User Name: Intel Date: 02-12-20

Project: Mak University Drawings Time: 13:04:46


Subproject: Boys Hostel Road, 003 Page: 1

ROADCALC DESIGN EARTHWORK - RAW VOLUMES


================================================================================
CUT AREA CUT VOLUME FILL AREA FILL VOLUME
STATION MATERIAL (m^2) (m^3) (m^2) (m^3)
________________________________________________________________________________
0+000.000 Orig_Surface 0.000 0.000
Total 0.000 0.000 344.763 0.000

0+025.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 295.940 8008.794

0+050.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 265.558 7018.730

0+075.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 275.246 6760.054

0+100.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 297.236 7156.028

0+125.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 314.775 7650.135

0+150.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 332.166 8086.761

0+175.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 349.462 8520.347

0+200.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 366.592 8950.670

0+225.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 381.832 9355.294

0+250.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 397.950 9747.268

0+275.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 413.295 10140.561

0+300.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 427.427 10509.032

0+325.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 440.515 10849.275

0+350.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 452.961 11168.448
User Name: Intel Date: 02-12-20
Project: Mak University Drawings Time: 13:04:46
Subproject: Boys Hostel Road, 003 Page: 2

ROADCALC DESIGN EARTHWORK - RAW VOLUMES


================================================================================
CUT AREA CUT VOLUME FILL AREA FILL VOLUME
STATION MATERIAL (m^2) (m^3) (m^2) (m^3)
________________________________________________________________________________
0+375.000 Orig_Surface 0.000 0.000
Total 0.000 0.000 465.401 11479.526

0+400.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 477.840 11790.511

0+425.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 488.126 12074.580

0+450.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 492.953 12263.489

0+475.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 495.468 12355.263

0+500.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 492.332 12347.501

0+525.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 489.275 12270.082

0+550.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 488.830 12226.311

0+575.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 490.298 12239.103

0+600.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 492.172 12280.870

0+625.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 494.558 12334.117

0+650.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 464.908 11993.326

0+675.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 471.335 11703.040

0+700.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 481.373 11908.852

0+725.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 487.923 12116.201
User Name: Intel Date: 02-12-20
Project: Mak University Drawings Time: 13:04:46
Subproject: Boys Hostel Road, 003 Page: 3

ROADCALC DESIGN EARTHWORK - RAW VOLUMES


================================================================================
CUT AREA CUT VOLUME FILL AREA FILL VOLUME
STATION MATERIAL (m^2) (m^3) (m^2) (m^3)
________________________________________________________________________________
0+750.000 Orig_Surface 0.000 0.000
Total 0.000 0.000 490.895 12235.222

0+775.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 490.290 12264.808

0+800.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 487.086 12217.430

0+825.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 483.987 12139.073

0+850.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 480.677 12058.957

0+875.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 476.856 11969.630

0+900.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 473.144 11875.282

0+925.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 469.227 11780.216

0+950.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 457.963 11592.233

0+975.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 454.368 11407.456

1+000.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 448.056 11282.264

1+025.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 440.780 11111.501

1+050.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 435.748 10958.314

1+075.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 410.246 10580.726

1+100.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 375.439 9831.471
User Name: Intel Date: 02-12-20
Project: Mak University Drawings Time: 13:04:46
Subproject: Boys Hostel Road, 003 Page: 4

ROADCALC DESIGN EARTHWORK - RAW VOLUMES


================================================================================
CUT AREA CUT VOLUME FILL AREA FILL VOLUME
STATION MATERIAL (m^2) (m^3) (m^2) (m^3)
________________________________________________________________________________
1+125.000 Orig_Surface 0.000 0.000
Total 0.000 0.000 342.420 8984.602

1+150.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 306.999 8127.968

1+175.000 Orig_Surface 0.000 0.000


Total 0.000 0.000 256.580 7056.203

1+195.222 Orig_Surface 0.000 0.000


Total 0.000 0.000 215.975 4781.611

Total Orig_Surface 0.000 0.000


Total 0.000 0.000 20625.245 507559.139