Operations & Maintenance Management System

PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 3000HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

Unit Number: Customer: Date:


Hour Meter Reading: Country: Location:
Engine/Comp Model: Providence: Technician:

Safety
2 Complete JSA before beginning job. ☐Completed ☐N/A
Safety • Be sure to list all people working on the job.
• Make sure all hazards and special requirements are addressed.

3 Complete any required Work Permits. ☐Completed ☐N/A


Safety • Attach JSA to Work Permit and give to Safety Coordinator for approval.
• Have Tool Box Talk with Safety Coordinator and technicians involved.
• Make sure all departments in the surrounding work area are notified.
• Lock Out/Tag Out (LOTO) procedures must be documented and
followed.

4
Complete Lock Out / Tag Out procedure (LOTO). Indicate number of Number of
Safety
points locked out Lock Outs
• List the number of points a lock was applied. Example; Suction=1,
Discharge=1, Scrubber Drain=1, Fuel Gas=1, Total would be 4.
• Record count of lock points where single or group LOTO applied.

7 Is H2S known to be present on location? ☐Yes ☐No


Safety If yes, obtain current PPM level before proceeding.
Test and inspect all PPE before any work is performed. Local HSE department will PPM
assist in determining the proper PPE and special instructions.

8 Is CO2 known to be present on location? ☐Yes ☐No


Safety If yes, obtain current percentage level before proceeding.
Test and inspect all PPE before any work is performed. Local HSE department will %
assist in determining the proper PPE and special instructions.

PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 1 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

Operating Parameters
10 Record unit RPM and Overspeed setting
Running Unit overspeed setting should be set no higher than 5% over the maximum RPM Current Overspeed
of compressor frame or 5% over the maximum RPM of engine, whichever is RPM Setting
lowest.
20 Record Compressor Flow Rate (MMCFD) and Percent Recycle Valve
Running open. Discharge Fuel Gas Recycle
Inlet Meter
If unavailable note N/A Record Meter Meter Open %
In
MMCFD

25 Record process gas system pressures – inlet and discharge of all stages.
Running Record Safety Setting Low (SSL), and Safety Setting High (SSH) for each
process gas panel gauge. Suction Disch. 1 Disch. 2 Disch. 3 Disch. 4 Disch. 5
• Process gas pressure safety settings should be set so that inlet pressure Pressure
cannot approach a vacuum, no system will approach max working
pressure, and that no stage can approach max rod load. SSL
• Compressor performance programs would be an appropriate source for
determining process pressure safety settings. Special situations would SSH
require management approval.
30 Record process gas temperatures - inlet and discharge of all stages.
Running Record temperature safety settings. Cyl-1 Cyl-2 Cyl-3 Cyl-4 Cyl-5 Cyl-6
• Cylinder discharge temperature SSH's should be set at normal operating Inlet Temp
temperature plus 10%, with 350°F being the maximum allowable setting
unless approved by management. Disch. Temp
• Refer to the compressor performance program for calculated discharge
temperatures. SSH

35 Inspect inlet gas cone screen/strainer pressure drop (if equipped).


Running • Inlet gas cone screen/strainer should be monitored via differential ☐ Completed ☐ N/A
pressure each service interval. Percent Pressure Drop
• If there is excessive pressure drop, remove and clean after LOTO of Across Cone Strainer
process system

PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 2 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

40 Record all oil pressures and their SSL's. Record all available oil
Running temperatures and their SSH's, Record all filter ΔP's.
• Refer to current OEM publications for minimum and maximum oil PSI SL Filter ∆ Temp SSH
pressure and temperature settings.
Engine Oil
• Record oil filter differential pressure (DP) if gauges are available, smaller
units are usually not equipped to read oil filter differential. Comp. Oil
• Normal oil filter DP 2-15 PSI, change oil filters if 15 psi differential
pressure.
50 Record all coolant temperatures and their SSH. Record all coolant
Running pressures and their SSL. PSI SSL Temp SSH
Refer to current OEM publications for min. and max. coolant temperatures and
safety settings Engine
Auxiliary

55 Record catalysis performance, if equipped.


Running • Record each cylinder exhaust temperature and the SSH, if available. Catalyst ☐N/A In Out SSH
• Maximum exhaust system backpressure - 12 in. of water column at 1200
rpm, 145 BMEP (full load). Temperature
• Subtract 1 in. of water column for each 100 rpm reduction.
LB/RB DT
• Subtract 1 in. of water column for each 10 BMEP reduction.
• Do not apply these reductions beyond a minimum exhaust system
backpressure of 4 in. of water column.
• Maximum exhaust temperature variation on an engine running at 1000-
1200 rpm at 138 BMEP on natural gas fuel.
• Between cylinders on the same bank - approximately 100° F
• Maximum exhaust temperature variation between respective cylinders on
different banks (#1R versus #1L, #2R versus #2L, etc.) is approximately 50° F

Exhaust Temp Cyl 1 Cyl 2 Cyl 3 Cyl 4 Cyl 5 Cyl 6 Cyl 7 Cyl 8 Cyl SSH Turbo SSH
Left Bank
Right Bank

PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 3 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

60 ESM Engine Controller; Verify that each cylinder is firing. Any Issues? ☐ Issues repaired ☐ Issue need to be addressed ☐ All OK
Running Record peak spark/firing number.
Record current ignition timing. Peak Spark/Firing Number Timing BTDC
Record current WKI or Methane number (as applicable) set in controller.
• Confirm cylinders are firing by viewing the ignition control panel diagnostics
screen, and via cylinder exhaust temperature. WKI / Methane Number
• A correct WKI value must be entered into ESM and timing will be managed
through the ESM system. Refer to Waukesha Form 6295, ESM Manual
and/or Waukesha SB 11-2558E, VHP Timing.
65 Record AFR controller data (If equipped). Record target value and sensor Stepper
Running value. Record stepper position(s). Record controller gain setting. Note if Target Actual Position Gain Tracking?
controller is “Tracking” or out of range. Review, analyze and correct any
faults. Right Bank
Become familiar with current local emissions regulations. Follow compliance
Left Bank
regulations when operating and maintaining emission control systems.

70 Record intake manifold pressure from each bank.


Running PSI SSL SSH Temp SSH
• Verify that bank to bank balance is within 4” W.C.
• Record Intake Manifold Pressure, Temperature, and corresponding SSL, Single / Left
SSH’s. Bank
• Manifold Pressure Exceeding 5 PSI (40"HgA) (turbo charged engines) Engine
Right Bank
is likely to be in overload!
• Manifold Temperature Normal: Up to 10° F above design intercooler water For Dual Carbureted Engines
inlet temperature. Record DP Across Manifold
• Alarm: 15° F above design intercooler water inlet temperature.
• Shutdown: 20° F above design intercooler water inlet temperature. (normally
150° F)
75 Record bearing temperature reading and SSH (Safety Setting High) (as Highest
Running equipped Engine and/or Compressor) SSH
Temp

• Verify temperatures and trends are within limits and SSH are correctly
Engine Bearing
set. Comp. Bearing
• Maximum Main Bearing Temperature 250°F.

PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 4 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

80 Record engine control screen shots. (ESM) Attach Screen Shots ☐Completed ☐N/A
Running
85 Review and analyze all safety settings for adequate equipment ☐Completed ☐N/A
Running protection limits.
Compare found settings to where they SHOULD be set at. Research current OEM
publications and the compressor performance program for correct settings.
90 Review and analyze alarm codes and fault history. Record any issues ☐Completed ☐N/A
Running that will need to be addressed.
100 Document all comments and issues found regarding parameters. Type comments or issues found:
Running

Visual Walk Around Inspection


110 Any oil leaks? ☐Yes ☐No
Running
120 Any coolant leaks? ☐Yes ☐No
Running
130 Any process gas leaks? ☐Yes ☐No
Running
140 Any compressor rod packing gas or oil leaks? ☐Yes ☐No
Running
150 Any issues with the condition of hoses and clamps? ☐Yes ☐No
Running
160 Any loose bolting including mounting of engine, compressor, cooler, ☐Yes ☐No
Running skid, pipe supports, flanges, etc.?
170 Any unusual noises? ☐Yes ☐No
Running
180 Any excessive or abnormal vibrations? ☐Yes ☐No
Running
PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 5 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

199 Document all issues discovered during walk around inspection. Type comments or issues found:
Running

Temperature Checks (IR Gun)


210 Check for issues with EJW, auxiliary water, and/or compressor oil ☐Completed ☐N/A
Running thermostats.
To verify proper valve and thermostat function, obtain and analyze inlet and
outlet temperatures of each thermostatic valve housing, inlet and outlet
temperature of each system, and the temperature drop across each cooler.
220 Check compressor valve cap surface temperatures under normal ☐Yes ☐No
Running operating conditions. Are any like valves >20°F apart and/or
temperatures higher than calculated temperatures.
Like valves should be less than 20°F apart and within range of calculated
temperatures. Seek advice on tailoring valves to site-specific application when
having premature, and/ or reoccurring failures.
230 Check compressor crosshead guide surface temperatures under normal
Running operating conditions. Throw #1 #2 #3 #4 #5 #6
Reading are "surface" temperature and will vary based on load, speed, ambient,
and surface (paint, oil, dirt) conditions, however monitoring and trending will Temp.
assist in identifying potential issues prior to catastrophes.
Cross heads:
• Shoot temperature within 6" of top of guide where cross head runs
• Record reading per throw

240 Record vibration damper surface temperature (viscous type) while


Running engine is under load. Temperature
• Use extreme caution around moving components, shoot from a safe
distance.
• The surface temperature should be approx. 10-15 degrees above engine
oil temperature.

PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 6 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

299 Document all issues discovered during temperature gun checks. Type comments or issues found:
Running

Compressor Cylinders, Packing Lubrication & Scrubber Controls


300 Record the setting of each compressor VVCP and how each cylinder is
Running loaded.
Measure in inches the distance that the pocket is opened. Cyl-1 Cyl-2 Cyl-3 Cyl-4 Cyl-5 Cyl-6
• Fully Closed = 0.0"
Cyl. Throw
• Indicate how each cylinder is loaded;
DA = Double Acted VVCP Inches
SAHE = Single Acted Head End
SACE = Single Acted Crank End Cyl. Loading
UL = Unloaded, All Suction or Discharge Valves Removed
Float = All Valves Removed
Spacers = Cylinder has Valve Spacers
Blank = No Cylinder
• The compressor performance program should be referred to often to
determine optimal VVCP settings.
310 Check all cylinder and packing lubrication. Are check valves hold or ☐Yes ☐No
Running leaking?
320 Is oil reaching the check valve from divider block? ☐Yes ☐No
Running
330 What is/are the lubrication rate(s) in seconds?
Running • Guidance: If greater than 40 seconds consult supervisor or manual RB Seconds LB Seconds

PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 7 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

340 Any internal leakage at compressor recycle valve, dump valves, relief ☐Yes ☐No
Running valves?
Check the temperature difference between downstream vs upstream of a
particular valve to determine if leakage is occurring. Downstream side will be
cooler then upstream side.
350 Inspect scrubber dump valve controllers. Are scrubber level controllers ☐Yes ☐No
Running maintaining the appropriate level?
360 Are there any apparent worn or otherwise malfunctioning parts with ☐Yes ☐No
Running scrubber level controllers, dump valves, or site glasses?
370 Are all scrubber site glasses clean and valves are functioning? ☐Yes ☐No
Running
380 Verify correct instrument supply pressure and record reading.
Running Pressure

399 Document all discovered Cylinder lubrication and scrubber dump issues. Type comments or issues found:
Running

Miscellaneous Unit Parameters


405 Record air filter DP and inches of water column. Check air filter
Running restriction indicator.
• If air filter Δ P is excessive, replace filter element when unit is down Filter DP
Turbocharged engines require air filter change when filter Δ P > 10" H2O
• Naturally aspirated engines require air filter change when filter Δ P > 3" H2O
410 Record oil tank levels. Drain condensation from oil tank(s). ☐Full ☐3/4 ☐1/2 ☐1/4 ☐Empty
Running
Drain Condensation ☐Completed ☐N/A
415 Verify oil level controllers are functioning properly. Use dip stick when ☐Completed ☐N/A
Running applicable.
420 Record current crankcase pressure.
Inches of H2O
Running

PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 8 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

425 Adjust crankcase pressure to 0” to -2” H₂O (if adjustable). ☐Completed ☐N/A
Running
430 Record estimated hours on engine and/or compressor oil (if NOT
Running changing this service). Engine Oil Hours Comp Oil Hours

435 Indicate oil samples were collected? ☐Engine Oil Sample collected ☐Compressor oil Sample Collected
Running Did the previous oil analysis flag any issues? ☐Yes, Issues flagged ☐No issues flagged ☐Unknown
Sample at operating temperature, using a clean sample port located upstream of, ☐Not sampled
or prior to, filtering.
440 Collect coolant sample. ☐Sample collected ☐Not Sampled
Running Sample using a clean sample port (collected every 6 months).

445 Did the previous coolant analysis flag any issues? ☐Already addressed ☐Addressing this service
Running ☐Not sampled ☐No Issues ☐Unknown
450 Inspect coolant condition and color. Mark all that apply.
Running Perform freeze point test on coolant to verify sufficient protection. ☐Good Color ☐Clean ☐Not Freeze
☐ Weak Color ☐Dirty Checked Point

455 Inspect for intercooler issues. ☐Completed ☐N/A


Running Check for coolant and/or oil in air side of cooler. Check temperature drop across
cooler.
460 Bleed air from compressor cylinder coolant jackets and oil cooler, if ☐Completed ☐N/A
Running applicable.
Indicate if checked and ok.
465 Prove governor response by upsetting linkage and examining governor ☐Completed ☐N/A
Running reaction. Check compensation setting and oil level if applicable.

PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 9 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

470 Drain fluid from fuel filter, fuel header, and supply gas regulators. ☐Filters Drained ☐N/A
Running Verify regulators are functioning properly. Pressure Setting
Verify start gas, fuel gas, and instrument supply pressures are set at Start Supply Left “A” Regulator
correct pressure. Record pressures
Item Recommended Maximum Fuel Supply Right “A” Regulator
IR Vane Starter 150 psi 150 psi Instrument Left Power Screw
TDI Turbine Starter 40 - 150 psi 150 psi
Fuel (2nd Cut)- L5794GSI; L7044GSI 24 – 50 psi 75 psi Pre Chamber Right Power Screw
Fuel (2nd Cut) - L5794LT; L5774LT 43 – 60 psi 75 psi
Fuel “A” Reg.- GSI 4” – 5” H2O 7” H2O
Fuel “A” Reg.- LT 5.5” – 6.5” H2O 7” H2O
Instrument Gas System dependent 30-45 psi
499 Document all discovered issues with the coolant, cooling system, Type comments or issues found:
Running governor and misc. items.

Electrical Systems
500 Record alternator AMP output (if equipped).
Running Record total battery voltage (if equipped). Amps Volts ☐N/A

599 Document all discovered issues with the electrical and charging system. Type comments or issues found:
Running

Safety Shutdown and Gages


600 Prove all panel safety devices for function. ☐Completed ☐N/A
Running
610 Test all No-Flow devices. Record shut down times.
Running Looking at engine flywheel determines Left Bank (LB) & Right Bank (RB) Switch-LB Switch-RB
No. of Seconds

PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 10 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

620 Test all oil level shut down devices.


Running Test coolant SSL. Number of Oil Level Safeties Checked
Test all scrubber SSH. Number of Coolant Level Safeties Checked
Test all vibration switches.
Number of Scrubber Level Safeties Checked
Note number of devices checked Number of Vibration Switches Checked

630 Test all ESD switches and actuators prior to start-up. ☐ Completed ☐N/A
Running Note number of devices checked. No. Devices checked

640 Verify fuel valve closes on shutdown ☐ Completed ☐N/A


Shutdown
650 Verify all process gauges return to zero once unit is blown down. ☐ Completed ☐N/A
Shutdown Calibrate all gauges found not to be correct.
660 Winterize gauge lines with anti-freeze or methanol as needed. ☐ Completed ☐N/A
Shutdown Required when ambient temperatures are near or below freezing. Winterizing
includes lines are reamed and are filled with a nonfreezing liquid.
699 Document comments and all issues found regarding process gauges. Type comments or issues found:
Shutdown

Engine Cylinder Head Compression


800 Remove cannon plug from magneto/alternator/ignition system & verify ☐ Completed ☐ N/A
Shutdown battery power is off, prior to running compression test.
Verify battery power is LOTO - This action is a safety measure to prevent flash
fires from discharging ignition.
810 Verify valve rotator function while testing compression. ☐ Completed ☐ N/A
Shutdown Mark all valve rotators with a paint stick to verify they are rotating while
conducting compression test. > A typed or written "Y" represents all rotators
functioning.

PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 11 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

820 Record the compression pressure of each cylinder.


Shutdown • Compression tests are performed to identify head and cylinder issues.
• Test prior to adjusting valves or replacing heads, regardless of normal Left 1 Right 1
PM or Top End.
• Note - Compression test not required on overhaul. Left 2 Right 2
• With throttle wide open, crank engine minimum 100 rpm until gauge
reading stabilize. Left 3 Right 3
• Lower RPMs and/or higher altitudes will result in lower values.
Left 4 Right 4
• No cylinder should deviate more than 15 psi from average value, RUN A
WET TEST. Left 5 Right 5
• Condemning limit - 25% or 50 psi drop from new or average
Normal Range Left 6 Right 6
Model C/R Pressure (psi)
L5794LT 10.2 to 1 228 – 255 Left 7 Right 7
L5774LT 10.2 to 1 228 – 255
Left 8 Right 8
L5794GSI 8.2 to 1 177 – 198
L7044GSI 8.0 to 1 172 – 195
P9394GSI 8.0 to 1 172 – 195
898 Document comments and all issues found regarding cylinder Type comments or issues found:
Shutdown compression.

PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 12 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

Cylinder Head Valve Recession


1025 Record current valve projection of engine valves.
Shutdown • Measure using approved tooling and methods
• Compare to previously recorded Baseline readings
• Schedule head change at 0.050”; change if exceeding 0.060”
• The acquired measurements will be utilized during sequential PM’s to establish current recession of each exhaust valve

INTAKE EXHAUST INTAKE EXHAUST


Position 1 Position 2 Position 3 Position 4 Position 1 Position 2 Position 3 Position 4
Base 1L 1R Series 4
Current 1L 1R
Recession 1L 1R

Base 2L 2R
Current 2L 2R
Recession 2L 2R

Base 3L 3R
Current 3L 3R
Recession 3L 3R

Base 4L 4R
Current 4L 4R
Recession 4L 4R

Base 5L 5R
Current 5L 5R
Recession 5L 5R

Base 6L 6R
Current 6L 6R
Recession 6L 6R

PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 13 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

1050 Set engine cylinder head valves (Per Cylinder Method – hydraulic lifters) ☐Completed ☐N/A
Shutdown
Clearances, Torques and Firing order
Valve Valve Setting Bridge Setting Firing Order
Intake 6 Cylinder 12 Cylinder 16 Cylinder(*)
0.000” + ½ turn CW 0.000” - Flat
Exhaust 1-5-2-4-3-6 1R 6L 5R 2L 3R 4L 6R 1L 2R 5L 4R 3L R1 L1 R3 L3 R7 L7 R5 L5 R8 L8 R6 L6 R2 L2 R4 L4
Mating Cylinder 6-2-5-3-4-1 6R 1L 2R 5L 4R 3L 1R 6L 5R 2L 3R 4L R8 L8 R6 L6 R2 L2 R4 L4 R1 L1 R3 L3 R7 L7 R5 L5

1. Roll to TDC No1 R - COMPRESSION STROKE


a. Watch rocker arm assemblies of mating cylinders to determine TDC compression stroke
b. As the exhaust valves are just closing and intakes are just opening on the mating cylinder, the
cylinder is at TDC compression stroke
2. Back off pushrod adjusting screws (dead men) ½ turn (older models); Back off bridge adjusting screws ½
turn (newer models)
3. Set both bridge to valve adjusting screws to zero lash & tighten (holding bridge)
4. Set Rocker to bridge adjustment
a. Old Style - Adjust rocker to bridge screws to zero lash & tighten, then tighten pushrod adjusting
screws (dead men) ½ turn (to preload hyd. lifter)
b. New style - Adjust rocker to bridge screws to zero lash, then turn clock wise ½ turn & tighten (to
preload hyd. lifter) Series 2
5. Repeat steps 1-4 rolling CCW to each cylinder’s TDC position (set to firing order, watching mating valve)
until all valves are set (Total of two rolls of Crankshaft)
a. Usually only cylinders 1 Right & 1 Left are marked
with timing tape, the other cylinder need to watch
mating valve to determine TDC
b. Right and left sides of engine are determined by
facing flywheel.
c. Cylinders farthest from flywheel on right and left
sides are #1R and #1L cylinders, respectively.

(*) 16 cylinder - current order - change began with S/N 30688 -


always check engine nameplate.
Series 4

PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 14 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

1070 Inspect valve cover gaskets, replace if needed (always replace on Top ☐OK- Reused ☐Replaced ☐N/A
Shutdown Ends and Overhauls when gaskets are provided in Head set).
1090 Inspect main and auxiliary water pumps (Rebuild or exchange if worn). ☐Rebuilt ☐Exchanged ☐OK – Reused ☐N/A
Shutdown
1099 Document comments and all issues found regarding Top End Task. Type comments or issues found:
Shutdown

Fuel, Start And Governor System


1705 Visually inspect starter, if there are issues rebuild/replace as ☐Inspect ☐Repaired ☐Replaced ☐N/A
Shutdown appropriate.
For vane type starters, refill lubricator.
1710 Visually inspect Sealco (or "Dead Man") valve for damage (if equipped). ☐Completed ☐N/A
Shutdown
1745 Visually Inspect throttle linkage ☐Completed ☐N/A
Shutdown Look for straightness and damage; inspect rod ends and ensure jam nuts are
tight
1750 Inspect all starter, fuel, and process gas hoses. Replace as needed. ☐Completed ☐N/A
Shutdown
1799 Document comments and all issues found with start, fuel, carburetor Type comments or issues found
Shutdown and governor systems.

Catalyst And Control System


1810 Replace / Calibrate O₂ (or NOx) sensors as applicable (if equipped). ☐Replaced ☐Calibrated ☐OK ☐N/A
Shutdown • Replace Rich burn O2 sensors as prescribed by emission regulations.
• Heated Lean Burn sensors generally can be calibrated when flagged
1899 Document comments and all issues found with O2 Sensors or Catalyst. Type comments or issues found:
Shutdown

PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 15 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

Exhaust And Air Intake Systems


1900 Check turbochargers for buildup, for signs of oil leakage, signs of cold ☐Completed ☐N/A
Shutdown housing contact and for excessive play in shaft.
If in doubt, measure play with indicator, compare to specification.
1920 Visually inspect turbo oil supply line clamps ☐Completed ☐N/A
Shutdown Supply lines will crack without clamps in place.
1930 Visually Inspect for signs of leakage at air inlet hoses, O-rings and ☐Completed ☐N/A
Shutdown gaskets, exhaust manifolds, expansion joints, exhaust collar rings,
after/inner coolers, turbo(s) and waste gates (as applicable).
Repair as needed
1999 Document comments and all issues found with turbo (and/or air intake) Type comments or issues found:
Shutdown systems.

Engine And Compressor Lube Oil


2000 Extender Series (with enlarged pan and MicroSpin filter) Oil Filters ☐Changed ☐Not Changed ☐N/A
Shutdown • Change filters every PM Lube Oil ☐Changed ☐Not Changed ☐N/A
• Change engine oil via analysis up to a maximum 0f 5000 hours
• For all other Series 4 non extenders, or if otherwise directed by Enter hours on oil
management, Change engine oil and filters on this service if NOT changed
2050 Compressor oil and filter(s). Oil Filters ☐Changed ☐Not Changed ☐N/A
• Compressor oil shall be changed when engine oil is changed Lube Oil ☐Changed ☐Not Changed ☐N/A
• If directed by management or otherwise NOT changed, indicated
hours on compressor oil at this service. Enter hours on oil
if NOT changed
2099 Document comments and all issues found regarding engine and Type comments or issues found:
Shutdown compressor oil.

Oil Supply, Air Filters And Crankcase Breathers

PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 16 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

2110 Clean (replace if needed) the following (AS APPLICABLE): ☐Completed ☐N/A
Shutdown • Engine crankcase breather element(s)
• Compressor crankcase breather element(s)
• Pre filter element(s)
• Air filter element(s)
Spark Plugs And Ignition System
2200 Inspect spark plugs. Clean, gap, and reuse or replace as needed. Standard
Gap Torque
Shutdown • Replace specific spark plug if defined fraught via exhaust temperatures, Plug
firing, etc. RB77CC 0.015" 35 ft. lbs.
• Clean spark plug with Actrel® 3338L dielectric solvent or compatible
solvent. Type Installed Replaced? Estimated hours if reused
• Install spark plug dry (no oil, anti-seize, or other lubricant).
• Note - Change spark plug gasket every time the plug is removed
☐Yes ☐No
2210 Address ignition system by fixing any found Magneto, wiring, or coil ☐All OK ☐Found Issues (see comments)
Shutdown issues found during running inspection
Also visually check ignition system by:
• Spot checking wiring harness for wear, nicks, cuts, & loose connections
• Spot checking high tension wiring, isolators, & caps for wear
• Spot checking coils corrosion & wear (no green stuff or cracks)
• Verifying “G” lead is attached and secure
• Address all found issues
2299 Document comments and issues found related to spark plugs and Type comments or issues found:
Shutdown ignition system.

Engine Control System


2300 Inspect integrity of "Engine Control System" wiring harnesses and wiring ☐Completed ☐N/A
Shutdown harness components (as equipped).
Visually inspect all ESM models and control system wiring
Cooler And Coolant System
2400 Inspect main and auxiliary water pumps (if equipped). Inspect weep ☐Completed ☐N/A
Shutdown holes for signs of coolant leakage. Address issues if present.
PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 17 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

2420 Is coolant analysis indicating flushing cooling system sooner than the ☐Yes – Flushed ☐Needs Flushing ☐Analysis states condition OK
Shutdown Top End/Overhaul schedule? If yes, complete the following:
• Flush system; ☐Unknown
• Inspect compressor cylinder water jackets (if applicable);
• Inspect coolant sides of oil coolers;
• Remove and inspect thermostats; replaced as required;
• Clean and check aftercooler;
• Clean & inspect cooler water sections internally;
• Charge with new fresh coolant.
2430 Check shutter condition each service Shutter Position
Shutdown > Note current position of shutters ☐Condition OK ☐N/A
2499 Document comments and all issues found regarding cooling systems. Type comments or i sues found:
Shutdown

Cylinder Lubrication System


2699 Document comments and all issues found with lubricator drive box, Type comments or issues found:
Shutdown lubricator pump(s), divider blocks, and no flow(s).

Pressure Relief Valves (PSV), Dump Valves And Controllers


2700 Visually inspect all PSV's. ☐Completed ☐N/A
Shutdown • Verify if seal is valid (legible and not broken).
• Address issues found.
2710 Repair any faulty dump controllers, leaking dump valves, and clean any ☐Completed ☐N/A
Shutdown dirty sight glasses.
2799 Document comments and all issues found with PSV’s and scrubber Type comments r issues found:
Shutdown dumps.

Belts, Sheaves, And Bearing Grease


PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 18 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

2800 Inspect applicable belt condition and tension, along with respective Replaced Adjusted Need N/A OK ☐
Shutdown drive sheaves, replace as needed. Alternator ☐ ☐ ☐ ☐ ☐

All Applicable - OK
Cooler Drive ☐ ☐ ☐ ☐ ☐
• Properly tensioned belts will feel alive springy. Belts too tight will not Fan/Radiator ☐ ☐ ☐ ☐ ☐
deflect, loose belts feel non-reactive.
Governor ☐ ☐ ☐ ☐ ☐
• Refer to Annex “Belt Tensions or service manual for tension information
• Mark what belt issues were addressed and how
PTO Drive ☐ ☐ ☐ ☐ ☐
• A single X in the “All applicable – OK” column represents all applicable WP – Aux. ☐ ☐ ☐ ☐ ☐
check and all OK WP - Main ☐ ☐ ☐ ☐ ☐
Sheaves ☐ ☐ ☐ ☐ ☐
2900 Grease all applicable points as defined below. Indicate number of points Item Amount No. Points
Shutdown greased.
• Use a Lithium based grease such as Hydrotex Parasyn 70, Lithoplex® Actuator Linkage ½ -1 Pump each joint
Grease No 2, or equivalent. Alternator Idler 1- 2 Pumps
• Use High Temperature Grease on Spill Port Valves and on Linage near Aux. Water Pump 1 Pump
waste gates. Cooler Bearings 3 – 5 Pumps
• Repair any broken grease lines. Control Linkage ½ -1 Pump each joint
• Replace any non-working grease fittings. Fan Bearing (Radiator) 1- 2 Pumps
• All points grease each down service except VVCP’s Fan Idler (Radiator) 1- 2 Pumps
• VVCP need only to greased annually VVCP’s 1 Pump annually
2999 Document all discovered issues with belts, sheaves, and grease points. Type comments or issues found:
Shutdown

Startup
3000 Check battery electrolyte levels. ☐Completed ☐N/A
Shutdown Not all "maintenance free" batteries are truly maintenance free.
SAFETY NOTE: Ensure eye protection is worn when working with batteries

3010 Prepare unit for restart. (Note multiple steps!) ☐Completed ☐N/A
Starting 1. Inspect all work, remove LOTO, check for leaks, purge, pressure test system,
and close out all safety permits.

PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 19 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

2. Reset regulators, carburetors, steppers that were replaced or repaired to


previously recorded setting.
3. Check fluid levels, drain valves, make up tank valves, and process valve
positions.
4. Test engine pre-lube function. Refill lubricator
5. Test compressor pre-lube function. Refill lubricator
6. Ensure all personnel are clear.
7. Restart, check oil pressures and conduct walk around before and after
loading.
Safety Note: Never address any leak under pressure! Always blow down and
initiate LOTO.
3030 Verify fuel settings RIGHT BANK (And Single Carbureted Engines)
Running RICH BURN (No AFR Controller)
Manifold Pressure
1. Verify Engine is loaded, running at a steady RPM, and fuel is at a steady state
2. Verify fuel pressure regulator settings are correct. “A” Regulator Setting
3. Verify ignition system is functioning properly - no miss-fires; engine timing Power Screw Position or Inches OUT
correct. Load Screw

MID
4. Additionally (R) | | | | | | (L) Inches
a. On dual carbureted Vee-Engines, verify banks are balanced OUT
mechanically. ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐
5. On turbocharged engines, verify that wastegate’s establish sufficient boost
(but not excessive boost) over manifold differential pressure.
6. Tune power screws (and sequentially A Regulator(s)) if needed to obtain LEFT BANK
lowest manifold pressure (Boost Method), then lean out ½” Hg per bank – Manifold Pressure
Stoichiometric setting “A” Regulator Setting
7. Record final Settings (as applicable)
Power Screw Position or Inches OUT
Load Screw
RPM

MID
(R) | | | | | | (L) Inches
Load (HP %) OUT
Bank Balance ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐
Fuel Supply PSI

PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 20 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

3030 Verify fuel settings RIGHT BANK (Or Single Carbureted Engines)
Running RICH BURN WITH AFR CONTROLLER
Manifold Pressure
1. Verify Engine is loaded, running at a steady RPM, and fuel is at a steady state
2. Verify fuel pressure regulator settings are correct. “A” Regulator Setting
3. Verify ignition system is functioning properly - no miss-fires; engine timing Power Screw Position or Inches OUT
correct. Load Screw

MID
4. Additionally (R) | | | | | | (L) Inches
a. On dual carbureted Vee engines, verify banks are balanced OUT
mechanically. ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐
b. On turbocharged engines, verify wastegate’s establish sufficient Stepper Position Range H/L
boost (but not excessive boost) over manifold differential pressure. Current O2 Value O2 Target
c. On electronically controlled engines, verify A3, ESM, CEC, or other
controller is correctly programed. LEFT BANK
5. Verify stepper motors are functioning and near mid-range Manifold Pressure
a. IF NOT tune power screws (and sequentially A Regulator(s)) if
“A” Regulator Setting
needed to center range.
6. Verify emissions using an Exhaust Gas Analyzer, gradually adjust carburetor Power Screw Position or Inches OUT
power screw to obtain desired emissions- CO, NOx, O2. Load Screw

MID
7. Verify ARF controls can “swing” to handle Fuel BTU changes (R) | | | | | | (L) Inches
8. Record final Settings (as applicable) OUT

RPM NOX PPM ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐


Load (HP %) CO2 PPM Stepper Position Range H/L
Bank Balance O2 % Current O2 Value O2 Target
Fuel Supply PSI NMHC PPM

3040 Wash unit ☐Completed ☐N/A


Running
3050 Run under load for one hour.
Running 1. Complete necessary paperwork Disc. Meter Inlet Meter Make – Up Fuel Gas
2. Verify all readings against recorded operating parameters taken before P.M. Record (Injection) (Tubing) (Bypass) Meter
3. Make a final inspection of unit. In
4. Verify operating parameters against initial and adjusted settings. MMCFD

PM-3000HR-WAUK-VHP-S4-R1-20161030 Page 21 of 22
Operations & Maintenance Management System
PM Plan: PM-GC-3000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 1500HR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 6 Hours

3099 Document final PM comments/Issues. Type comments or issues found:


Running

Document final PM comments/Issues.

Additional Materials Used Additional Comments


Qty. Part Number Description

Date & Technicians Mileage and Labor Hours


Date Technicians Working Mileage Travel Hours OT Hrs

Company Representative Estimated Totals


Customer Representative Date Totals