You are on page 1of 8

Short-circuit current calculation: a comparison between methods of IEC and ANSI

Standards using dynamic simulation as reference

Albert0 Berizzi, Andrea Silvestri, Dario Zaninelli Stefan0 Massucco


Politecnico di Milano University of Pavia
Piazza Leonard0 da Vinci, 32 Via Abbiategrasso, 209
20133 Milano, ITALY 27 100 Pavia, ITALY

Abstract-An essential issue concerning short-circuit studies is Not all the above mentioned calculations are required at
about how much precise should short-circuit calculations be. the preliminary stage of a project and also their accuracy can
Simplified procedures have been proposed since many years by be less strict at this point than at more advanced stages.
International Committees to provide reference methods for the Short-circuit current studies are a typical example of this.
manual computation and for the use of rated, rather than
operating, equipment data. Recently, dynamic programs have
They are essential studies in system design as well as in
been used to accurately simulate short-circuit currents. Two equipment sizing and selection. Their accuracy can be quite
widely adopted international standards (ANSIAEEE Merent: they can be based on simulation, that must adopt
C37.010.1979 and IEC 909 Standards) are investigated in this very detailed models representing the dynamic behaviour of
paper for comparing and pointing out the most significant system components, or they can use simplified approaches by
differences in methodologies, assumptions, computed currents a quasi-steady state representation of the system components.
and results. An outline of the two standards is presented and a Simplified procedures for short-circuit current calculation
detailed comparison is carried on. The procedures of the two have been proposed long since by International
standards are applied to a test network proposed in the IEC Organizations [3],[4],[5],[6], [7],[81. The adoption of
909 Standard. Results of calculations by the two standards are
compared using the results of a transient study performed by dynamic simulation is relatively more recent and is related to
the EMTP simulation program as a reference basis. the availability of powerful computers and software tools,
which are successive to the development of standards,and to
I. INTRODUCTION the availability of a much larger set of data (the recent
document [91 provides information about power system
Planning, design and operation of electrical power systems equipment).
require several studies to evaluate and assess performances, The enormous development of computer hardware and
reliability and safety of the system. Examples of these studies s o h a r e could have forced power system engineers to adopt
are: load flow, fault and short-circuit, motor starting, extensively dynamic simulation for short-circuit studies and
stability, protective device coordination, reliability analysis to set aside the use of simplified procedures offered by
[I]. Although there is a great interest in power system standards. On the contrary, there is still a great interest in
operation (as the large number of works on hardware and short-circuit current calculation by international standards as
software tools to improve system operation can test$ [2]), it it can be deduced by the continuous process of revision and
is common experience that a poor electrical system design consolidation they are subjected to (for instance, see [4],[7]
can lead to serious consequences in the system safety and and [6],[8]). Moreover, this interest is confirmed by the
operation. Problems cannot be solved and sometimes the significant presence in the software market of many
system situation cannot be improved by subsequent adoption programs that make use of the quasi-steady state
of control methodologies and devices. Bad system operation computational method proposed by international standards
may often be prevented by a correct planning and design. A [lo] and by recent works which compare standards and
good system design based on a careful selection of voltages, procedures from different countries [11],[ 121.
electrical system one-line diagram, on adequate sizing of The aim of the present paper is to give evidence of the
system equipment and on proper setting of protection different approaches offered by dynamic and standard based
devices, is still a basic and unquestionable requirement. calculation of short-circuit currents and to remind the
Some of the mentioned studies need complex and detailed specific fields of application and the limits of both.
models to represent the behaviour of the power system; other Afterwards, it seemed worthwhile to compare the
studies can utilize less sophisticated approaches based on methodologies offered by two important international
simplified but valid analytic procedures. The kind and detail standards, namely the ANSYIEEE C37.010.1979 [ 5 ] and the
of the analysis are strictly related to the stage of the project IEC 909 [ 6 ] , which is the recent result of a long revision
under development. work. It is evident that the comparison between the IEC and
0-7803-1462-~/93$03.0001993IEEE
1420
the ANSI/IEEE Standards is not immediate and needs some equivalent voltage source cUn at the faulted bus. The results
considerations due to the differences in computed quantities. are made d c i e n t l y accurate by using some corrective
The outlines of the two standards are reported in the factors. The voltage factor c assumes different values
following Sec.II by pointing out the most significant according to the system rated voltage ( ~ inl low-voltage
differences in methodologies, assumptions, computed systems 230 V/400 V, 50 Hz;~ 1 . 0 5in other low-voltage
currents and results. The comparison between the standards systems; ~ 1 . in 1 medium and high-voltage systems): it is
is carried out in Sec.III on the basis of results derived by used to set the most adequate voltage level that determines
applying the procedures of the two standards to an electrical the maximum short-circuit current. Another factor &
test network proposed in the Appendix of the IEC 909 allows the calculation of the corrected value of the generator
Standard. This test network consists of a large generator impedance: ZGK=&&+jX",), where is a fictitious
connected to an external system by means of a step-up value of resistance (generally higher than the actual value of
transformer and supplying power to an internal network the stator resistance) assigned by the Standard as a function
including several motors at different voltage levels. The of the subtransient reactance X", for different ranges of
network is quite interesting because it takes into voltage and rating of the generator. Analogously, other
consideration balanced short-circuit faults near to generator specific corrective factors are proposed for power station
and in presence of motor contributions. units, depending on whether generators and transformers are
In order to present a more significant comparison, the to be considered separately or not. As for the other element
same electrical test network has been investigated by using a -
impedances such as external network, two or three winding
recent version of the E m , a widely spread international -
transformers, overhead lines and cables the Standard gives
computer code for electrical transient analysis [13]. The appropriate formulae. Motors are modelled by their locked
results of the transient analysis are in terms of current rotor impedance.
waveforms versus time: after some elaborations, they are I", is calculated as: I"k=cU,,/d3&, where Z, is the
used as a reference to compare the different values of short- equivalent impedance as seen from the faulted bus; Z,
circuit currents computed as required by the ANSI/IF!EE and includes rotating machines' impedances only if the fault is
the IEC Standards. near-to-generators (and motors).

11. OUTLINES OF THE TWO STANDARDS Separated formulae for near-to or far-from-generator

A . The IEC 909 Standard


short-circuitsare proposed to compute ),, 1, G I k , both
because of their inherent dependence 0 I k and ermore
because these characteristic values depend on the time
The IEC 909 Standard [6] distinguishes between near-to- behaviour of the short-circuit current, influenced by possible
generator and far-from-generator (and motor) short-circuits, contributions of synchronous andlor induction machines.
a commonly adopted practice in German technical literature The Standard also provides different approaches
[14]. The short-circuit current is the sum of an ac -
according to network configuration radial or meshed and -
symmetrical component and of an aperiodic component .i, to fault location. For radial systems, the total short-circuit
Near-to-generator short-circuit current presents a -
current is computed in a simplified but more conservative
symmetrical component decaying with time, while far-from- manner - as the algebraic sum (instead of vector sum) of all
generator symmetrical component is constant. contributions from the paths connected to the fault location;
In particular the IEC 909 Standard considers only the otherwise, in the case of meshed networks, this is not
following values of short-circuit currents: possible and a different procedure must take place.
I", rms initial symmetrical component; 0 Computation of ip. It is necessary to distinguish the cases
ip peakvalue; of radial or meshed network.
Ib symmetrical short-circuit breaking current at the - In the case of radial network, i, is the sum of
instant,,,t of contact separation of the first pole of contributions iPi from the i-th path converging to the fault
a switching device; bus. Each ipi is computed as a function of I", as ipi=Kid21",,
I,, asym rms asymmetrical short-circuit breaking current; where each coefficient K,depends (by a formula or a graph)
1, rms steady state short-circuit current. on the X/R ratio of the corresponding element.
Afterwards, reference is made to the case of three-phase - In the case of meshed network, as the behaviour of the
balanced short-circuit, because [6] applies only superficially short-circuit current in each path depends on all network
to unbalanced faults. Some details to unbalanced faults are branch parameters, the IEC 909 suggests three different
reported in the mentioned revision of the E C 909 Standard approximated methods (named A, B and C) to compute an
181. equivalent X/Rratio for the direct determination of i .
0 Computation of Illk The approach of the IEC 909 method 0 Computation of 1, In the case of short-circuit &-from-
consists in an approximation of the superposition method. It generators and independently on the network structure, the
neglects the state prior to the faults and considers an

1421
following holds: Ib=I'tk=I,. In the case of near-to-generator paper.
short-circuit it is necessary to distinguish between radial and The ANSI Standard allows a simplified calculation of
meshed networks: short-circuit currents by reducing the electric system to an
- radial networks: 1, can be expressed as the sum of equivalent network made by an ideal voltage source E
different Ibi contributions, where Ibi=piqi Illfi. The factor pi behind an equivalent reactance (both expressed in P.u.). The
can be determined by a formula or a graph as a function of voltage magnitude E is the highest typical operating voltage
the minimum contact parting time Inand of the ratio I",/I,, at the faulted bus and it represents the pre-fault voltage. In
where the considered values oft,,, are 0.02, 0.05, 0.1 and 2 many cases, when the operating voltage is unknown, the
0.25 s and where I, is the rated current of the machne nominal voltage is utilized.
related to the i-th branch; for extemal network supplies, By means of appropriate corrective factors, the ANSI
pi=l is adopted. The factor qi is set equal to 1 unless the Standard considers both the dc and the ac decay of the short
branch is an induction motor. In the latter case qi (11) is a circuit current. The dc decay is determined by the X / R ratio
function oft,,, and of rated power per pair of poles; of the equivalent impedance as seen from the fault point; the
- meshed networks: it can be assumed Ib=I''k, according to ac decay takes into account the behaviour of the system's
a conservative approximation of a more complicated rotating machines such as induction motors and synchronous
formula. generators. Concerning the ac decay, two possibilities are
Computation of 1, asym. It can be calculated as considered: rotating machines can be either near to or
remote from the fault location.
2 2 The ANSI Standard aim is to determine a symmetrical
Ib asym = ,/Ib -k l,,
rms current on the basis of which it is possible to choose a
This formula is also adopted, with different symbols, in [5]
circuit breaker rated on symmetrical current basis as stated
(Sec.5.1.3 and Appendix A4). The component i, must be
in ANSI C37.04-1979 [15] and ANSI C37.06-1987[16],
evaluated at the instant t,,,( as well as Ib), by the formula
although older breakers can still be selected on a total
,,i = &I; exp(-2 d t /~X ) (1) current basis [17]. The considered faults are both
where the value of the ratio X/R is computed differently symmetrical and non-symmetrical; the Standard pays
according to the radial or meshed network structure. particular attention to three-phase and line-to-ground faults.
- radial network: i,=CiDci Three types of duties are taken into consideration by the
where for each branch (1) applies with its proper X/R. ANSI C37.010-1979:
- meshed networks: iDc is directly computed using (l), a) first-cycle duty
where the equivalent raho X/R can be computed by using b) contact-parting duty
one of the methods B or C adopted by the standard to c) short-circuit current for time-delayed relaying devices.
calculate i,. No indication is given about the calculation of Each of the cited duties is calculated using a different
the single contributions iDci. network. The characteristics of these duties are described
Computation of 1,. Two different procedures are and commented with reference to the mentioned ANSI
considered for the cases of faults far-from or near-to- Standard.
generators. In the former 1, is assumed equal to 1"k; in the a) Firstcycle duty: it is the half-cycle rms current and it
latter many parameters atTecting the current behaviour must allows the evaluation of stresses during the first cycle after
be accounted for: magnetic circuits saturation, excitation the fault. To compute it, a first-cycle network must be built:
type and voltage ceiling, automatic voltage regulator, type of this requires to ignore the static loads' impedances, to use the
machine (turbogenerator or salient poles generator). branches' impedances and to correct the rotating machines'
The IEC 909 Standard furnishes two graphs for each type subtransient impedances with multiplicative factors which
of machne relating Ihax and 1- to the ratio I''kG/Ifi and, take into account their typical ac decay. Reactances instead
in the case of Ihax, to the direct axis synchronous reactance of impedances can be used. The rotating machines'
saturated value. multiplicative factors are collected into a table; in particular
induction motors are classified into three groups in
B. The ANSIIEEE C37.010-1979 Standard accordance with their rated power and number of poles. The
calculation of the first-cycle duty does not require any
The purpose of the ANSI/IEEE C37.010-1979 Standard consideration about local or remote short-circuit current
[5] - afterwards cited simply as ANSI Standard - is to allow sources.
a good sizing of medium and high-voltage breakers (rated on Once the equivalent reactance X is obtained, the first-
symmetrical current basis) installed at 1000 V and above; cycle duty can be evaluated as E/X (symmetrical, rms); this
the corresponding Standard for low voltage breaker is the symmetrical duty must be lower than the breaker closing and
ANSI/IEEE C37.013-1981, which is not considered in this latching capability and it does not take into account the dc
component decay; so it is possible to calculate the

1422
asymmetrical duty (rms) by multiplying E/X by the factor [18]) are available in the Sec.5.3.2 of the Standard [5] for
1.6; moreover, ifE/X is multiplied by 2.7, one can evaluate evaluating the factor F: a local curve and a remote one. The
the peak value of the first-cycle short-circuit current. The former, which refers to faults fed predominantly from near
factors 1.6 and 2.7 are not empirically determined: their generators, takes into account both the ac and the dc decay
meaning is described in [18] and they can be derived and it is only empirically known [191. The latter w e is
respectively from the formulae: related to faults far from generators and considers only the
dc decay: in this case F can be analitically expressed as a
S- = ,/I + 2 exp(-4 Z J ~/RX ) (2) function of X/R. When both local and remote sources are
present, it is not easy to decide which curve is needed. The
S+ = &[I + exp(-2njt~/ X I ] (3) more conservative procedure consists in applying the higher
where f is the frequency, X and R are the equivalent factor, i.e. the one related to the remote curve. In [20] an
reactance and resistance of the first-cycle network. Actually, interpolation technique is applied to single contributions to
factors 1.6 and 2.7 are derived respectively from (2) and (3) the fault; a different multiplying factor is applied to each
by adopting m 2 5 . Nevertheless, due to the common contribution.
exponential shape of (2) and (3), the value of X/R which c) Short-circuit currents for timedelayed relaying devices:
determines the previously mentioned factors is indicated in it is necessary to evaluate this current in case of application
[18] equal to 15: this value is clearly established by the of timedelay relays beyond six cycles. The short-circuit
ANSI Standard as regard to the different procedures for current is calculated as E/X where the corresponding
computing the contact-parhng duty (seethe next point b). network must be built only with generators as well as with
The Standard recommends to use two different networks passive elements such as lines and transformers, and
to evaluate X and R, one with only reactances and the other omitting motor contribution, which can be considered
with only resistances: this procedure is more conservative vanished. Generators are represented by their transient
than the one consisting in the calculation of the complex reactances or by a larger reactance that takes into account
impedance, for which X and R would be the immaginary and the ac decay; moreover, the dc component is supposed to be
the real part respectively. zero. Consequently, this current can be compared with Ik of
b) Contact-parting duty: it is the rms current at the parting the IEC 909.
of the breaker poles. In the Standard, only breakers with
minimum contact-parting time in the interval 1.5-4 cycles
are considered. An interrupting network has to be built, 111. SHORT-CIRCUIT CALCULATION AND COMPARISON OF
composed by the pre-fault voltage source and by an RESULTS
equivalent impedance. This equivalent impedance (or
reactance X, as permitted by the Standard) is calculated as in A. Test network
the previous point a: the multiplicative factors of rotating
machine subtransient reactances are different, because the ac The test network adopted for comparing the two standards
decay at minimum contact-parting time is larger than during is proposed in the Appendix A3 of the IEC 909 Standard
the first cycle. and reported in fig.1. It consists of a power station unit
The ANSI Standard provides two procedures to select the connected to a 220 kV system. The auxiliary transformer AT
proper breaker: the most simple possibility, when X/R is is of the three-winding type and feeds two auxiliary busbars
unknown, is to select as adequate a breaker with symmetrical B and C at the nominal voltage of 10 kV. Fig.1 indicates the
capability larger than 1.25 Em.Otherwise, it is necessary to principal characteristics of all equipment. The data of the
analyse the ratio X/R and the knowledge of the system transformer and of the external supply system are the same
resistances is necessary. If X/Ris lower than 15, the breaker as in [6], while the data of the generator and of the motors
symmetrical capability can be selected as 2ElX; on the (handled as groups of motors) are specified in [21] also-
contrary, a more detailed procedure (named "with those unnecessary for the use of the standards but essential
adjustment for ac and dc decrement") comes into play and it for the dynamic simulation. Balanced short-circuit current
will be considered subsequently. faults at F1, F2 and F3 (see fig.l) are taken into
Following this method, once E/X is calculated, it is consideration. Concerning the dynamic simulation, the
possible to select the breaker by using a proper corrective steady-state condition preceding the fault is assumed to
factor (cited here as F) which depends on the actual X/R correspond to the functioning of motors at nominal slip,
ratio: the rated symmetrical capability of the breaker must be while the generator has a load angle which assures the
larger than F.E/X; the so selected interrupting device is delivery of the nominal power at the nominal power factor;
adequate as for the total (asymmetrical) short-circuit current besides, the effect of the automatic voltage regulators is not
too. accounted for, because it influences the phenomenon only
Two set of w e s (the meaning of which is described in after about 200 ms.

1423
Tii;l
Unit transformer T:
Sr~=250MVA
U , T H V / U , T L V = ~ ~1*12%)/21
O~V kV
Ukr = 15% ; PkiT = 520 kW

Generator G:
S,c=250 MVA
U,G=21 kV
x;i=17% 3-
cos ( 4 , ~=0.78
Auxiliary transformer AT
&TAB = S,TAC= &TBC = 2 5 MVA
UTA 21 kV ; U,TE= Ufic = 10.5 kV
UkrAE=uk,AC=7% :UkrBC =13%
pkrTA6=PkrTAC = 59 k W ; PkrTBc =114 kW

Auxiliary busbar E, U. =10 kV Auxiliary busbar C, U, =10 kV


F3f7

Fig.1. High and medium voltage test network with faults near-to-generatorand motors. Network used for comparison of results: faults at F1, F2, F3

B. Basisfor the comparison of the two standards (P.u.) of the IEC 909 Standard and X is the reactance of the
first-cycle network.
The ANSI Standard is not directly addressed to the The IEC 909 calculates the peak short-circuit current i,.
calculation of short-circuit currents but its aim is to choose The ANSI Standard does not directly consider t h s quantity,
as well as possible the circuit breaker; the IEC 909 is not but allows to calculate it by multiplying the Same term E/X
particularly oriented to breaker sizing, but rather to the by 2.7.
calculation of short-circuit currents; the dynamic simulation 0 Concerning the instant of the contact parting, the IEC
gives the current waveform, independently from the 909 allows the calculation of the symmetrical component I,,
engineering application of this information. So, as the goal and only in one of the examples in the Appendix it shows
of this paper is to compare the ANSI and IEC Standards and the value of the asymmetrical component 1, as,,,; the ANSI
the dynamic simulation, considerations about breaker sizing Standard considers only the breaker symmetrical duty.
are left out (while they are treated in detail in [22]) and The term corresponding to 1, can be evaluated in the ANSI
attention is focused on the calculation methodologies of the Standard as E/X, where X is the equivalent reactance of the
two standards which are analysed accurately, to define interrupting network (see I1 B, b). Although the ANSI
common quantities comparable also with those evaluated by Standard does not consider the asymmetrical short-circuit
means of computer dynamic simulation. current at the minimum contact parting time, it is possible to
0 A first comparison between the characteristic values of evaluate it by the following logical process. Once the breaker
the short-circuit current considers the initial symmetrical is chosen, its asymmetrical capability is univocally
current. The I", in the IEC 909 can be related to the term determined from its symmetrical rating supposing X/R=15;
E/X of the ANSI Standard, where E corresponds to cU, the asymmetrical short-circuit current is assumed equal to

1424
the breaker asymmetrical capability and comparable to motors. Dynarmc simulation confirms this approach. In fact,
'b asym. the corresponding contribution (expressed as the current in
the primary of the three-winding transformer) has, for
C. Comments and results example, a peak value of 0.46 kA which is negligible. Even
using the ANSI Standard but neglecting the contribution of
Tab.1 shows the characteristic values of the short-circuit motors, we obtained for example a peak value of 54.12 kA,
current at the fault points for the IEC 909, the ANSI very close to the one referred in Tab.I(54.49 U).
Standard, and the dynamic simulation carried out by means - Concerning the calculation of $, by the ANSI Standard, it
of the EMTP simulation program [13]. The table refers is possible to note that, using the c d c i e n t derived by the
respectively to the faults F1, F2 and F3 (fig.1) and the actual X/R instead of the coefficient 2.7, its determination in
symmetrical and asymmetrical breaking currents are the case of F1 and F3 is closer than in the case of F2 to the
evaluated at fm=O. 1 s (5 cycles). one by EMTP. In fact, in the cases Fl and F3 the ratio WR
Referring to Tab.1, it is possible to make the following is lower than 25 (about equal to 18 and 24, respectively)
comments. while in F2 it is greater than 25 (about equal to 60).
- The IEC 909 and the ANSI Standard give results that are - In the case of fault F3 it is possible to note a difference
overestimated with respect to dynamic simulation, clearly in on the value of I, determined by the two standards compared
favour of a safety margin. In general, this overestimation is with the dynamic simulation. This is due both to the beating
less marked in the ANSI Standard: its results are closer than of the symmetrical component of the short-circuit current (a
the IEC 909 to those obtained by the dynamic simulation. typical dynamic phenomenon, which is clearly shown in
- The IEC 909 does not indicate how to calculate Ib asp in fig.2) and to the overestimation by the standards of motor
this example, while it is possible to deduce it by the contributions to the fault (see Tab.11 and the corresponding
procedure used in the ANSI Standard, obtaining values in comments).
agreement with the dynamic simulation. As concems the calculation of the contributions to the
-
- In case of fault F1, the IEC 909 differently from the fault current, it is important to note that the ANSI Standard
-
ANSI does not take into account the contribution of seems not explicitly to consider this possibility.
Nevertheless, it is possible to imagine the calculation of
TABLE I these contributions considering the reactance of the
CHARACTERISTICVALUES (IN kA)OFTHE SHORT-CIRCUITCURRENTAT PI, FZ AND corresponding network branches and attributing to them the
F3 (SEE FIG.1): COMPARISONBETWEEN ANSI. IEC STANDARoSAND DYNAMIC relevant E K .
SIMULATION. THE CHARACTERISTICVALUES ARE REPRESENTED W l l l i THE Tab.11 reports the contributions to the fault F3 current
SYMBOLSUSEDIN THE IEC909 (SEE SEC.IIA).THE PEAK VALUE F O R T H E h S I IS from the three-winding transformer AT (secondary B side),
CALCULAmD B m WlTH THE EXACT VALUE OF X/R AND MULTIPLYING THE FIRST from the group of motors M1-M7 and from the motors M+T
CYCLE E/X BY 2.7 ON THE BRACKETS) 15-20, feeding the fault through their transformers. As
shown in Tab.11, the proposed method to determine the fault
Fault location I ANSI IEC I EMTP current contributions with the ANSI Standard gives results
in accordance to the IEC Standard and both the standard
I",=2 1.04 Yk=22.73 1",=22.03

F1 ip=54.49(56.80) ip=56.64 ip=51.71 40. I I I I I I


I
I,=20.99 I,=22.57 Ib=20.30 [kAl

I, =,,,,=2 1.30 - I, =,,,,=20.47 20.


I

I",=75.83 I"y81.42 I",=7 1.62

F2 i,=208.94 (204.69) ip=217.36 i,=201.65


0.
1,=74.35 I,=74.43 1,=60.23

I, =,,,,=87.50 - I, =,,,,=87.80
-20.

-40. I I I I I I I
1,=25.98 1,=23.68 I,=17.75 ,005 .1 .2 Is1 .3

I, ss,,,,=28.06 - Ibar,,,,=21.63
Fig.2. Symmetrical short-circuit current in the case of fault F3.

1425
TABLE I1 IV. CONCLUSIONS
CON-rrUBUIlONSOF THE CHARACEUSTIC VALUES OFTHE FAULT
F3 CURRENT
FROM THE AUXILIARY
TRANSFORMER OF MV MUTORS
(AT). FROM THE GROUP The present work performed a comparison between two of
(MI..M7)AND FROM THE GROUP
OFTRANSFORMERS-MOTORS
(M+T,I5..ZO) the most significant international standards for short-circuit
calculation: the IEC 909 Standard and the ANSVEEEE
C37.010-1979. Although the methodologies of the two
standards are both based on a steady-state approximation of
18.27 18.17 17.55 the short-circuit phenomenon, they are quite different. The
ANSI Standard is more oriented to breaker selection, while
I", X(Ml..M7) 9.13 10.00 7.82 the IEC Standard gives general guidelines for short-circuit
I", C(M+T,15..20) 2.35 2.63 1.55 current computation: consequently the comparative analysis
was not so evident and some detailed considerations had to
48.40 51.39 49.40 be done in performing the comparison. A set of short-circuit
24.19 24.77 10.87
currents, directly extracted from the standards or obtainable
after some elaborations, were determined as values useful
6.22 5.03 3.41 for the comparison. A detailed dynamic analysis performed
by using a well known program for electromagnetic
'bAT 18.22 18,17 16.97
simulation was used as reference for the comparison between
Ib C(Ml..M7) 6.09 4.82 1.15 the two standards. This latter analysis is expected to provide
a more accurate evaluation of the short-circuit currents
Ib qM+T,15..20) 1.66 0.69 0 because of its inherent superiority in modelling the physical
phenomenon.
The comparison between the two standards carried out in
procedures overestimate fault currents with respect to the this paper shows that the IEC 909 is somewhat more
dynamic simulation results. ponderous than the ANSI Standard. Hypotheses and
This overestimation is higher for motor contributions, as assumptions are more numerous and more detailed in the
above mentioned, due to the fact that the dynamic simulation IEC 909 than in the ANSI Standard. In the former standard
takes into account the electric and mechanical transient more information and more formulae about the possibility of
behaviour of the motors. Only this simulation can reveal that neglecting motor contributions are presented, as well as the
basis for determining whether short-circuit is to be
during the short-circuit transient the motors near to the fault
considered near or far-from-generators. The ANSI Standard
point behave as generators (the torque changes its sign) but
presents more empirical but as much efficient solutions. The
the motors far from the fault point still operate as motors. results of calculations, in fact, confirm that both the
Fig.3, depicting the transient of the MV motor torques in the standards gives satisfactory approximations of the short-
case of fault F3, is a significant example of this. circuit currents whch are, mostly, on the safety side.
Sometimes the better accuracy offered by dynamic analysis
T CkNml becomes a must, such as in case of short-circuit currents that
4 /I exibit a large asymmetrical component, or when more
detailed information about actual rotating machine
contributions are needed, or when evaluation of voltage
regulator effects on fault currents is required. Nevertheless
the traditional short-circuit analysis based on the standards'
methodologies is still very important. The adoption of the
standards (and of adequately validated computer programs
based on their methodologies) should be encouraged if an
unique reference for comparing different designs is needed,
particularly at the beginning of a project development, or if
there is lack of data and of their accuracy for transient
" -
-5x ,m 1.0
analysis.
Although the EMTP simulation program used in this
t Cmrl paper is widely adopted, there is still no evidence of the
existence of a uniquely recognized international dynamic
Fig3. Torques (T) ofmotors Ml..M7 and M8..M14respectively in case of program which can be used as a reference, in the same way
fault F3. as the international standars are.

1426
REFERENCES A l3aizzi, F. Cartelli Desa, S. Mwucco. A Silvebri, D.ZmimIli,
"Evolution of & e m a t i d d.ndsrds fix short-ciwii dcul.tiola: a
Industrial and commercial power system analysis, ANSYIEEE cnnpurtive analysis rupported by simulation tsstr", V Intemutional
516399-80. IEEE Book, 1980. Symposium on Short-circuit Currents in Power Systema. Wuraw
working (iroup 01 of study Commiaee 3 7 "Flexibility of power (Polandh 8-9 septsmba 1992.
qst".. Rinciples, meam of *wanalt and .pprolches for facing -
ATP "Alterdvc Transient Rognm Rule Book ",Leuven EMTP
unoertamty by pluming flenble development of power systans", Csnta, July 1987
.
K U C
' m . 135, pp.75-101, April 1991. R R a p a . Short-circuit current calculations in three-phase systems,
Recommendation for the calculation of short-circuit current, W E 2nd ed. John Wiley and Sons, 1985.
0102 st.ad.rd,Part 1111.1971 mdPartU11.1975. Il?EE Standard rating structure for ac high-voltage circuit breakers
short-circuit current evaluation with special regard to rated short- rated on a symmetrical current basis, ANSVIEEE Std. (37.04-1979.
circuit capacity of short-circuit breakers in installation in ships, IEC AC high-voltage circuit b r e a k s rated on a symmetrical current basis
Publication363. First edition, 1972. - Pr0fsrr.d ratings and related required capabilities, ANSVIEEE
Application guide for AC high-voltage circuit breakers rated on a StdC37.06-1987
symmetrical basis, ANSYIEEE Std C37.010-1979. Guide for calculation of fault currents for application of ac high-
Short-circuit current calculution in three-phase as. systems, IEC voltage circuit breakers rated on a total current basis, ANSMEEE
Publication909, First edition, 1988. StdC37.5-1979.
Short-circuit current evaluation with special regard to installation in C.N. Ha~tman," U " ' g Isymmdry", I- Trans. on Industry
ships and offshore drilling units, IEC Publication 363, Draft serrmd Applications, vol. IA-2 1, a4. pp.842-848, July/August 1985.
edition, April 1990. C.R. StPicm, "Sample ryrtem for tlaespbue rhort-circuit
Revision of IEC 909, 1988. Short-circuit current calculation in three- calculotipp", IEEE Trans. on Industry Applicationx, vo1.26. n2,
phase ac systems. IEC Preliminary Draft, 73 (Sec.) 56, January 1993. pp.203-211, M~cWApril,1990.
-
Electrical equipment Data for short-circuit current calculations in IEEE Recommended practice for electric power distribution for
accordance with I . 909 (1988), IEC Technical Report 909-2, First industrialplants,ANSVIEEE Std.141-1986, IEEE Red Bods 1986.
edition 1992-08. F. Cdstclli DGZZJI,A Silvabi, D.Zrninslli "Ihe IEC 909 st.adud and
N.N. &ngiUnin, F.H. H o l m b , " P C - b d ~ O W C Isystrm ~ ~ f t w a r r : dynamic simulation of short-circuit cunant", E'ITEP - E u r o p n
wmparing functions and features", IEEE Computer Applications in Transaction on Electrical Power Engineering. in par.
Power, vol. 5. n 1, pp. 3540, January 1992. B.Baidger, "All cunpsns arc not sated equal: a conrprrison of "t
J.R Dunki-Jaoobr, B. P. Lam,RP. stratford, "A ~ 0 m p h 0 1 1of ANSI- of hi&tl-volt.gc cirmii brrrkas rated d g to ANSI and IEC
based and dynamically rigorous short-circuit current calculation stad". IEEE Trans. on Industry Applications, ~01.29, nl,
proceduns", IEEE Trans. on Industry Applications, vol. 24, a 6, Jmuaty/Fcbrua~y1993.
pp.1180-1194, N~vanber/December1988.

1427

You might also like