Professional Documents
Culture Documents
3. Learn how draw down can be balanced using the lift system as a control
to obtain best production
ARCHITECTURE
OF THE AUTOMATED SYSTEM
SIMPLIFYING THE
OPTIMISATION PROCESS
TO THIS
Tubing Gradient
Well Potential
Draw Down
19 Sept 2013
Target BHFP Current BHFP Reservoir Pressure
© 2013 Zenith Oilfield Technology | www.zenithoilfield.com Slide 12 of 46
Target BHFP
Well Potential
Well Potential
GAS
OIL
WATER
GAS
OIL
WATER
GAS
OIL
WATER
GAS
OIL
WATER
GAS
OIL
WATER
OPTIMISED WELLS
GAS
OIL
WATER
GAS
OIL
WATER
GAS
OIL
WATER
GAS
OIL
WATER
GAS
OIL
WATER
AUTOMATED RECOMMENDATION
The automated system relayed the following recommendation for the well
optimization:
57 HZ
Well test total liquid flow at 57 Hz 998 stb/day
Virtual total liquid flow at 57 Hz 1031 stb/day (+3.3% variance from well test)
Well test water cut at 57 Hz 22%
Virtual water cut at 57 Hz 19% (-2.5% variance from well test)
RESULTS
The pump operating point at 47Hz is shown to fall below the pump curve due
to reduced head performance of the ESP whilst emulsions were forming.
The ESP design was slightly oversized to compensate.
19 Sept 2013 © 2013 Zenith Oilfield Technology | www.zenithoilfield.com Slide 34 of 46
CASE STUDY #2:
The gradient plot taken at 47Hz The live IPR Plot shows the
shows bottom hole flowing pressure BHFP operating point on the well
has achieved the target of 370psi inflow curve
RESULTS
The VSD frequency was increased from 43Hz to 47Hz over the course of
optimisation
Correspondingly the production rate was increased from 570 stb/day to
671 stb/day
With water cut averaging 73% this equated to a 27 bopd increase in
production:
AN UNDERPERFORMING
& UNDERSIZED ESP
The target BHFP was set at 1131 psi Reservoir Press
AN UNDERPERFORMING
& UNDERSIZED ESP
The bottom hole flowing pressure stabilised
at 1267 psi with a liquid rate of 2720 stb/day
The target bottom hole flowing pressure
provided scope for an additional 1142 stb of
fluid (PI 8.4 stb/d/psi )
The ESP installed was not capable of providing
this additional flow rate
In January 2012 the ESP was resized based on
the recommendations of the real time system
and draw down was optimised to the target
bottom hole flowing pressure
Flow rate was increased to 4027 stb/d
19 Sept 2013 © 2013 Zenith Oilfield Technology | www.zenithoilfield.com Slide 38 of 46
CASE STUDY #3:
RESULTS
Automated diagnosis and frequency optimisation of the underperforming
ESP provided an additional 73,000 barrels of oil ($7.15 Million) in the 334
days of operation with the real time system
The ESP under performance issue was highlighted immediately the
automated system was implemented on the well
Further increase in rate was limited by the upper flow range of the ESP
Resizing of the ESP in January 2012 resulted in:
www.zenithoilfield.com