Professional Documents
Culture Documents
Arm pod
Page 1 of 7
For terms and conditions of use visit excatech.org
Excatech.
“Fix it once avoid hit and miss techniques”
A common requisite of excavator operators in the North of America is that the raising and lowering of the
boom (Hoist) should be controlled by the left control lever, whilst the arm (Stick) in and out should be
controlled by the right side lever.
For the purpose of this document the focus will be to make the change in this example, however the priciple
method may apply to other patterns of operation.
Buffy
Arm pod
Page 2 of 7
For terms and conditions of use visit excatech.org
Excatech.
“Fix it once avoid hit and miss techniques”
Circuit diagram
2 T 2 T
3 1 3
P P 4
4
Page 3 of 4
For terms and conditions of use visit excatech.org
Excatech.
“Fix it once avoid hit and miss techniques”
Option 1 Remove the arm pod covers so that you may access the remote control valve fixings.
Tip if the pod forms part of the adjustable seat, slide the seat backwards this will normally allow more
hose flexibility.
Mark the hoses to be removed to avoid mistake, note manufacturers often mark the ports in some way.
Most if not all valves will have six hose connections, four of which are service ports and the remaining
two are pressure (feed “P”) and tank (or drain “T”).
Note changing the connections at the remote control valve avoids valve issues downstream.
Remove the hose’s and arrange the relevant run to both left and right remote control valve.
It may be necessary to cut plastic tie raps these will require replacement is chaffing is to be avoided.
Ports 1-2-3-4 are regulated secondary pressure (0> <
pilot pressure) these will connect to each end of the
main valve operating spool.
The pressure varies from zero to full pilot pressure in
ports 1 to 4.
Port “P” is that which has a fixed pilot or servo pressure
whilst the machine is running (Input).
The “T” or drain ports connect to the tank please be
aware that fluid will continually run from open lines and
T ports so be prepared and have those caps and plugs
ready.
P
Page 4 of 7
For terms and conditions of use visit excatech.org
Excatech.
“Fix it once avoid hit and miss techniques”
Port 2 Port 2
Port 4 Port 4
Buffy
Page 5 of 7
For terms and conditions of use visit excatech.org
Excatech.
“Fix it once avoid hit and miss techniques”
Option 3 The following information illustrates that of a solenoid valve installation however the principle
and method remains the same whichever component is chosen for the machine.
Hoses and connectors will be required during installation and the provision should be planned prior to
execution of the actual task.
This option requires electrical connection to activate the pattern change; an important point to be taken
into account is that in the event of an electrical failure the valve will adopt the default position marked
with blue highlight.
Tip connecting the valve power feed via the cabin lock out circuit will prevent unpredictable operation in
the event of power failure.
Note that excavators of today rely on electrical processor units; these devices are vulnerable to voltage
spikes.
Solenoids when deactivated can generate such spikes, to prevent damage the coil should have either a
quench diode or resistor installed, your supplier should be able to make this provision at the point of order.
Page 6
For terms and conditions of use visit excatech.org