Professional Documents
Culture Documents
Abstract - IEEE Guide for the Specification of Scope and 2) Capacitor banks are fed from and operate at 13.2 kV and
Deliverable Requirements for an Arc-Flash Hazard Calculation 2.4 kV
Study in Accordance with IEEE Std 1584, recommends that
alternate scenarios should be modeled considering minimum B. Switchgears
and maximum values of utility fault current, if actual utility fault Numerous 13.2 kV and 2.4 kV double-ended switchgears.
current cannot be obtained from the utility company. This paper
is a case history that proves the value of using minimum and C. Motor Control Centers
maximum utility provided fault contribution at an industrial Numerous 2.4 kV and 0.48 kV single and double-ended
facility served by several 13.2 kV incoming feeders. Equipment Motor Control Centers (MCC’s).
in the facility includes a wide range of electric motors; VFD’s
and double ended motor control centers. Multiple scenarios D. Electric Motors
were performed to account for the various complex modes of Electric motors operating at 0.48 kV range from 75 hp to 200
operation, and to present the worst-case arc-flash results. hp. Medium voltage motors operating at 2.4 kV range from 250
hp to 2500 hp. A standalone 3000 hp motor operate at 13.2 kV.
Index Terms — Arc Flash, Utility Fault Contribution, Motor
Control Center E. Capacitor Banks
2.4 MVAR and 4 MVAR are connected to the system both at
I. INTRODUCTION 13.2 kV and 2.4 kV, respectively.
2.55 Arcing Fault (kA) Arcing Time (sec) Incident Energy (call/cm2)
1.42 1.47 C. Bus 3 is a switchgear bus that feeds a downstream MCC
0.55 with five standalone motors totaling
t 2200 hp. Scenario
#2 generates the highest incidenti energy with the
Arcing Fault (kA) Arcing Time (sec) Incident En
nergy (call/cm2) minimum utility fault contributio
on and all motors running.
2
D. Bus 4 is a MCC with five standalon ne motors totaling uced the incident energy in
or system reliability have redu
1550 hp. Scenario #1 generates the e highest incident all three scenarios.
energy with the maximum utility fault contribution and all
motors running. A slight decrease in th he relay Time Dial
setting that did not impact selectivity orr system reliability
have reduced the incident energy in a all three scenarios Bus 6 - 2.4
4 kV
by more than 35%.
Sce.#1 Sce.#2
2 Sce.#3
19.27
Bus 4 - 2.4 kV
Sce.#1 Sce.#2 Sce.#3 14.68 14.12
11.50
14.91
9.40 8.40
11.34
11.38
9.70 9.30 9.10
0.34 0.35 0.34
Bus 7 - 2.4
4 kV
E. Bus 5 is a MCC bus with five standalone motors totaling
2400 hp. Scenario #1 generates the e highest incident Sce.#1 Sce.#2
2 Sce.#3
energy with the maximum utility fault contribution and all
motors running. Reducing the setting o on the feeder relay
to the MCC was not a good option a as it compromises 23.78
selectivity with the largest motor fuse.
21.95
17.12
Bus 5 - 2.4 kV
Sce.#1 Sce.#2 Sce.#3
14.90
0.01 0.01 0.01 0.40 0.30 0.30
11.34 11.34 11.100 10.70
10.20 Arcing Fault (kA) Arcing Time (sec)) Incident Energy (call/cm2)
3
Bus 8 - 2.4 kV Bus 10 - 0.48 kV (EExisting )
Sce.#1 Sce.#2 Sce.#3 Sce.#1 Sce.#2
2 Sce.#3
44.20 44.80
15.64 14.91
34.10
11.12
0.9
600 600
500 500
2.0
relatively low due to the fast clearing time by upstream
400 400
300 300
R-SUB29-P
50
600/5
fuses.
200 51 200
100 100
2.0
90 90
80
70 T-SUB29 80
70
60 60
500 kVA
2.0
50 50
40
5.2% T-SUB29
500 kVA
40
30 30
9.8
20 20
9.8
10
9
R-SUB29-P 10
9
8
7 51/50 8
7
9.8
Sce.#1 Sce.#2 Sce.#3
6 6
Very Inverse
TIMEINSECONDS
TIMEINSECONDS
5 5
BL-SUB29-M
4
CT Ratio = 600/5 4
.7
13
3 BUS 10 3
Tap = 5 (600A)
2
Time Dial = 3 2
32.53 .4
.3
Frame = 800A (800AT)
.4
.3
Plug = 800
.2
Inst = High (6000A) .2
.1 .1
.09 .09
.08 .08
21.91 .07
.06
.05
.04
.07
.06
.05
.04
.03 .03
.02 .02
.01 .01
.5 .6 .8 1 2 3 4 5 6 7 8 9 10 2 3 4 5 6 7 8 9 100
0 2 3 4 5 6 7 8 9 1000 2 3 4 5 6 7 8 9 10000
CURRENT IN AMPERES X 10
00 AT 480 VOLTS
4
CURRENT IN AMPERES X 100 AT 480 VOLTS
.5 .6 .8 1 2 3 4 5 6 7 8 9 10 2 3 4 5 6 7 8 9 100 2 3 4 5 6 7 8 9 1000 2 3 4 5 6 7 8 9 10000
Case” incident energy for any on ne bus could be obtained
1000 1000
900
800
700
T-SUB29
FLA
R-SUB29-P
0016-B-260
900
800
700
when the system is operating wiith maximum or minimum
0.9
600
500
600
500 utility fault contribution or with moto
ors over 50 hp fully running
2.0
400 400
300
R-SUB29-P
300 or turned off. Bus arcing faults alo ong with protective device
200 6
600/5
50
51 200 arcing time both determine the outcome of the incident
energy. Hence, having low arrcing currents does not
100 100
guarantee low incident energy if clearing
c times become too
2.0
90 90
80 80
70
T-SUB29 70
60 60
slow. Arc flash mitigation using setting changes without
2.0
50
500 kVA 50
40 T-SUB29 40
30
5.2% 500 kVA
2.4 - 0.48 kV
30 impacting selectivity or system reliability and utilizing digital-
5.2% based trip units is readily achie evable when the different
9.8
20 20
9.8
10 R-SUB29-P 10
9
8
7 51/50
9
8
7
adjustability available in modern de evices is used.
9.8
6 6
Very Inverse
TIME IN SECONDS
TIME IN SECONDS
5 5
BL-SUB29-M
4
CT Ratio = 600/5 4
.7
13
3 BUS 10 3
Tap = 5 (600A)
2
Time Dial = 3 2
1
.9
Bus 10 Proposed
P Solution 1
.9
.8 .8
.7 .7
.6 .6
.5
BL-SUB29-M .5
VI. RENCES
REFER
.4 .4
Sensor = 800
.3
Plug = 800 BL-SUB29-M .3
.2
Cur Set = 1 (800A) 100% .2
LT Band = C-5 Arcing Current [1] IEEE Guide for the Spec cification of Scope and
.1
STPU = 5.5 (4400A) 6221A .1
.09
.08
.09
.08 Deliverable Requirements forfo an Arc-Flash Hazard
.07
ST Delay = 3 .07
.06
.05
ST Delay I²t = Out
.06
.05 Calculation Study in Accordan
nce with IEEE Std 1584™.
.04 .04
.02
12000A .02
Inst = 14 (11200A)
VII VITA
.01 .01
.5 .6 .8 1 2 3 4 5 6 7 8 9 10 2 3 4 5 6 7 8 9 100 2 3 4 5 6 7 8 9 1000 2 3 4 5 6 7 8 9 10000