You are on page 1of 2

Monobore design can benefit high-rate gas wells

MONOBORE COMPLETION tech- REMEDIAL ADVANTAGES tion system where a 10-in. liner was set
niques are becoming more standard in and an intermediate tubing string was
the industry today. The remedial advantages of monobores landed in the tieback receptacle (TBR)
may not be realized until later in the below the liner hanger. This portion
“Monobore” describes a completion in field’s life. landed static seals into the TBR with an
which the ID of the completion string is
Running service and intervention equip- upper polished bore receptacle (PBR)
the same size from top to bottom.
ment is made easier by the elimination above a compression-set packer.
As the industry moves toward high rate of restrictions. In addition, one has full The third trip landed a set of dynamic
gas completions, many of which will rely access to the liner top to allow easier production seals into the PBR and was
on 95/8-in. tubing, the benefits of running squeeze or mechanical isolation. By tied back to surface.
monobore completions are more readily increasing tubing size—thus reducing
attained. Eleven completions of this type were put
the frictional pressure drop during pro-
into service with no equipment failures
These benefits fall into two main cate- duction—it is possible to delay the need
since that time while delivering higher
gories: well production and remedial to bring compression on line as well.
than predicted production.
operations. Thus, the value of increasing tubing size
can reach into the millions of dollars for DESIGN IMPROVEMENTS
PRODUCTION BENEFITS infrastructure, wellbore construction,
Responding to a growing industry
The most obvious benefit associated and maintenance alone.
demand for an improved 95/8-in. comple-
with increased tubing size is greater per tion design, one service company under-
However, the dramatically decreased
well deliverability. took a design program to develop an
field development time that running 95/8-
This reduces the number of wellbores in. monobores provides cannot be integrated large monobore completion
required to drain a reservoir efficiently. ignored. This shortened time to first system. Considering the success of the
production will allow operators to either Arun field development, this concept
For offshore projects in particular, was used as a starting point.
this can mean a reduction in the Figure 1: Cost simulations At the time of the Arun project
number of platforms required. 5 1/2-in. completion
there was no 95/8-in. tubing retriev-
Reducing the number of wellbores 23 wells
able safety valve (TRSV) available.
decreases both operational and 125 MMscfd/well
$268 MM With production rates in excess of
maintenance expenses for the field. 7-in. completion 200 MMscfd anticipated, the poten-
Long-term reliability is increased 15 wells tial impact any loss of well control
as monobore completions tend to 201 MMscfd/well will have is magnified.
be less complex than standard com- $220 MM
pletions and the elimination of 9 5/8-in. completion Environmental, health, and eco-
internal restrictions reduces areas 8 wells nomic consequences of such an
of gas turbulence. 383 MMscfd/well event made the development and
$195 MM installation of a reliable 95/8-in.
To demonstrate the well production TRSV critical.
benefits, a hypothetical high-rate
gas reservoir was constructed from The second area identified for
which inflow performance models improvement was the elimination of
were run to determine the number of the upper dynamic seal stack and the
produce first gas much quicker or delay
wellbores needed at project’s beginning associated PBR.
starting the project by that same
and end to meet field deliverability amount of time. Doing so has several advantages. First,
requirements of 1.6 bcfd. the completion will be less complicated
This factor can be the most significant
Simulations were run for 51/2-in., 7-in., and a potential leak path is eliminated.
impact on the net present value of a
and 95/8-in. completions. In addition, large project. For many projects, this In addition, the third trip required to
drilling and completion costs were esti- increase in value more than pays for the land the upper completion is no longer
mated and accounted for increased rig increase in cost associated with using necessary. Completion cost will be lower
capacity needed for running a 95/8-in. larger tubing. as well as both pieces of equipment will
completion string. The estimate be unnecessary.
accounted for no topside structures or The original high-rate gas completions
equipment other than wellheads and were run by Mobil Oil Indonesia in To realize these benefits, a packer capa-
Christmas trees. their Arun field in 1991 and 1992 and ble of withstanding all compressive and
are shown in Figure 2 as the “Original tensile loads on the tubing string during
The results of combining these two esti- Completion Concept.” production, stimulation, or well kill
mates are shown in Figure 1. operations is needed.
This project called for a 3-trip comple-

48 D R I L L I N G C O N T R A C T O R March/April 2001
Referring to Figure 3, the latest Figure 2: Original concept Figure 3: Improved concept imparted and any slip inva-
evolution of the 95/8-in. monobore sion in the production casing.
completion system is shown as 9 5/8 in.
9 5/8 TRSV
The slip is located above the
the “Improved Completion Con-
20 in. PBR & TBG 20 in. multi-durometer element
cept.” After setting the 95/8-in. Seal assembly package, with prevents com-
liner, the rest of the completion
pressive loads from being
can be run on the second trip. Packer High Load Packer transmitted through the ele-
After clean up, the well can be
ments as a burst load into the
produced.
production casing. Since
Disappearing Plug
In order to develop equipment there is no slip below the ele-
with sufficient reliability, it is ment, ramped element tech-
critical that a thorough design Liner hanger nology is used to set the ele-
verification test program be con- TBG & Liner Hanger ment package.
13 7/8 in. 13 3/8 in.
Tieback seals TBG & Tieback
ducted. This ensures the relia-
Seals Instead of using compressive
bility of newly developed equip-
force to seal the element to
ment and provides an industry
the production casing the ele-
appropriate (rather than opera- 10 in. 9 5/8 in. ment is forced up onto a por-
tor or project specific) solution.
tion of the mandrel with an
EQUIPMENT DETAILS 133/8-in. production casing. This geome- increased OD. This axial force seals the
try is a direct result of cooperative annulus and prevents element relax-
A 95/8-in. wellhead plug incorporating a design efforts between the service com- ation over time. The packer design also
non-bearing no-go has been developed. pany and major operators. allows for retrieval in the event of an
The no-go feature allows a significantly emergency while providing permanent
larger bore while decreasing its OD. The original design called for a 141/2-in.
packer performance and reliability.
This feature, along with its short length, OD for a 95/8-in. valve, which is unaccept-
can potentially reduce the size and able to the operator community. Testing to ISO V0 requirements were
therefore cost of the riser, tree, associ- scheduled to be completed in late
To get the reduced OD/ID ratio, the use
ated valves and the BOP stack. March. Three methods are available to
of contoured flapper technology is need-
set the high load packer, two of which
A back pressure valve has also been ed. While a standard, proven platform
require no intervention.
developed that uses the same service was chosen to base the design upon,
equipment as the wellhead plug. A larg- three new features have been developed The first of these (and easiest) is to
er flow area through this valve is avail- to provide reliability and performance. apply pressure against the liner or for-
able due to the wellhead plug’s mation to set the packer. If that is not
First, dual rod piston actuation with
increased ID. Both the wellhead plug possible, a disappearing plug has been
independent metal-to-metal sealing was
and back pressure valve have been suc- developed. The barrier is comprised of a
selected to improve the performance of
cessfully run downhole. salt/sand matrix.
the valve.
The liner hanger selected for the 95/8-in. By running a fill device above the matrix
Second, a mechanism combining a com-
completion system uses unique slip one can run in with the tubing closed.
pression spring and beam spring has
geometry that greatly reduces the stress When infused with water or some com-
been used to close the flapper. Due to its
imparted to the production casing. pletion fluids the matrix dissolves and
weight, the use of a standard torsion
can be expended by applied pressure
Unlike standard cone and wedge type spring closure mechanism is not desir-
from the surface, allowing full access to
systems, increasing the load capacity of able. This modification allowed the
the liner.
this hanger does not alter the OD/ID design team to produce a more robust
ratio of the tool. Thus, the tool can be hinge configuration for the flapper/seat. The third option is a retrievable bridge
modified to accept a variety of load con- plug. The design selected is currently
Lastly, flapper supports have been
ditions. available and has an extensive field his-
placed in pockets machined into the seat
tory.
Depending on whether liner rotation is that provide a greater bearing area.
required, this liner hanger can be set These supports prevent flapper deflec- FOCUS ON COSTS
either mechanically or hydraulically. tion under load. This valve design has
been successfully high-rate gas slam Natural gas is becoming a larger portion
The design was used successfully in
tested at rates in excess of 400 MMscfd of many nations’ energy strategy. Thus,
Arun, has a considerable field history
and endurance tested to simulate a 20- the pressure to deliver gas supplies
and a battery of successful design verifi-
year life cycle. Seven of these valves safely, reliably, and more economically
cation tests for the hanger, liner wiper
have been run to date in the Gulf of Mex- is growing.
plugs, drill pipe darts and landing col-
lars. ico.
The benefits associated with monobore
The hydraulic-set packer developed to completions in general, and large mono-
Perhaps the most significant feature of
eliminate the upper PBR and seal bore completions in particular, will help
the slim 95/8-in. TRSV developed for the assembly incorporates 360° bi-direction- realize this goal. n
system is its capability to be run inside al slips. This minimizes both the stress

March/April 2001 D R I L L I N G C O N T R A C T O R 49

You might also like