Unit 1: Requirements Planning

Figure 17: Time-Phased Planning with Delivery Cycle

For articles that have a fixed delivery date as well as a fixed order date, you can use a planning
calendar to define a delivery cycle as well as a planning cycle.
The planned delivery time is interpreted as the minimum delivery time. In other words, at least
that many days pass between planning, ordering and inbound delivery. If, in the example, you
order the goods on Tuesdays, they can be delivered on Friday at the earliest.