Professional Documents
Culture Documents
B-4
D-0
1 A-1 8 9
2 4 5
C-3 E-8 F-1 J.2 K-2
G-12
I-1
6 7
H-2
S-10
10 11 12 13 14 15
K-2 M-8 O-7 P-2 Q-1 R-14
U-4
16
V-1
L-5
17
T-3
20 22 23
Y-4 Z-6
X-4
18 19
V-1 W-2
N-0
21
DATA RESULT
ACTIVITY DURATION
A (1-2) 1
B (2-3) 4
C (2-4) 3
D (3-4) 0
E (4-5) 8
F (5-8) 1
G (5-6) 12
H (6-7) 2
I (7-9) 1
J (8-9) 2
K (9-10) 2
L (10-21) 5
M (10-11) 8
N (21-23) 0
O (11-12) 7
P (12-13) 2
Q (13-14) 1
R (14-15) 14
S (15-17) 10
T (17-20) 3
U (15-16) 4
V (16-18) 1
W (18-19) 2
X (19-20) 4
Y (20-22) 4
Z (22-23) 6
DATA RESULT
JOB DESCRIPTION
A. Clearing, Layouting, and Staking
B. Excavation of Foundation, and Septic tank
C. Start of Steel Fabrications
D. Dummy
E. Steel Installation for Column footings and Columns
F. Concreting of Column footings
G. Steel Installation for Wall-Footings and Foundation wall
H. Installation of forms for Wall-Footings/tie beam
I. Concreting of Wall-Footings
J. Installation of Scaffoldings and Forms for Columns
K. Concreting of Columns and Tie beams
L. Steel Installation,Laying of CHB, and Pouring of Concrete for Septic Tank
M. Laying oF CHB for Walls and Backfilling
N. Dummy
O. Fabrication and Installation of Rebars for Roof beams
P. Installation of Forms for Roof Beams
Q. Concreting of Roof Beams
R. Fabrication and Installation of Trusses, Purlins, G.I. Sheets and other Roofing works
S. Plastering of walls,Columns and Beams
T. Installation of Doors, Windows and Stainless Steel Railings for Porch
U. Fabrication and Installation of Rebars for Floors
V. Pouring of Concrete for Floors Slab
W. Tile Works
X. Installation of Ceilings
Y. Installation of Electrical Wiring/ Fixtures and Plumbing FIxtures
Z. Paint Works and Finishes
PATH TOTAL DURATION
A-B-D-E-F-J-K-M-O-P-Q-R-S-T-Y-Z 73
A-B-D-E-F-J-K-M-O-P-Q-R-U-V-W-X-Y-Z 71
A-B-D-E-G-H-I-K-M-O-P-Q-R-S-T-Y-Z 85
A-B-D-E-G-H-I-K-M-O-P-Q-R-U-V-W-X-Y-Z 83
A-B-D-E-G-H-I-K-L-N 35
A-B-D-E-F-J-K-L-N 23
A-C-E-F-J-K-M-O-P-Q-R-S-T-Y-Z 72
A-C-E-F-J-K-M-O-P-Q-R-U-V-W-X-Y-Z 70
A-C-E-F-J-K-L-N 22
A-C-E-G-H-I-K-M-O-P-Q-R-S-T-Y-Z 84
A-C-E-G-H-I-K-M-O-P-Q-R-U-V-W-X-Y-Z 82
A-C-E-G-H-I-K-L-N 34
DATA SHEET
ACTIVITY DURATION ES EF LS LF TF FF Critical Activity
A (1-2) 1 0 1 0 1 0 0 *
B (2-3) 4 1 5 1 5 0 0 *
C (2-4) 3 1 4 2 5 1 1
D (3-4) 0 5 5 5 5 0 0 *
E (4-5) 8 5 13 5 13 0 0 *
F (5-8) 1 13 14 25 26 12 0
G (5-6) 12 13 25 13 25 0 0 *
H (6-7) 2 25 27 25 27 0 0 *
I (7-9) 1 27 28 27 28 0 0 *
J (8-9) 2 14 16 26 28 12 12
K (9-10) 2 28 30 28 30 0 0 *
L (10-21) 5 30 35 80 85 50 50
M (10-11) 8 30 38 30 38 0 0 *
N (21-23) 0 35 35 85 85 50 50
O (11-12) 7 38 45 38 45 0 0 *
P (12-13) 2 45 47 45 47 0 0 *
Q (13-14) 1 47 48 47 48 0 0 *
R (14-15) 14 48 62 48 62 0 0 *
S (15-17) 10 62 72 62 72 0 0 *
T (17-20) 3 72 75 72 75 0 0 *
U (15-16) 4 62 66 64 68 2 0
V (16-18) 1 66 67 68 69 2 0
W (18-19) 2 67 69 69 71 2 0
X (19-20) 4 69 73 71 75 2 2
Y (20-22) 4 75 79 75 79 0 0 *
Z (22-23) 6 79 85 79 85 0 0 *
ACTIVITY Bid Amt.(Ᵽ) Re. Wt. % 0 1 2 3 4 5 6 7
A (1-2) 6861.25 0.005
B (2-3) 13400.00 0.010
D (3-4) 0.000 0.000
E (4-5) 86163.25 0.067
G(5-6) 109491.5 0.085
H (6-7) 23007.5 0.018
I (7-9) 8554.00 0.007
K (9-10) 36344 0.028
M (10-11) 119438 0.093
O (11-12) 57157 0.044
P (12-13) 43355 0.034
Q (13-14) 15245 0.012
R (14-15) 92710 0.072
S (15-17) 62526 0.049
T (17-20) 111400 0.087
Y (20-22) 98880 0.077
Z (22-23) 83320 0.065
C (2-4) 11700.00 0.009
F (5-8) 26483 0.021
J (8-9) 101646.25 0.079
L (10-21) 22292.32 0.017
N (21-23) 0.000 0.000
U (15-16) 35921.5 0.028
V (16-18) 39933 0.031
W (18-19) 48135 0.037
X (19-20) 31625 0.025
TOTAL 1285588.57 1.000
Projected Accomp.
Daily 0.005 0.003 0.006 0.006 0.006 0.008 0.008 0.008
Commulative 0.005 0.008 0.014 0.019 0.025 0.033 0.042 0.050
Daily
0.008 0.008 0.008 0.008 0.008 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007
0.058 0.067 0.075 0.084 0.092 0.099 0.106 0.113 0.120 0.127 0.134 0.142 0.149 0.156 0.163 0.170 0.177
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
4150 4150 4150 4150 4150 4150 4150 4150 4150 4150 4150 4150 4150 4150 4150 4150 4150
25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41
0.030 0.048 0.046 0.014 0.014 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.006 0.006 0.006 0.006
0.207 0.255 0.301 0.315 0.330 0.341 0.353 0.364 0.376 0.388 0.399 0.411 0.422 0.429 0.435 0.441 0.448
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 1 2 2 2 2 2 2 2 2 2 2
4 8 4
2 2 2 2
11 14 10 3 3 4 4 4 4 4 4 4 4 8 8 8 8
5950 7400 5350 2550 2550 2800 2800 2800 2800 2800 2800 2800 2800 3800 3800 3800 3800
42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
0.006 0.006 0.006 0.017 0.017 0.012 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005
0.454 0.461 0.467 0.484 0.501 0.512 0.518 0.523 0.528 0.533 0.538 0.543 0.549 0.554 0.559 0.564
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2
2 2 4 4 4 4 4 4 4 4 4 4
2 2 2
8 8 8 7 7 2 6 6 6 6 6 6 6 6 6 6
3800 3800 3800 3550 3550 2300 4000 4000 4000 4000 4000 4000 4000 4000 4000 4000
58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74
0.005 0.005 0.005 0.005 0.005 0.005 0.012 0.012 0.012 0.012 0.036 0.024 0.024 0.011 0.035 0.035 0.035
0.569 0.574 0.579 0.585 0.589 0.594 0.606 0.618 0.630 0.642 0.678 0.701 0.725 0.736 0.771 0.806 0.841
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 3 3 3 3 3 5 3 3 3
4 4 4 4 1 1 1
3 3 3 3 2 3 3 3
6 6 6 6 6 6 14 14 14 14 14 8 8 9 7 7 7
4000 4000 4000 4000 3650 3650 6700 6700 6700 6700 6350 4150 4150 5100 4250 4250 4250
75 76 77 78 79 80 81 82 83 84 85
100
95
90
85
80
75
70
65
60
55
50
45
40
35
30
25
20
15
10
5
0
0.019 0.019 0.019 0.019 0.011 0.014 0.014 0.014 0.014 0.014
0.860 0.879 0.899 0.918 0.929 0.943 0.957 0.971 0.986 1.000
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1
1 1 1 1
4 4 4 4 4 4
6 6 6 6 4 4 4 4 4
3400 3400 3400 3400 2500 3500 3500 3500 3500 3500
ACTIVITY Bid Amt.(Ᵽ) Re. Wt. % 0 1 2 3 4 5 6 7
A (1-2) 6861.25 0.005
B (2-3) 13400.00 0.010
D (3-4) 0.000 0.000
E (4-5) 86163.25 0.067
G(5-6) 109491.5 0.085
H (6-7) 23007.5 0.018
I (7-9) 8554.00 0.007
K (9-10) 36344 0.028
M (10-11) 119438 0.093
O (11-12) 57157 0.044
P (12-13) 43355 0.034
Q (13-14) 15245 0.012
R (14-15) 92710 0.072
S (15-17) 62526 0.049
T (17-20) 111400 0.087
Y (20-22) 98880 0.077
Z (22-23) 83320 0.065
C (2-4) 11700.00 0.009
F (5-8) 26483 0.021
J (8-9) 101646.25 0.079
L (10-21) 22292.32 0.017
N (21-23) 0.000 0.000
U (15-16) 35921.5 0.028
V (16-18) 39933 0.031
W (18-19) 48135 0.037
X (19-20) 31625 0.025
TOTAL 1285588.57 1.000
Projected Accomp.
Daily 0.005 0.006 0.006 0.006 0.003 0.008 0.008 0.008
Commulative 0.005 0.011 0.017 0.022 0.025 0.033 0.042 0.050
Daily
0.008 0.008 0.008 0.008 0.008 0.028 0.047 0.047 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.009
0.058 0.067 0.075 0.084 0.092 0.120 0.166 0.213 0.220 0.227 0.234 0.241 0.248 0.255 0.263 0.270 0.277 0.286
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2
4 4 4
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
8 8 8 8 8 13 16 16 8 8 8 8 8 8 8 8 8 6
4150 4150 4150 4150 4150 6100 7550 7550 4150 4150 4150 4150 4150 4150 4150 4150 4150 4000
26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42
0.009 0.007 0.014 0.014 0.015 0.015 0.015 0.015 0.015 0.012 0.012 0.012 0.006 0.006 0.006 0.006 0.006
0.295 0.301 0.315 0.330 0.345 0.360 0.375 0.390 0.405 0.417 0.428 0.440 0.446 0.452 0.459 0.465 0.472
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 2 2 2 2 2 2 2 2 2 2
4
2 2 2 2 2
6 2 3 3 8 8 8 8 8 4 4 4 8 8 8 8 8
4000 1950 2550 2550 3800 3800 3800 3800 3800 2800 2800 2800 3800 3800 3800 3800 3800
43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58
0.006 0.006 0.017 0.017 0.012 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005
0.478 0.484 0.501 0.518 0.530 0.535 0.540 0.545 0.550 0.556 0.561 0.566 0.571 0.576 0.581 0.586
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2
2 2 4 4 4 4 4 4 4 4 4 4 4
2 2
8 8 7 7 2 6 6 6 6 6 6 6 6 6 6 6
3800 3800 3550 3550 2300 4000 4000 4000 4000 4000 4000 4000 4000 4000 4000 4000
59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75
0.005 0.005 0.005 0.012 0.012 0.012 0.012 0.036 0.024 0.024 0.011 0.011 0.011 0.035 0.029 0.029 0.019
0.592 0.597 0.602 0.614 0.626 0.637 0.649 0.685 0.709 0.732 0.743 0.754 0.765 0.801 0.829 0.858 0.878
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1
1
3 3 3 3 5 3 3 3 3 3
4 4 4 2 2 2 3 1 1
3 3 3 3 1 1 1
6 6 6 14 14 14 14 14 8 8 9 9 9 7 4 4 6
4000 4000 4000 6700 6700 6700 6700 6350 4150 4150 5100 5100 5100 4250 2800 2800 3400
76 77 78 79 80 81 82 83 84 85
100
95
90
85
80
75
70
65
60
55
50
45
40
35
30
25
20
15
10
5
0
1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1
1 1 1
1 1 1
4 4 4 4 4 4
6 6 6
3400 3400 3400 2500 2500 2500 2500 2500 2500
PROGRAM OF WORKS
b. Labor Costs
Engineer 1 5 600.00 3000
Foreman 1 5 500.00 2500
Laborers 4 5 250.00 5000
10500
22292.32
M. Laying oF CHB for Walls and Backfilling
a. Material Costs
4" CHB 2291 pcs. 16.00 36656
Sand 16 cu.m 1232.00 19712
cement 166 bags 245.00 40670
97038
b. Labor Costs
Engineer 1 8 600.00 4800
Foreman 1 8 500.00 4000
Mason 2 8 350.00 5600
Laborers 4 8 250.00 8000
22400
119438
N. Dummy
21425
b. Labor Costs
Engineer 1 4 600.00 2400
Foreman 1 4 500.00 2000
carpenter 2 4 350.00 2800
Laborers 3 4 250.00 3000
10200
31625
Y. Installation of Electrical wirings/ Fixtures and Plumbing FIxtures
a. Material Costs
*electrical
Duplex convenient outlet 9 sets 80.00 720
one-way switch 5 sets 100.00 500
tw0-way switch 2 sets 130.00 260
Lighting Fixture (cir. FL) 5 pcs 400.00 2000
lighting Fixture (CFL) 9 pcs. 200.00 1800
Other fixtures (estimated) 20000
*plumbing
Estimated lumpsum 60000
85280
b. Labor Costs
Engineer 1 4 600.00 2400
Foreman 1 4 500.00 2000
electrician 1 4 400.00 1600
Plumber 1 4 400.00 1600
Laborers 6 4 250.00 6000
13600
98880
Z. Paint Works and Finishes
a. Materials
Paint roller 2 pcs. 90.00 180
Paint brush 3" 4 pcs. 65.00 260
Paint brush 2" 4 pcs. 45.00 180
Concrete Neutralizer 10 gal 400.00 4000
Flat Latex Paint BP 6 pail 2800.00 16800
Gloss Latex Paint BP 6 pail 2800.00 16800
Masonry Putty 6 pail 2800.00 16800
Sand Paper #100 5 pcs. 20.00 100.00
Flat Enamel Paint 6 pail 2600.00 15600
70720
b.Labor Costs
Engineer 1 6 600 3600
Foreman 1 6 500 3000
Painter 4 6 250 6000
12600
83320
TOTAL 1285588.57