Professional Documents
Culture Documents
Introduction
Base plates and anchor rods are often the last
structural steel items to be designed but the first items
required on the jobsite
Therefore the design of column base plate and
connections are part of the critical path
1
4/14/2020
Introduction
Vast majority of column base plate connections are
designed for axial compression with little or no uplift
Column base plate connections can also transmit uplift
forces and shear forces through:
Anchor rods
Friction against the grout pad or concrete
Shear lugs under the base plate or embedding the column
base can be used to resist large forces
Column base plate connections can also be used to
resist wind and seismic loads
Development of force couple between bearing on concrete
and tension in some or all of the anchor rods
Introduction
Anchor rods are needed for all base plates to prevent
column from overturning during construction and in some
cases to resist uplift or large moments
Anchor rods are designed for pullout and breakout
strength using ACI 318
Critical to provide well-defined, adequate load path
when tension and shear loading will be transferred
through anchor rods
2
4/14/2020
Introduction
Grout is needed to serve as the connection between the
steel base plate and the concrete foundation to transfer
compression loads
Grout should have design compressive strength at least
twice the strength of foundation concrete
When base plates become larger than 24” , it is
recommended that one or two grout holes be provided
to allow the grout to flow easier
Two categories
Cast-in place: set before the concrete is placed
Drilled-in anchors: set after the concrete is hardened
3
4/14/2020
4
4/14/2020
5
4/14/2020
6
4/14/2020
7
4/14/2020
8
4/14/2020
9
4/14/2020
10
4/14/2020
11
4/14/2020
12
4/14/2020
13
4/14/2020
Example 1
1. Determine the required strength due to uplift on the column.
Example 1
14
4/14/2020
Example 1
Example 1
15
4/14/2020
Example 1
Hook bearing capacity :
N pn = φ ψ c , P 0.9 fc ' e h d a
Example 1
Concrete breakout strength :
16
4/14/2020
Example 1
17
4/14/2020
18
4/14/2020
19
4/14/2020
20
4/14/2020
21
4/14/2020
22
4/14/2020
23
4/14/2020
24
4/14/2020
If Nua /(ϕNn) > 0.2 for the governing strength in tension and
Vua/(ϕVn) > 0.2 :
N ua Vua
+ ≤ 1.2
φ N n φVn
25
4/14/2020
V = 23k
(Due to WL)
Example 4
1. As determined in Example 1, the required strength due to
uplift on the column = 69.8 kips.
2. A total of four anchor rods is used. Use plate washers
welded to the top of the base plate to transfer the shearto
all four anchor rods. Try four 7/8-in.-diameter F1554 Grade
36 anchors. For combined shear and tension the anchor rods
must meet the AISC provision.
Stresses in rods :
26
4/14/2020
Example 4
Example 4
27
4/14/2020
Example 4
28
4/14/2020
29
4/14/2020
References
American Concrete Institute (ACI) 318M-19
AISC Steel Design Guide (2nd Edition) Base Plate and Anchor Rod Design
AISC Steel Construction Manual 14th
30