Professional Documents
Culture Documents
Pipeline Start Up and Commissioning PDF
Pipeline Start Up and Commissioning PDF
Pipeline
- B. B. Prasad
Objective of the commissioning
Flash Point:
The flash point of a volatile liquid is the lowest temperature
at which it can vaporize to form an ignitable mixture in air.
Vapor Pressure:
The vapor pressure of a liquid is the pressure exerted by its
vapor when the liquid and vapor are in dynamic equilibrium.
MS 375‐412 mm Hg. ‐ 43 0C
SKO <0.1 mm Hg > 38 0C
HSD 2.12 to 26 mm Hg. > 42 0C
ATF <0.1 mm Hg > 42 0C
NAPHTHA 450‐472mm Hg. ‐22 0C
CRUDE OIL 230 – 300 mm Hg 37‐620 C
LPG > 1000 mm Hg at 250C ‐600C to ‐1040C
Preferred Liquid for Commissioning
A device that moves through the inside of
a pipeline for the purpose of cleaning,
dimensioning, sealing and inspect.
Objective of Pigging
New Pipeline
• Remove debris
• Verify ovality, dent etc
• Water filling & dewatering after hydro‐testing
• Sealing of product or water during commissioning
In Service Pipeline
• Maintain line efficiency
• Corrosion control
• Check dents, buckles and any other internal abnormality
• To minimize interface generation between two dissimilar
products
• To avoid cross‐contamination
• To evacuate the pipeline
Conventional / Utility Pigs – Different types
• To record bends,
dents, ovality, bend
radius & angle.
PIG Launching / Receiving Barrel
Commissioning of a Multi-products Pipeline
• Air from entire Pipeline is displaced with Nitrogen column using a Bi-Di Pig
• Air from entire Pipeline is displaced with Nitrogen column using a Bi-Di Pig
Commissioning Steps:
Super dry air with dew point (-) 20 deg. C will have sufficient
capacity to absorb water vapour to the extent of 30 % of
the desired capacity.
Commissioning of a Gas Pipeline
Commissioning Steps:
Super dry air with dew point (-) 20 deg. C will have sufficient
capacity to absorb water vapour to the extent of 30 % of
the desired capacity.
Commissioning of a Gas Pipeline
Commissioning Steps:
¾ Vacuum Drying
The process utilizes high capacity vacuum to reduce
pressure within the Pipeline to a level from 760 Torr to 40
Torr. At this pressure (40 Torr), any water within the
pipeline will start boiling and vaporizing.
¾ Nitrogen Purging
At vacuum level 7.6 Torr and dew point (-) 20 deg.C, the
oxygen content inside the Pipeline is 0.20%.