Professional Documents
Culture Documents
2. One duty pump and one spare pump 4. Two duty pumps and one spare pump
• Each pump is to be installed with separate lines • The two duty pumps are installed with a separate
and sized to 100% of the nominal flow. lines and the spare pump is designed to pump
• Not Functional failure scenario: into either line. All three pumps are sized to
o Work is scheduled when a functional pump 50% of the nominal flow.
failure is imminent or when parts and • Not Functional failure scenario:
maintenance crews are available. o Work is scheduled when a functional
o Production rates will be reduced to failure is imminent or when parts or
75% for ½ hour while pumps are being maintenance crews are available.
switched and production rates will o Production rates will be reduced to
return to full rates after the pump 75% for ½ hour while pumps are being
switching has successfully occurred. switched and production rates will be
This production loss is to account for returned to full rates after the pump
the potential production upset when switching has successfully occurred
pumps are being switched. If the stand- • Functional failure scenario:
by pump fails during start-up, the duty o If the failure occurs on the off-shift,
pump will be put back in service until maintenance personnel are not called
the stand-by pump is repaired. out to repair the failure unless the
• Functional failure scenario: stand-by pump does not start.
o If the failure occurs on the off-shift, o If the failure occurs during the day
maintenance personnel are not called shift, the weekly schedule is broken
out to repair the failure unless the into to repair the failure.
stand-by pump does not start. o Production will be reduced to 50% until
o If the failure occurs during the day the stand-by pump is started using
shift, the weekly schedule is broken similar pump starting assumption times
into to repair the failure. as in the one duty pump and one stare
o Production loss would be 100% until pump functional failure case.
the stand-by pump has started. Based
on interviews with operations personnel Information used in the Pump Life Cycle
it usually takes 1 hour to start the stand-
by pump, but can take as little as 15 Cost analysis:
minutes or as long as 6 hours if the 1. Capital costs were based on a class 5 costs estimate
stand-by pump has a failure while completed by engineering consultants on the
starting. For this analysis it was expansion project.
assumed that on average a 2 hour
outage will occur when attempting to 2. Maintenance costs resulting from failures were
start the stand-by pump at a functional broken in to 5 types - belt failure, packing failure,
failure of the duty pump. pump failure resulting in pump needing to be replaced,
motor failure and instrument failure. As mentioned
3. Three duty pumps and no spare pumps above the failure types were broken into functional
• Each pump is to be installed with a separate line and non-functional failures since maintenance
and size to 50% of the nominal flow.
strategies will be different for the two types of lost production, tradespersons would be called in
failures. and repair would be done on overtime).
• Mean Time Between Failure (MTBF) was
determine using historical SAP data from existing 3. Predictive/Preventative Maintenance Costs were
pumps (61071/61480, 61437/61438 and calculated with information provided by the
61474/61745) from January 2005 till December Reliability Supervisor Huw Morris and factored for
2008 and modified assuming that the MTBF will the number of operating pumps.
increase with the pump system design
improvements planned on Vault. 4. Stocked spares costs were not included in the
o Belt failure – calculated MTBF = 2.3 analysis because it was unknown how many pump sets
years; MTBF used = 4 years would require the different types of stocked spare
o Packing failure – calculated MTBF = 9 parts and when factored over the number of pump sets
months; MTBF used = 1.5 years would not make a significant change in the results.
o Pump Replacement – calculated MTBF
= 1 year; MTBF used = 2 years 5. Energy costs were calculated using the calculated HP
o Motor failure – Calculated MTBF = 8 required and the pump efficiency for the type of pump.
years, MTBF used = 8 years The pump efficiency was factored for the type of
o Instrument Failure – Calculated MTBF pump, since the larger the pump the more efficient it
= 4 years, MTBF used = 4 years was. Another factors is where the system curve would
• Repair costs were determined using existing sit on the pump curve. On 2 duty and 3 duty options
SAP data from existing pumps (61071/61480, the flow rate range was wider than for the options with
61437/61438 and 61474/61745) and factored for a stand-by pump, and thus the normal operating point
the size of the pump. Repair costs were was lower in the pump curve.
calculated using the material costs for the repair
and the labor costs calculated from the 6. Lost production was based on the MTBF, repair time,
maintenance repair time. failure type and consequences of failure. Using these
• Repair time was determined using SAP data factors the equivalent hours of annual down time was
from existing pumps (61071/61480, 61437/61438 calculated. The consequences of failure were the key
and 61474/61745) and information provided from assumption which varied for the various pump options
maintenance planners Bryan Busby and Gerald as discussed above.
Fehr. The repair time was factored for the size of
pump (longer repair time to replace a 6X4 pump 7. Operator costs were based on information provided
compared to a 12X10 pump), failure type (non- by Operations Superintendent Brad Lefebvre and
functional failures were treated as planned work factored for the number of operating duty and stand-by
orders and functional failures were treated as spare pumps. It was assumed that an operator would
non-planned or emergency work orders) and spend 10 minutes per shift on an operating a duty
production consequence (if a failure resulted in pump and 5 minutes per shift on a stand-by pump.
Capital Cost
Number of 1 Duty 2 Duty
Pump Sets 2 Duty 1 Standby 3 Duty 1 Standby
8 $8,990,567 $13,266,252 $8,517,325 $8,167,725
18 $21,105,019 N/A N/A $21,257,565
1 Duty 2 Duty
Option # 2 Duty 1 Spare 3 Duty 1 Spare
Capital Acquisition Costs $954,908 $1,752,288 $1,031,888 $983,888
Advanced Growers
Technologies:
Leader in Specialty
Fertilizers
Turf,
$350-million sales
Home,
Garden
Capital Cost
Number of 1 Duty 2 Duty
Pump Sets 2 Duty 1 Standby 3 Duty 1 Standby
8 $8,990,567 $13,266,252 $8,517,325 $8,167,725
18 $21,105,019 N/A N/A $21,257,565
Summary the Pumping
Strategy