Professional Documents
Culture Documents
Lieferant / Supplier
Seitenanzahl Format
Originator Document Number
Page Number
21054-409-10 1 of 26
33 A4
21055-409-10
21056-409-10
Dokumententitel / Document Title: Unid
Änderungen / Changes:
0 09-Jun-16 EH OO
Jun 09, 2016 LFER PSME First issue
Reviewed Approved
Rev. Date Prepared by Remarks
by by
Amendment to NEM standard specification for
fabrication and supply of Piping (IKZ 09 409-10)
Project
1 Scope
ASME I ed. 2015
2 Engineering
(not amended)
7 Documentation
(not amended)
8 Relevant documents
Following documents are relevant and included in this specification unless indicated otherwise:
IKZ09 309-01, Standard specification for Tolerances.
IKZ09 713-10, Standard specification for marking, packing and notification (not included in this specification).
IKZ09 784-01, Buyers project specification for painting and corrosion prevention (not included in this specification).
IKZ09 900-20, Instruction document numbering (not included in this specification).
IKZ09 909-00, Glossary of terminology used in standard specifications. Comentado [u2]: 8 documentos relevantes
IKZ09 909-10, Instruction for compilation of manufacturing data records. Los siguientes documentos son relevantes e incluidos en esta
especificación a menos que se indique lo contrario:
IKZ09 909-12, Instruction for heat treatment of ferritic steels.
IKZ09 309-01, especificación estándar para tolerancias.
IKZ09 909-16, Instruction for cleanliness and preservation. IKZ09 713-10, especificación estándar para marcado,
IKZ09 909-20, Requirements for ASME Boiler/pressure parts manufacturing. embalaje y notificación (no incluida en esta especificación).
IKZ09 784-01, especificaciones del proyecto de compradores
Following documents are not relevant for this project: para pintura y prevención de la corrosión (no incluidas en esta
IKZ09 909-11, Instruction for hardness testing. especificación).
IKZ09 909-14, Instruction for fabrication and supply of 9Cr-1Mo modified materials. IKZ09 900-20, numeración de documentos de instrucciones
(no incluida en esta especificación).
IKZ09 909-15, Instruction for fabrication and supply of 15NiCuMo materials.
IKZ09 909-00, Glosario de terminología utilizado en las
IKZ09 909-17, Instruction for fabrication and supply of 2¼Cr-1Mo modified materials. especificaciones estándar.
IKZ09 909-21, Instruction for EN 12952 requirements. IKZ09 909-10, Instrucción para la compilación de registros
IKZ09 909-22, Instruction for PED requirements. de datos de fabricación.
IKZ09 909-23, Instruction for AS requirements. IKZ09 909-12, Instrucciones para el tratamiento térmico de
IKZ09 909-27, Instruction for fabrication and supply of 9Cr-2W materials. aceros ferríticos.
IKZ09 909-16, Instrucciones de limpieza y conservación.
IKZ09 909-20, Requisitos para la fabricación de calderas /
End piezas de presión ASME.
Comentado [u3]: Los siguientes documentos no son
relevantes para este proyecto:
IKZ09 909-11, Instrucción para pruebas de dureza.
IKZ09 909-14, Instrucciones para la fabricación y suministro
de materiales modificados con 9Cr-1Mo.
IKZ09 909-15, Instrucción para la fabricación y suministro de
materiales 15NiCuMo.
IKZ09 909-17, Instrucción para la fabricación y el suministro
de materiales modificados 2¼Cr-1Mo. IKZ09 909-21,
Prep'd:
Instrucción para los requisitos EN 12952.
IKZ09 909-22, Instrucción para requisitos de PED.
Printdate: 14-6-2016 Page 1 of 1
IKZ09 909-23, Instrucción para requisitos de AS.
IKZ09 909-27, Instrucciones para la fabricación y suministro
de materiales 9Cr-2W.
Book IKZ09
Number 409-10
Rev. 3
Page 1/4
Piping
FOR
OF
PIPING
tervention points (e.g. hold, witness and random inspection
points) according to buyer’s ITP. All applicable codes, stan-
1 SCOPE dards, tolerances and acceptance criteria shall be included.
Once returned by buyer without comments, this document
1.1 This specification covers the Buyer standard re- will supersede the buyer ITP, as issued earlier.
quirements for the engineering, fabrication and supply of pip-
ing. For project specific requirements, this standard specifica- 2.4.1 Fabrication steps of each isometric shall be re-
tion shall be read in conjunction with the overruling amend- corded on a traveller specific for that component. Comentado [u5]: 1 ALCANCE
ment applicable to the project. 1.1 Esta especificación cubre los requisitos estándar del
2.4.2 In case a master traveller is used to obtain buyer’s
Comprador para la ingeniería, fabricación y suministro de
1.2 The amendment to this specification will also iden- approval, then the specific travellers shall be based on the
tuberías. Para los requisitos específicos del proyecto, esta
tify code and other (detail) specifications and instructions master traveller entries only. The specific travellers do not especificación estándar debe leerse junto con la modificación
which are applicable to the scope. need to be submitted for buyer’s approval when based on an de anulación aplicable al proyecto.
accepted master. 1.2 La modificación a esta especificación también identificará
1.3 All work executed under this specification shall be of el código y otras especificaciones (detalladas) e instrucciones
first class, made of new materials and be of good workman- 2.5 Fabricator shall uniquely identify each joint. This
will be referenced on the LISL and filled out on the As- que son aplicables al alcance.
ship. Vendor shall further ensure that execution does not 1.3 Todo el trabajo ejecutado bajo esta especificación debe
jeopardize local law and regulations at the construction site. Built version of the drawing.
ser de primera clase, hecho de nuevos materiales y ser de
Vendor is to adhere to all relevant codes, procedures and 2.6 Welding typicals shall be prepared to facilitate the buena mano de obra. El proveedor deberá garantizar además
practices, expressed or implied, to ascertain conformity to the review of welding documents by Buyer. The welding typical que la ejecución no ponga en peligro las leyes y regulaciones
intent of this specification. will address all joint configurations applicable to the project locales en el sitio de construcción. El proveedor debe
with cross reference to the selected WPS. adherirse a todos los códigos, procedimientos y prácticas
1.4 A clarification of the terminology used in this speci- relevantes, expresas o implícitas, para determinar la
fication can be found in instruction 909-00. 2.7 Preparation of WPS/PQR: conformidad con el propósito de esta especificación.
a) WPS must be submitted for every weld configu- 1.4 Una aclaración de la terminología utilizada en esta
ration and each material type. especificación se puede encontrar en la instrucción 909-00.
2 ENGINEERING
b) Each WPS shall be supported by a PQR. Comentado [u6]: 2.2 Una actividad de fabricación,
2.1 Fabricator is to submit the documents as per VDRS; c) WPS shall identify actual brand and type of soldadura o ECM no puede iniciarse antes de que el
the following documents are required as a minimum: filler metal. Comprador haya revisado la documentación relacionada
a) WPS/PQR and test procedures. d) Thermocouple welding require WPS to be sub- según VDRS.
b) Weld matrix, showing WPS’s planned to be used mitted. Comentado [u8]: 3.1 La certificación del material debe
for the project cumplir con EN 10204-3.1 como mínimo para partes que
c) Other documents as per applicable VDRS contienen presión y otras partes unidas permanentemente a la
3 QUALIFICATIONS AND CERTIFICATION misma.
2.2 A manufacturing, welding or NDE activity may not
be started before the related documentation as per VDRS has CERTIFICATION OF MATERIALS Comentado [u7]: 2.3 Los planos generados por el
been reviewed by Buyer. comprador y los certificados de material de emisión libre
3.1 The material certification shall comply with EN
serán emitidos por el comprador con una transmisión. A
2.3 Buyer generated drawings and free-issue material 10204-3.1 as a minimum for pressure containing parts and menos que se identifique específicamente como de
certificates will be issued by buyer with a transmittal. Unless other parts permanently joined to it. información, el vendedor considerará estos documentos como
specifically identified as being for information, vendor shall PERSONNEL
"aprobados para la construcción".
consider these documents as being “approved for construc-
tion”. 3.2 Welder’s Qualifications shall be made available. Comentado [u9]: 3.2 Las calificaciones del soldador
For special materials (e.g. P91), critical welding positions estarán disponibles. Para materiales especiales (por ejemplo,
2.4 A (master) traveller (including sample LISL) shall be (e.g. poor accessibility) or questionable results during fabri- P91), posiciones de soldadura críticas (por ejemplo,
prepared by fabricator as a sequential plan, including the in- accesibilidad deficiente) o resultados dudosos durante la
cation Buyer may request additional qualifications.
fabricación, el Comprador puede solicitar calificaciones
adicionales.
Book IKZ09
Number 409-10
Rev. 3
Page 2/4
Piping
3.3 NDE personnel shall be qualified according stan- 4.15 All welds and surrounding areas shall be chipped,
dards acceptable to the code. ground, or wire brushed to remove all flux, scale and spat-
ter.
5.4 Welder performance qualifications and LISL’s shall Comentado [u11]: 4.9 Las pasadas de raíz de penetración
WELDING
be available at Fabricator’s premises for review on Buyer completa de un solo lado deben hacerse con GTAW.
4.10 Single pass welding in pressure retaining joints is request.
prohibited.
NDE GENERAL
4.11 Socket connections shall have a gap of 2mm between Comentado [u17]: 5.5.1 Cuando se aplica RT de rayos,,
pipe end and bottom of the socket. 5.5 Non destructive examination (NDE) shall be car- solo se seleccionará Ir 192 como fuente a menos que el
ried out after the procedures have been reviewed by Buyer. Comprador acepte lo contrario.
4.12 Use of low carbon filler metal (C%<0.05) for weld-
ing creep resistant CrMo-steel is prohibited. 5.5.1 Where -ray RT is applied, only Ir192 shall be se- Comentado [u18]: 5.5.2 Donde deba realizarse la
lected as source unless specifically accepted otherwise by detección de defecto de superficie (es decir, MT, PT), esto
4.13 Dissimilar joints between ferritic and austenitic steel Buyer. debe hacerse después de PWHT (en caso de que se requiera
shall be welded using E(R)309 filler metal for service tem- este tratamiento).
5.5.2 Where surface defect detection (i.e. MT, PT) shall
peratures below 300°C. For service or PWHT temperatures
above 300°C filler metals ERNiCr-3 or ENiCrFe-2, ENiCrFe-
be performed, this need to be done after PWHT (in case this Comentado [u12]: 4.13 Las uniones desiguales entre el
treatment is required). acero ferrítico y austenítico se deben soldar con metal de
3 shall be selected.
aporte E (R) 309 para temperaturas de servicio inferiores a
5.5.3 Repairs shall be examined by the same technique
4.14 Weave width of deposited beads shall be limited to 300 ° C. Para temperaturas de servicio o PWHT superiores a
that revealed the initial defect.
10mm for GTAW, 15mm for FCAW and 3 times electrode 300 ° C, se deben seleccionar los metales de relleno ERNiCr-
diameter for SMAW. 3 o ENiCrFe-2, ENiCrFe-3.
Comentado [u13]: 4.14 El ancho de tejido de las perlas
depositadas se limitará a 10 mm para GTAW, 15 mm para
FCAW y 3 veces el diámetro del electrodo para SMAW.
Book IKZ09
Number 409-10
Rev. 3
Page 3/4
Piping
6.1 Goods shall be stored under cover, free from the 8.10 IKZ09 909-14, Buyer’s instruction “Fabrication of
ground. Piping etc. shall be stored on a slope. 9Cr-1Mo modified materials”.
Book IKZ09
Number 409-10
Rev. 3
Page 4/4
Piping
STANDARD SPECIFICATION
FOR
TOLERANCES
Book IKZ09
Number 309-01
Rev. 0
Page 2/2
Tolerances
Book IKZ09
Number 909-00
Rev. 4
Page 1/5
Definition of terminology
GLOSSARY
OF
TERMINOLOGY USED
IN
STANDARD SPECIFICATIONS
1.9 Buyer shall mean any company belonging to the
1 DEFINITIONS NEM group issuing a purchase order or a party enforcing
a buyer (group) frame agreement.
1.1 Abrasive blasting is the method to clean steel
surface using particle impact energy. Particles shall be 1.10 Client shall mean Buyer’s customer.
inert to the subsequent processes, e.g. grit or steel shot of 1.11 CMTR, or Certified Material Test Record. Test
compatible metal or Garnet (Almandite) with less than results as demanded by the material specification shall be
1% free Silica (SiO2). Sand is prohibited for abrasive certified by a quality department of the material producer
blasting on water/steam side and should in general be that is independent from the production department.
avoided for health considerations and silica contamina- Scope and responsibilities is identical to an EN10204-3.1
tion of boiler parts. type certification.
1.2 AI(A) or Authorised Inspector (Authorised In- 1.12 CoBo, or Competent Body, is an entity estab-
spection Agency), Inspection authority for ASME code lished in the European community. For PED projects a
design and manufacturing. CoBo is commonly involved in auditing (production)
1.3 Alloy steel, in the context of this specification, is quality systems for material manufacturers.
a steel composition where elements are added on purpose 1.13 Code shall mean fabrication, testing and/or de-
to improve steel properties. In high alloyed steels the sum sign regulation or standard.
of alloying elements is greater than 5%.
1.14 Cold forming is defined as a deformation process
1.4 And/Or may be used to indicate the applicability that takes place at a temperature below the maximum al-
of a case to one or more conditions. Those conditions are
lowable PWHT temperature specified for the material
not necessarily exclusive. The term –although gramati-
grade concerned. See also hot forming.
cally and logically unsound– is used to avoid the logically
correct use of “or” as this is often incorrectly interpreted 1.15 Cruciform joints are three members joined by a
as a mutually exclusive condition. (groove and-) fillet weld. Two members are not necessar-
ily perpendicular to the third, but are aligned with each
1.5 Basic arrangement drawing contains lay out, ma-
other, usually forming a cross when viewed in cross-
terials, beam sizes, tolerances and applicable calculations
section.
and design specifications.
1.16 CVN stands for Charpy-V Notch impact test. Test
1.6 BM means base metal, i.e. the two main bodies
results are expressed in absorbed energy at a predefined
forming a joint, fused by WM (weld metal).
test temperature, e.g. 27J @ 21°C
1.7 Bundle is a set of tubes in between two or more
1.17 Default is a value used when none has been
manifolds. Tubes are generally connected with elbows to
given. Often used attributively, e.g. default value.
form multiple pass in the gasflow. Typically, the tubes
are supported by tubesheets. This assembly is the heat 1.18 Demand Critical Welds are welds that are a part
exchanging element for a boiler with a vertical exhaust of seismic load resistance system that are deemed to be
gas flow. In smaller configurations, vertically arranged critical, since they are designed to transfer important
bundles can be applied in a horizontal gasflow. earthquake loads.
1.8 Butt joint is a joint between two members 1.19 Dimensions in this specification are in millime-
aligned approximately in the same plane. Weld between tres unless noted otherwise. (Where indicated, inches may
header and forged flat cover shall be considered to be a be used).
“butt joint”
1.20 DFT means Dry Film Thickness.
Book IKZ09
Number 909-00
Rev. 4
Page 2/5
Definition of terminology
1.21 Drawings and specifications will be referred to 1.37 Hot forming defined as a deformation process
by their 5 digits in a xxx-xx format. that takes place at a temperature above the maximum al-
lowable PWHT temperature specified for the material
1.22 Engineering shall comprise all vendor actions in grade concerned. See also cold forming.
the fabrication stadium necessary as preparation or sup-
port the actual production. Reference to documents previ- 1.38 HRSG stands for Heat Recovery Steam Genera-
ously approved by Buyer might suffice if appropriate to tor.
the scope.
1.39 Instructions, IKZ09 909 series, define require-
1.23 Enhanced materials are those material grades ments on a specific topic to complement the main specifi-
where properties are improved by modification of the cation. Instructions may refer to other instructions.
chemistry in combination with a specific thermal treat-
ment. Often these materials require extra attention during 1.40 ITP stands for Inspection and Test Plan. Issued
manufacture, fabrication and heat treatment. Examples by buyer, it indicates the inspections and tests required
are: P23, P91, 15NiCuMo. together with the intervention points for parties concerned
as known at time of issue.
1.24 ESR, or Essential Safety Requirement, is a set of
requirements that need to be fulfilled for PED projects. 1.41 Joint is the generic term for a welded connection
The ESR’s can be found in 97/23/EC (PED), annex I. of any type (butt-, fillet-, seal-, etc.).
1.25 Fabricator shall mean the party responsible for 1.42 K-Area, applicable to rolled profiles in seismic
the physical execution of the contract. In those cases loaded structures (SLRS), designate the volume of a web
where the fabricator received the purchase order from where it meets the radiused transition with the flanges,
buyer directly, vendor and fabricator shall be considered see picture.
one entity.
1.52 N+T stands for normalizing and tempering heat 1.69 Review will result in a document status. See in-
treatment. struction 900-20 for description of status indicators.
1.53 Outlet duct is a transition duct between boiler 1.70 Ronnie is a solution to a problem that did not ex-
casing and stack. ist before, often leading to problems that cannot be solved
anymore. Named after a facilities manager, in apprecia-
1.54 Out-of-roundness (%) of pipe or tube bends shall tion.
be calculated using the following relation:
dmax - dmin 1.71 RTPO or Recognised Third Party Organisation is
Out-of-roundness (%) = an entity established in the European community. For
X X 100
2 dmax + dmin PED projects, a RTPO can perform the procedure and
personnel qualifications (PQR, WPQ and NDE).
with: dmin = minimum diameter
dmax = maximum diameter
and dmin dmax 1.72 SAT shall mean Site Acceptance Test.
1.55 Ovality see out-of roundness 1.73 SAW is Submerged Arc Welding.
1.56 P23 is a generic term for all 2¼Cr-1Mo modified 1.74 Secondary steel covers railing, platforms, lad-
materials, e.g. grade T23, grade F23, grade 23, ders, stairs, kick plates, grating, silencer supports and
7CrWVMoNb91, etc. bracings.
1.57 P91 is a generic term for all 9Cr-1Mo modified 1.75 SLRS is Seismic Load Resistance System.
materials, e.g. grade T91, grade F91, grade 91, WP91,
X10CrMoVNb91, C12A, etc. 1.76 SMAW is Shielded Metal Arc Welding.
1.58 PBHT is Post Bend Heat treatment. 1.77 Softcopy is a digital representation of the re-
quired data. This is usually in the form of a scan that is
1.59 PED is the Pressure Equipment Directive, saved as Adobe’s Portable Document Format (PDF) file.
97/23/EC, of the European community. Note that specific requirements to the scan quality may
apply.
1.60 Pipe is used, as distinguished from tube, to apply
to tubular products of dimensions commonly used for (in- 1.78 Specifications define requirements on specific
terconnecting) piping systems. Pipe dimensions of sizes products. Specifications refer extensively to obligatory
12” and smaller have outside diameters numerically lar- supporting instructions.
ger than their corresponding size denominator.
1.79 Spot examination defines the extent of examina-
1.61 PMA stands for Particular Material Appraisal. tion. The amount of tests required (i.e. the value of the
This is a material grade and type specific inventory of variable “spot”) is defined on the amendment and can dif-
(additional) requirements to adhere to in order to have fer per project.
non EN harmonized material comply with PED essential
safety requirements. 1.80 Stack is a self supporting structure, designed for
the vertical transport of forced or natural draft fluegases.
1.62 PMI stands for Positive Material Identification. It excludes the outlet duct.
A method to detect alloying elements in metal to ascer-
tain use of correct metals. Usually a portable device 1.81 Strain (%) in outer fiber (extrados) on bending
based on X-ray fluorescence. plate, tube or pipe, shall be calculated using the following
relation:
1.63 PQR is a (welding) Procedure Qualification Re- D
cord. bending strain (%)= X 100
2R
1.64 Protected zone is a designation to areas in struc-
with: D = outer diameter of tube/pipe bending, or
tural members used in the AISC seismic design (SLRS) D = thickness of plate bending
where specific (and restrictive) fabrication requirements R = bending radius along neutral axis
apply.
1.82 T-Crossing is where butt joints in a plate field
1.65 PWHT is Post Weld Heat Treatment. join at an angle in the same plane.
1.66 Raw materials are construction materials, e.g. 1.83 T-Joint is two members joined by a (groove and-)
bare tube, pipe, fittings, rods, forgings, wrought, rolled fillet weld. The members are not necessarily perpendicu-
and cast products, which are meant for fabricator’s action lar to each other.
under this specification. Bends made out of straight pipe
1.84 TC is abbreviation used for Thermocouple.
or tubes are not considered being raw material.
1.85 Temperature controller is an instrument control-
1.67 Reading is the result of one hardness test inden-
ling the heat source to achieve temperature set point, rate
tation.
of heating and rate of cooling.
1.68 Release Note is issued at the fabrication locations
1.86 TOFD stands for Time Of Flight Diffraction.
indicated in the ITP once the buyer representative is satis-
fied the quality and quantity as called for are met.
Book IKZ09
Number 909-00
Rev. 4
Page 4/5
Definition of terminology
Next day
production
Spot Examina- 2x Spot
tion
100%
Y N
OK?
Next day Y N
OK?
production
Book IKZ09
Number 909-10
Rev. 1
Page 1/2
Compilation of Manufacturing Data Record (MDR)
INSTRUCTION
FOR
COMPILATION
OF
MANUFACTURING DATA RECORDS
e) Each volume shall be marked with buyer’s pro-
ject number and volume number.
1 OBJECTIVE f) Each volume shall contain a main list of con-
tents with reference to part, volume number,
1.1 This instruction covers the buyer standard mini- chapter and paragraphs, for all included docu-
mum requirements for the compilation of final manufactur- mentation.
ing data packages. These packages shall describe the
buyer-approved results of production steps for subcon- 1.7 The vendor shall file all the relevant documents and
tracted parts, bought-out items, engineered equipment and supporting records (e.g. RT films) in a conditioned area for a
erection. period of 15 years. These documents/records shall be sub-
mitted to buyer upon request.
1.2 The manufacturing data record shall be compiled
in accordance with this specification, and shall: 1.8 The manufacturing data record shall be reviewed
a) contain all the information as required per during the final inspection and stamped by buyer’s QC de-
vendor document requirement sheet and reflect partment. The original shall be sent to buyer.
the fabrication history of the produced parts,
b) provide all information necessary for commu- 1.9 Notes on the use of typical index:
nication about the produced parts, a) These instructions do not replace any other re-
c) state the compliance with PO number, appli- quirement for authority documentation; these
cable code and specification by certificate of books shall be compiled and issued separately.
compliance, written in the contract language b) It is understood that control methods during
and manufacturing can result in final documentation
d) be legible and suitable for reproduction. compilation that differs from the Typical index.
This is acceptable provided the information as
1.3 Originals shall be provided where practicable. prescribed in this specification is available and
traceable to the manufactured parts described.
1.4 Each manufacturing data record submitted by the c) The sequence as indicated below under Typical
fabricator/vendor to buyer shall contain the contents as de- index is preferred as it enables swift review.
scribed below. For chapters, which are not applicable, the Each topic, where applicable, shall start with a
list of contents shall state “not applicable”. new sub-number (e.g. RT test reports will ap-
1.5 The manufacturing data record shall be compiled pear in paragraph. 11.1).
progressively during the fabrication. Proof of same will be d) Documents required as per contract, either for
demonstrated to the satisfaction of buyer’s QC department. review or to support requested information shall
be incorporated in manufacturing data record.
1.6 One manufacturing data record shall be compiled e) Italicised text is for reference and shall be de-
per purchase order. leted in case paragraph 2 is used as general in-
a) All volumes shall be filed in secured bundles, dex.
size: A4, four holes drilled in ‘888’ pattern. f) Pages shall be numbered sequentially starting
Folders or binders are not required. Drawings, with each chapter.
reduced to A3 size, shall be folded to A4. g) Procedures and other documents that have been
b) Each volume shall include a front sheet. submitted to and accepted by NEM shall bear
c) All documents/sheets shall be marked with visible proof of such acceptance.
document number and buyer’s project number. h) Data shall be provided as required by code or
d) The documentation shall be divided into sec- regulation applicable to country/state of ultimate
tions, sections into chapters and chapters into operation.
paragraphs.
Book IKZ09
Number 909-10
Rev. 1
Page 2/2
Compilation of Manufacturing Data Record (MDR)
2 TYPICAL INDEX
1. GENERAL TABLE OF CONTENTS
In addition to this, each volume shall have its own table of contents
2. RELEASE NOTES
Issued and signed by all parties concerned.
3. CERTIFICATE OF COMPLIANCE
See paragraph 1.2c).
6. INSPECTION PLAN
TRAVELLER
Signed off at relevant points by all parties identified.
7. PROCEDURES
Non-Destructive examination
RT, MT, PT, UT
Testing
Pneumatic, Hydraulic, Destructive, Hardness
Metallurgical
PMI, Ferrite, Chemical analysis, Etching, Replica
Fabrication
WPS/PQR, Repair, Lining, Welder performance qualifications summary list
Surface treatment
8. DRAWINGS (AS-BUILT)
Dimensioned outline drawings and weights
Cross sectional drawings, including parts list
Material take off
Isometrics
9. MATERIAL CERTIFICATES
Component certification (e.g. Nema, EexD etc.)
Also for welding material. An index, referring to the physical location of material is being used, shall be included in
this section. All material where certification is required as per VDRS shall be incorporated, documented according to
EN10204-2.2, 3.1 or 3.2.
1
Hardness test results shall be made available to NEM separate from the MDR by default. Only on specific request from NEM results of hard-
ness tests are to be incorporated in the MDR.
Book IKZ09
Number 909-12
Rev. 2
Page 1/7
Instruction for heat treatment of ferritic steel
INSTRUCTION
FOR
HEAT TREATMENT
OF
FERRITIC STEEL
2.5 PWHT shall not exceed the lower transformation
1 SCOPE temperature (Ac1). Lower transformation temperature de-
pends on the chemical composition and may differ for weld
1.1 To ascertain proper heat treatment this instruction and base metal in which case the lowest is governing.
shall be observed for heat treatment of ferritic steel, i.e. car-
2.5.1 PWHT at a temperature higher than the tempering
bon and (low) alloy steel, including enhanced materials. This
temperature used during manufacturing of raw material may
instruction provides proper selection and application of heat
result in decrease of tensile strength. Buyer shall be re-
treatment and furnace survey.
quested for disposition in case PWHT temperature would ex-
ceed the tempering temperature recorded on CMTR.
2 HEAT TREATMENT 2.5.2 PWHT temperature close to the lower end or around
the mid of the specified range prevents possible over-
2.1 Heat treatment shall be performed in accordance tempering, i.e. a drop in tensile properties.
with project related (and code) requirements. In case of any
conflict between instructions below and project specific re- 2.5.3 Total duration at specified PWHT temperature shall
quirements, the most stringent is applicable. be 10 hours maximum. This applies for each individual joint.
If more than one cycle is applied the total duration shall be
2.2 Fabricator shall provide a written instruction to fur- determined by summation of all individual holding times
nace operator. from the separate PWHT cycles. Comentado [u22]: 2.5.3 La duración total a la temperatura
2.3 General 2.5.4 Normalizing of carbon and low-alloy weld metal de PWHT especificada será de 10 horas como máximo. Esto
may cause a drastic drop in tensile strength. However, P91 aplica para cada articulación individual. Si se aplica más de
2.3.1 Post weld heat treatment is typically used to lower weld metal properties will not be affected by N+T. un ciclo, la duración total se determinará sumando todos los
internal stresses, i.e. stress relieving. tiempos de espera individuales de los ciclos de PWHT
2.5.5 Holding time at normalization temperature shall be separados.
2.3.2 PWHT temperature holding time and gradients if not
limited to prevent excessive grain growth.
detailed in paragraph 2.8 can be found in the applicable pro-
2.5.6 During heating, holding and cooling, the furnace at-
ject specifications and/or code. Comentado [u21]: 2.3.2 El tiempo y los gradientes de
mosphere shall be controlled so as to avoid excessive oxida- mantenimiento de la temperatura del PWHT, si no se detalla
2.3.3 PWHT temperature shall be controlled to the nomi- tion.
nal temperature. en el párrafo 2.8, pueden encontrarse en las especificaciones
2.5.7 During complete heat treatment cycle the compo- y / o códigos de proyecto aplicables.
2.3.4 Normalizing and tempering is typically applied to nents shall be adequately supported to prevent distortion.
obtain the required properties of the raw material, e.g. for Cr- Comentado [u23]: 2.5.7 Durante el ciclo completo de
Mo steels. 2.5.8 In case burners are used as heating source, the fuel tratamiento térmico, los componentes deberán soportar
shall not contain any detrimental elements. Furnace shall be adecuadamente para evitar la distorsión.
2.3.5 Normalizing and tempering can be used to restore equipped to avoid flame impingement on the objects.
mechanical properties, after e.g. hot forming or wrong
PWHT. Note that this is only effective when the complete 2.6 Furnace or local heat treatment
object can be subjected to this heat treatment.
2.6.1 Piping spools, drums and individually heat treated
2.3.6 Normalizing without subsequent tempering is ap- headers shall have PWHT in a batch type furnace, e.g. a top-
plied to improve or restore mechanical properties of unal- hat furnace.
loyed carbon base material, especially toughness.
2.6.2 For harp assembly, i.e. header joints, header to fin-
2.4 Heat treatment shall not deteriorate materials prop- tube joints or weld-end to (fin)tube joints shall be heat
erties. treated in one cycle in a clamshell furnace. Where the header
already received a PWHT than this cycle shall be taken into
account with respect to paragraph 2.5.3.
Book IKZ09
Number 909-12
Rev. 2
Page 2/7
Instruction for heat treatment of ferritic steel
2.6.3 Local PWHT of joints in piping shall be done by re- 2.9 Temperature variation.
sistance or induction heating in accordance with Figure 1 for
2.9.1 Maximum allowable temperature variation during
butt joints.
holding at heat treatment temperature is 30 °C. In case of
2.6.4 Local PWHT of piping branch connections may only P91 the variation shall be 20°C maximum.
be done in accordance with Figure 3 after Buyers acceptance.
2.9.2 Minimum holding temperature shall be achieved for
2.6.5 Local PWHT of joints to ‘olets, nozzles or stubs and the specified holding time as minimum.
the like shall include provisions to avoid detrimental effects
2.9.3 Furnace shall be loaded in such a manner that the
on the run line, see also 2.7.4. Thermocouple shall be placed
(heat flow) situation is identical for all welds subjected to the
at location “TC3” (see Figure 3), whereby:
heat treatment cycle.
0°C ≤ T weld − TC3 ≤ 250°C
2.10 Thermocouples and recording equipment
with: Tweld = PWHT temperature at weld
TC3 = Temperature measured at TC3 location 2.10.1 Sufficient thermocouples shall be applied to the
work piece to obtain the highest and lowest material tem-
2.6.6 In case of normalizing, the entire component (or perature attained during the heat treatment.
complete structure) shall be subjected to N+T cycle.
2.10.2 Thermocouples shall be attached by capacitor dis-
2.6.7 Furnace and heat treatment equipment used for P91 charge welding.
and 15NiCuMoNb5 shall be certified by furnace survey in
2.10.3 Steering TC shall be attached at locations represen-
accordance with paragraph 3. Further, a furnace survey may
tative for complete furnace load and to a Temperature Con-
be required to check the performance of heat treatment
troller at the other end.
equipment used for other materials.
2.10.4 Steering TC shall be attached at the location where
2.7 Heating pad placement the highest temperature input is expected.
2.7.1 Equipment used for local PWHT shall be so ar- 2.10.5 Typically, steering TC and controller will not be
ranged that the weld and the base materials on both sides are used to chart the heat treatment curve.
heated in such a manner that uniform heating without distor-
tion can be achieved. 2.10.6 For local PWHT, each graph shall represent one
joint. One PWHT cycle on more than one joint may be com-
2.7.2 Due consideration for difference in thickness shall bined in one graph after buyer’s prior approval. TC set-up
be given when selecting heat input capacity. and identification shall be included on the graph.
2.7.3 Local overlapping of pads or mats (e.g. where pipe 2.10.7 Thermocouples shall be attached at a location or in a
diameter is smaller than pad length/width) is prohibited. manner so that contact with heating element and incorrect
2.7.4 Heat treatment on joints as per 2.6.5 shall include a registration of temperature is avoided.
provision to heat up run line. This to avoid local heat input 2.10.8 Temperature controllers and recorders shall be cali-
potentially leading to run line deformation. Also this will brated at a 6 month interval.
avoid the run line to act as heat sink, thus enhancing the risk
of overheating at the heat input locations (i.e. weld and/or its 2.10.9 Recording thermocouples shall be attached at loca-
joining parts). tions representative for complete furnace load to record the
complete heat treatment cycle.
2.8 Heating and cooling rate a) Minimum 6 recording thermocouples shall be
2.8.1 Heating and cooling rate shall be 220°C/hour maxi- applied for heat treatment in batch type furnace
mum. P91 and 15NiCuMoNb5 heating and cooling rate shall on the component and/or the furnace itself.
be 100°C/hour maximum. b) For heat treatment of headers in a clamshell fur-
nace recording thermocouples shall be attached
2.8.2 The temperature of the furnace shall not exceed
at the header and weld ends as per Figure 4.
300°C at the time the component is placed into or taken out
of the furnace. c) For heat treatment of stream drums the recording
thermocouples shall be attached in accordance
2.8.3 After holding at normalizing temperature the com- with Figure 5. For drums with a thickness over
ponent shall be cooled in still air or oil as specified by the 50mm TC number 2 and TC number 5 shall be
raw material specification. For thicker parts accelerated cool- attached at the inner side of the drum.
ing may be necessary. Continuous cooling diagram can be d) For heat treatment of piping spools and individu-
used for estimation of required cooling rate.
ally heat treated headers in batch type furnace
minimum of 6 recording thermocouples shall be
attached on the heat treated items at locations
nearest to bottom, top and outer sides of the fur-
nace.
Book IKZ09
Number 909-12
Rev. 2
Page 3/7
Instruction for heat treatment of ferritic steel
e) Local PWHT shall have recording thermocouples 3.2 Thermocouples to monitor time-temperature curve
attached according Figure 2 for piping butt joints shall be placed at locations in the working zone of the fur-
and according Figure 3 for branch welds in pip- nace, so that the highest anticipated temperature variation is
ing. recorded. The thermocouples shall be attached to the test
load and/or to the furnace itself.
2.11 Larson Miller Parameter
3.3 For furnace survey minimum of 12 thermocouples
2.11.1 Larson Miller Parameter can be used to express the
shall be used. A sketch shall clearly indicate the working
effect of PWHT temperature and time, using the following
zone of the furnace, the location of the test load and thermo-
relation
couple locations, identifying steering or as recording TC.
LMP= T (20+log t) 10-3
3.4 Heat treatment cycle for furnace survey shall be rep-
with: T = temperature in degrees Kelvin resentative for actual heat treatment during fabrication. In
t = holding time in hours
case of furnace survey for P91 the following heating cycle
applies.
2.11.2 LMP is only valid in the range of stress relieving
a) Heating rate up to 300°C not limited.
temperature, i.e. up to lower transformation temperature.
b) Heating from 300°C with 100°C/hour up to
2.11.3 Equal LMP for different PWHT temperatures and 760°C.
times are considered to have same effect.
c) Holding at 760°C for 2 hours.
For example, PWHT at 700°C for 1.5 hour results in a LMP
= 19.6. For a comparable PWHT at 680°C, a 4 hour holding d) Cooling from 760°C to 300°C with 100°C/hour.
time is required to have the same heat treatment effect. e) Cooling from 300°C in still air to ambient tem-
perature.
2.11.4 Ranges and temperatures as detailed in this specifi-
cation shall be adhered to. Deviation from the specified heat 3.5 Test results shall be submitted to buyer for review.
treatment range using LMP motivation may only be used on
buyer's prior consent.
2.11.5 PWHT temperatures shall be in accordance with
4 DOCUMENTATION
Table 1. Note that these temperatures apply for ASME I and 4.1 Fabricator’s heat treatment procedure shall have all
ASME B31.1 (values between brackets apply for EN pro- required information to guarantee proper heat treatment ac-
jects). For other codes or standards PWHT temperature cording contract requirements. The procedure shall be sub-
ranges may differ. mitted to buyer for review and at least address
For dissimilar joints involving P91-P22 and P23-P91, PWHT a) Item to be heat treated.
depends on the type of filler metal used. Refer to instruction
b) Type of heat treatment, i.e. furnace or local.
IKZ09 909-14 and 909-17 respectively.
c) Type of heating source, e.g. use of resistance or
Table 1 PWHT temperatures for material combinations induction heat, gas, etc.
Temperature range (ºC) d) Furnace type, with sketch of working zone.
Steel Grades CS 1¼Cr ½Mo 2¼Cr 1Mo 9Cr 1Mo V e) Number of thermocouples applied and their loca-
tions.
Carbon steel 615± 15 665± 15
[565±15] [note 1] 4.2 Actual heat treatment production data shall be com-
P11 665± 15 715± 15 piled into manufacturing data record (see buyer specification
[13CrMo4-5] [665±15] [670±10] IKZ 09 909-10). In case curve information is transferred,
proper reference to original shall be made.
P22 715± 15 735± 10
[10CrMo9-10] [695±15] [735±10]
3.1 Equipment for heat treatment shall be certified by a 5.3 Dirscherl, R., A simplified method for determining
furnace survey performed by the subcontractor and witnessed test specimen heat treatments, Metal Progress, May 1979,
by a buyers appointed engineer. Furnace certification shall be p84-87.
provided showing actual temperature on a representative ob-
ject. A furnace modification or repair requires a new survey.
Book IKZ09
Number 909-12
Rev. 2
Page 4/7
Instruction for heat treatment of ferritic steel
5.4 Spaeder, C.E. and Doty, W.D., ASME Post-Weld 5.5 Bailey, N., Weldability of ferritic steels, Abington
Heat treating practices: an interpretive report. WRC bulletin publishing, 1994.
407, p50-65.
Figure 2 Location and quantity of recording thermocouples (TC) at piping butt joints
TC
TC TC
TC
TC
OD ≤ND50 ND50 < OD ≤ ND300 OD > ND300
Book IKZ09
Number 909-12
Rev. 2
Page 5/7
Instruction for heat treatment of ferritic steel
Figure 3 Local heat treatment of branch and nozzle connections with recording thermocouple location
tb Rb
Min. Insulated
Min. Heated band width:
band width:
W TC 4* 5 R btb
TC 1
tr 2.5 Rbtb
≤ 2 tr
Rr TC 2
TC 3
TC 3 TC 4
TC 5 & 6
TC 1 & 2
View A View B
TC 7, 8
TC 9, 10 TC 11, 12
TC 1, 2
TC 5, 6
Weld-end
TC 7, 9, 11
Bare end (fin) tube
20mm
TC 8, 10, 12
TC
View A
Butt welded cover View B
Plate cover
Book IKZ09
Number 909-12
Rev. 2
Page 7/7
Instruction for heat treatment of ferritic steel
Figure 5 Recording thermocouple location for heat treatment on steam drums.
Book IKZ09
Number 909-16
Rev. 3
Page 1/2
Instruction for cleanliness and preservation
INSTRUCTION
FOR
CLEANLINESS AND PRESERVATION
3.1.6 Any oxidation near weld edge connections shall be
removed before welding.
1 SCOPE
3.1.7 Header and tube internal surface shall be cleaned
1.1 In addition to general requirements as defined in before welding (fin-) tubes.
the applicable project specifications, the instructions below
shall be observed. The intention is to arrive at a product 3.1.8 After fabrication is completed, objects shall be
condition which will not have adverse effects on further cleaned by means suitable for removing all scale, welding
work or during operation. slag and spatter or other foreign matter.
3.1.9 Hydrotested parts shall have remaining water ex-
1.2 This instruction applies to incoming raw material,
pelled.
work during fabrication and on finalized parts ready for
transport. 3.1.10 For objects with weld overlay:
a) Corrosion inhibitor shall be added to the cool-
1.3 Guidelines for extended storage of boiler pressure
ing water used during overlay welding to keep
part internals are included.
the inner side of the tubes free of corrosion.
1.4 This instruction shall be read in conjunction with For recommended corrosion inhibitor see Table
fabrication and surface treatment specifications applicable 1.
to the project. b) Contamination of high alloy weld overlay sur-
face, e.g. due to welding or grinding on carbon
and low alloy steels, shall be prevented.
2 STORAGE OF RAW MATERIALS
3.2 Projected weld areas of structural parts shall be free
2.1 Raw materials for pressure parts shall be stored from rust, varnish or other foreign matter.
under cover.
2.2 Materials shall be kept dry during storage.
4 HYDROSTATIC TESTING OF PRESSURE
2.3 Hollow sections, e.g. tubes, piping etcetera shall be PARTS
stored sloped to prevent the accumulation of water.
4.1 General
4.1.1 All water that will be brought into contact with
3 CLEANLINESS DURING FABRICATION large area’s of fabricated items, e.g. hydrostatic test, shall be
analyzed and comply with following requirements.
3.1 Pressure parts
a) pH: >6.5, <8.0.
3.1.1 All pressure parts (shell, pipe, fittings) with outer
b) Chloride: <75ppm (mg/l).
diameter of DN 80 and over shall be blasted abrasively on
in- and outside surface. c) Direct conductivity: <1000 S/cm (100 mS/m).
a) For (fin-) tubes, grit blasting is not required. d) Suspended solids: <1ppm (mg/l).
However, tube surface condition shall not e) Clear, odorless and colorless.
cause bonding failures during finning. 4.1.2 Vapour phase corrosion inhibiting preservative
b) Grit blasting shall be done before processing, shall be added to hydrostatic test water. Refer to Table 1 for
i.e. cutting and welding. Grit blasting cleanli- acceptable VpCI.
ness shall be SA2 as minimum.
c) Fabricator shall include inspection steps to ver- 4.2 Objects shall be drained after hydrostatic test. Each
ify complete removal of blast media. harp or bundle shall be placed on a rig under an angle to al-
low the hydrostatic test water to come out. After draining
3.1.2 Inside surfaces shall be cleaned before welding. the harp or bundle may be left damp.
3.1.3 Foreign matter shall be removed from tube bore by 4.3 The concentration of VpCI shall be tested and re-
sponge pigging each tube after machining and before fit-up. ported monthly.
3.1.4 Materials shall be kept dry and clean during manu- 4.3.1 The VpCI shall be suitable for the test used.
facturing.
4.3.2 Typical test method is a refractometer. A molybdate
3.1.5 Drilled holes, welding faces and tubes shall be dry, testkit can be used in case Mo is present in VpCI product.
clean and free of dirt, grease or oxides.
Book IKZ09
Number 909-16
Rev. 3
Page 2/2
Instruction for cleanliness and preservation
5 APPLICATION OF CORROSION INHIBITOR 6.1.2 All openings shall be closed with edge covering,
tight fitting and taped-off caps.
5.1 After drainage, VpCI shall be introduced into the
tubular objects within two weeks of hydrotest. The VpCI 6.2 Pressure parts without hydrostatic test at the shop
shall be suitable for fogging application as indicated in (e.g. drums, piping).
Table 1. 6.2.1 Inside surface shall be clean and dry.
5.1.1 To obtain the optimal distribution of VpCI powder 6.2.2 For drums preservation shall be in accordance to
through the harps or bundle, only two nozzles shall be left paragraph 5.2.
open. One nozzle shall serve as inlet. Another nozzle, di-
agonally across the inlet shall be left open to serve as outlet. 6.2.3 Piping shall be closed with edge covering, tight fit-
All other openings need to be capped. ting and taped caps.
5.1.2 The amount of VpCI powder to be blown through 6.3 Non-pressure parts.
the object shall be calculated on basis of object volume and 6.3.1 Exterior shall be painted with a primer, 75 m DFT
required amount of VpCI per cubic metre. See Table 1. (dry film thickness). Paint shall be so selected as to provide
5.1.3 The VpCI fogging need to continue until a “mist” for ample protection against handling and one year outside
of powder comes out of the outlet nozzle and calculated storage. Requirements of specification 784-01 will prevail.
amount of powder has been introduced into the object. If a
continuous “mist” comes out the object before the calcu-
lated amount of powder is fogged in, then reduce the veloc- 7 GUIDELINES FOR EXTENDED STORAGE
ity of fog entry and repeat operation. PERIOD
5.1.4 Openings shall be closed immediately after suc-
7.1 Fabricated parts shall be stored dry and under
cessful fogging with edge covering, tight fitting plastic
cover.
caps. Caps shall be securely taped to the protected object.
7.2 For extended storage, i.e. longer than one year after
5.2 The interior of a drum or vessel shall be provided completion.
with silica gel, the dosage is at least ½kg per m3. The inte-
rior shall be sealed from the atmosphere. The bags are to be 7.2.1 Sealing function of caps and tape shall be verified
securely fastened to the plastic caps. The amount of desic- regularly.
cant added shall be clearly indicated, detailing number of 7.2.2 Internal surface condition shall be checked periodi-
bags involved. A warning note to remove the given amount cally.
of silica gel bags before operating the unit shall be affixed
to each manhole cover. 7.2.3 Additional fogging shall be performed with VpCI
as recommended in Table 1.
7.2.4 Internal surface of drums, vessels, modules, harps,
6 PRESERVATION OF FABRICATED PARTS bundles and piping shall be checked each half-year and re-
6.1 For pressure parts hydrostatically tested at the sults reported.
shop. 7.3 Additional measures shall be taken on basis of pe-
6.1.1 Preservation shall be in accordance to paragraph 5. riodic inspections whenever necessary.
Cortec 611 Hydrotest 5-10 g/l Short Corrosive for copper and soft yellow metals
Cortec 609 Fogging 300-500 g/m3 Long Corrosive for Cu and Ni-alloys; Silica Free
Cortec 309 SF Fogging 300-500 g/m3 Long SF = Silica Free; neutral for Cu or Ni
Note 1. 1 gram per liter [g/l] = 1000 gram per cubic metre [g/m3] ≈ 1000ppm = 0.1 percent [%].
Note 2. Protection period: short = 1 month, moderate = 6 months, long = over 1 year.
Note 3. VPCI selected for hydrostatic test water and subsequent fogging shall be of same brand.
Book IKZ09
Number 909-20
Rev. 0
Page 1/2
Requirements for boiler manufacturing under ASME
REQUIREMENTS
FOR
ASME
BOILER/PRESSURE PARTS MANUFACTURING
4.2 Where indicated on buyer’s design documents, heat
1 SCOPE treatment requirements as per ASME VIII div 1 shall be ob-
served and a separate procedure is to be submitted to buyer
1.1 This instruction covers requirements for the engi- for review.
neering, fabrication and supply of boilers parts under the
ASME Boiler and Pressure Vessel Code. This instruction is
intended to inform vendor about ASME requirements spe- 5 TESTING AND INSPECTION
cifically where it relates to the scope of supply. It is not in-
tended to be an abstract, nor does it replace any section of 5.1 Boiler Proper (BP) and Boiler External Piping (BEP)
the applicable ASME code. spools are subject to code authority inspection and certifica-
tion. Non Boiler External Piping (NBEP) shall be subject to
1.2 Items and equipment manufactured under this speci- vendor’s quality system and vendor’s inspection, taking the
fication shall be code certified (ASME “stamped”) minimum requirements as per ASME B31.1 into account.
5.2 Drums are subject to code authority inspection.
2 ENGINEERING Drum will receive ASME stamp upon completion.
2.1 The applicable edition of ASME section I, B31.1, 5.3 For ASME VIII div. 1 compliant vessels observe
B16.25 and codes referenced herein shall be the codes by de- applicable joint efficiency (indicated on construction draw-
fault, unless otherwise specified by an amendment to this ing) and ASME VIII div. 1 UW-12 for extent of RT.
specification. Piping identified as boiler proper per PG-58 5.4 If RT per ASME PW-11 is applicable note that:
shall comply with ASME section I. Economiser, Evaporator and Condensate preheat sections
2.2 In case of ASME VIII div. 1 vessel(s), fabricator have water service
shall ensure that Buyer’s design data is present at time of re- Superheater and Reheater sections have steam service.
view by fabricator’s authorized inspector in order to obtain 5.5 Volumetric examinations (e.g. RT, UT) shall be per-
proper code authorization and stamp. formed before PWHT. Execution of surface defect detection
2.3 Design code jurisdiction is indicated on each iso- methods (e.g. PT, MT) shall be timed after PWHT.
metric drawing. 5.6 For procedures and acceptance criteria for inspec-
tions as per NEM requirements (see relevant specification for
fabrication) but outside ASME code scope, the following
3 QUALIFICATIONS AND CERTIFICATION shall apply. The requirements set out below are minimum re-
quirements and are irrespective of fabrication scope.
3.1 Welding Procedure Qualifications: ASME IX.
5.6.1 Visual examination (VT)
3.2 Welder’s Qualifications: ASME IX.
a) Procedure to be based on ASME V, art. 9. De-
3.3 NDE procedures: ASME V. fault (assisted) direct visual examination.
b) Acceptance criteria according to ASME I, PW-
3.4 NDE personnel Qualifications: ASNT-TC 1A (edi- 33 and PW-35 for alignment and reinforcement
tion/addendum as per ASME I A-360), minimum level II. tolerances respectively.
3.5 Welding consumables shall be provided in accor- 5.6.2 Magnetic particle examination (MT)
dance with ASME II - part C, SFA/AWS-A5.01, level of a) Procedure to be based on ASME V, art. 7. De-
testing schedule F. Alternatively, a test report conform fault colour contrast AC Yoke technique.
EN10204-2.2 can be supplied after Buyer prior consent.
b) Acceptance criteria according to ASME VIII-1,
appendix 6.
4 FABRICATION 5.6.3 Dye penetrant examination (PT)
a) Procedure to be based on ASME V, art. 6. De-
4.1 Bending and forming shall be in accordance with
fault colour contrast technique.
ASME section B31.1.
Book IKZ09
Number 909-20
Rev. 0
Page 2/2
Requirements for boiler manufacturing under ASME