Course Code – Course Name: CBC212 - Class: A
Project Management
Day/Date: Thursday/ April 9, 2020 Student Name: Aliefia Apridha Surdadi
Time: 08.30 am Student ID: 18111007
Facilitator: Sony W. Antonio
Study Program: Business Administration
Exam Type: Open Book
Declaration:
I certify and acknowledged by proctor that this is entirely my own work, except where I
have given fully-documented references to the work of others, and duly accept any
pertinent consequences of false declarations in accordance with the IPMI International
Business School regulations.
Part A :
2. Task dependencies is the nature of the relation ship between two task. There are
common type of task dependencies such as Finish To Start, Start to start, Finish To
Finish, Start To finish.
3. Critical Path on a project → The series of activities that determined the earliest time
by which the project can be completed. It is the longest path through the network
diagram and has the least amount of slack or float.
4. PERT→ it can be used to estimate project duration. PERT applies the critical path
method or we can say CPM to weighted average duration estimates.
5. PERT weight average = optimistic time + 4*most likely time + pessimistic time
6