You are on page 1of 10

Marine Technology, Vol. 30, No. 3, July 1993, pp.

178-187

Vapor Recovery on Tankers from Design to Operation


Chris Clement 1

Vapor control legislation has presented the vessel operator with a multitude of factors that must be given
consideration during the retrofitting of a vessel vapor control system. This paper discusses notable aspects
concerning the integration of various facets of vapor control as they relate to vessel installations from
conceptual design through operation. While complete vessel collection and processing systems are
permitted by the Regulations, discussions in tllis paper are limited to vessel collection systems because,
for the most part, industry has adopted the concept of limiting vessels to the collection of vapors only,
with subsequent transfer to shoreside facilities for processing. Discussions are based on experience
gained during development of vapor collection systems for two different classes of inerted, multi-grade
cargo product tankers. Accordingly, some topics are not applicable or can be simplified when considering
installations on board tank vessels carrying si'~gle cargoes or on non-inerted tank vessels.

Introduction operations, it is t h e facility t h a t is n o r m a l l y responsible to


t a k e corrective action. As a result, t h e r e is a t e n d e n c y to view
VAPOR CONTROL legislation has presented the vessel opera- the vessel vapor collection system as a simple extension of
tor with a m u l t i t u d e of factors t h a t m u s t be given consicier- the existing inert gas a n d cargo t a n k venting system, with
ation d u r i n g t h e retrofitting of a vessel vapor control system. some additional piping and i n s t r u m e n t a t i o n .
Local and state a i r quality m a n a g e m e n t districts have man- F o r some applications, such as a single cargo vessel t r a d i n g
dated vapor control and set compliance dates. U.S. Coast between only two or t h r e e ports, simple extensions of existing
G u a r d Regulations have been p r o m u l g a t e d t h a t set m i n i m u m systems a r e often a d e q u a t e in satisfying the new regulations,
s t a n d a r d s for construction and operation. The A m e r i c a n Pe- the o w n e r ' s / o p e r a t o r ' s r e q u i r e m e n t s a n d m i n i m u m installa-
t r o l e u m I n s t i t u t e has developed and adopted guidelines per- tion cost. However, for vessels with more sophisticated cargo
t a i n i n g to s t a n d a r d i z a t i o n of the t e r m i n a l / v e s s e l interface. r e q u i r e m e n t s and m u l t i p l e port call possibilities, consider-
In addition, consideration m u s t also be given to the vessel ation of more t h a n system extensions is in order d u r i n g t h e
o p e r a t o r ' s own safety and operation requirements, special design process. Several additional factors can be identified
c h a r t e r p a r t y r e q u i r e m e n t s t h a t m a y exist, t h e size a n d type and should be evaluated. These factors include, b u t a r e cer-
of facilities t h e vessel m a y call upon, e q u i p m e n t availability, t a i n l y not limited to:
a n d t h e time available for system installation.
• Cargo operation versatility, based on the mix and quan-
This p a p e r discusses notable aspects concerning the inte-
t i t y of r e g u l a t e d and non-regulated cargoes carried,
g r a t i o n of various facets of vapor control as t h e y relate to
w h e r e a r e g u l a t e d cargo is defined as one whose vapors
vessel i n s t a l l a t i o n s from conceptual design t h r o u g h opera-
m u s t be recovered, and a non-regulated cargo is de-
tion. W h i l e complete vessel collection and processing systems
fined as one whose vapors can be vented to atmosphere.
a r e p e r m i t t e d by the Regulations, discussions in this p a p e r
• Configuration of the vapor collection piping system and
a r e limited to vessel collection systems because, for the most
its effect upon operational flexibility.
part, i n d u s t r y has adopted the concept of limiting vessels to
• P r e s s u r e drop calculations and pipe sizing to optimize
t h e collection of vapors only, with subsequent t r a n s f e r to
i n s t a l l a t i o n cost versus achievable loading rates.
shoreside facilities for processing. Discussions a r e based on
• The level of control, monitoring and a l a r m functions to
experience gained d u r i n g d e v e l o p m e n t of vapor collection
be provided in relation to necessary m a n n i n g levels
systems for two different classes of inerted, multi-grade cargo
product tankers. Accordingly, some topics a r e not applicable for p r u d e n t a n d safe operation.
or can be simplified when considering i n s t a l l a t i o n s on board • The q u a n t i t y and type of pressure safety devices installed
t a n k vessels c a r r y i n g single cargoes or on non-inerted t a n k in the system and t h e i r effect upon t a n k protection
vessels. versus nuisance vapor emissions.
• R e g u l a t o r y body considerations.
• Anticipation of f u t u r e control m e a s u r e r e q u i r e m e n t s in
Design considerations a r e a s where the vessel m a y trade.
Cargo operations versatility---Cargo operations can be di-
General--Vessel vapor collection systems a r e for the most rectly i m p a c t e d by vapor control legislation. Therefore, t h e
p a r t passive systems. Aside from some initial start-up and
required cargo operations should be clearly defined a t t h e
disconnecting procedures, vessel personnel's role is often li:m-
outset of the design. Consideration m u s t t a k e into account
ited to m o n i t o r i n g of various p a r a m e t e r s ; the facility u s u a l l y
w h e t h e r a cargo is r e g u l a t e d or non-regulated. Major opera-
controls the start-up, the recovery process and the shutdown
tions a n d factors t h a t should be considered include:
c o n c u r r e n t with cargo loading. In addition, most facilities
• Single cargo loading.
control the pressure of the vapor coming off the vessel and,
• S i m u l t a n e o u s loading of r e g u l a t e d a n d loading of a non-
therefore, correspondingly control t h e pressure in the vessel's
r e g u l a t e d cargo.
cargo tanks? W h e n variations a n d / o r upsets occur d u r i n g
• S i m u l t a n e o u s loading of a r e g u l a t e d cargo a n d discharg-
1Clement Engineering Services, Novato, California. ing of a r e g u l a t e d cargo.
Presented at the March 12, 1992 meeting of the Los Angeles Metropoli- • S i m u l t a n e o u s loading of a non-regulated cargo a n d dis-
tan Section of THE SOCIETY OF NAVAL ARCHITECTS AND MARINE ENGINEERS. charging of a r e g u l a t e d cargo.

178 0025-3316/9313003-0178500.45/0 MARINE TECHNOLOGY


• Cargo vapor compatibility considerations. required to achieve a purged state using this procedure. Short
° Housekeeping operations within jurisdictional areas. circuiting is also a distinct possibility because tank vapor
• Ballasting operations within jurisdictional areas. would be vented through the same branch line that is used
The ability to perform the identified operations at a facility to supply the inert gas.
located in an area, that requires vapor control, should be In the future, the ability to perform housekeeping functions
prioritized from most important to least important. with vapor control may become a significant issue. At present,
Piping configuration--Vapor collection piping can be ar- only one air quality management district on the West Coast
ranged in a variety of configurations to provide a wide range has adopted a control measure which regulates housekeeping
of operating capability. The configuration that best suits an activities. However, other districts are known to be consider-
individual vessel will be based on cargo, ballasting, and ing such measures and their adoption could severely limit
housekeeping operations required to be performed at the this activity in port.
facilities at which the vessel will call. Pressure drop calculations--Pressure drop calculations are
Three piping configurations that have been employed uti- necessary to evaluate existing IG piping if it is to be utilized
lize all or part of the existing deck inert gas (IG) main and for vapor collection, a n d / o r to evaluate new piping installa-
branch distribution piping to provide vapor collection capabil- tions. In addition, both U.S. Coast Guard Regulations and the
ity. These configurations from lowest cost to most expensive American Bureau of Shipping Guide require pressure drop
are (1) System 1: Single IG/Vapor Main; (2) System 2: Single calculations be performed for vessel vapor collection systems,
IG/Vapor Main with individual cargo group venting to atmo- in order to provide personnel with pressure drop data as a
sphere; and (3) System 3: Dual IG/Vapor Main configuration. function of loading rate.
These arrangements are shown in Figs. 1, 2, and 3 respec- A basic primer to performing pressure drop calculations is
tively. As with most alternatives, the lowest cost configura- to clearly and concisely define assumptions and allowable
tion also corresponds to least capable system and the highest limits. Often when it comes to pressure drop, there is an
cost configuration provides the greatest capability. inclination towards conservatism in either the assumptions
The relative merits of each configuration are compared in a n d / o r limits. A primary reason for this is that no one wants
Table 1. Of notable importance is the fact that only the dual to be party to a system that cannot achieve design flow capaci-
main system is considered to be capable of handling ties after it is constructed. A secondary cause is that the
housekeeping operations, such as hydrocarbon purging of source for certain data required for pressure drop calcula-
tanks containing vapors from regulated cargoes. In the dual tions is empirical or experimental in origin. For vapor collec-
main system, inert gas can be introduced continuously into tion systems, these two reasons are often compounded by the
a tank through one IG Main and associated tank branch fact that a vapor control system involves two separate piping
piping, and vapor (or inert gas) can be displaced out of the systems, one on the vessel and one shoreside.
t a n k and transported ashore via the other IG/Vapor main Conservatism can appear in many forms. Design facility
and its associated tank branch distribution piping. For single maximum cargo loading rates may be assigned that are
main systems, the only method available for purging is to higher than actual achievable rates. Loading rates may be
first pressurize the subject tank with inert gas, close the IG realistic, but with an unrealistic condition attached. One ex-
deck block valve, and then vent the tank to shore via the ample would be an assumption that cargo is only being loaded
IG Main, branch distribution piping, and the vapor header into one tank at the maximum cargo loading rate, when in
connection. When the tank is vented to shore, the header fact the geometry of the vessel systems would require that
valve would be closed, the deck block valve reopened and the the cargo be loaded into a minimum of two or more tanks.
process repeated. At a minimum, several cycles would be Permissible pressure drops may be unduly restrictive. Proper-

SYMBOLLIST
'a", ;£3 JC~: :.'~*," IES~EL'~@~ ~ 5J-TERrL' ~AL',{
O: :T'I S ~ r#,/ V&'tE
[
' -- r''- (q'ii~ .... ~ ~ [~ L jljlrj ¢ LLED

Ak~c,TO~

~ j ~ Pi~

I zz 1
"~._

:L: '

J* ~L_

IVY%ELvAP~. J
7'4~EU:O~] ]
i
'j,I. I B:, [ ~Jc), , rJC}. t
"L',' '} L~qr '- Th, ,.
Fig. 1 Vapor control system No. 1 piping diagram: Single IG/Vapor Main

JULY 1993 MARINE TECHNOLOGY 179


VENTBASI WITH S'rMBQ£LIS"
FLk~E ARPESTOR
(TYP 5 PLACES) VESSELVAPOR BUTTERFLY VALVE

EZ2~ P/v/v~NTVALVE
~ ( ~ BALL ) / / ~ LrQIJIO FILLED
\. ./
12" -. \. / / P/v ~BKEF'
/- \ ' FLNE
/ "-... AR~7OR
® / ,/ -,\ 8"
/ ~, pIjRDE PIP~

" :m r6Ti

~8

DECX SEAL

I ¢
\ ~ ' 8"
,\ .,"
8" 6 14" "~ /
12" / "\
\.
-'"" (S~ B~LLj \-

' \ VESSEL VAPOR

NO.6 4 NO. 5 I NO. 4 __ NO. 3 NO. 2 NO. 1 !


TANKS TANKS TANKS TANKS '-- TANFS TANKS
Fig. 2 Vapor control system No. 2 piping diagram: single IG/Vapor Main with individual group venting

S'TM~L L IS]
vENT ~$1 RISER FOR
NON EGULATEO CA.qC,O ~SSEL VAPOR
x BUTTERFLT VALVE

~] P/V V,~LVE

~' _ IOUI~ r ILLE[I


E] ~'/V B ~ E r-"

FLAME
AR~STOR

,@ P,J~E P ' ~

v,~rzdp
C:INNECTI]N

L.~ No. 6
TANk'[i
NO. 5
TAN~L
I
I_
'-
NO. 4
TANKS
NO. 3
TAN~S
'
I NO z
TANFS
A NU. 1
-ANFS
Fig. 3 Vapor control system No. 3 piping diagram: dual IG/Vapor Main arrangement

ties of the vapor composition may be conservatively esti- Figure 4 is a graph of pressure drop in a vessel vapor collec-
mated, since the composition of the mixture changes through- tion system over a range of cargo loading rates. The upper
out the loading cycle. curve represents System 1 and the lower curve S y s t e m 2. The
Effects of conservatism can be dramatic. Sophisticated, systems are identical, except that the 20-ft section of branch
easy to use and accurate pressure drop programs have been piping in System 1 is 6 in., Schedule 80 steel pipe and in
developed for personal computers which offer the designer a System 2 the branch piping has been increased to 8 in. IPS.
quick and effective tool for identifying the impact of conserva- A s s u m e for the m o m e n t that the owner has imposed a maxi-
tive assumptions. Once the piping system geometry is mathe- m u m loading rate of 18 000 bbl/hr at a m a x i m u m pressure
matically defined, the effect on variations in flow rate, pipe drop of 15 in. of water. At this pressure drop, System 1 can
sizes, and/or gas properties can be evaluated quickly, thereby achieve a m a x i m u m allowable loading rate of 16 000 bbl/hr
providing a quick and accurate tool for assessing the impact and System 2 can achieve a rate of 20 000 bbl/hr. For new
of assumptions, limits, and changes in pipe sizes. installations, the designer would select System 2 without

180 JULY 1993 MARINE TECHNOLOGY


Table 1 Relative merits of three vapor collection system configurations for inerted tank vessels
System
Item Description No. 1 No. 2 No. 3
1. Installed cost Lowest Middle Highest
2. Single cargo loading and discharge yes yes yes
3. Multiple cargo loading
multiple regulated cargoes together a yes yes yes
regulated and non-regulated cargoes together (compatible
vapors) yes yes yes
regulated and non-regulated cargoes together (incompati-
ble vapors) no yes yes
multiple non-regulated cargoes together ~ yes yes yes
4. Multiple cargo discharging
multiple regulated cargoes together ~ yes yes yes
regulated and non-regulated cargoes together (compatible
vapors) yes yes yes
regulated and non-regulated cargoes together (incompati-
ble vapors) no no yes
multiple non-regulated cargoes together ~ yes yes yes
5. Simultaneous loading and discharging
loading regulated cargo and discharging any cargo (corn yes ''d yes~'d yes
patible vapors) (3) (4) (3) (4)
loading regulated cargo and discharging any cargo (incom- no d no d yes
patible vapors) (4) (4)
loading any cargo and discharging regulated cargo (corn
patible vapors) yes yes yes
loading any cargo and discharging regulated cargo (incom-
patible vapors) no yes yes
6, Ballasting into cargo tanks yes yes yes
7. Housekeeping operations
purging vapor to atmosphere (regulated or non-regulated
vapor) yes yes yes
purging vapor to shore (regulated or non-regulated vapor) no no yes
a All regulated cargo vapors are assumed to be compatible.
All non-regulated cargo vapors are assumed to be compatible.
c Loading rate must be higher than discharge rate. Vapors displaced from tank being loaded must vent to tank being discharged
and ashore.
a IG deck block valve must be closed when discharging vapor ashore.
System description:
No. 1: Single IG/Vapor Main with common vent to the atmosphere for all tanks.
No. 2: Single IG/Vapor Main with individual cargo group venting to atmosphere.
No. 3: Dual IG/Vapor Mains with individual branch connections to each tank from each main. Each main vented separately
to atmosphere.

Pressure Drop from Most Remote Tank to Ve~,selVapor Connection. I n e r t gas systems are required to be sized to supply suffi-
~40 cient inert gas to m a i n t a i n a m i n i m u m t a n k pressure of 100
I
, z/' m m w a t e r gage at 125% of t h e vessel's m a x i m u m discharge
g 30 rate. W h e n used for vapor collection, it is cautioned t h a t t he
c i n er t gas deck distribution piping system m a y be found to be
, !
wholly i n a d e q u a t e for vapor collection. This can occur for a
20
O m u l t i t u d e of reasons. First, a growth factor of 25%, (or ot he r
justifiable growth factor), of the m a x i m u m allowable loading
~ 1o rate must be assumed in t h e calculations. Second, the facility
m a x i m u m cargo loading rate, for which t h e vessel system
m u s t be designed, m a y be substantially g r e a t e r t h a n t he ves-
15 5.0 7.5 I0.0 115 15.0 17.5 20.0 22,5 25.0 sel's m a x i m u m cargo discharge rate. Thirdly, allowable pres-
L O A D I N G R A T E (1(X~'sBarreLsper Hour) sure drops for vapor collection m a y be less t h a n t h a t permit-
+ System w/th 20 Ft. Long Section of 8" IPS Branch Piping, ted for i n er t gas distribution. Fourthly, viscosity and gas
IdenticalSystemwith 2.0Ft. Long SectJon of 6" IPS Branch PipinB. density have a substantial effect on pressure drops. For a
I) Loading a pair of wing tanks simultaneously. given volume flow rate, t h e pressure drop t h r o u g h a system
2) 25% Vapor Growth Rate assumed for both Conditions, c a r r y i n g i n e r t gas s a t u r a t e d w i t h hydrocarbon vapor will
be a p p r o x i m a t e l y 50% h i g h e r t h a n for t h e identical system
Fig. 4 Vapor recovery system pressure drop considerations
carrying only i n er t gas. This relationship is portrayed in Fig.
6 and is based on gas m i x t u r e s with the following properties:
question. However, for existing installations t h a t had 6 in.
IPS branch piping in the i n e r t gas system, b la n k e t acceptance I n e r t gas:
of the design conditions could result in the rip-out and re- Density: 0.077 l b / f t 3
p l a c e m e n t of substantial portions of existing piping. In such Viscosity: 11.5 × 10 -6 lb (mass)/ft-sec
cases, the design conditions, th e i r origin, their rigidity and I n e r t g a s / h y d r o c a r b o n vapor mixture:
the i r effect on sizing should be discussed by all involved Density: 0.1256 l b / f t 3
parties. Viscosity: 6.5 × 10 -6 lb (mass)/ft-sec

JULY 1993 MARINE TECHNOLOGY 181


b r a n c h connections from each m a i n to each t a n k , a n d individ-
Pressure Drop from Most Remote Tank to Vessel Vapor Connection. ual t a n k purge pipes connected by valves such t h a t t h e y can
be vented to a t m o s p h e r e or into one of t h e v a p o r mains.
F i n a l l y , a s s u m e t h a t t a n k s c a r r y i n g a G r a d e "E" cargo, such
20 ,~ as lube oils, a r e to be isolated from both I G / V a p o r M a i n s a n d
° j m a i n t a i n e d in a non-inerted s t a t e w i t h direct v e n t i n g t h r o u g h

,-I
/ an ullage opening. This is in fact t h e v e r s a t i l i t y of the d u a l
I G / V a p o r M a i n a r r a n g e m e n t shown in Fig. 3. In t h e s y s t e m
depicted in Fig. 3, six possible t a n k I G / V a p o r s y s t e m align-
// m e n t s a r e possible for each t a n k , including those r e q u i r e d
for h y d r o c a r b o n purging. Also, w h e n loading a cargo, t h e
previous cargo t h a t was in the t a n k m u s t be considered such
° I t h a t t h e r e a r e two ways to a t t a i n c e r t a i n valve a l i g n m e n t s .
~. 2.5 5.0 7.5 10.0 12.5 15.0 17.5 20.0 22.5 25.0 Therefore, for each t a n k t h e r e a r e eight possible processes to
LOADING RATE (1000's Barrelsper Hour) be considered for loading. If all t a n k s were lined up at one
System Collecting Inert Gas Saturated with HydrocarbonVapor. time, p o t e n t i a l l y one h u n d r e d a n d sixty different combina-
-4- Identical System Collecting only Inert Gas. tions of valve a l i g n m e n t would h a v e to be considered. Of
1) Loadinga pair of wingtanks simultaneously. course cargo loadings rarely, if ever, s t a r t and complete simul-
2) ~% Vapor Growth Rate assumed for both Conditions. taneously. C e r t a i n cargoes m a y be loaded c o n c u r r e n t l y , while
Fig. 5 Vapor recovery system pressure drop considerations o t h e r cargoes load sequentially. Some cargoes m a y o v e r l a p
t h e loading or discharge of others. Therefore, in o r d e r to
insure p r o p e r a l i g n m e n t , the a c t u a l valve positioning c a n n o t
be p e r f o r m e d until such time t h a t cargo o p e r a t i o n s for t h a t
In this example, t h e vapor composition of t h e I n e r t G a s / t a n k commence.
H y d r o c a r b o n m i x t u r e has been a s s u m e d to be 45% i n e r t gas Computer-based artificial intelligence systems provide a
a n d 55% h y d r o c a r b o n vapor, which corresponds to the theo- m e c h a n i s m to insure p r o p e r a l i g n m e n t s for each t a n k based
r e t i c a l s a t u r a t i o n value of h y d r o c a r b o n v a p o r in i n e r t gas. It on the cargo to be loaded and t h e previous cargo in t h e tank.
is noted t h a t this m i x t u r e is slightly more conservative t h a n F o r each cargo, t h e proper valve a l i g n m e n t can be stored in
t h e 50-50 I n e r t G a s / H y d r o c a r b o n V a p o r m i x t u r e required
p e r m a n e n t memory. W h e r e a p p r o p r i a t e , two a l i g n m e n t s for
by t h e U.S. Coast G u a r d Regulations. a given cargo can be stored in m e m o r y , if t h e previous cargo
Control, monitoring, and alarm functions--Minimum re- could effect alignment. Previous cargo d a t a can a u t o m a t i -
q u i r e m e n t s for control, m o n i t o r i n g and a l a r m functions a r e cally be stored in m e m o r y based on t h e last loading port.
defined in t h e regulations. These functions a r e required to Then, for a n y given t a n k , the o p e r a t o r can e n t e r t h e cargo
m i n i m i z e t h e likelihood of t a n k overfilling a n d provide pro- to be loaded by n a m e a n d the c o m p u t e r can d e t e r m i n e t h e
tection from o v e r / u n d e r p r e s s u r e and a r e c e r t a i n l y a d e q u a t e proper alignment. The a l i g n m e n t produced by t h e c o m p u t e r
for vessels h a n d l i n g single cargoes. However, for m u l t i p l e m a y be used by t h e o p e r a t o r as a n aid in p r o p e r l y a l i g n i n g
cargo vessels, the designer m a y find it p r u d e n t to analyze a t h e tanks, or if t h e I G / V a p o r valves have been fitted w i t h
vessel's operations a n d provide additional control, monil~or- power actuators, t h e c o m p u t e r can a c t u a l l y e x e c u t e t h e align-
ing, a n d a l a r m functions to both increase t h e safety of opera- ment. W h e r e valves a r e fitted with actuators, t h e use of artifi-
tions a n d to m i n i m i z e the p r o b a b i l i t y of accidently releasing cial intelligence offers an additional advantage. N a m e l y , t h e
a r e g u l a t e d v a p o r into the atmosphere. cargo officer, u s u a l l y t h e chief mate, can produce a l i g n m e n t
F o r vessels c a r r y i n g m u l t i p l e cargoes, t a n k s m a y periodi- scenarios for all t a n k s at one time, a n d t h e a c t u a l a l i g n m e n t s
cally be isolated from the V a p o r Collection Main(s) for a w~ri- can be executed by t h e officer on w a t c h at t h e t i m e cargo
e t y of reasons. W h e r e isolation is a common o p e r a t i n g prac- operations for t h a t t a n k commence. This c a p a b i l i t y mini-
tice, it is p r u d e n t to provide p r e s s u r e indication for each t a n k mizes the probability of a control m e a s u r e violation for regu-
or group of t a n k s t h a t can be isolated, in addition to t h e lated vapor releases because of possible valve m i s a l i g n m e n t
r e q u i r e d indication on t h e vapor collection main. P r e s s u r e in complex systems.
i n d i c a t i o n i n s t r u m e n t s provide personnel with a method to Artificial intelligence requires a m a n / m a c h i n e interface,
observe t h e effects t h a t e n v i r o n m e n t a l conditions, such as u s u a l l y in t h e form of a PC-type c o m p u t e r or o t h e r specially
sun loading, have on isolated tanks. designed processor, k e y p a d and d i s p l a y u n i t combination. In
W h e r e complex operations, involving s i m u l t a n e o u s han- most cases t h e e q u i p m e n t can or is fitted with c o m m u n i c a t i o n
dling of m u l t i p l e r e g u l a t e d cargoes and m u l t i p l e non-regu- ports, which allow i n f o r m a t i o n from o t h e r systems to be dis-
l a t e d cargoes, a r e common practice, the o w n e r / o p e r a t o r m a y played as a n a u x i l i a r y screen on t h e c o m p u t e r display. One
wish to consider a sophisticated control a n d m o n i t o r i n g Sys- e x a m p l e of this is the collection and d i s p l a y of t a n k level
t e m to provide: d a t a directly from the t a n k level i n d i c a t i n g system. Also, t h e
1. Compliance with the safety r e q u i r e m e n t s for pressure c o m m u n i c a t i o n ports can be used to t r a n s m i t d a t a to a r e m o t e
a n d level indication a n d a l a r m . source. One such i n s t a l l a t i o n has t h e p r i m a r y m a n / m a c h i n e
2. Centralized r e m o t e control of t a n k b r a n c h valves to off- interface (computer) in t h e cargo control room w i t h a slave
set a d d i t i o n a l vessel personnel workload caused by vapor col- unit on t h e navigation bridge. The Bridge u n i t is a m o n i t o r
lection system i n s t a l l a t i o n a n d operation. only t y p e u n i t from which all t a n k level, p r e s s u r e a n d valve
3. Artificial intelligence to t r a c k cargoes by t a n k to i n s u r e position d a t a can be m o n i t o r e d b u t not controlled.
p r o p e r valve a l i g n m e n t , so t h a t accidental releases of regu- Pressure~vacuum safety devices.--Prior to t h e i n t r o d u c t i o n
l a t e d cargo vapors into t h e a t m o s p h e r e a r e prevented. of vapor control, t a n k vapor displaced d u r i n g cargo loading
T h e use of a r t i f i c i a l intelligence m a y i n i t i a l l y a p p e a r to be was vented to atmosphere. W i t h t h e a d v e n t of v a p o r control,
overkill for t h e t a s k a t hand. However, t h e r e is justification t h e v a p o r for r e g u l a t e d cargoes is displaced to t h e facility
for this level of sophistication in c e r t a i n applications. Con- vapor control system. F r o m t h e vessel's s t a n d p o i n t t h e facil-
sider a vessel with t w e n t y cargo t a n k s and t e n cargo systems ity m u s t be considered to be a p o t e n t i a l l y closed-end device.
t h a t r o u t i n e l y c a r r i e s seven to t e n cargoes simultaneous}.y. Some facilities utilize t h e vessel's t a n k p r e s s u r e as t h e p r i m e
A s s u m e this vessel has a d u a l I G / V a p o r M a i n s with valw~d mover of t h e vapor, while o t h e r facilities a r e utilizing blowers

182 JULY 1993 MARINE TECHNOLOGY


or compressors to pull t h e v a p o r from t h e vessel. R e g a r d l e s s r e q u i r e m e n t s . P u r p o s e l y excluded from t h i s discussion is t h e
of t h e principle used for displacing t h e gas, all facilities h a v e overall issue of safety of v e s s e l / f a c i l i t y v a p o r control systems,
s h u t d o w n s y s t e m s which can close a valve t h a t blocks flow which is considered to be a topic to which a n e n t i r e p a p e r
of v a p o r from t h e vessel's cargo tanks. Facilities t h a t utilize could be dedicated.
blowers or compressors h a v e f a i l u r e scenarios which could It is noted t h a t both U.S. Coast G u a r d a n d t h e A m e r i c a n
r e s u l t in a v a c u u m being p u l l e d on t h e vessel's cargo tanks. B u r e a u of S h i p p i n g (ABS) have p r o m u l g a t e d rules a n d regula-
T h e p r o b a b i l i t y of a t a n k o v e r / u n d e r p r e s s u r e condition is tions for vessel v a p o r control systems. U.S. Coast G u a r d Regu-
i n c r e a s e d w i t h v a p o r control, because t h e vessel's v e n t i n g lations were adopted first and, subsequently, a c o n c e n t r a t e d
s y s t e m is i n t e r c o n n e c t e d to a n o t h e r system t h a t is controlled effort has been e x p e n d e d to i n s u r e t h a t t h e ABS " G u i d e for
by others. Accordingly, t h e i m p o r t a n c e of t h e o v e r / u n d e r Cargo V a p o r Emission Control S y s t e m s on Board T a n k Ves-
p r e s s u r e safety devices is g r e a t l y increased. sels" is consistent w i t h the U.S. Coast G u a r d Regulations.
T h e two most common devices for p r e s s u r e / v a c u u m protec- Consistency has been achieved w i t h t h e exception of t h e set
tion a r e t h e p r e s s u r e / v a c u u m relief valve (P/V valve) a n d point r e q u i r e m e n t s for the t a n k overflow a l a r m s .
t h e liquid filled p r e s s u r e / v a c u u m b r e a k e r ( P / V breaker). The ABS requires t h a t t h e overflow a l a r m s m u s t be set a t a
p r i m a r y a d v a n t a g e of P / V valves is also t h e w e a k n e s s of P / point in which cargo loading can proceed a t t h e M a x i m u m
V b r e a k e r s : n a m e l y P / V valves will r e s e a t after a p r e s s u r e Allowable T r a n s f e r R a t e (MATR) for at least 60 seconds be-
excursion (either p r e s s u r e or vacuum), w h e r e a s when a P / V fore t a n k overflow, w h e r e t h e M A T R is defined as t h e maxi-
b r e a k e r blows a n d t a n k p r e s s u r e equalizes to a t m o s p h e r i c m u m v o l u m e t r i c r a t e at which a vessel m a y receive cargo or
unless t h e b r e a k e r can be isolated. However, if a b r e a k e r can ballast. Thus, a t o t a l vessel r e q u i r e m e n t is being a p p l i e d to
be isolated, it does not qualify as a required pressure relieving a single t a n k , which could r e s u l t in a n u n r e a l i s t i c a l l y low set
device. The p r i m a r y a d v a n t a g e of P / V b r e a k e r s is t h a t t h e y point for the overflow a l a r m .
provide for full flow relief a t t h e set point. A n o t h e r a d v a n t a g e In contrast, t h e U.S. Coast G u a r d R e g u l a t i o n is m o r e realis-
of P / V b r e a k e r s is t h e w e a k n e s s of P / V valves. P / V b r e a k e r s tic. It states, " T h e t a n k overfill a l a r m m u s t a l a r m e a r l y
provide a t i g h t seal right up to t h e i r set point, w h e r e a s a P / enough to allow t h e person in c h a r g e of t r a n s f e r o p e r a t i o n s to
V valve will begin to l e a k a t some point before r e a c h i n g t h e stop t h e t r a n s f e r operations before t h e cargo t a n k overflows."
p r e s s u r e or v a c u u m set point. The reason for the l e a k i n g is This inconsistency h a s been pointed out to ABS on s e v e r a l
t h a t most valves use weights or springs to provide resistance occasions, since t h e first publication of t h e Guide, b u t as of
to pressure. R e s u l t a n t l y , t h e force holding t h e disc a g a i n s t this writing, t h e inconsistency h a s not been resolved.
t h e seat is g r e a t e s t a t zero pressure a n d decreases to zero a t The regulations require t h a t each t a n k be fitted w i t h a
t h e set point. high level and a t a n k overfill a l a r m , a n d t h a t t h e t a n k overfill
W h e n selecting a n d positioning P / V valves and P / V break- a l a r m s have audio a n d visual indications t h a t can be seen
ers, consideration should be given to t h e s t r e n g t h s a n d weak- a n d h e a r d on t h e vessel where cargo t r a n s f e r is controlled a n d
nesses of each, t h e i r set points, a n d t h e new and existing in t h e cargo deck area. F o r vessels w h e r e cargo is n o r m a l l y
sources of p r e s s u r e and v a c u u m excursions. W h e n loading controlled from a cargo control room, t h e r e q u i r e m e n t for
cargo with vapor collection, t h e m a x i m u m source of t a n k t h e overfill a l a r m s being e x t e n d e d to t h e deck have been
p r e s s u r e is compression of v a p o r within a t a n k as liquid dis- the subject of some controversy. One position h a s been t h a t
places t h e v a p o r space a t the m a x i m u m liquid loading rate. individual a l a r m s for each t a n k m u s t be provided on deck,
V a c u u m conditions can occur if vapor is being pulled from and t h e o t h e r position has been t h a t a single s u m m a r y a l a r m
t h e space (from a blower or compressor ashore) a t a faster on deck satisfies t h e i n t e n t of t h e regulations. In S e p t e m b e r
r a t e t h a n liquid is being loaded into t h e tank. W h e n discharg- 1991, U.S. Coast G u a r d accepted t h e single s u m m a r y a l a r m
ing cargo, p r e s s u r e build-up in a t a n k can be no g r e a t e r t h a n as m e e t i n g t h e i n t e n t of t h e Rules. F o r vessels loading m o r e
t h e IG fan capacity, a n d t h e r a t e of pressure reduction c a n n o t t h a n one cargo simultaneously, it is t h e opinion of m a n y ,
be g r e a t e r t h a n the vessel p u m p i n g system capacity con- including this author, t h a t t h e single visual s u m m a r y a l a r m
nected to t h e t a n k . is a c t u a l l y safer t h a n individual t a n k a l a r m s in t h e cargo
Most systems use a combination of P / V b r e a k e r s a n d P / deck area. On occasions when t h e officer on d u t y is on deck
V valves to protect a g a i n s t the aforementioned sources of a n d an a l a r m does occur, a single s u m m a r y a l a r m provides
p r e s s u r e a n d vacuum. P / V b r e a k e r s will be located on the t h e officer only one choice: s h u t down all cargo or risk a t a n k
v a p o r collection m a i n to satisfy t h e 125% relieving require- overflow event. In t h e case of i n d i v i d u a l a l a r m s , an officer
m e n t a t t h e m a x i m u m allowable loading r a t e required by could conceivably choose to s h u t d o w n a specific cargo i n s t e a d
t h e vapor control regulations. P / V valves will n o r m a l l y be of all cargo. In such cases, t h e r e is a risk t h a t he could choose
positioned to protect t a n k s or groups of t a n k s t h a t can be to stop the incorrect cargo.
isolated from t h e vapor collection main, a n d sized a r b i t r a r i l y Also, with respect to t a n k overflow deck a l a r m s , t h e regula-
or according to IG blower a n d cargo p u m p capacities. tions do not specifically address w h e t h e r or not these a l a r m s
Set point considerations a r e twofold in nature: One, P / V can be disabled a t sea. The r e a l i t y of the m a t t e r is t h a t t a n k
v a l u e p r e s s u r e set points should be set as far above t h e in- overflow alarms, a n d a n y o t h e r a l a r m s t h a t t h e d e s i g n e r m a y
t e n d e d o p e r a t i n g pressure as practical. The g r e a t e r the differ- elect to place on deck, m u s t be defeated d u r i n g n a v i g a t i o n of
e n t i a l b e t w e e n set point a n d o p e r a t i n g pressure, t h e g r e a t e r the vessel. F a i l u r e to do so could r e s u l t in a l a r m s occurring
t h e sealing force between the seat and disc and t h e less likely when t a n k s a r e full a n d t h e vessel rolls. A t night, the a l a r m s
t h e valve is to leak. Two, the P / V b r e a k e r set points (both would most c e r t a i n l y be a d i s t r a c t i o n to navigation. T i m e
p r e s s u r e a n d vacuum) should be set slightly outside the P / V delays could be i n c o r p o r a t e d into t h e a l a r m s , b u t doing so
valve set points. Configured in this m a n n e r , the P / V valves effectively raises the set point of t h e a l a r m s .
will absorb t h e m a j o r i t y of p r e s s u r e / v a c u u m excursions, t h u s The vapor control system r e g u l a t i o n s r e q u i r e a pressure-
m i n i m i z i n g vapor releases due to blown P / V breakers. sensing device in t h e m a i n vapor collection line. F o r those
Regulatory body considerations--In the course of designing, who consider electric-type t r a n s m i t t e r s , t h e r e g u l a t i o n s re-
i n s t a l l i n g a n d witnessing t h e operation of several vessel va- quire t h a t t h e t r a n s m i t t e r be explosion-proof if located on
por collection systems, a few concerns and inconsistencies deck a n d of t h e intrinsically-safe type if w i t h i n t h e cargo
w i t h t h e r e g u l a t i o n s have occurred, which a r e w o r t h y of men- tanks. Coast G u a r d has now m a d e an i n t e r p r e t a t i o n of t h e
tion. These include concerns about level a l a r m set points, rules a n d requires t h a t electric-type t r a n s m i t t e r s used in a
level a l a r m indication, a n d p r e s s u r e indication e q u i p m e n t vapor collection m a i n m u s t be of the intrinsically-safe type.

JULY 1993 MARINE TECHNOLOGY 183


F o r most t r a n s m i t t e r s , t h e p r e s s u r e sensing d i a p h r a g m is of t h i n - w a l l e d (Schedule 10) c o r r o s i o n - r e s i s t a n t piping, such
outside the explosion-proof barrier. Since t h e d i a p h r a g m is as stainless steel. If inch a m a t e r i a l is d e t e r m i n e d acceptable,
exposed to the m e d i a being m e a s u r e d and since t h e vapor t h e i n s t a l l a t i o n benefits a r e enormous. I n s t a l l e d cost for
m a i n can be an e~plosive m i x t u r e , the intrinsically-safe t y p e stainless steel on a retrofit basis has proven to be lower t h a n
t r a n s m i t t e r h a s p r o p e r l y been d e e m e d chosen. for coated carbon steel pipe, because savings in l a b o r costs
Future control measures--Early v a p o r control m e a s u r e s m o r e t h a n offset increased m a t e r i a l costs. L a b o r savings a r e
t h a t h a v e been adopted a n d a r e now in effect, address only achieved since t h e n u m b e r of t a k e down joints can be r e d u c e d
t h e control of volatile organic compound, (VOC), emissions a n d because once t h e pipe spools a r e a b o a r d t h e vessel, t h e i r
d u r i n g t h e loading of cargo. L a t e r measures, which have been fit-up a n d i n s t a l l a t i o n is basically a one c r a f t job, i n s t e a d of
passed b u t a r e not y e t in effect, e x p a n d r e g u l a t e d o p e r a t i o n s a four craft job. In a m a j o r i n s t a l l a t i o n , w h e r e s t a i n l e s s steel
a n d in m a n y cases include h o u s e k e e p i n g a n d b a l l a s t i n g opera- piping was a c t u a l l y used in lieu of coated carbon steel, t h e
tions. F u t u r e r e g u l a t e d operations, such as housekeeping, c a l e n d a r d a y t i m e savings was e s t i m a t e d to be a p p r o x i m a t e l y
could have a profound i m p a c t on a v a p o r collection system 20%.
design. If a vessel will t r a d e in a subject a r e a after t h e effec- Automation--When considering a n y a u t o m a t i o n system, it
tive d a t e a n d will have to conduct operations subject to these is emphasized t h a t t h e p r i m a r y reason for a n y a u t o m a t i o n
s t r i n g e n t controls, t h e n n e c e s s a r y c a p a b i l i t y should be in- is to reduce overall life cycle cost. This life-cycle cost m u s t
cluded in t h e i n i t i a l design of the system. include initial cost, m a i n t e n a n c e cost, cost savings from re-
duced labor, a n d lost o p p o r t u n i t y cost if t h e s y s t e m should
Installation considerations not function properly. Some subjective issues, such as t h e
r a m i f i c a t i o n s of i m p r o p e r o p e r a t i o n of a system a n d its poten-
The t i m e r e q u i r e d for t h e r e t r o f i t t i n g of a vessel vapor tial costs m u s t also be considered.
collection system is of course v e r y d e p e n d e n t upon its com- One of t h e most misconceived benefits of t o d a y ' s s t a t e of
plexity. Regardless of t h e complexity of t h e system, t h e t h e a r t d i s t r i b u t e d control systems over a c o n v e n t i o n a l h a r d -
o w n e r / o p e r a t o r will w a n t it installed a n d m a d e operable in a wired system is reduced i n s t a l l e d costs. By s t r a t e g i c place-
t i m e f r a m e t h a t does not exceed t h e vessel's n o r m a l s h i p y a r d m e n t of I / O stations t h r o u g h o u t t h e control a n d m o n i t o r i n g
a v a i l a b i l i t y . F o r simple installations, w h e r e existing systems area, t h e required a m o u n t of system components a n d cable
a r e e x t e n d e d a n d / o r modified, this goal is u s u a l l y a t t a i n a b l e can be optimized. W h e n p r e p a r i n g proposals, v e n d o r s will t r y
w i t h o u t incident. However, for complex systems with signifi- to optimize I / O p l a c e m e n t in o r d e r to be competitive. As a
c a n t a m o u n t s of new piping a n d / o r a u t o m a t i o n , completion result, when considering an a u t o m a t i o n package, the de-
of a n i n s t a l l a t i o n in a period of two or t h r e e weeks is a chal- signer is likely to receive a m u l t i t u d e of proposals, none of
lenge t h a t r e q u i r e s engineering, with due consideration for which m a y r e p r e s e n t t h e m i n i m u m life-cycle cost for t h e
m i n i m i z i n g t h e i n s t a l l a t i o n period. owner.
Piping installation--When significant a m o u n t s of pipe A n e x a m p l e c l e a r l y d e m o n s t r a t e s this paradox. One auto-
w o r k a r e involved, it is essential to p r e f a b r i c a t e as much pipe m a t i o n design t h a t t h e a u t h o r has been associated with con-
as possible p r i o r to t h e vessel's a r r i v a l a t the facility, no t a i n e d a p p r o x i m a t e l y 500 i n p u t s a n d o u t p u t s (I/O points),
m a t t e r w h a t pipe m a t e r i a l is to be used. P r e f a b r i c a t i o n re- including r e m o t e a c t u a t i o n a n d position i n d i c a t i o n for ap-
quires t h a t a r r a n g e m e n t plans be completed in a t i m e l y man- p r o x i m a t e l y 50 valves a n d position indication only for an-
n e r a n d t h a t t h e c o n t r a c t for the work be a w a r d e d e a r l y o t h e r 20 valves. Valves and o t h e r I / O points were s p r i n k l e d
enough to p e r m i t t h e c o n t r a c t o r to survey t h e vessel in suffi- from one end of t h e cargo deck a r e a to the other. Based on
cient detail to g e n e r a t e spool drawings. Such surveys a r e p r e l i m i n a r y discussions from a u t o m a t i o n vendors, it was esti-
i d e a l l y to be m a d e with t h e designer present, so t h a t t h e m a t e d t h a t cable r e q u i r e m e n t s for power a n d control cable
effect on design p a r a m e t e r s of cost a n d / o r t i m e saving ideas would r a n g e from 7000 to 10 000 ft of 10-conductor, 14-AWG
p u t forth by t h e c o n t r a c t o r can be e v a l u a t e d on the spot. In cable. F o r c o m p a r a t i v e purposes, a n i n t e r n a l e s t i m a t e for a
developing pipe spools, t h e sequence of i n s t a l l a t i o n m u s t be hard-wired system was prepared, which i n d i c a t e d t h a t ap-
given consideration, so t h a t t a i l pieces for fit-up can be pro- p r o x i m a t e l y 20 000 ft of cable would be required. Based on
vided as necessary, b u t not in excess. This is critical for piping the vastly different a m o u n t s of cable required, i n i t i a l l y it
t h a t m u s t be i n t e r n a l l y coated. a p p e a r e d t h a t t h e d i s t r i b u t e d control system offered signifi-
In a d d i t i o n to p r e - p l a n n i n g t h e piping a r r a n g e m e n t , consid- c a n t savings in both cost and i n s t a l l a t i o n time.
e r a t i o n should be given to piping m a t e r i a l a n d coating re- As expected, when initial proposals were received, all were
q u i r e m e n t s . T r a d i t i o n a l l y , i n e r t gas system piping has been based on m i n i m i z i n g cable by locating I / O s t a t i o n s on t h e
constructed from i n t e r n a l l y coated, heavy-wall carbon steel w e a t h e r deck w i t h i n e x p l o s i o n - p r o o f / w a t e r t i g h t enclosures.
pipe, in o r d e r to s t a n d up to the corrosive effects of i n e r t gas Not one contained a n a l t e r n a t i v e w h e r e all I / O was located
a n d cargo vapor containing large a m o u n t s of sulfur. This has in a c e n t r a l location, such as t h e cargo control room. D u r i n g
p r o v e n to be a n effective combination for t h e service, b u t its the t i m e between initial and final proposals, a d e t a i l e d s t u d y
i n s t a l l a t i o n is also a t i m e consuming process on a retrofit of t h e cable i n s t a l l a t i o n was made. The most significant con-
basis, a n d one w h e r e control of t h e i n t e r n a l coating q u a l i t y clusion from the s t u d y was t h a t t h e 10 000 to 13 000 addi-
is s o m e t i m e s beyond the r e a c h of the vessel owner. T h e r e a r e tional feet of cable required for a centralized system was
two p r i m a r y factors t h a t m a k e coated carbon steel pipe time- d i s p r o p o r t i o n a t e l y inexpensive cable from both a cost a n d
c o n s u m i n g to install: (1) a significant n u m b e r of t a k e d o w n i n s t a l l a t i o n standpoint. Most of t h e a d d i t i o n a l cable would
j o i n t s a r e r e q u i r e d to insure good i n t e r n a l coating and (2), on be located in the existing fore-aft w i r e w a y on t h e u p p e r deck,
a r e t r o f i t basis, coated carbon steel piping requires the efforts which would have to be opened up from end to end, r e g a r d l e s s
a n d coordination of four labor crafts: pipefitters, rigging, of the system chosen. New a t h w a r t s h i p deck r u n s of cable
t r a n s p o r t a t i o n , a n d p a i n t e r / b l a s t e r s . A f t e r final fit-up a n d were essentially t h e s a m e for both t h e d i s t r i b u t e d a n d central-
weld-out a r e complete, pipe spools m u s t be removed from t h e ized systems. The a d d i t i o n a l cost for wiring to a c e n t r a l loca-
vessel, t r a n s p o r t e d to the p a i n t shop, p r e p a r e d a n d coal;ed, tion a m o u n t e d to a m a t e r i a l cost for cable only. L a b o r cost
r e t u r n e d to t h e vessel, lifted aboard, and t h e n reinstalled. for r u n n i n g the cable was offset by t h e savings realized by
F o r i n s t a l l a t i o n on board vessels, w h e r e corrosion from e l i m i n a t i n g t h e explosion-proof, w a t e r t i g h t boxes on deck.
sulfur is of reduced concern, such as vessels with diesel fired The system installed was a h a r d - w i r e d centralized control
i n e r t gas g e n e r a t o r s , consideration should be given to t h e use system with all I / O positioned in a single location. W h i l e

184 JULY 1993 MARINE TECHNOLOGY


i n s t a l l e d cost of t h e centralized system was slightly higher, c e r t a i n l y conceivable t h a t a P / V valve could have lifted on
it is e s t i m a t e d i n s t a l l a t i o n t i m e was identical to a d i s t r i b u t e d pressure, r e l e a s i n g t a n k vapors to t h e a t m o s p h e r e .
control system. In addition, t h e benefits of t h e centralized Pressure control--A survey of six facilities in t h e San F r a n -
system over t h e life of t h e vessel far outweighed t h e addi- cisco A r e a r e v e a l e d t h a t four of t h e six used blowers or com-
t i o n a l first costs. Some of t h e more i m p o r t a n t benefits of the pressors to t r a n s p o r t vapor from t h e vessel to t h e d e s t r u c t i o n /
c e n t r a l i z e d system as i n s t a l l e d are: recovery device. These facilities h a d m e a n s to control vessel
1. All I / O is located in a controlled e n v i r o n m e n t a n d not t a n k pressures via a p r e s s u r e control valve n e a r t h e facility
in a Class I, Division 1 h a z a r d o u s area, which is periodically vapor connection. Two facilities relied solely on vessel t a n k
a w a s h w h e n the vessel is a t sea. p r e s s u r e for t h e d i s p l a c e m e n t ashore a n d t h r o u g h t h e de-
2. All I / O is located in a c e n t r a l location, which g r e a t l y s t r u c t i o n / r e c o v e r y device. A t these facilities, no p r e s s u r e con-
simplified s t a r t - u p and troubleshooting of t h e system. trol valve was installed shoreside.
3. All e q u i p m e n t on deck can be electrically isolated indi- F o r i n e r t e d t a n k vessels, it is desirable to h a v e a m e t h o d
vidually, allowing a n y c o m p o n e n t to be serviced or replaced, to control p r e s s u r e a t the vessel vapor connection, so t h a t
w i t h o u t h a v i n g to shutdown t h e e n t i r e system. vessel personnel can m a i n t a i n positive t a n k p r e s s u r e to be
sure of m a i n t a i n i n g an i n e r t e d e n v i r o n m e n t at all times.
Accordingly, some inerted vessels have p r e s s u r e control
Operating experience valves fitted in t h e i r collection systems for this purpose. A t
Systems, which have been designed to the latest U.S. Coast facilities w i t h o u t pressure control, the vessel control valve is
G u a r d Regulations, have been in operation since the middle set at an agreed to set point a n d opens only far enough to
m a i n t a i n the set point pressure. If loading r a t e increases or
of 1990 t h r o u g h o u t t h e country. S t a r t - u p of facilities and
decreases, the valve adjusts accordingly. Since vapor is h i g h l y
t h e i r interface with vessels has for t h e most p a r t been w i t h o u t
compressible, t h e r a t e of change of vapor flow is sufficiently
incident. However, some i n t e r e s t i n g experience has been
g a i n e d t h a t deserves comment. slow t h a t it does not adversely effect the d e s t r u c t i o n / r e c o v e r y
device operation.
Tank pressure considerations--The most p r o m i n e n t i m p a c t
F o r vessels fitted with t h e i r own p r e s s u r e control valve,
t h a t vapor control has h a d on vessel operations is r e g u l a t i o n
calling a t facilities with t h e i r own p r e s s u r e control valve,
of cargo t a n k pressures. Regulations for inerted t a n k vessels
t h e r e is often a conflict because the two p r e s s u r e control
r e q u i r e t h a t t h e cargo t a n k s be m a i n t a i n e d a t a slight positive
valves will f r e q u e n t l y be connected in series. In such situa-
pressure; 4 in. of w a t e r (0.144 psig) m i n i m u m . If pressure
tions, t h e facility in all likelihood will r e q u i r e t h e i r valve be
drops below the pressure a l a r m set point, pressure can be
used to control pressure and t h a t the vessel control valve be
increased t h r o u g h the admission of i n e r t gas. P r i o r to vapor
blocked open. Preferably, however, the vessel o p e r a t o r m a y
control legislation, excess pressure could be vented directly
convince the facility to allow t h e vessel control valve to be
to a t m o s p h e r e using e i t h e r a pressure control valve set at a
set at a p r e s s u r e below the facility set p r e s s u r e b u t above t h e
given p r e s s u r e or by a high velocity vent valve. In t h e event low pressure a l a r m point. In this a r r a n g e m e n t , t h e vessel
of an o v e r p r e s s u r e or v a c u u m condition, t h e t a n k s were pro- valve would n o r m a l l y r e m a i n fully open, b u t in the e v e n t t h e
tected by e i t h e r a p r e s s u r e / v a c u u m relief valve a n d / o r a shore side valve failed open, t h e vessel control valve would
liquid filled p r e s s u r e / v a c u u m breaker. close as necessary to m a i n t a i n t h e vessel's t a n k pressure. This
W i t h vapor control, flexibility for controlling t a n k pressure a r r a n g e m e n t allows the facility to o p e r a t e in t h e i r n o r m a l
is reduced a n d the consequences of pressure excursions is m a n n e r and also provides vessel personnel w i t h a s s u r a n c e
increased. Additionally, vapor control introduces a n o t h e r t h a t the facility system will not pull v a c u u m on t h e vessel's
v a r i a b l e into t h e equation: namely, different facilities have tanks.
different t a n k pressure requirements. A t facilities on the Pressure units--None of t h e regulations, guidelines or con-
W e s t Coast, desired pressures at t h e r a i l have r a n g e d from trol m e a s u r e s address t h e subject of units of pressure. As a
8 to 20 in. of w a t e r (0.3 to 0.7 psig). W i t h i n jurisdictional result, facilities a n d vessels use different units such as pounds
a r e a s today, v e n t i n g to reduce cargo t a n k pressures violates per square inch absolute (psia); pound p e r square inch gage
t h e i n t e n t of t h e control measures. Excess pressure adjust- (psig); inches of w a t e r gage (INWG); m i l l i m e t e r s w a t e r gage
m e n t s m u s t now be m a d e prior to e n t e r i n g the j u r i s d i c t i o n a l (mmWG). A t facilities where t h e units of p r e s s u r e a r e differ-
area. Depending on t h e location of the facility, this adjust- e n t t h a n those used on the vessel, it is r e c o m m e n d e d a conver-
m e n t m a y have to be m a d e four to six hours, or more, prior sion table be provided a t t h e pre-loading conference a n d
to c o m m e n c e m e n t of loading. Since e n v i r o n m e n t a l effects a g r e e m e n t be reached as to which units a r e to be used in
could have a significant i m p a c t on pressure over this time communications between t h e facility a n d vessel.
frame, personnel m u s t t a k e t h e m into account as well as the Standby time--Initial o p e r a t i o n of t h e v a p o r control sys-
facility p r e s s u r e requirements. tems has resulted in s u b s t a n t i a l increases in s t a n d b y t i m e a t
F o r vessels calling at facilities designed to h a n d l e only in- t e r m i n a l loading berths. As shoreside a n d vessel p e r s o n n e l
e r t e d t a n k vessels, v a c u u m conditions within a t a n k can be become accustomed to t h e a d d i t i o n a l o p e r a t i n g r e q u i r e m e n t s
devastating. In the event t h a t v a c u u m in a t a n k is g r e a t of vapor control, it is expected t h a t s t a n d b y t i m e will be
enough to pop a relief valve on vacuum, sufficient a i r could reduced to a n acceptable level. In fact, a f t e r t h r e e to four
be introduced into a t a n k to b r i n g total oxygen levels above m o n t h s of operation, reductions in s t a n d b y t i m e a r e being
t h e 9% shutdown threshold. Thus, v a c u u m conditions m u s t realized. N u m e r o u s factors h a v e c o n t r i b u t e d to t h e i n c r e a s e
be carefully m o n i t o r e d a n d avoided. in s t a n d b y time. Some b u t not all a r e included h e r e i n to
E n v i r o n m e n t a l effects on t a n k p r e s s u r e can be substantial. provide the r e a d e r with a n idea of t h e incidents t h a t h a v e to
One d r a m a t i c e x a m p l e occurred at a facility in t h e San F r a n - be t a k e n into account.
cisco A r e a w h e r e cargo operations were i n t e r r u p t e d for the M a n y facility systems a r o u n d t h e San F r a n c i s c o a r e a a r e
loading of vessel stores. A vapor control shutdown occurred incineration-type systems, which utilize a t h e r m a l oxidizer
w h e n r e s t a r t i n g cargo causing a d d i t i o n a l delay in v a p o r flow. as t h e destruction device. The oxidizers have w a r m - u p periods
All total, v a p o r flow from t h e vessel was curtailed for a four on t h e order of t h r e e to four hours. F a i l u r e to w a r m up t h e
hour period, d u r i n g which t i m e sun loading on t h e deck in- oxidizer prior to a vessel's a r r i v a l can cause delay. Also, cer-
creased t a n k pressures by more t h a n 18 in. of water. H a d the t a i n shutdown scenarios will r e s u l t in s u b s t a n t i a l cooling of
d e l a y been longer a n d initial t a n k pressures higher, it is t h e oxidizer stack. A n y such s h u t d o w n will r e q u i r e t h e oxi-

JULY 1993 MARINE TECHNOLOGY 185


dizer to be w a r m e d up to p r o p e r o p e r a t i n g t e m p e r a t u r e , prior Conclusions
to r e s t a r t i n g cargo operations.
The oil t r a n s p o r t a t i o n i n d u s t r y as a whole has responded
U.S. Coast G u a r d R e g u l a t i o n s have s u b s t a n t i a l testing a n d
d i l i g e n t l y to meet t h e new r e q u i r e m e n t s of v a p o r control t h a t
c a l i b r a t i o n r e q u i r e m e n t s for system m o n i t o r i n g a n d shut- have been imposed by local a i r q u a l i t y m a n a g e m e n t districts.
down devices, t h a t m u s t be accomplished w i t h i n 24 hr" of a P r i o r to t h e issuance of r e g u l a t i o n s by the U.S. Coast G u a r d
loading event. W h e n e v e r a device fails to pass the t e s t i n g t h a t governed t h e construction s t a n d a r d s , m a n y o p e r a t o r s
a n d / o r c a l i b r a t i o n devices, t i m e is required to r e p a i r a n d / o r were v o l u n t a r i l y engaged in t h e design of vessel s y s t e m s in
r e p l a c e t h e failed component. an effort to meet t h e effective dates of the control measures.
A t m a n y of t h e facilities in t h e Bay area, the Bay A r e a A i r In m a n y cases, i n s t a l l a t i o n w o r k a c t u a l l y c o m m e n c e d before
Q u a l i t y M a n a g e m e n t District requires t h a t t h e t a n k s into the final U.S. Coast G u a r d r e g u l a t i o n s b e c a m e effective.
which a r e g u l a t e d cargo is to be loaded be tested for leaks In spite of the efforts expended to date, t h e i n d u s t r y still
w i t h i n the first 20% of t h e loading. This testing can be per- faces w h a t m a y be its g r e a t e s t challenge with respect to v a p o r
f o r m e d e i t h e r by a n i n d e p e n d e n t gaging c o m p a n y or by t h e control. Local a i r q u a l i t y m a n a g e m e n t districts continue to
vessel's crew. Regardless of who performs t h e tests, a n y leaks pass control m e a s u r e s a r o u n d t h e c o u n t r y in a n effort to m e e t
above t h e 10 000 p p m t h r e s h o l d m u s t be rectified within one- the r e q u i r e m e n t s of t h e Clean A i r Act of 1990. The control
h a l f h o u r of discovery, or loading is to be c u r t a i l e d until ..such m e a s u r e s all have t h e s a m e f u n d a m e n t a l goal, b u t t h e i r spe-
t i m e t h a t t h e l e a k can be fixed. W h e r e a n outside gaging cific r e q u i r e m e n t s v a r y from one location to a n o t h e r . Efforts
c o m p a n y is used, t h e r e is also a p o t e n t i a l for d e l a y if person- to achieve consistency a m o n g t h e control m e a s u r e s by t h e
i n d u s t r y have been m a r g i n a l l y successful at best. Vessels,
nel a r e not i m m e d i a t e l y a v a i l a b l e a t the r e q u i r e d time. The
which by t h e i r v e r y n a t u r e a r e c o n s t a n t l y moving b e t w e e n
S o u t h Coast A i r Q u a l i t y M a n a g e m e n t District Control Mea-
j u r i s d i c t i o n a l areas, a r e being subjected to a v a r i e t y of new
sure, which goes into effect on J a n u a r y 1994, imposes a 1000 requirements. Consequently, a vessel with a collection system
p p m l e a k threshold, which could have an a d d i t i o n a l i m p a c t designed a n d i n s t a l l e d when t h e initial control m e a s u r e s
on this t y p e of delay. were enacted m a y s o m e d a y have severely r e s t r i c t e d utility,
Facility shutdowns--For facilities, t h e r e g u l a t i o n s require unless a major refit is made.
t h a t a quick closing valve be provided n e a r the facility vapor The major gain in t h e control of VOC emissions from t a n k
connection a n d t h a t t h e valve close within 30 seconds after vessels will come from t h e r e g u l a t i o n of f r e q u e n t operations,
detection of a n y of numerous, specified shutdown conditions such as cargo loading. M a r g i n a l gains t h a t m a y be realized by
w i t h i n the facility system. A t m a n y facilities, this quick clos- r e g u l a t i n g infrequent events, such as h y d r o c a r b o n purging,
ing r e q u i r e m e n t has been e x t e n d e d to t h e stop valves in t h e need to be reconsidered. To recover vapor d u r i n g t a n k purg-
cargo lines. The r a t i o n a l e being when v a p o r flow stops, cargo ing operations m a y in some cases be justified, b u t t h e collec-
flow should also be t e r m i n a t e d to p r e v e n t pressure b u i l d u p tion system required is vastly m o r e complex a n d costly t h a n
in t h e vessel's tanks. t h a t r e q u i r e d for loading operations only. The v e r y complex-
F o r vessels t h a t engage in s i m u l t a n e o u s loading a n d dis- ity of such systems could r e s u l t in a net i n c r e a s e in VOC
c h a r g e operations, t h e facility's shutdown logic should be emissions, due to increases in o p e r a t i o n a l upsets. Also, t h e
c a r e f u l l y discussed a n d understood d u r i n g the pre-loading wisdom of r e g u l a t i n g b a l l a s t i n g operations (into cargo tanks)
should be questioned. B a l l a s t i n g into cargo t a n k s has a l r e a d y
conference. If t h e facility control logic in a vapor shutdown
been legislated into extinction on t h e F e d e r a l level as t h e
condition closes a cargo valve t h a t t h e vessel can conceivably
i n d u s t r y is compelled to replace its existing fleet w i t h new
be p u m p i n g against, t h e hose could be subjected to a cargo
double-hulled ships with segregated b a l l a s t tanks.
p u m p shutoff head. Now t h a t vapor control has been i m p l e m e n t e d in t h e S a n
Leak Testing--Leak testing of t a n k p e n e t r a t i o n s in accord- Francisco Bay Area, s u b s t a n t i a l reductions in VOC emissions
ance w i t h E P A Method No. 21 is required by m a n y of the can a n d a r e being achieved. However, it is a p p r o p r i a t e to
control m e a s u r e s in effect today. E P A Method 21 outlines a assess t h e effectiveness of the original concept in m e e t i n g
p r o c e d u r e t h a t employs a p o r t a b l e i n s t r u m e n t to detect VOC its i n t e n d e d mission a n d to consider a n y i m p o r t a n t lessons
l e a k s for i n d i v i d u a l sources. The type of i n s t r u m e n t is not l e a r n e d t h a t m i g h t help improve f u t u r e activities in o t h e r
called out, b u t t h e specifications for it are. The most com- geographical areas. One f u n d a m e n t a l l y i m p o r t a n t s e g m e n t
m o n l y used i n s t r u m e n t in use on t h e West Coast is an Organic of vapor control which m a y benefit from r e e x a m i n a t i o n is
V a p o r A n a l y z e r (OVA). This t y p e of i n s t r u m e n t is portable, t h e selection of control technology. Most control m e a s u r e s in
e a s y to use, o p e r a t e s a p p r o x i m a t e l y eight hours on a b a t t e r y effect today state only specific reduction levels for VOC's; t h e
charge, a n d is a v a i l a b l e in intrinsically-safe models. The raa- technology by which t h e reduction is accomplished is left to
j o r d r a w b a c k s of t h e i n s t r u m e n t s a r e t h a t t h e y have high the facility operator. In t h e San Francisco Bay A r e a , it is of
i n i t i a l cost a n d r e q u i r e c a l i b r a t i o n by a qualified technician i n t e r e s t to note t h a t prior to e n a c t m e n t of t h e control mea-
on t h r e e - m o n t h intervals. sure, the two facilities t h a t had a p p l i e d for p e r m i t s to i n s t a l l
E P A Method 21 offers bubble testing as an alternatl[ve m a r i n e vapor control systems chose recovery type processes.
s c r e e n i n g procedure with some l i m i t a t i o n s prior to using a Subsequent to e n a c t m e n t of the control m e a s u r e , w i t h speci-
p o r t a b l e meter. A r e a s t h a t a r e proven bubble t i g h t need rmt fied reduction levels, most all facilities have selected incinera-
tion t y p e processes. This decision h a s c l e a r l y b e e n m o t i v a t e d
be tested with t h e OVA. The l i m i t a t i o n s a r e t h a t bubble test-
by t h e considerations of cost and a need to m a k e a conserva-
ing c a n n o t be used on e q u i p m e n t with continuously moving tive selection, which will g u a r a n t e e complete compliance
p a r t s (such as shaft seals when a p u m p is running) or on with t h e control limits over a long period of time, even with
e q u i p m e n t t h a t has open a r e a s too large to be bridged by t h e some d e t e r i o r a t i o n in performance. However, t h a t decision
soap solution. In tests using t h e bubble test a n d an OVA also has consequences such as d r a m a t i c increases in t h e gen-
together, it has been found t h a t emissions from s m a l l leaks, e r a t i o n of combustion products, which a r e e x h a u s t e d to t h e
identified using t h e bubble test, were well below t h e 10 000 atmosphere. F u r t h e r , for systems h a n d l i n g n o n - i n e r t e d ves-
p p m t h r e s h o l d p e r m i t t e d by t h e control measures. Therefore, sels, a d d i t i o n a l fuel is injected into t h e vapor to i n s u r e t h a t
p r o v i n g all p e n e t r a t i o n s bubble t i g h t m a y be in excess of t h e t h e m a t e r i a l flowing in t h e system is "over-rich." Such conse-
t i g h t n e s s level n e c e s s a r y to pass an AQMD inspection. quences raise t h e question, " A r e we g e t t i n g best possible cost/

186 JULY 1993 MARINE TECHNOLOGY


benefit ratio in the reduction of air pollution from the vapor products of each system, the relative energy consumption,
control systems?" What seems to be lacking at this point is and conventional pollution created by each system. The re-
a carefully reasoned and thoroughly developed study of vapor sults of such an analysis could then be used to either confirm
control performance. Such a study would consider the rela- the current methods of control technology selection or sug-
tive abilities of the different technologies (i.e., refrigeration, gest that by adjusting the basic control limit, a better technol-
incineration, absorption, etc.) to remove VOC's from the va- ogy could be utilized which would result in greater overall
por stream, the consequent quantity and type of discharge reductions in air pollution, quite possibly at a lesser cost.

JULY 1993 MARINE TECHNOLOGY 187

You might also like