You are on page 1of 12

Proceedings of the 2014 10th International Pipeline Conference

IPC2014
September 29 - October 3, 2014, Calgary, Alberta, Canada

IPC2014-33740

PUMP STATION DESIGN

Jim W. Horner Martin R. DeBusman


Enbridge Pipelines Jacobs Canada
Edmonton, Alberta, Canada Edmonton, Alberta, Canada

ABSTRACT
This paper reviews Enbridge’s recent experience with the Reductions in station construction costs are obtained by
design and construction of new pump stations during its most minimizing pipe, fitting and equipment sizes. A typical 4-unit,
recent wave of expansion that started in 2007. This expansion NPS 24 station has been consolidated such that total extend of
includes over $4 billion in pump station construction and the station piping is less than 100 m. Culverts are not
upgrade. Enbridge is working on its third generation station acceptable for access to larger equipment, so keeping piping
design and is starting to benefit from a consistent design systems aboveground also helps to minimize the length of
composed of standard elements. piping, number of fittings and welded joints needed to
“porpoise” buried piping aboveground to allow access to these
The principle objective of this design effort was to improve components. Due to this advantage and others, it became an
environmental protection at pump stations. In the design’s early design philosophy to keep station piping above grade.
development many different areas of concern were investigated
including: building code compliance, pump shelter ventilation Keeping station piping aboveground also improves
requirements, improvements to station metering accuracy, constructability as it increases the potential for prefabrication.
mitigations to improve fire safety, inclusion of an aboveground Aboveground piping also minimizes the costs associated with
sump tank, and equipment access and removal to name a few. excavation, shoring, treatment of groundwater collecting in
While work has been done to improve mechanical and excavations and the complexities attendant with confined
structural systems, they have also been standardized in an spaces.
attempt to develop consistent components. The objective of the
paper is to provide a summary of these developments and some Finally, improvements in environmental protection are
background on the thinking that shaped the design. achieved by upgrading containment for minor leaks and
improving detection of major leaks. These improvements
INTRODUCTION would also include the potential to minimize cleanup costs
The development of the new station design had several associated with a leak resulting from an operational error and
objectives that included: minimize site disturbance during construction.
• Improvement of operational integrity;
As can be seen, these design objectives are not mutually
• Reduction in station construction costs; exclusive. Concepts that emerged included: keeping the piping
• Improvement in station constructability; and aboveground; creation of better containment and detection
• An improvement in environmental protection. systems; and minimization of pipe, fitting and equipment sizes.
To further eliminate buried piping it was also decided to
Improving operational integrity includes elimination of incorporate an aboveground sump tank into the design so that
buried piping that cannot be internally inspected. This all drain lines would be aboveground. Putting the sump tank
objective also means that equipment is to be readily accessible aboveground also minimizes drain line runs as it can be placed
for maintenance and “dead ended” piping should be minimized in closer proximity to the drain source. This is an incidental
to reduce contamination between batches. These maintenance use tank, not a storage tank, and is empty most of the time.
requirements do not permit burying of piping components like Aside from compliance with accepted tank construction and
instrumentation, flow meters and pressure control valves. venting standards it does not pose a safety risk.

1 Copyright © 2014 by ASME


PUMP SHELTER
The pump shelter is the most overlooked component of the The main detriment of any building system is that it
pump station. It is often viewed as an expensive accessory, and inhibits access to the piping and equipment it shelters and may
often eliminated to the chagrin of operations and maintenance inhibit dissipation of any flammable gases that might evolve
staff. This paper begins with an examination of the benefits from the process equipment. Some strategies have been
and constraints associated with this core element. developed to deal with the access constraint and include:
• Installation of roof hatches over major pieces of
The pump shelter building has been considered an asset for equipment to allow external crane access;
equipment maintenance and can have some benefit in
improving equipment reliability. The cost benefits of these • Providing limited crane capacity for equipment
features have usually been difficult to quantify. The first maintenance with access doors and entry corridors to
paradigm shift made in the development of Enbridge’s new allow crane access inside the structure;
pump station design was to consider the pump shelter to be part • Providing a full capacity crane and access to lift any
of the station containment system. Cleanup costs associated piece of equipment contained within the structure and
with a single minor incident can be in the millions of dollars. place it on a transport.
Considering the frequency of minor leak events and the
potential impact on a pipeline company’s “social license”, a Two design strategies evolved. Initially building designs
reasonable level of investment can be justified. included a drive through lane with access doors at each end of
the building. The intent was to allow crane access within the
The shelter containment system has three critical functions: building. As larger station designs were developed this strategy
capture or deflection of leakage to the building’s containment was abandoned for a structure with an integral crane to reduce
slab; rapid detection of a leak to facilitate shut down and the building foot print. As will be discussed in more detail
isolation of the station piping and exclusion of water from the later, the change was made to ensure compliance with building
environment that might cause a false indication. The most and fire codes.
important element is the ability to detect the leak rapidly. Even
a minor leak from a ruptured instrumentation connection can Other areas that had to be revisited with a new, larger
create a significant incident if it continues undetected for hours building design included:
at a remote site. Therefore the system has to be simple, reliable
• fugitive emissions due to the increase in piping and
and protected from the influence of the elements.
equipment included in the building envelope;
This system includes a low point floor sump with level • any additional ventilation requirements owning to higher
switch instrumentation as part of the floor slab. Any liquids piping design temperatures (60°C);
will flow to the sump and be detected. This allows the control
center to react quickly to isolate the source of pressure and • any building or fire code implications; and
minimize the impact of the leak. The shelter, floor slab and • fire studies to validate separation criteria for critical
detection instrumentation are the major elements of this facilities.
containment system.

In the past, as the name suggests, pump shelters have Ridge Vent
generally been restricted to a weather shelter for the mainline
pumping units and their associated driver. To provide a more
complete containment system, the pump shelter had to be
expanded to cover the pump’s isolation valves, the header
piping, control valves, flow meters and as much of the Exhaust Fan
associated instrumentation as possible, or in short to contain as
many of the leak sources as possible. To minimize the cost
associated with this larger building the associated piping was
made as compact as possible to minimize the footprint and
alternative building styles were considered.
Access Door Inlet Louvers
ALTERNATE BUILDING DESIGNS
To offset the increased cost associated with these larger
“containment structures”, alternative fit-for-purpose strategies
were considered. Typically, pump shelters have been metal
clad, metal framed buildings. Metal framed, fabric clad
buildings have become more popular recently and can be 30%
to 40% lower in cost than a comparable metal clad structure. Figure 1: Pump Shelter Building

2 Copyright © 2014 by ASME


VENTILATION REQUIREMENTS
A ventilation check was necessary because the pump The Average Emission Factor Approach included in API
shelter would now house more piping, fittings and equipment. Std. 46382 was used to estimate the fugitive emissions from
The new aboveground sump tank was of particular concern. piping and equipment within the pump shelter. The number
The function of the sump tank is to provide 795 m3 (5000 gal.) and type of emission sources were tabulated and assigned
of temporary containment for fluid drained from the pumps for emission factors from API Std. 46153. The emission factors
maintenance or released from the pumps seals or thermal relief were multiplied by the numbers of fittings to determine the
valves. The sump includes a reinjection system to return this total fugitive emissions.
drained fluid to the pipeline. The tank vent and connections to
pump into or out of the sump tank are outside the building. The A worst case emission rate of 0.549 kg/hr was obtained for
sump tank includes level measurement instruments and a hatch the situation where the sump tank access hatch had been left
to dump small quantities of fluid and to allow visual inspection open. This translates to a volumetric rate of 0.150 cfm. This
of the tank level. The sump tank was brought into the pump requires a minimum ventilation rate of 210 cfm to maintain
shelter to minimize drain piping and to keep it aboveground. vapour levels below 20% of LEL (this includes a safety factor
The building slab also provides secondary containment and of 4). The twelve (12) ACH requirement results in a ventilation
leak detection for the sump tank. rate of 75,000 cfm, for the size of pump shelter contemplated,
which more than exceeds the dilution requirements. Therefore
For the purposes of this design, adequate ventilation was the electrical area classification inside the building is Class 1,
defined as ventilation (natural or artificial) that is sufficient to Zone 2 above the sill of the inlet louvers.
prevent the accumulation of significant quantities of vapour-air
or gas-air mixtures in concentration above 20% of their Lower In addition to the ventilation rate required to achieve the
Explosive Limit (LEL). In addition, API RP 5051 requires a appropriate dilution, the ability to meet the natural and artificial
minimum air flow rate of twelve (12) air changes per hour air change requirement was also reviewed. Preliminary
(ACH) for naturally ventilated enclosed areas. calculations indicated that the required air changes could be
achieved with inlet louvers along both sides of the building and
To confirm ventilation requirements were met, a fugitive exhaust louvers on the end walls. This could provide cost
emissions study was completed. Enbridge standards also savings over a building ventilation system that had exhaust
require a further six (6) ACH of artificial ventilation be vents on the ridge of the roof or ridge vents (see Figure 1).
incorporated and activated for LEL excursions above 20% or if These ridge vents had been accepted practice in past designs;
the internal building temperature exceeds 35°C (95°F). therefore air modeling studies were completed to validate this
new approach.
Figure 2: Pump Shelter Ventilation without Ridge Vent

3 Copyright © 2014 by ASME


A number of scenarios were evaluated covering a range of BUILDING & FIRE CODE COMPLIANCE
temperatures and wind conditions. It was found that the end In over 60 years of operation, Enbridge has not had a pump
wall exhaust vents failed to provide the necessary natural and station fire resulting from equipment or piping failure.
artificial air changes during calm wind conditions or when the Considering the number of pump stations in operation this
prevailing wind approached from an end wall (see Figure 2). represents thousands of years of station operation. This record
The ridge vent design, which included exhaust fans on the end is attributed to robust process controls, operating procedures
walls only, provided the required ventilation under all and operator training. However, the frequency of a product
conditions and maintained lower temperatures within the leak is significantly greater than a fire event at a pump station.
building with natural ventilation (see Figures 3 & 4). The
analysis also confirmed that the greatest heat source in the While the objective of the pump shelter containment
building was the pump motors and the heat rejected from the concept was to reduce the environmental risk, Enbridge also
piping operating at 60º C (140°F) was inconsequential. sought to confirm that the system was in compliance with

Figure 3: Pump Shelter Temperature Profile without Ridge Vent

Figure 10: Pump Shelter Temperature Profile without Ridge Vent

Figure 4: Pump Shelter Temperature Profile with Ridge Vent

4 Copyright © 2014 by ASME


applicable building and fire codes. These codes set a level of • The pump and motor are also equipped with seal leak,
fire protection and life safety requirements for buildings and vibration, and bearing, motor winding and case
their occupants. However, the primary focus of these codes is temperature instrumentation to detect a fault and de-
for urban environments and they do not adequately address all energize electrical systems to further eliminate ignition
hazards and building uses. sources.

The pump shelter is considered to fall within the building • The potential of explosion due to buildup of vapours is a
code category Group F, Division 2. This type of building remote risk due to the natural and artificial ventilation
requires a water supply for firefighting if the floor space provided and the gas detection systems.
exceeds 600 m2 (6455 ft2) and a sprinkler system if it exceeds
800 m2 (8600 ft2). Because most pump station sites are remote, By completing the required risk assessment and using
they are not within the range of municipal water supplies or published variances allowed by provincial authorities, the
within local fire response areas. Even if a clean water supply building size requirement for fire water can be increased to
was maintained on site, the time needed for a local response is 1200 m2 (12,900 ft2). In spite of the fire water relief provided
too great to prevent loss due to fire. Instead a risk assessment by these variances, it became a default design constraint to limit
by a professional engineer was completed for the building the building footprint to a maximum of 800 m2 so that
detailing the fire prevention measures included in the design. sprinklers are not required. This limitation also helps to
Some of the key analysis points of the risk assessment were: minimize potential building egress path lengths.

• The pump house is not normally occupied. Personnel FIRE STUDY


are only in the building during maintenance and One of the guiding principles of the design effort was to
inspection activities and these personnel are trained for provide containment for as many if not all of the potential leak
work in this environment. sources associated with the station piping. This initially
included the mainline sectionalizing valve and the two (2)
• Ignition sources are limited as all electrical and
station isolation valves (commonly referred to as the 3-valve
instrumentation is rated for Class 1, Zone 2 hazardous
cluster). The concept is such that there would only be welded
areas as a minimum.
pipe outside the containment system. In spite of the low fire
• The likelihood of a hydrocarbon release is reduced by risk mentioned it was decided that these “mainline”
having the mechanical seals on the pumps directly components would not be located inside the shelter.
connected by piping to a sump tank.
A typical 3-valve cluster design includes a through conduit,
• If a hydrocarbon release does occur, there are controls in slab gate sectionalizing valve located such that it is in line with
place to warn personnel. In addition to the leak the buried pipeline. The actuator and valve bonnet are above
detection instrumentation, fire and combustible gas grade for ease of access and maintenance. The station isolation
detection will initiate evacuation alarms. The fire and valves are ball valves located aboveground and connected to
gas detection will also close the station isolation valves the pipeline on either side of the sectionalizing valve via
eliminating the flow of hydrocarbons into the station and vertical risers. As will be explained later, this
limit the size of a potential release.

Figure 5: Fire Study Pipe Temperatures

External Pipe
temperatures
acceptable

5 Copyright © 2014 by ASME


arrangement is preferred for the ball valves to allow a
horizontal stem orientation (with actuators above ground) and
to keep the lines to and from the station aboveground to
facilitate inspection.

A fire study was conducted to investigate the impact of a


fully involved station fire and to confirm separation criterion
from the 3-valve cluster. The study included a simulation of a
station fire that assumed a leak sufficient to fill the containment
slab (≈95 m3 or 600 bbl). The results showed that the
separation criteria, of 7.6 m (25 ft.), would be sufficient to keep
the valve temperatures well within an acceptable range and not
compromise their ability to isolate the station (Figure 5). This
agrees with the same separation required for the electrical
buildings. Additionally it was also decided that power and
control cabling to these valves would be protected by burying
them or keeping them at least 7.6 m from the pump shelter.

PIPE SIZING
At the outset of design efforts, pipe sizing was based on Figure 6: Flow Distortion at Elbow
limiting the velocity in station piping to 3.65 m/s (12 ft/s). It
was felt that this limit was too conservative. Pipe sizes
determined by this method yielded lower pressure drops, but it
also resulted in significantly higher station construction costs requires more pipe and fittings to achieve the necessary piping
and greater pipe stresses owing to the larger and more rigid flexibility. Therefore, the most common piping schemes keep
piping. This limiting velocity was based on recommendations the elbows vertical with 2D of straight pipe between the elbow
in API 14E4. and the pump suction. This ensures the turbulence induced by
the elbow in the vertical plane does not affect the axial or
Many publications have shown API 14E to be too horizontal flow split in the pump case as the fluid is distributed
conservative. It was subsequently decided to increase the between the two suction eyes of the pump impeller.
limiting velocity based on the work of Salama5 on piping
erosion with fluids containing sediment. The accuracy of his Past practice turned the elbows down to allow good access
work was verified by four independent laboratories by to the pump, but the pump suction and discharge lines had to be
measuring erosion rates in pipe bends. Testing of various crude routed under the pump house floor which made inspection
streams helped to determine a basis for particulate size and problematic and also increased construction challenges. As
concentration. This work indicated that a maximum velocity of pumps became larger it became common to elevate the pumps
11.74 m/s (38.5 ft/s) in crude oil would result in an acceptable such that a horizontal flange pair could be installed near floor
erosion rate. Therefore, the limiting velocity was increased to level at the base of the elbow to facilitate removal of the piping
6.1 m/s (20 ft/s). This decreased the station piping size from and to add a degree of flexibility in the fit-up of the piping.
NPS 30 to NPS 24, saving over $2.5 million per station. Alternately trenches or basements have been employed to allow
access to the piping, but this introduces structural complexity
and, added cost, and also creates a confined space.
PUMP PIPING DESIGN
One of the major determinants of pump station piping
Some station designs have been executed with the pump
design is the hydraulic considerations associated with the
elbows turned up. The advantage of this type of arrangement is
pumps. Elbows generate turbulence that can affect the flow
that the pump and motor can be placed at ground level
distribution entering a pump nozzle as shown in Figure 6. This
providing good access to the equipment while eliminating the
is particularly problematic on the single-stage double suction
need for platforms. The drawback with this design is that what
pumps most commonly used in pipeline applications. Enbridge
goes up must come down. There is a significant volume of
standards require keeping suction elbows out of plane with the
additional fluid in these vertical loops that has to be drained to
pump axis or adding 5D to 7D of straight pipe between the
allow equipment maintenance. Proper venting of the loops can
elbow and the pump suction.
be problematic and this approach requires extra fittings, pipe
and welded joints. While these vertical loops can provide
Adding straight pipe to the pump suction to keep the piping
excellent flexibility this can also be a drawback as they need to
flat increases the spacing between the pumps and ultimately
be stabilized to prevent excessive vibration. Due to adverse
increases the footprint of the station. This configuration also
experiences, this type of design is discouraged at Enbridge.
inhibits access to the pump for maintenance and usually

6 Copyright © 2014 by ASME


The approach adopted was to elevate the pumps on raised The length of station header between the pump isolation
foundations to allow the elbows to be placed in a vertical down valves includes a check valve. This check valve closes to
orientation. The pumps were elevated so that all station piping prevent recirculation from the pump discharge to its suction
was kept aboveground for ease of access and leak monitoring. during normal operation. When the pump is isolated, this check
This configuration requires the addition of an access platform valve opens to allow flow to bypass the pump as shown in
around the pumps and motors, but it allows a critical ancillary Figure 7. There can be significant turbulence at the discharge
benefit. The sump tank and associated drain piping can be Tee as the flow turns into the header. This turbulence can cause
brought aboveground. The pumps can drain by gravity to the the check valve to remain open temporarily during pump
sump tank and the sump can be placed on the pump shelter startup. If the check valve remains open as the pump continues
containment slab which in turn provides secondary containment operation it will eventually close under full differential pressure
and leak monitoring. developed by the pump. Closure of the check valve under these
conditions will cause water hammer and premature wear to the
HEADER PIPING DESIGN check valve seats. For this reason the check valve is usually
The other major hydraulic consideration is in the positioned closer to the suction Tee to minimize the influence
manifolding or interconnection of the mainline pumps. Pumps of the turbulence at the discharge Tee.
can be connected in either series or parallel to provide the
specific combination of flow and pressure required. Most of After the last pump, the header is normally turned back
the systems are currently being designed to accommodate 180º towards the 3-valve cluster. This “return” header provides
higher viscosity crudes. Due to the steep “system curve” or the necessary straight pipe for the pressure control valve (PCV)
higher pressure gradient associated with viscous crudes, series if required and the station flow meter. The flow meter was not
pumping configurations tend to provide the greatest utility. always a common component of pump station design, but it is
now considered essential to augment the accuracy of leak
With the pipe to pump interface and manifold detection systems. To obtain the desired accuracy, Enbridge
configuration selected, the piping layout can proceed. The standards require 20D of straight pipe immediately upstream of
general configuration starts with the station suction entering the meter and 10 D downstream.
one end of the pump shelter with connection to a Tee at the
suction of the first pump. The Tee directs the flow into the In the past, the pump header and this length of straight
suction of the first unit or allows the flow to bypass the pump if return pipe were outside the pump shelter building. In this new
it is out of service. The bypass outlet from the Tee is the design, all this piping is included in the pump shelter. The
beginning of the “station header”. This common length of return header continues outside the building to make
piping provides the manifold that connects to the suction and connection to the station discharge isolation valve. This covers
discharge of each pump. Each pump has a valve on the suction all the major piping components except the Bypass Check
and discharge piping to allow isolation for maintenance. Valve and the station Discharge Check Valve.

The bypass check valve is only required on pump stations


Figure 7: Pump Unit Piping
that employ PCVs. It is required by Enbridge standards to
safeguard against inadvertent closure of the PCV. If such an
event occurs it can cause a significant transient and lead to a
cascading shutdown of the pipeline. To prevent damage and
this loss of control, a bypass line complete with check valve is
installed connecting the station suction to the return header
Suction downstream of the PCV, but upstream of the station flow meter.
Valve This provides an alternate “relief” flow path should the PCV
close while continuing to provide flow measurement. The 20D
of straight pipe required upstream of the flow meter means this
Unit
Check Valve
line is significantly longer than it would be prior to the
inclusion of the flow meter.
Discharge
Valve
The station discharge check valve is usually positioned
between the PCV and the bypass connection to the return
header. The function of the discharge check valve is to prevent
a major back flow through the station that might cause the loss
of line pack or an idle pump to “windmill” in reverse rotation.
Starting a pump under this condition could cause shaft or
coupling damage. The one unintended outcome of adding this
check valve is that it can separate the header into two sections
complicating thermal relief (see Figure 8).

7 Copyright © 2014 by ASME


Three Valve
Cluster
By Pass Flow Meter
Check Valve
Discharge
PCV Check Valve
Sump Tank

Figure 8: Station Piping Layout

When piping is sheltered from the elements, thermal relief The piping between the pump and the unit isolation valve
required by solar heat gain can be eliminated. The exposed was designed to be as short as possible to minimize the impact
lengths of suction and discharge piping between the pump of thermal growth on this segment. The greater problem was
shelter and the 3-valve cluster provide sufficient exposure that the interaction with the longer station header. A common
thermal relief was deemed necessary. The station discharge method of controlling stress is to increase flexibility by adding
check valve would normally require thermal relief on either loops or bends. The standard header design is composed of
side of the valve. To eliminate this redundancy, and allow a straight pipe with check valves between a series of Tees
better positioning of the relief valve, the discharge check valve connecting each pump suction and discharge line. To provide
is drilled with a 12.7 mm hole (0.5 inch) so that it can still the desired flexibility, a series of functional loops were
prevent massive back flow, but not allow a pressure differential incorporated between each pump.
to develop. This is a common strategy used in petrochemical
plant piping to allow some flushing of idle pumps. Expansion loops between each pump were created by
turning the Tee on the discharge of the first pump such that the
PIPE STRESS flow went straight through the Tee instead of turning into a
After the pipe layout has been developed, a stress analysis straight header. The header continues with two 90° elbows
is conducted to confirm that the combined stresses in the piping returning straight through a second Tee into the suction of the
meets code requirements. The major consideration usually next pump as shown in Figure 7.
tends to be the load limits imposed by the pump. The pump
vendor stipulates acceptable forces and moments that can be This loop reduces the pressure drop between the units as
absorbed at the pump nozzles. These levels are well below the head loss flowing straight through the two Tees is 12 times
those that might lead to failure, but are designed to keep less than turning through each Tee. This associated reduction in
imposed distortions at a level that will not impede the long term turbulence also lessens the negative influence on the unit check
reliability of the pump. Another important design parameter is valve.
the operating temperature. The design temperature on several
of the Enbridge systems is 60°C (140°F). While this relatively Aside from anchors to control header deflection, the only
modest temperature isn’t sufficient to cause derating of carbon other major control feature was a restraint required on the
steel piping under CSA Z6626 it was found to have an impact suction of the first unit and the discharge of the last unit. A
on the piping stress. knee brace support was required to counteract reactions from

8 Copyright © 2014 by ASME


the header pushing against the pump nozzles through the unit rotation of the ball such that it mimicked the movement of the
lines. These supports resist these deflections limiting loads on gate in a slab gate valve.
the pump nozzles (Figure 9).
Slab gate and ball valves share a common problem. The
closure element (gate or ball) is drawn across the seats through
the entire stroke. A common mode of failure is that deleterious
material is drawn into the seats during operating and becomes
lodged. This material can then score the closure element over
time impairing the seal. Gate valves are typically designed
such that the gate moves up to open and grit that has settled
next to the bottom of the gate is pulled away from the seat and
usually flushed clear by flow through the valve.

If the ball valve stem is in the vertical orientation, material


can be drawn into the bottom of the seat as it opens. With the
stem in the horizontal orientation, the ball moves up relative to
the seats on one side and down on the other. It was decided to
select the valve rotation such that the ball moved up on the
header side and down on the pump side. The rational for this
arrangement is that the pump side of the valve has a small
Figure 9: Piping Knee Brace Support volume of fluid with a limited supply of sediment. Conversely,
there is continuous flow on the header side with the potential to
deposit a larger amount of sediment adjacent to closed valves.
VALVE SELECTION
Therefore it is assumed that the greater risk of damage is on the
Historically station designs used through conduit, slab gate
header side.
valves for all large bore piping. This type of valve has been
favored for pipeline applications because it is simple, relatively
One drawback of the horizontal stem orientation is that it
low in cost, includes a double block and bleed capacity (DBB)
complicates removal of the actuator in the field. A vertical
and can be maintained in place as it is normally a top entry
stem orientation allows a simple rigging of the actuator such
design. The problem with this type of valve is that they are a
that it can be pulled vertically. While this isn’t a major deficit,
rising stem design so the actuator is located on top. Due to the
the design team worked with maintenance personal and the
tall body, a platform is required to access the actuator. Another
actuator vendor to develop a viable solution. It was found that
feature of the design is that the valve body is isolated from the
the addition of a couple of attachment points to the actuator
flowing fluid when it is fully open or closed. This minimizes
would allow safe rigging of the actuator so that it could be
contamination between the flowing fluid and the fluid trapped
moved horizontally off the valve stem.
in the valve body cavity. The problem with this feature is there
isn’t a lot of mixing as the valve transitions and emulsified
water can precipitate out of the crude and become trapped in Figure 10: Ball Valve Flushing
the valve body where it can freeze.

Ball valves are being used more extensively in the pipeline


industry as they are more compact, and competitively priced.
They can also eliminate the need for platforms to access the
actuator. They also have the added benefit of providing greater
flushing of the body cavity as the ball transitions between the
closed and open position (Figure 10).

There have been some adverse experiences with the use of


ball valves in liquid pipelines; therefore, every effort was made
to engineer a successful installation. The one assumed
weakness of the ball valve with the stem in the vertical position
was the lower trunion bearing. It was felt that water could
precipitate into this region like the slab gate and cause
corrosion of the trunion bearing or inhibit valve operation if it
became frozen. It was decided to install the valve with the stem
in the horizontal orientation. This alignment had two other
benefits; it positioned the actuator on the side of the valve
where it can be accessed without a platform; and changed the

9 Copyright © 2014 by ASME


PUMP SELECTION usually eliminates any cost advantage. The 1800 RPM units
The pump chosen for the mainline unit is a single stage, also have greater reliability owing to the lower operating speed.
double suction, horizontally split case, between bearings design
which is simply designated a BB1 in API 6107. This style of EQUIPMENT FOUNDATION DESIGN
pump has a long established history in pipeline service. The The foundations for the rotating equipment are designed
greater problem with the pump selection can be the definition for both the static weight of the equipment and the dynamic
of operating parameters for the pump. Pipelines are often operation loads. The foundation is composed of three main
constructed to operate at a lower initial rate and over time components: the pedestal supporting the pump and motor; the
expand capacity as greater volumes materialize. This often underground foundation block; and the supporting piles.
requires a costly replacement of the pump and driver and
modification of the associated piping. The design of the pedestal portion of the foundation is not
governed by the weight of the unit but by the piping. The
An alternative approach is to install a larger capacity pump height of the pedestal is dictated by the elevation required to fit
case that can be hydraulically modified to operate at a lower the piping connected to the pump. A secondary height
flow rate efficiently (Horner8). This can be done with a pump consideration is to allow personnel access to the unit valves,
case design that includes a replaceable element that can be under the platform around the units.
changed in the field to modify the hydraulic characteristics.
Two common methods of achieving this flexibility are to These elevation constraints made the pedestals relatively
incorporate a diffuser element or replaceable volute lip inserts. high, so it became a challenge to reduce the amount of concrete
The design chosen by Enbridge was a pump with removable required. The section of the foundation under the motor is
volute inserts (Figure 11). narrower than the pump section because the motor is narrower
than the pump. As well, the length of the pedestal is reduced as
Figure 11: Volute Insert much as possible based on the equipment size.

The underground foundation block transfers the loads from


the pedestal to the piles. Its size is dictated by the horizontal
area required to fit enough piles under the foundation. A
dynamic analysis was conducted using DYNA-6.1 software.
Operating speeds in the range of 50% to 110% of the pump
design speed were checked for resonance conditions. Due to
the mass available in the higher pedestals, it was found that the
foundation block could be kept quite shallow and still have
enough mass for dampening.

The strategy usually requires that the pump is initially


provided with volute inserts for about half the ultimate capacity
of the pipeline. The motors may be slightly oversized, but not
much larger than is required for the initial capacity. In this way
the pre-investment is limited to the pump. The pump is
purchased with a second set of inserts that have been ground to
blend into the unique contours of each casting. When the
Figure 12: Stepped Foundation
capacity has to be increased the inserts are changed and a new
impellor is installed. The new impellor is sized to operate
EQUIPMENT INSTALLATION
efficiently at the higher capacity, but typically it produces less
Pumps and motors are commonly installed on a common
head as limited by the power of the motor. Additional pumps
baseplate supplied by the pump vendor. While this approach
have to be installed in series to make up for the head deficit.
claims construction efficiencies, they are seldom achieved in
practice with large pumps (Horner9). Baseplate requirements
The pumps employed are 4,300 kW (5,750 HP) to 5,200
included in API 610 have developed significantly over the
kW (7,000 HP) units. Lower speed 1800 nominal RPM units
years. At the same time pump power requirements have grown.
are preferred; because even at these power levels, bearings can
Most common baseplate designs are not adequately designed to
be obtained that eliminate the need for forced lube systems.
withstand the rigors of transport and installation and require in
Higher speed 3600 RPM pumps are common and have lower
place machining after grouting to obtain the required coplanar
costs, but the added cost of the required forced lube system
tolerances at the motor mounting surfaces.

10 Copyright © 2014 by ASME


Therefore, pumps are ordered with a smaller baseplate The analysis indicated that the small bore piping
sized to support the pump and coupling guard only. This connections did require minor modification. Structural bracing
smaller baseplate has shown to be more robust as demonstrated was developed to limit relative movement of the small bore
by a relatively trouble free installation history. The motors are piping at the connection with the large bore piping. The
installed separately on machined rails. The motor shaft bracing was only required at the thermal relief valve and the
centerline to bottom of stator dimension is often 500 mm (20 sump tank reinjection connection.
inches) less than the pump so the common baseplate approach
can have elevated rails on pedestals which can have CONCLUSION
troublesome resonances. With the grouted rail design the The main objective of this design effort was to improve the
concrete foundation is stepped as shown in Figure 12 so the pump station’s environmental protection capability without
motor rails are mounted directly on the concrete. This helps to introducing a significant new operating or process safety risk.
isolate the pump from the motor and provide a very stable The secondary objective was to improve constructability and
mounting surface for the motor. develop a more cost effective design. This design exercise
required a re-evaluation of many accepted practices and design
The mounting rails are drilled and tapped to accept jacking assumptions. The result was a significant departure from past
bolts and anchor bolts. The rails are adjusted with the jacking designs, due to the many new constraints introduced in the
bolts to meet the required level and coplanar tolerances, and are design. Some of the cost saving innovations that helped reduce
held fast by the anchor bolts. The rails are grouted and the costs by $3.5 million per station included:
jacking screws removed. 25 mm to 50 mm of grout will
provide a homogeneous bedding for the mounting rails. The • Drilling the station discharge check valve to eliminate a
rails are then drilled and tapped in the field to accept the motor second thermal relief valve and some challenging drain
hold down bolts. This final step ensures that the motor is piping.
located to suit the pump and provide the best possible • Reduction in station piping costs by increasing the
alignment. limiting velocity to 20 ft/s and reducing pipe and
equipment sizes.
DYNAMIC ANALYSIS
A concern with transitioning station piping aboveground • Elimination of the buried sump tank. The installed cost
was that the loss of damping by the soil might result in higher of the buried tank is almost twice that of an
piping vibration. Several design constraints were adopted to aboveground tank.
mitigate this potential issue. These strategies included: • A significant reduction in the heat traced and insulated
• Limiting pipe support spacing to a maximum of 6.1 m drain header.
(20 ft.) regardless of pipe size; • The use of ball valves instead of slab gate valves. The
• Keeping all small bore connections within 1D of pipe ball valve has a lower cost; the required actuator is
supports; smaller and accessible without a platform.

• Using adjustable pipe supports that maintain good • Reduction in pump shelter costs due to the use of a
contact with the pipe, while allowing for removal for fabric clad building.
inspection; and • Greater degree of prefabrication minimizing the number
• Enbridge’s piping design standards require use of a of field welds.
design factor (F) of 0.6 instead 0.8 (as required by CSA
Z6626). This reduces operating stress levels by requiring NOMENCLATURE
an increase in pipe wall thickness and/or pipe SMYS. ACH Air Changes per Hour
cfm Cubic Feet per Minute
ips Inches per second
To assess the magnitude of the vibration problems that LEL Lower Explosive Limit
might result by bringing the station piping aboveground, a PCV Pressure Control Valve
dynamic analysis was also completed. This assessment SMYS Specified Minimum Yield Strength
included a forced response analysis of the pumps and piping. A
rotating unbalance force of 67 N peak (15 lbf) over the ACKNOWLEDGMENTS
operating range of 900 to 1800 RPM was imposed at the Dave Lawson, Enbridge, Edmonton, AB
centerline of each pump. The maximum vibration levels over Ryan Champney, Enbridge, Edmonton AB
the operating range were observed on the unit piping and found Joe Dhaliwal, Enbridge, Edmonton AB
to be a maximum of 7% of the vibration acceptance criteria of Rob Ladner, Jacobs Canada, Edmonton AB
2.54 mm/s (0.1 ips). Kevin Oldham, Jacobs Canada, Edmonton AB

11 Copyright © 2014 by ASME


REFERENCES
[1] API Recommended Practice 505, “Recommended
Practice for Classification of Locations for Electrical
Installations at Petroleum Facilities Classified as Class 1,
Zone 0, Zone 1 and Zone 2”, August 1998, American
Petroleum Institute.
[2] API Recommended Practice 4638, “Calculation
Workbook for Oil and Gas Production Equipment Fugitive
Emissions”, April 1996, American Petroleum Institute.
[3] API Recommended Practice 4615, Emission Factor
for Oil and Gas Production Operations, December 1994,
American Petroleum Institute.
[4] API Recommended Practice 14E, “Recommended
Practice for Design and Installation of Offshore
Production Platform Piping”, 1991, American Petroleum
Institute.
[5] Salama, M.M., 1998, “Alternative to API 14E
Erosional Velocity Limits for Sand Laden Fluids”,
Proceedings of the Annual Offshore Technology
Conference OTC Paper 8898 Tulsa, OK.
[6] CAN/CSA-Z662-11. “Oil and Gas Pipeline Systems”,
2011, Canadian Standards Association.
[7] API Standard 610, “Centrifugal Pumps for Petroleum,
Petrochemical and Natural Gas Industries”, October
2004, American Petroleum Institute.
[8] Horner, J.W., 1995, “Development of a Diffuser Pump
for Pipeline Service”, Proceedings of the Pipelines,
Terminals and Storage Conference, Houston, Texas
[9] Horner, J.W., 1998, “Installation of Pipeline Pumps”,
Proceedings of the International Pipeline Conference,
Calgary, AB.

12 Copyright © 2014 by ASME

You might also like