Professional Documents
Culture Documents
CLIENT CONSULTANT
NOTES :
KEY PLAN
1 2 3 4 5 6 7 8 9 10 11
PART01
PART02
A STAIRS
A
COMMUNI. ROOM PDU-1A-1 PDU-2A-1 PDU-3A-1 PDU-4A-1 PDU-5A-1
ITR ITR ITR ITR ITR
300KVA 300KVA 300KVA 300KVA 300KVA F14
F19 WC
F17
UP CRAH ROOM
6.47+m Main contractor :
F18
F.F.L KITCHENETTE
F16
B F.F.L B
UP
1 LOBBY LOBBY
HIGH
DENSITY RACK
F15 F13
F22 F11
SECURITY ROOM
STAGING
6.32+m F12
F20
F.F.L
6.32m
CORRIDOR
F.F.L
F10
C FM 200 FM 200
LOBBY C
F09
F23 RACKS ( 1200*600) F25
OFFICE ROOM Main consultant :
14 F24
F
HIGH
F21 DENSITY RACK
G 03 CORRIDOR
G04
CORRIDOR
ARCHITECURE & LANDSCAPE CONSULTANT:
F07
COMMUNI. ROOM
D LOBBY F08
D
6.32+m
G02
F.F.L
E UP E
6.47m
FREIGHT LIFT
STAIRS CRAH ROOM F.F.L
B05
B01 UP F06
1 2 3 4 5 6 7 8 9 10 11
PART02
PART01
DRAWING TITLE :
FIRST FLOOR PLAN
EARTHING SYSTEM LAYOUT
OVERALL