
For the purpose of settlement analysis, the soil profile and soil
properties can be simplified as shown in Table 3.1.
Settleme
nt gauge
Observation Top
embankment platform
Water
Sand level
PVD piezometer
Figure 3.7 Settlement plot for embankment with and without surcharge
preloading
For platform fill of 1m, the total settlement was 261mm. When
surcharge pre-load of 1m and 2m high were used, the 90%
consolidation settlement was reached after 5.3 months and 3
months respectively. Table 3.2 shows the estimated time required
for various backfill and surcharge heights.
Vertical drain was installed in the swampy area where the
depth of compressible layer reaches 14m. For the worst case
analyzed above and with the installation of vertical drain, the
consolidation time was further reduced to one month. Figure 3.8
shows the achievement of settlement criteria when vertical drain
was used.
66
3.5 Conclusions
References
Asaoka, A (1978). Observational Procedure of Settlement
Prediction. Soils and Foundation. 18 (4): 87-101.
Bardet, J.P. (1997). Experimental Soil Mechanics. New Jersey.
Prentice Hall.
Bergado D.T., Alfaro, M.C., and Balasubramaniam, A.S. (1993).
Improvement of soft Bangkok clay using vertical drains.
Geotextiles and Geomembranes , 12 (7): 615-664
Bumimetro Engineering Corporation Sdn Bhd. (2002). Factual
Report on SI Works for Cadangan Merekabentuk, Membina dan
Menyiapkan Kolej Universiti Kejuruteraan & Teknologi
Malaysia (KUKTEM) di Pekan, Pahang Darul Makmur
Carillo,N. (1942).Simple Two and Three Dimensional Cases in the
Theory of Consolidation. Journal of Mathematics s,21(1):1-5.
70