Details of Inspection Activities at Fabcon As On 11th February 2020 Is As Below
Details of Inspection Activities at Fabcon As On 11th February 2020 Is As Below
Dear Marco,
Pipings final review not done, SGF AGF K.O.Drums not done.
RT Film Review for Pipings balance.
All Post Painting works of both K.O.Drums balance.
o NAMEPLATE CHECK,
o MANUFACTURER DATA REPORT,
o SPARE PARTS CHECK,
o PACKING, MARKING & SHIPPPING,
o DOCUMENTATION REVIEW OF MDR,
o FINAL INSPECTION RELEASE NOTE / CERTIFICATE
Different Reports (RT, pickling, ) to be provided or changed, calibration
certificates of pneumatic test gauges, surface profile gauge , ASNT Level
2, Coating Inspctor certificates to be attached in MRB.