Professional Documents
Culture Documents
A. Safety Notices:
1. Installation and maintenance/servicing are to be performed only by trained and
qualified personnel familiar with commercial refrigeration systems.
2. Ensure that all field wiring conforms to the equipment requirements and all applicable
local and national codes.
3. Disconnect all power sources before servicing the refrigeration equipment.
4. Sheet metal and coil surfaces have sharp edges. Use appropriate protective gloves to
prevent injury.
5. Use appropriate eye protection during installation and servicing.
B. Pre-Start Checks:
1. Verify that all service valves are fully open.
2. Ensure that all refrigerant and electrical connections are tight.
3. Verify that the wiring and piping is properly routed and secured.
4. The compressor mounting bolts are properly adjusted .
5. All fan motors and mounting brackets are tight.
6. The condensing unit base and evaporator coil are properly secured
C. Installation:
At the time of installation, following points should be noted to ensure proper installation
2. Ducting
a. Joints for ducts are made as per Indian Standard specifications
b. To give rigidity to ducting , angle iron frames should be fitted from outside at regular
intervals
c. Care should be taken of aesthetics while ducts pass through occupied spaces
d. Insulation should be fire proof. Glass wool pads are safer and easy to install. However
these are covered by wire mesh and plastered with cement for longer life etc.
3. Refrigeration Plant
a. If more than one AHU is to be served by a plant , then chilled water system is used.
Therefore a chillers of adequate capacity is installed in a plant room.
b. The chilled water pipes should be properly insulated and protected against physical
damage. If these are located underground wherever possible , the damage can be avoided.
c. The condenser should be located below or above a compressor to reduce piping and make
installation more compact.
d. The piping should be supported from ceiling or from sides to prevent vibrations. Excessive
vibrations may lead to opening of joints.
e. Cooling tower if natural should have adequate open space for natural wind
f. A water softening plant should be used if the source of water is hard water.
g. Adequate ventilation should be maintained in plant room etc.
E. Performance Tests
a. Phase I Tests: This is carried out before acceptance of the plant and before formal
Completion. Such test is carried out to test the system rigorously and in diligent manner. If
this test is carried out correctly
b. Phase II Tests: Plant is again tested in next one year during seasons other than the seasons
of Phase I Test.