Professional Documents
Culture Documents
Piping Fabrication
Document Number: XXXX XXXX XXXXX
XXXXXX—XXXX--XXXXX
Piping and Mechanical Works
Contract No. XXXXXXXXX
X
Piping Fabrication
No. Operation Standard, Verifying Inspection Remarks
Spec or Document/ Response Workshop Fabricato Client (May be used as a sign off column by xxxxxxxxxxx or the
Document Fabricator Client to indicate that the activity has been satisfactorily
Drawing Report . r
completed)
Number
1.0 Approvals
1.1 Welding Procedure Specification (WPS) approval Project Quality AS4041 Approved PE/QC H H/R R
Plan WPS/PQR
1.2 Qualify welders to approved WPS AS4041 WQR PE/QC H H/R M/R
1.3 Prepare WPS and Approved Welder Registers AS4041 Registers PE/QC H H/R R
1.4 Review Subcontractors ITP’s XXXXXXXX ITP PE/QC H H/R R Not required if this pre-approved ITP is
used
2.0 Materials
2.1 Receive materials Project Quality AS4041 D/Dkt/PO WF/ST M M M
Plan
2.1 Inspect materials: D/Dkt/PO WF/ST V/D M M
• quantities XXXXXX
• conformance to requirements
• dimensional
• damage
• material certification
Piping Fabrication
No. Operation Standard, Verifying Inspection Remarks
Spec or Document/ Response Workshop Fabricato Client (May be used as a sign off column by xxxxxxxxxxx or the
Document Fabricator Client to indicate that the activity has been satisfactorily
Drawing Report . r
completed)
Number
3.6 Check fit up, configuration, dimension and orientation WPS AFC Dwg WF/QC V/M M M
3.7 Check for spool and sub spool identification AFC Dwg WF/QC V/M M M
AFC Drawings
3.8 Check welder qualification Welder Register/WQR WF/QC R M M
Register
3.10 Check weld marking (welder’s ID, date and consumable) Weld Maps WF/QC V/M M M
3.11 Check weld root and hot pass WPS WF/QC V/M M M
3.12 Check removal of slag, spatter, scale and flux AS4041 ITP WF/QC V/M M M Verify & accept by signing section 4.6 of this
ITP
3.13 Check completed weld AS4041 ITP WF/QC V/M M M Verify & accept by signing section 4.6 of this
ITP
Piping Fabrication
No. Operation Standard, Verifying Inspection Remarks
Spec or Document/ Response Workshop Fabricato Client (May be used as a sign off column by xxxxxxxxxxx or the
Document Fabricator Client to indicate that the activity has been satisfactorily
Drawing Report . r
completed)
Number
6.0 Delivery
6.1 Ensure that all inspections and tests are completed, all reports Project AS4041 Reports/ PE/Ex H/R H/R R
and documentation are available and all results comply with Management AFC Drwgs Checklists
requirements Plan P. O./ Scope
6.2 Check tagging/marking is in place, correct and secure AS4041 Ex M M M
6.3 Check Delivery Docket completed and forwarded to projects Delivery Docket Ex H/R M M/R Every item shall be marked and listed on the
office Delivery Docket
Piping Fabrication
No. Operation Standard, Verifying Inspection Remarks
Spec or Document/ Response Workshop Fabricato Client (May be used as a sign off column by xxxxxxxxxxx or the
Document Fabricator Client to indicate that the activity has been satisfactorily
Drawing Report . r
completed)
Number
6.4 Ensure that all items are loaded with sufficient dunnaging to Ex M M M
allow safe transport and unloading and prevent damage to
material and surface coatings
6.5 Weights and dimensions of the load shall comply with Ex M M M
statutory requirements. Compliance is the responsibility of the
approved transport contractor
6.6 Deliver product and documentation to nominated location Contract/ D/Dkt Ex/PE R R R
Purchase
Order
7.0 Records
7.1 Check MDR complete and available. Project Quality AS4041 MDR Records PE/QC R R R/H MPDJV Rep to review completed MDR at
Plan source (MEA or Subcontractor facility) covering
SEP.70
SOW