You are on page 1of 3

Part 5

38 TheStructuralEngineer Technical
May 2014 Composite/Steel compendium

Composite and Steel


Construction compendium
Part 5: Construction of composite floors
This article is part of a series in-plane stiffness of the decking itself, and secondly how it is fixed
that will gradually build to form a to the beam. If the ribs of the decking run parallel to the beam,
Composite (steel-concrete) and then no restraint is provided at the construction stage, as the
Steel Construction compendium. decking would merely act like a concertina were the beam flange
Written by leading experts to try and move sideways. If the ribs run perpendicularly then the
from the SCI, the articles aim decking may be assumed to have sufficient stiffness. However, to
to provide a real insight into exploit this stiffness it will need to be adequately fixed to the beam.
composite and steel construction, When shear studs are present and they have been through-deck
to help practicing engineers get welded, as is common UK practice, the decking may be assumed
the most from these materials. to be adequately held in place. Otherwise, when the decking
is fixed (using discrete connectors such as shot-fired pins) the
designer must provide an adequate number of connectors, taking
Introduction into account their individual resistances and the force needed to
The designer of a composite floor has a number of basic and restrain the beam flange2.
obvious decisions to make, including what type of beam to
use and what type of decking. He or she also has some more Propping of the decking and/or beams
detailed decisions, such as the choice of propped or unpropped Why prop?
construction, whether the steel beams will be restrained during The term ‘propping’ is used to describe the provision of temporary
construction, and how will the upper surfaces of the slabs be supports to the steelwork. The benefit of propped construction
levelled during concreting? All these decisions need to be well is that it results in a greater part of the loading being applied to
thought through, rather than assumptions made, and the more the (stiffer and stronger) composite section, be it beam or slab,
detailed decisions need to be communicated to those who and less to the steel element alone. Greater spans may then be
will construct the floor so that site practice reflects design achieved. For long span beams this can be particularly beneficial by
assumptions. There may also be specialists involved in the design, reducing dead load deflections. Propping of decking (or ‘sheeting’
e.g. to establish the precise details of how the decking will be as it is termed in the Eurocodes) may enable secondary beams
delivered and laid out. These individuals must also have a clear to be more widely spaced, and so the steelwork costs may be
understanding of the primary designer’s assumptions. reduced (Figure 1). The disadvantage is that the construction
This final article in the composite part of this construction process may be adversely affected.
compendium looks at three aspects of construction; the provision
of lateral restraint to the beams, whether the steelwork is propped What should be specified?
and how the concrete is levelled. A simple statement on a drawing such as: ‘beams and decking to be
propped’ will not suffice. That statement might be read as implying
Provision of lateral restraint to the beams the designer assumed continuous support during concreting, but
For bracing against buckling, two requirements may be identified clearly that could not be achieved in practice.
for all restraint systems: Propped construction essentially means that at the construction
1. Sufficient stiffness; to increase the buckling load of the restrained stage, the steel element (beam or decking) has a different
member to the desired level by limiting the buckling deformations. structural form – typified by shorter spans and continuity over
2. Sufficient strength; to resist the loads transmitted as a result of additional support/s. Typically there would be a prop at mid-span,
restricting the buckling deformations. or possibly at third-span points. A proportion of the construction
loading is transferred by the props to the floors below. When the
Despite the importance of both stiffness and strength, many concrete has attained sufficient strength, the props are removed,
structural design codes provide only strength requirements, and the self-weight is resisted by the composite section. The steel
assuming that a member of such strength will possess adequate element must be able to span between the props when subject to
stiffness. EN1993-1-1 Clause 5.3.3(2)1 defines an equivalent the construction loading.
stabilising force.
The elimination of lateral torsional buckling as a failure mode may When we come to consider a composite floor, rather than individual
enable a lighter section size to be used. However, a designer should elements, the situation becomes a little more complex and one can
recognise that profiled steel decking will not always provide this envisage two scenarios (Figure 2). From a design point of view,
level of restraint. Two things need to be considered; firstly the the easier situation to consider is that shown in Fig. 2a, where the

TSE29_38-40 CSCC 5 v4.indd 38 24/04/2014 08:29


www.thestructuralengineer.org

39

N Figure 1
Propping of decking (note that props
should be braced in both directions)

beams are propped but the decking is not. For a beam spanning
between columns, the support stiffness provided by the columns
will be similar to that provided by the temporary supports. In Fig.
2b the decking is propped and the beams are not. This option
is complicated because the permanent supports to the decking
(the beams) will deflect as load is applied, whereas the temporary
supports will barely move (unless they are supported off the beams a. Props placed directly below beams
themselves). Normally the outcomes of this ‘support incompatibility’
are not considered in the design of the elements, with loads
distributed between supports assuming the supports have equal
stiffness, rather than the stiffer temporary supports picking up a
relatively higher proportion of the load. However, the ‘differential
settlement’ that results from these different support stiffnesses b. Props placed between beams (to support the decking)

should certainly be taken into account when considering the


thickness of concrete to design for.
 Figure 2
Propping of beam or decking
Good practice on site
Careful attention should be paid when propping decking on site
because of the nature of the product (formed from thin steel). to do this could see excessive self-weight of concrete applied to the
Timber bearers or steel runners should be used to span between structure. The two principal ways in which the upper surface of the
individual props. They must be sufficiently stiff, and always extend concrete can be controlled during casting, are:
the full width of the bay to avoid localised problems (Fig. 1).
Typically they are 75-100mm wide to provide adequate bearing and • Maintain a reasonably constant thickness of slab. As the beams
avoid local damage to the decking. Props are normally placed at and decking deflect under the wet weight of concrete, the upper
approx. 1m centres. surface of the concrete ‘deflects’ to follow their form. This is
achieved by setting tamping rails on the beam lines
Levelling of the concrete surface • The upper surface of the concrete is maintained level (meaning
Just as there are different ways in which a floor can be propped, there ‘flat’). As the steelwork deflects, more concrete will be added to
are different ways in which a concrete slab (its upper surface) can be compensate, and the thickness of concrete will clearly not be uniform.
levelled. To avoid overloading in the temporary condition it is essential Laser levelling may be used as a quick and cheap solution, possibly
that the designer’s assumptions are reflected in site practice. Failure with power floating (Figure 3) to avoid the need for a screed.

TSE29_38-40 CSCC 5 v4 NEW.indd 39 24/04/2014 11:24



Part 5

40 TheStructuralEngineer Technical
May 2014 Composite/Steel compendium

W Figure 3
Power floating of concrete
to produce flat upper surface

ALAMY
"A simple statement on a References and further reading
drawing such as: ‘beams and 1) British Standards Institution (2005) BS EN 1993-1-1:2005
decking to be propped’ will Eurocode 3. Design of steel structures General rules and rules
for buildings London: BSI
not suffice" 2) Steel Construction Institute (2011) Stability of Steel Beams
and Columns (P360), Ascot, Berkshire: SCI

3) British Standards Institution (2005) BS EN 1994-1-1:2004


Eurocode 4. Design of composite steel and concrete structures
‘Level’ may also mean ‘at a certain height’, in which case as-built – General rules and rules for buildings London: BSI
deviations in the height of the steelwork may compound the situation
previously described. 4) British Standards Institution (1994) BS EN 5950-4:1994
Structural use of steelwork in building code of practice
For the aforementioned situation, the deflection of the decking might for design of composite slabs with profiled steel sheeting
be in addition to the deflection of a secondary beam to which it is (superseded/withdrawn) London: BSI
attached, and in addition to the deflection of a primary beam to which
the secondary is attached. As such, the extra thickness of concrete Further reading
could be significant. The Concrete Society (2008) Composite concrete slabs on
steel decking. Guidance on construction and associated design
Design codes recognise the fact that as the decking deflects, more considerations (includes amendment No. 1, September 2013),
concrete may be added (known as ‘ponding’ of the concrete), for Camberley, UK: The Concrete Society
example EN 1994-1-1 (Clause 9.3.2(2))3 suggests that if the central
deflection of the decking is more than 10% of the slab thickness, Beal, A. N. (2011) ‘Floor slabs, lasers and levels’, Concrete,
ponding should be allowed for. It also suggests that the decking Camberley, UK: The Concrete Society
should not deflect more than L/180 (where L is the effective span
between supports) under its own weight plus the wet weight of MCRMA/Steel Construction Institute (2009) Composite Slabs
concrete. BS 5950-44 set a similar limit but added an absolute limit of and Beams using Steel Decking. Best Practice for Design and
20mm (unless ponding had been explicitly allowed for, in which case Construction (Revised Edition) (P300), Ascot, Berkshire: SCI
more relaxed limits could be applied). However, all these measures
are relative to the ends of the decking span and do not reflect the
potential additive effect of supporting beams. Clearly this is incorrect
(when used in conjunction with modern site practice, which has
Web resources
changed since the Eurocodes were written), and designers should
carefully consider all sources of deflection. The Steel Construction Institute: www.steelconstruction.info

TSE29_38-40 CSCC 5 v4 NEW.indd 40 24/04/2014 11:24

You might also like