5 Elevation Grooves
A Ground Floor Rft 241.50 17.00 4,106.00 13,550.00 In original budget,
B First Floor Rft 241.50 18.70 4,517.00 structural glazing was
C Second Floor Rft 241.50 20.40 4,927.00 considered.
6 Terrace water proofing Sqft 1763.00 25.00 44,075.00 44,075.00 No work on terrace floor
was considered.
7 Parapet wall Sqft 517.50 22.00 11,385.00 11,385.00 No work on terrace floor
was considered.
11 Curing Charges Sqft 7.00 8900.00 62,300.00 62,300.00 We had deployed Mr.
Gurusiddappa.
13 Add 5% consultancy on %age 77,90,649.00 5.00% 3,89,533.00 3,89,533.00 1) Total Estimated Cost=
Material Rs. 1,00,04,000.00/-
2) Labour Cost=
Rs. 22,13,351.00/-
3) Hence Material cost =
Rs. 77,90,649.00/-
4) 5% of above material
cost towards consultancy
fees = Rs. 3,89,533/-
Name of Work :Proposed Residencial Building Estimation for Shri.Raghavendra A Betageri at Old Hubli (Ward no. 5, CTS no.
3382 and 3381 B)