On 26th august, Mr. Madhav informed us that, house opening ceremony date is fixed on 14 th
November.
On 16th September there was labour problem and we had to change mason’s gang.
From 17th September till 22nd October i.e. in 5 weeks we deployed multiple/additional
mason’s gang without worrying about our economical consequences and just to keep our
word. We completed all the balance masonry work (masonry, plastering and related works).
During this period, we had paid Rs. 1,86,750.00 to mason’s teams. This works out to be
Rs.33.00/Sq.ft. Our budget for mason’s work was Rs. 95/Sq.ft. and now we have spent Rs.
157.00/Sq.ft. (This includes Rs.124/- per Sq.ft. paid to Moulali + Rs.33/- per Sq.ft. paid during
said 5 weeks.). We have never complained.
In spite of numerous problems (between 16 th September to 22nd October) we took the work
in hand as challenge at personal level without bothering about our monetary losses and
completed the balance work.
We don’t expect any appreciation but wish to convey that we would have easily given up the
idea of completion of work as the owner had fixed the date for house opening ceremony
and could have completed the work as per our own schedule to make it financially viable for
us.
Various extra works were executed at site on your insistence have not been quantified and
no claim of additional bill has been settled so far.
We have worked in good faith in light of our harmonious relations in the past. We have
never complained nor narrated losses incurred by us. We specifically wish to put on records
that the responsibility of arrangement of curing was of owner(s). However, we noticed at
initial period that the owner was not particular about making such arrangement. As
Engineers, we know the importance of curing, so we voluntarily arranged for curing till
completion of RCC frame, masonry work for all three floors and inside plaster work of
ground and first floor. It is to specifically inform that curing arrangement for external
plastering were very poor and damages surfacing in future due to improper curing will be
attributable to owner only.
As regards to certain errors in plumbing work, we accept that there were human errors. We
have corrected errors in consultation with you. It is usual experience that certain errors
come to light when we start to use the building and it is generally opined that such errors
can be repaired.
We can resort to arbitration by either some 2+1 arbitration team or a person who is well
wisher to both the parties.
Cost of arbitration has to be borne by both the parties equally. So also, both the parties have
to undertake to abide by arbitrator’s decision.
Before the arbitration to be invoked, the arbitrator has considered following points;
1. We are qualified Engineers in civil works and have never had any bad intention during
the entire execution period.
2. An engineer was exclusively deployed on site to supervise the work.
3. All alterations/changes were made as directed by owners (Betageri family). Betageri
family is particularly complaining about the plumbing work, which Is partially true.
4. Statement was made by the owners in front of Mr. Irrayya (Electrician, we had
employed) that “there was lack of supervision on our part”, which is not acceptable and
hurt us deeply.
Settlement options
Option 3: Forget supervision charges and sum up the entire expenditure incurred by the us
based on the payment vouchers. Positive or negative cash impact to be borne by the owner.
Items of work Budgeted Extra Spent amount Balance to be -ve/+ve
amount expenditure paid
Masonry 5,27,440.00 3,45,640.00 8,73,080.00 3,45,640.00 -3,45,640.00 Due to increase
quantity of
padadi,
staircase
portion
masonry, etc.
Electrification 60,000.00 20,000.00 62,000.00 20,000.00 -20,000.00 Due to increase
in number of
electric points
Cantering & 4,99,680.00 23,820.00 5,23,500.00 23,820.00 -23,820.00 Sump tank,
shuttering double staging,
etc
Painting 66,624.00 40,876.00 1,07,500.00 40,876.00 -40,876.00 Wall care, POP
finishing etc.
Plumbing 54,000.00 - 47,808.00 - 6,192.00
Watchman/Curin 0.00 62,300.00 62,300.00 0.00 -62,300.00 Owner had not
g arranged for
proper curing
hence for the
well-being of
everybody we
arranged for
curing up to
masonry
complete,
plastering
partially
complete
Supervision 3,50,000.00 - 2,02,500.00 1,22,500.00 -1,22,500.00 Paid to staff
charges
Other works - - 62,000.00 62,000.00 -62,000.00 Misc. other
extra works
Flooring 66,624.00 40,376.00 1,07,000.00 40,376.00 -40,376.00 Increase in
number of
toilet units, sill
granite fixing,
kadapa
cubboards
Total = 20,47,688.00 6,55,212.00 -7,11,320.00