Professional Documents
Culture Documents
IPC2014
September 29 - October 3, 2014, Calgary, Alberta, Canada
IPC2014-33740
ABSTRACT
This paper reviews Enbridge’s recent experience with the Reductions in station construction costs are obtained by
design and construction of new pump stations during its most minimizing pipe, fitting and equipment sizes. A typical 4-unit,
recent wave of expansion that started in 2007. This expansion NPS 24 station has been consolidated such that total extend of
includes over $4 billion in pump station construction and the station piping is less than 100 m. Culverts are not
upgrade. Enbridge is working on its third generation station acceptable for access to larger equipment, so keeping piping
design and is starting to benefit from a consistent design systems aboveground also helps to minimize the length of
composed of standard elements. piping, number of fittings and welded joints needed to
“porpoise” buried piping aboveground to allow access to these
The principle objective of this design effort was to improve components. Due to this advantage and others, it became an
environmental protection at pump stations. In the design’s early design philosophy to keep station piping above grade.
development many different areas of concern were investigated
including: building code compliance, pump shelter ventilation Keeping station piping aboveground also improves
requirements, improvements to station metering accuracy, constructability as it increases the potential for prefabrication.
mitigations to improve fire safety, inclusion of an aboveground Aboveground piping also minimizes the costs associated with
sump tank, and equipment access and removal to name a few. excavation, shoring, treatment of groundwater collecting in
While work has been done to improve mechanical and excavations and the complexities attendant with confined
structural systems, they have also been standardized in an spaces.
attempt to develop consistent components. The objective of the
paper is to provide a summary of these developments and some Finally, improvements in environmental protection are
background on the thinking that shaped the design. achieved by upgrading containment for minor leaks and
improving detection of major leaks. These improvements
INTRODUCTION would also include the potential to minimize cleanup costs
The development of the new station design had several associated with a leak resulting from an operational error and
objectives that included: minimize site disturbance during construction.
• Improvement of operational integrity;
As can be seen, these design objectives are not mutually
• Reduction in station construction costs; exclusive. Concepts that emerged included: keeping the piping
• Improvement in station constructability; and aboveground; creation of better containment and detection
• An improvement in environmental protection. systems; and minimization of pipe, fitting and equipment sizes.
To further eliminate buried piping it was also decided to
Improving operational integrity includes elimination of incorporate an aboveground sump tank into the design so that
buried piping that cannot be internally inspected. This all drain lines would be aboveground. Putting the sump tank
objective also means that equipment is to be readily accessible aboveground also minimizes drain line runs as it can be placed
for maintenance and “dead ended” piping should be minimized in closer proximity to the drain source. This is an incidental
to reduce contamination between batches. These maintenance use tank, not a storage tank, and is empty most of the time.
requirements do not permit burying of piping components like Aside from compliance with accepted tank construction and
instrumentation, flow meters and pressure control valves. venting standards it does not pose a safety risk.
In the past, as the name suggests, pump shelters have Ridge Vent
generally been restricted to a weather shelter for the mainline
pumping units and their associated driver. To provide a more
complete containment system, the pump shelter had to be
expanded to cover the pump’s isolation valves, the header
piping, control valves, flow meters and as much of the Exhaust Fan
associated instrumentation as possible, or in short to contain as
many of the leak sources as possible. To minimize the cost
associated with this larger building the associated piping was
made as compact as possible to minimize the footprint and
alternative building styles were considered.
Access Door Inlet Louvers
ALTERNATE BUILDING DESIGNS
To offset the increased cost associated with these larger
“containment structures”, alternative fit-for-purpose strategies
were considered. Typically, pump shelters have been metal
clad, metal framed buildings. Metal framed, fabric clad
buildings have become more popular recently and can be 30%
to 40% lower in cost than a comparable metal clad structure. Figure 1: Pump Shelter Building
The pump shelter is considered to fall within the building • The potential of explosion due to buildup of vapours is a
code category Group F, Division 2. This type of building remote risk due to the natural and artificial ventilation
requires a water supply for firefighting if the floor space provided and the gas detection systems.
exceeds 600 m2 (6455 ft2) and a sprinkler system if it exceeds
800 m2 (8600 ft2). Because most pump station sites are remote, By completing the required risk assessment and using
they are not within the range of municipal water supplies or published variances allowed by provincial authorities, the
within local fire response areas. Even if a clean water supply building size requirement for fire water can be increased to
was maintained on site, the time needed for a local response is 1200 m2 (12,900 ft2). In spite of the fire water relief provided
too great to prevent loss due to fire. Instead a risk assessment by these variances, it became a default design constraint to limit
by a professional engineer was completed for the building the building footprint to a maximum of 800 m2 so that
detailing the fire prevention measures included in the design. sprinklers are not required. This limitation also helps to
Some of the key analysis points of the risk assessment were: minimize potential building egress path lengths.
External Pipe
temperatures
acceptable
PIPE SIZING
At the outset of design efforts, pipe sizing was based on Figure 6: Flow Distortion at Elbow
limiting the velocity in station piping to 3.65 m/s (12 ft/s). It
was felt that this limit was too conservative. Pipe sizes
determined by this method yielded lower pressure drops, but it
also resulted in significantly higher station construction costs requires more pipe and fittings to achieve the necessary piping
and greater pipe stresses owing to the larger and more rigid flexibility. Therefore, the most common piping schemes keep
piping. This limiting velocity was based on recommendations the elbows vertical with 2D of straight pipe between the elbow
in API 14E4. and the pump suction. This ensures the turbulence induced by
the elbow in the vertical plane does not affect the axial or
Many publications have shown API 14E to be too horizontal flow split in the pump case as the fluid is distributed
conservative. It was subsequently decided to increase the between the two suction eyes of the pump impeller.
limiting velocity based on the work of Salama5 on piping
erosion with fluids containing sediment. The accuracy of his Past practice turned the elbows down to allow good access
work was verified by four independent laboratories by to the pump, but the pump suction and discharge lines had to be
measuring erosion rates in pipe bends. Testing of various crude routed under the pump house floor which made inspection
streams helped to determine a basis for particulate size and problematic and also increased construction challenges. As
concentration. This work indicated that a maximum velocity of pumps became larger it became common to elevate the pumps
11.74 m/s (38.5 ft/s) in crude oil would result in an acceptable such that a horizontal flange pair could be installed near floor
erosion rate. Therefore, the limiting velocity was increased to level at the base of the elbow to facilitate removal of the piping
6.1 m/s (20 ft/s). This decreased the station piping size from and to add a degree of flexibility in the fit-up of the piping.
NPS 30 to NPS 24, saving over $2.5 million per station. Alternately trenches or basements have been employed to allow
access to the piping, but this introduces structural complexity
and, added cost, and also creates a confined space.
PUMP PIPING DESIGN
One of the major determinants of pump station piping
Some station designs have been executed with the pump
design is the hydraulic considerations associated with the
elbows turned up. The advantage of this type of arrangement is
pumps. Elbows generate turbulence that can affect the flow
that the pump and motor can be placed at ground level
distribution entering a pump nozzle as shown in Figure 6. This
providing good access to the equipment while eliminating the
is particularly problematic on the single-stage double suction
need for platforms. The drawback with this design is that what
pumps most commonly used in pipeline applications. Enbridge
goes up must come down. There is a significant volume of
standards require keeping suction elbows out of plane with the
additional fluid in these vertical loops that has to be drained to
pump axis or adding 5D to 7D of straight pipe between the
allow equipment maintenance. Proper venting of the loops can
elbow and the pump suction.
be problematic and this approach requires extra fittings, pipe
and welded joints. While these vertical loops can provide
Adding straight pipe to the pump suction to keep the piping
excellent flexibility this can also be a drawback as they need to
flat increases the spacing between the pumps and ultimately
be stabilized to prevent excessive vibration. Due to adverse
increases the footprint of the station. This configuration also
experiences, this type of design is discouraged at Enbridge.
inhibits access to the pump for maintenance and usually
When piping is sheltered from the elements, thermal relief The piping between the pump and the unit isolation valve
required by solar heat gain can be eliminated. The exposed was designed to be as short as possible to minimize the impact
lengths of suction and discharge piping between the pump of thermal growth on this segment. The greater problem was
shelter and the 3-valve cluster provide sufficient exposure that the interaction with the longer station header. A common
thermal relief was deemed necessary. The station discharge method of controlling stress is to increase flexibility by adding
check valve would normally require thermal relief on either loops or bends. The standard header design is composed of
side of the valve. To eliminate this redundancy, and allow a straight pipe with check valves between a series of Tees
better positioning of the relief valve, the discharge check valve connecting each pump suction and discharge line. To provide
is drilled with a 12.7 mm hole (0.5 inch) so that it can still the desired flexibility, a series of functional loops were
prevent massive back flow, but not allow a pressure differential incorporated between each pump.
to develop. This is a common strategy used in petrochemical
plant piping to allow some flushing of idle pumps. Expansion loops between each pump were created by
turning the Tee on the discharge of the first pump such that the
PIPE STRESS flow went straight through the Tee instead of turning into a
After the pipe layout has been developed, a stress analysis straight header. The header continues with two 90° elbows
is conducted to confirm that the combined stresses in the piping returning straight through a second Tee into the suction of the
meets code requirements. The major consideration usually next pump as shown in Figure 7.
tends to be the load limits imposed by the pump. The pump
vendor stipulates acceptable forces and moments that can be This loop reduces the pressure drop between the units as
absorbed at the pump nozzles. These levels are well below the head loss flowing straight through the two Tees is 12 times
those that might lead to failure, but are designed to keep less than turning through each Tee. This associated reduction in
imposed distortions at a level that will not impede the long term turbulence also lessens the negative influence on the unit check
reliability of the pump. Another important design parameter is valve.
the operating temperature. The design temperature on several
of the Enbridge systems is 60°C (140°F). While this relatively Aside from anchors to control header deflection, the only
modest temperature isn’t sufficient to cause derating of carbon other major control feature was a restraint required on the
steel piping under CSA Z6626 it was found to have an impact suction of the first unit and the discharge of the last unit. A
on the piping stress. knee brace support was required to counteract reactions from
• Using adjustable pipe supports that maintain good • Reduction in pump shelter costs due to the use of a
contact with the pipe, while allowing for removal for fabric clad building.
inspection; and • Greater degree of prefabrication minimizing the number
• Enbridge’s piping design standards require use of a of field welds.
design factor (F) of 0.6 instead 0.8 (as required by CSA
Z6626). This reduces operating stress levels by requiring NOMENCLATURE
an increase in pipe wall thickness and/or pipe SMYS. ACH Air Changes per Hour
cfm Cubic Feet per Minute
ips Inches per second
To assess the magnitude of the vibration problems that LEL Lower Explosive Limit
might result by bringing the station piping aboveground, a PCV Pressure Control Valve
dynamic analysis was also completed. This assessment SMYS Specified Minimum Yield Strength
included a forced response analysis of the pumps and piping. A
rotating unbalance force of 67 N peak (15 lbf) over the ACKNOWLEDGMENTS
operating range of 900 to 1800 RPM was imposed at the Dave Lawson, Enbridge, Edmonton, AB
centerline of each pump. The maximum vibration levels over Ryan Champney, Enbridge, Edmonton AB
the operating range were observed on the unit piping and found Joe Dhaliwal, Enbridge, Edmonton AB
to be a maximum of 7% of the vibration acceptance criteria of Rob Ladner, Jacobs Canada, Edmonton AB
2.54 mm/s (0.1 ips). Kevin Oldham, Jacobs Canada, Edmonton AB