Professional Documents
Culture Documents
1. A project’s total cost is Rs.500 K and expected period of completion is 12 months. A review is
taken at the end of every three months. It is observed that for the 3 month period from January
to March 2011, the overall % of completion of the phase relating to the 3 month period is
only 80%. Primary measures are given in the following table:
(Rs. In ‘000)
Particulars January 2011 February 2011 March 2011 Total
BCWS or PV 20 30 50 100
ACWP or AC 18 30 44 92
BCWP or EV 16 24 40 80
Ascertain :
CASE STUDY
2. ABC Ltd., have a manually operated machine which has a scrap value of Rs.28,000. They wish to replace
it a new automatic machine at a cost of Rs.70,000, to reduce costs and thereby increase their profits at
least in the first three years after its installation. Cost of capital is 15%.However, due to uncertainty in the
expected demand for their product, the cash flows can not be accurately estimated. Following are the
details of expected cash flows and their probabilities, for the 3 years immediately after the installation of
the automatic machine.
Cash flow (Rs) Probability Cash flow (Rs) Probability Cash flow (Rs) Probability
Year PV Factor
1 .870
2 .756
3 .658
Pinky Dey Batch 17th PM Assignment
(i) Ascertain the NPV of the automatic machine and advise the company
on its purchase.
Expecte Expecte Expected
d cash d cash cash
YEAR 1 flow YEAR 2 flow YEAR 3 flow
Cash flow Probability Cash Flow Cash flow Probability Cash Blow Cash flow Probability CasH FLOW
(Rs) (Rs) (Rs)
(ii) On the basis of the random numbers given below, apply the Monte Carlo simulation to
decide upon the purchase of the automatic machine.
RANDOM NUMBERS
1 4 7 6 5 0
2 2 4 8 0 1
3 7 9 4 0 3
Set 5 (0, 1, 3) Looking at the net c/f from the 5 simulation sets;
Mean of net c/f (µ) = Rs 5,874
Cash PV Factor
Standard Deviation (σ) = Rs 12,099
Year Flow @15% NPV
Year 1 10,000 0.870 8,700
From z-table, for above µ & σ, the probability of
Year 2 10,000 0.756 7,560
net cash flow > 0 is 0.86.
Year 3 20,000 0.658 13,160
Total NPV of Future Cash Inflows 29,420 Hence, based on the Monte Carlo simulation, the
Scrap value (Cash Inflow) 28,000 firm will make profit 86% of times and hence it is
Total Cash Inflow 57,420 advisable to invest in the new automatic
Total Cash Outflow 70,000 machine.
Net Cash Flow (12,580)
The following information is available about a project’s activities. All times are in months. ( 3
point estimates)
A - 2 5 6
B - 4 6 9
C A 4 6 7
D A 4 7 10
E B, C 5 6 10
F D 3 5 8
G E 4 6 8
What are the expected time and variances for each activity?
Draw the AOA or AON network and find the critical path and time of
completion.
Which activities will you concentrate on for resource leveling and for reducing project
completion time?
If you do not want to have any chance of a time over run at all, what will be your report to
the board on the expected project completion time?
If we do not want any time run-over, the minimum completion time will be given by µ +
3.2σ
= 23 + 3.2*1.354
= 27.33 months.
= 27 months and 10 days
4. Information on the activities of a project is given below. All times are in days and all costs are
in Thousands of Rupees. Indirect costs are calculated@ Rs 50,000 per day. All activities can be
partially crashed.
Act Predecessor Normal Time Normal Cost Crash Time Crash Cost
Pinky Dey Batch 17th PM Assignment
A - 5 50 3 250
B - 4 40 2 200
C B 7 70 6 160
D A, C 2 20 1 50
E A, C 3 30 - -
F B 8 80 5 350
G D 5 50 4 100
H E, F 6 60 3 280
Crash Cost
Ac Predecesso Norma Norma Crash Crash per Day Crashabl
t r l Time l Cost Time Cost Cost e Days
A - 5 50 3 250 100 2
B - 4 40 2 200 80 2
C B 7 70 6 160 90 1
D A, C 2 20 1 50 30 1
E A, C 3 30 - -
F B 8 80 5 350 90 3
G D 5 50 4 100 50 1
H E, F 6 60 3 280 73.33 3
Draw the network and find the critical path and project duration and project cost for normal
levels of project activities.
If you are asked of your opinion about an estimate for the earliest project
completion time, what will be your report?
Optimal way to complete the project in 16 days is to crash the critical path activities by 4 days,
starting from the activity having the least Crashing Cost per Day
1st Day crash
Activity with lowest CC per day in critical path is H. We’ll crash it by 1 day.
Ac Normal Normal Crashing Days New New Total Cost after 1 day
t Time Cost Cost per Day Crashed Time Cost crashing
A 5 50 100 5 50 50+40+70+20+30+80+
B 4 40 80 4 40 50+133.33+50x19
C 7 70 90 7 70
2 20 = 473.33k + 950k
D 2 20 30
E 3 30 3 30
= Rs 1,423,333
F 8 80 90 8 80
Pinky Dey Batch 17th PM Assignment
G 5 50 50 5 50
H 6 60 73.33 1 5 133.33
After crashing the activity H by 2 days, we observe that there are 2 critical paths: B-C-D-G & B-C-
E-H.
Instead of focusing on lowest crash cost per day activity, we’ll focus on activity that is common
across both critical paths and we’ll crash the common activity with lowest crashing cost per day.
Activity common across the 2 critical paths and lowest crashing cost per day is B. We’ll crash it
by 1 day.
Pinky Dey Batch 17th PM Assignment
Ac Normal Normal Crashing Days New New Total Cost after 3 days
t Time Cost Cost per Day Crashed Time Cost crashing
A 5 50 100 5 50 50+120+70+20+30+80+
B 4 40 80 1 3 120 50+206.67+50x17
C 7 70 90 7 70
2 20 = 626.67k + 850k
D 2 20 30
E 3 30 3 30
= Rs 1,447,667
F 8 80 90 8 80
G 5 50 50 5 50
4 206.6
H 6 60 73.33 2 7
4th Day crash
After crashing the activity H by 2 days and activity B by 1 day, we observe that there again are 2
critical paths: B-C-D-G & B-C-E-H.
We’ll focus on activity that is common across both critical paths and we’ll crash the common
activity with lowest crashing cost per day.
Activity common across the 2 critical paths and lowest crashing cost per day is again B. We’ll
crash it by 1 more day.
Ac Normal Normal Crashing Days New New Total Cost after 4 days
t Time Cost Cost per Day Crashed Time Cost crashing
Pinky Dey Batch 17th PM Assignment
A 5 50 100 5 50 50+200+70+20+30+80+
B 4 40 80 2 2 200 50+206.67+50x16
C 7 70 90 7 70
2 20 = 706.67k + 800k
D 2 20 30
E 3 30 3 30
= Rs 1,506,667
F 8 80 90 8 80
G 5 50 50 5 50
4 206.6
H 6 60 73.33 2 7
Optimal Project cost of completing the project in 16 days is Rs 1,506,667.
The following information is available about a project’s activities. All durations are in days.
A - 4 X, Y
B A 2 X
C A 2 X
D B, C 4 X, Y
E D 5 W, X
F D 3 W, X, Y
G E, F 2 X, Y
Given that each resource is assigned 100% to each task, identify the resource constraints.
Pinky Dey Batch 17th PM Assignment
Here’s the resource calendar from Microsoft Project. Also presented is the leveled-out resource usage
from Microsoft project.
Resource Calendar
Assuming a 5 day week, prepare the resource calendar( Graph Sheet ). Level the resources.