Professional Documents
Culture Documents
Energy
journal homepage: www.elsevier.com/locate/energy
a r t i c l e i n f o a b s t r a c t
Article history: Cement industry uses very energy-intensive operations resulting in a suboptimal sustainable perfor-
Received 23 December 2017 mance. The objective of this research is to provide insight into the value of exergy analysis in sustain-
Received in revised form ability assessment of cement industry. For that purpose, a detailed exergy evaluation of a complete
18 April 2018
cement plant located in Morocco was performed using both conventional and advanced exergetic
Accepted 20 April 2018
Available online 21 April 2018
analysis. The major internal exergy losses were identified during the calcination process and the two raw
mill departments, which amounts to about 78.66%, 70.86%, and 72.12% respectively. Those irreversibil-
ities are split into avoidable/unavoidable exergy destruction in the advanced exergy analysis. Findings
Keywords:
Cement industry
show that 15%, 29.21% and 31.54% of the total exergy destruction in the calciner and the raw mills 1 and 2
Exergy analysis respectively are avoidable. However, there is a need for optimization of comminution and combustion
Exergy efficiency operating parameters in the cement production process currently in use.
Irreversibility © 2018 Elsevier Ltd. All rights reserved.
https://doi.org/10.1016/j.energy.2018.04.121
0360-5442/© 2018 Elsevier Ltd. All rights reserved.
S. Fellaou, T. Bounahmidi / Energy 154 (2018) 190e200 191
industry. They evaluated the specific energy consumption for farine heat pump dryer for medicinal and aromatic plants, evaluating its
production to be 24.75 kWh/ton farine. By using an external hot gas performance in parts and discussed possible structural improve-
supply, the energy consumption of the unit has been reduced by ments of the whole system and the remaining system components.
6.7% corresponding to a saving of 1.66 kWh/ton of farine produc- Results found in the open literature are not typically combined
tion. The trass mill in a cement production plant has been inves- to give an overall representation of the cement industrial process
tigated in relation to exergy analysis. The objective of So€güt et al. from an exergy perspective. Almost no comminution exergy model
[18] was to perform an energetic and exergetic assessment of a trass has been proposed nor applied to a cement process in which
mill process in a cement plant, the overall exergy efficiencies are comminution is carried out to produce material of controlled par-
found to be slightly less than the corresponding energy efficiencies ticle size [31]. The present work contributes to the current litera-
74% and 10.68% for energy and exergy efficiency, respectively. So €g üt ture from several perspectives. A detailed exergy evaluation of a
et al. [19] investigated the energy and exergy analyses of a coal- complete cement plant with all main units is performed using both
preparation unit in a cement plant. The mean values of energy conventional and advanced exergetic analysis. In one hand, with
and exergy efficiencies of the unit are found to be 74.03% and conventional exergy-based analysis, thermodynamic inefficiencies
21.36%, respectively while the average potential improvement of were assessed; the critical points were localized and information
the unit is calculated as 78.24%. In Madlool et al.’s [20] work a about improvements of the studied cement plant is revealed.
review of the exergy analysis was presented to demonstrate that Furthermore, exergetic ternary diagram as a new graphical repre-
the implementation of exergy analysis on the cement production sentation of the exergy balances allows the immediate visualization
line is a very efficient way to improve the performance of the of the results of exergy analysis and the comparison between the
system. Although Savaş et al. [21] presented comparative energy exergetic indicators (exergetic efficiency, irreversibility and exergy
and exergy analyses for specific dry clinker production by three losses) of each operation unit making up the whole system. In the
different methods, they concluded that the lowest irreversibility other hand, the advanced exergy analysis reveals the real potential
rate occurs in the serial flow pre-calcination cement production for improvement of the unit with the highest exergy destruction
method. The work of Bühler et al. [22] consists of analyzing the ratio by calculating the amount of its avoidable part. Based on the
energy and exergy efficiency, as well as the destroyed and lost findings, insights for improvement can be extracted.
exergy of 22 industrial sectors in Denmark for the years 2006 and Before detailing the advanced exergy analysis methodology and
2012. They concluded that industries with high temperature pro- explaining the graphical representation used to illustrate efficiency,
cesses such as cement production achieve the highest efficiencies. irreversibilities and external losses in section 3, a brief description
Koroneos et al. [23] examined the efforts to improve energy effi- of the cement-making process and data used is given. Section 4
ciency in cement production in Greece using exergy analysis. The discusses the main findings and provides guidance on the key
analysis includes calculation of energy and exergy contribution at considerations for the assessment of the system performance.
each stage of the cement manufacturing procedure. They found Finally, section 5 concludes our analysis.
that about 50% of the exergy is being lost while substantial amount
of waste heat is being recovered. In a study led by Ahamed et al. 2. Process description of the plant production line
[24] and Atmaca and Yumrutaş [25] the first and second law ef-
ficiencies of a clinker cooler were calculated. The study of [24] Cement production is a complex process which includes oper-
showed that about 38% and 30% of energy cost can be saved by ations such as preparation of raw materials, clinker formation and
changing mass flow rate of clinker and mass flow rate of cooling air, cooling to achieve a crystallographic structure that meets the
respectively. Atmaca et al. [1] and Atmaca and Yumrutaş [26] required cement specifications, and finish milling. For raw material
revealed interesting results in exergy analysis of the kiln system. In preparation and cement grinding, the main energy carrier is elec-
Ref. [1] they reduced the rate of heat loss from 22.7 MW to 17.3 MW tricity whilst the thermal energy is consumed in the calcination
by the application of insulation to the pyroprocessing unit of Gaz- process of clinker manufacturing. In the present study, a Moroccan
iantep cement plant in Turkey. They calculated that 1056.7 kW of cement plant with 1.2 million tons as an annual production ca-
electricity can be generated by using the waste heat and reduced pacity is considered as a case study for the exergy analysis assess-
the annual emission rates by 8.2%. ment. The plant required thermal energy inputs of 2.17 GJ/ton
Inefficiencies in an energy system can be quantitatively deter- clinker and 0.36 GJ electricity/ton cement. The main flows entering
mined through conventional exergy analysis; while sources of the or leaving the cement system boundary are summarized in Fig. 1.
irreversibilities and real improvement potential can be deducted Furthermore, each department is defined and delimited by a
using a relatively new method named as advanced exergy analysis boundary that cuts across all the streams and encloses each specific
[27]. This later is applied to determine real potential for thermo- process, but not their sub-system.
dynamic improvements of energy systems by splitting exergy The dry production process is used in the typical plant and it
destruction into unavoidable and avoidable portions. According to consists of grinding the mixture of raw materials (streams 8 and 24)
the current knowledge of the authors, until now no cement plant which are manufactured through a closely controlled chemical
has been analyzed and evaluated using this method. However, its combination of calcium, silicon, aluminum, iron and other in-
applications in other sectors are relatively low in numbers: Tsat- gredients to make a fine powder. The prepared raw meal (stream
saronis and Moung-Ho [28] discussed how to estimate the 37) is thus preheated in a four stage cyclone-type suspension pre-
avoidable-unavoidable exergy destruction. They evaluated parts of heater using the waste heat of the kiln (stream 47). The preheated
exergy destructions of compressors, turbines, heat exchangers and raw mix powder and gases are separated in the cyclone by the
combustion chambers, which were used to determine the centrifugal motion induced by the geometry of the cyclone, with
improvement potentials of a thermal system. Morosuk et al. [29] the exhaust gases passing out of the top of the cyclone and the
presented the theory of the conventional and advanced exergetic preheated raw mix passing out of the bottom of the cyclone to the
analyses. They concluded that the information resulted from the next lower stage of the preheater. The plant owns an additional
advanced exergy based method was very useful in developing ap- calcining vessel, in which the raw-mix undergoes calcination to a
proaches for improving the energy conversion systems. Gungor level of 90e95% [32]. This way, the preheated raw-mix (stream 44)
et al. [30] investigated the advanced exergy analysis to a gas engine enters the calciner together with the fuel and the hot tertiary air
(stream 51). Calcining takes place at 800e900 C and breaks the
192 S. Fellaou, T. Bounahmidi / Energy 154 (2018) 190e200
12 28
19 35 Solid
14 15
D2 D3
26’ Gas
F1 F2 30
19 31
10’ 17 33 Air
14’ 18 30’
34 Pet coke
9 M3 29
13
H2O/CO2 leakage
36 M2
M1 25
11 16 27
32
24
8 26
22 Mill
Mill 7
2
3
1 Air/Gas flow rate measurement
23 60
Dust
4 F 61 56’
10 D1 Flow rate showed on the control panel in the
1 20 60’
39 F3 57 control room
38 58
C1A C1B 62 59
39’ 56
42’
37 40
Mill 54
C2 55
48 D4 3 M7 74
41
37’ 40’
38’ 44’ 53
C3 41’ 63 64 F4
49 50
42 43
Classifier 52
C4 44 Calciner
51 71 72
Cement
Storage silo 43’ 46
88 90
89
70
Additions
Trémies
65
Gypsum
Cyclone
Clinker
47 73 82
88’ F5
Baghouse Kiln 66
Filter 45 67 Cooler 75 76 77
83 86
M Mixer M8
68
45’ 87 M9
69
D 78
81
M10
Mill 85
80 4 84
78’
79
calcium carbonate down into calcium oxide and carbon dioxide with the aid of the exergy balance is calculated. The exergetic ef-
throughout the process. Clinkering completes the calcination stage ficiency and exergetic improvement potential for each system
and fuses the calcined raw mixture into hard nodules resembling component and for the overall system were investigated then the
small grey pebbles. Molten clinker (stream 73) is quenched by cold exergetic tenary diagram is plotted to visualize clearly wasted,
air (stream 69) and finally grinded with gypsum and other additives useful and destructive exergy out of unit. The most favorable
in a ball mill to make the grey powder known as cement (stream operating conditions listed in Table 5 (unavoidable conditions) are
89). assumed and the avoidable/unavoidable exergy destruction for the
components with the highest exergy destruction ratios is calcu-
3. Exergy and advanced exergy analysis lated. The energy and exergy calculations are done using MS Excel
Professional Plus. The software makes it possible to analyze the
3.1. Exergy concept whole system by considering their interactions with each other.
X X
Calculation of exergy destruction E_ in ¼ E_ out (3)
exergy indicators: Exergetic ternary diagram e The system is assumed to be in steady state.
e The temperature and pressure of dead (environmental) state are
taken as the actual ambient conditions.
e The gases inside the systems are assumed to be ideal gases.
Selection of the components with highest ID e Electrical energy produces the shaft work in the system.
Table 5
Assumptions and summary results of advanced exergy analysis.
Table 1
Exergy balance equations in each department of the studied plant.
P0
_ _ CaCO3 Exch1 þ m_ MgCO3 Exch2
Note that the entropy change of an incompressible substance is Ex R1 ¼ m (13)
given by:
_ _ CaCO3 Exch1 þ m_ C3 S Exch3 þ m_ C2 S Exch4 þ m_ C3 A Exch5
Ex R2 ¼ m
T þ m_ C4 AF Exch6
s s0 ¼ cavg ln (8)
T0
(14)
Cpavg is the average specific heat between T0 and T.
It is noteworthy to mention that the exergy consumed in re-
The exergy of comminution is equal to [37]:
actions in preheater-calciner system corresponds to dissociation of
" # clay and MgCO3 plus 90% of CaCO3 calcination [41]. The amounts of
_ com ¼ DAv *g ¼ 6Fr 1 1 *g
Ex (9)
formed clinker phases in 1 kg of clinker are given as:
r df di r 0.593 kg C3S, 0.205 kg C2S, 0.107 kg C3A and 0.101 kg C4AF
Where DAv the increase in the surface area per unit volume after
comminution, Fr is the surface roughness factor, g the surface 3.3. Exergy efficiency
energy (specific) of material, r the density anddi ; df are the initial
and final geometric mean size of the particle. The exergy efficiency aims at measuring the degree of thermo-
The exergy of work can be calculated thanks to equation (10) dynamic perfection of the process under investigation. In the
[38] while exergy of heat streams is usually given by equation exergy literature there are many definitions of exergy efficiency, in
(11) where Q represents the amount of exchanged heat, T the this study, we used equation (15) below considering only the useful
temperature of the heat source and k the boundary of the exergy output from the process which represents the desired result
component. produced in system [36e43]:
P _ _ P
Exout Ex losses Useful Exergy from the process
_ W ¼W
Ex (10) ε¼ P _ ¼ P _
Exin Exin
(15)
X T
_ 1 0 _
Ex Q ¼ Q k (11)
T
The chemical exergy of the petroleum coke is written in the 3.4. Exergetic improvement potential
form [39]:
Besides exergy efficiency, an important parameter is applied to
_ x x investigate the performance of the cement plant in the conven-
Ex Petcoke ¼ D hPetcoke * 1:0437 þ 0:1896* H þ 0:0617* O
tional exergy analysis. Maximum improvement in the exergy effi-
xc xc
ciency for a process system is obviously achieved when the exergy
xN
þ 0:0428* þ 9710*xS (12) loss rate or irreversibility rate (Ex_in Ex_out Þ is minimized [44].
xc
Consequently, it is useful to employ the concept of an exergetic
WherexH ; xC ; xO ; xN ; xS are the mass fractions of the corre- “improvement potential” when analyzing different processes. This
sponding elements of the petroleum coke. improvement potential in the rate form, denoted IP_ , is given by
The chemical exergy of calcination and clinker formation in the Ref. [44]:
kiln are based on the chemical equations and the standard chemical
exergy values listed in Table 2. IP_ ¼ ð1 εÞ$ðEx_in Ex_out Þ (16)
The chemical exergy of the calcination and the clinker formation
are given by Ref. [41]: Where ε is the exergy efficiency.
Table 2
Chemical exergy values of the calcination and clinker formation reactions.
12 28
19 35 Solid
14 15
D2 D3
26’ Gas
F1 F2 30
19 31
10’ 17 33 Air
14’ 18 30’
34 Pet coke
9 M3 29
13
H2O/CO2 leakage
36 M2
M1 25
11 16 27
32
24
8 26
22 Mill
Mill 7
2
3
1 Air/Gas flow rate measurement
23 60
Dust
4 F 61 56’
10 D1 Flow rate showed on the control panel in the
1 20 60’
39 F3 57 control room
38 58
C1A C1B 62 59
39’ 56
42’
37 40
Mill 54
C2 55
48 D4 3 M7 74
41
37’ 40’
38’ 44’ 53
C3 41’ 63 64 F4
49 50
42 43
Classifier 52
C4 44 Calciner
51 71 72
Cement
Storage silo 43’ 46
88 90
89
70
Additions
Trémies
65
Gypsum
Cyclone
Clinker
47 73 82
88’ F5
Baghouse Kiln 66
Filter 45 67 Cooler 75 76 77
83 86
M Mixer M8
68
45’ 87 M9
69
D 78
81
M10
Mill 85
80 4 84
78’
79
calcium carbonate down into calcium oxide and carbon dioxide with the aid of the exergy balance is calculated. The exergetic ef-
throughout the process. Clinkering completes the calcination stage ficiency and exergetic improvement potential for each system
and fuses the calcined raw mixture into hard nodules resembling component and for the overall system were investigated then the
small grey pebbles. Molten clinker (stream 73) is quenched by cold exergetic tenary diagram is plotted to visualize clearly wasted,
air (stream 69) and finally grinded with gypsum and other additives useful and destructive exergy out of unit. The most favorable
in a ball mill to make the grey powder known as cement (stream operating conditions listed in Table 5 (unavoidable conditions) are
89). assumed and the avoidable/unavoidable exergy destruction for the
components with the highest exergy destruction ratios is calcu-
3. Exergy and advanced exergy analysis lated. The energy and exergy calculations are done using MS Excel
Professional Plus. The software makes it possible to analyze the
3.1. Exergy concept whole system by considering their interactions with each other.
X .X X .X .X plot the exergetic ternary diagram related to the process (Fig. 3). In
1¼ _
Ex _ þ
Ex _
Ex Ex _D
_ þ Ex _
Ex this graph, the position of each area corresponds to three factors (IL,
Usefull in lost in in
ID and IU) and size point is proportional to the sum of irrevers-
(19)
ibilities and external losses. As it can be seen in Table 3 and Fig. 3,
P _ P _ P _ P _ _ P _ the raw meal grinding departments are responsible for over 72% of
Where ExUsefull = Ex in ; Exlost = Ex in ; ExD = Exin repre-
the destroyed exergy in this unit, which are the irreversibilities
sent the indicators IU, UL and ID respectively. associated with heat transfer and friction [51,52]. In spite of the
In this study, in order to illustrate the results found the exergetic exergy efficiency calculated for the raw mills 1&2 is about 20.97%
ternary diagram was used as a graphical tool. This latter can be read and 19.69%. The exergy efficiency coefficient of the raw meal
from right to left. Unit operations that should be first analyzed are grinding systems remains lower than the literature [16,20,17].
located at the right. The purpose behind the consideration of this When it comes to exergy performance, particles size helps in
diagram is to make each unit operation to get closer to the 100% increasing the exergy efficiency, which appears clearly in the Pe-
efficiency side (left side) by minimizing exergy destruction and troleum coke and finish grinding departments (material feed size
losses [49]. In other words, as a result, this graphic presentation are 4 mm and 10 mm respectively) with an exergy efficiency of
specifies the efficient unit operation as the closest point to the IU 59.6% and 62.14% respectively. The exergy efficiency of the baking
vertex positioned inside the triangular diagram, while the closest line including the pre-heater/calciner and the rotary kiln is calcu-
point to the IL tip allows to search for the right waste stream so- lated from equation (15) to be 17.64% and 63.09% respectively. This
lutions and waste minimization techniques. Finally, the nearest corresponds to an exergy loss of 3.71% and 7.06% respectively in the
point to the ID tip shows up the presence of weak points in the line. Here most of the internal losses are due to combustion and
devices and the need of optimization of operating parameters that chemical reaction. Additionally, cooling the clinker to the lowest
will improve the performance of the unit operation significantly. possible temperature affords an exergy efficiency of about 48%
Additionally, the position of each area corresponds to the three which is low compared to 60% reported in literature [1].
coefficients (IU, ID and IL) and the point's size is proportional to the The baseecase process has a total irreversibility of 132.29 MW
amount of irreversibilities, physical and chemical losses in the unit and a total exergy loss of 15 MW. Those values should be put into
operations [50]. perspective, as the global exergy efficiency is 41.6% which is
considerably lower than the overall energy efficiency of the process
with a value of 55% [2]. The best way of decreasing the irrevers-
4. Results and discussion
ibilities for a process or system is to decrease the difference be-
tween the total exergy output and input values [44]. Determination
4.1. Discussion of research findings
of the exergetic improvement potential values to deduct the
possible improvements in each component along with the whole
It is generally more advantageous to conduct a comprehensive
system are calculated by the use of the Van Gool equation (16) and
exergy analysis covering entire cement production process. This is
are outlined in Table 4. The highest IP rate is calculated for the Pre-
due to the fact that all the unit operations are interrelated. The
heater/calciner as 24.33 MW, which has the lowest exergy effi-
present study extends the earlier research by applying both a
ciency. Thus, its exergy improvement potentials are important. The
conventional and an advanced exergy analysis to a typical Moroc-
rotary kiln, the cooler and the first raw mill department follow the
can cement plant. Exergy balances are thus made not only for the
pre-heater/calciner for the IP rates with 7.30 MW, 4.31 MW and
process as a whole, but for each department to evaluate and
4.12 MW respectively.
highlight the irreversibility and the thermodynamic inefficiencies.
The results obtained in this study prove clearly that the primary
In this work emphasis is put on breaking down the results among
contributors to exergy destruction are the exothermic combustion
the cement unit processes to assess the source and magnitude of
of the fuel, the strong endothermic calcination reaction, heat
exergy degradation per production step. By splitting the exergy
destruction into avoidable/unavoidable parts, the advanced exergy
analysis provided additional information to conventional exergy
Table 4
analysis for improving the cement production process. The input Exergetic improvement potential for the plant studied.
and output energy and exergy results of the various streams of the
Unit Inlet exergy Outlet exergy IP_ (MW)
cement production process calculated per kg of clinker produced
(kJ/kgcl) (kJ/kgcl)
are summarized in Table B.1 according to their state numbers as
Raw mill department 1 220 64 4.12
specified in Fig. 1. It is necessary to be stressed that results obtained
Raw mill department 2 101 28 2.01
in present work are deeply dependent of the quality of measure- Pre-heater/calciner 2633 1750 24.33
ments which often are not good enough. Hence, data reconciliation Rotary kiln 2266 1670 7.30
is mandatory to check the validity of the data collected before Cooler 630 382 4.31
exergy analysis. Pet-Coke mill department 53 35 0.24
Cement mill department 97 68 0.37
From the outlet exergy indicators of Table 3 it was possible to
Table 3
Outlet exergy indicators results.
Unit Inlet exergy (kJ/kgcl) Irreversibility (kJ/kgcl) Useful exergy Indicator (%) Wasted exergy Indicator (%) Destroyed exergy Indicator (%)
transfer and friction. To deal with them effectively, the principal energy loss rates considerably [57].
sources of inefficiency not only should be understood qualitatively, The results found in this study indicate a need to improve exergy
but also determined quantitatively [53]. Using the advanced exergy efficiency in comminution and justify reaching the decrease of
analysis, splitting the exergy destructions within a component into energy input for size reduction. As electricity use for raw meal and
avoidable/unavoidable parts helps facilitate a subsequent optimi- finish grinding depends strongly on the hardness of the material
zation of the overall system [27]. In this paper, values of unavoid- and on the surface area required for the final product [58] and the
able and avoidable exergy destruction are also presented for desired fineness of the product. Thus, for ball mills, it is advisable to
selected components (raw mill 1&2, preheater tower and the avoid feed over 8e10 mm in diameter, as larger particles will
calciner system) in the advanced exergy analysis. The results of the significantly raise energy requirements [59]. Furthermore, opti-
advanced exergetic analysis are summarized in Table 5 and are mizing the type of comminution equipment used and the operating
obtained using equations (17) and (18). The unavoidable exergy parameters can provide significant energy savings, which vary
destruction within the selected components of the plant is larger depending on the materials being comminuted [59]. The majority
than the avoidable one except for the preheater tower which 99% of losses in any system are from mechanical components (various
(23.32 MW) of its total exergy destruction rate is avoidable. This frictions). All friction losses are either directly proportional to or
result proves that the preheater is the most important system have a squared relationship to speed. Reducing the speed reduces
component according to the design standpoint. In the calciner unit, the friction; reducing the friction reduces the losses [60]. Signifi-
approximately 85% of the exergy destruction is unavoidable. Table 5 cant energy savings can also be obtained by the application of the
also shows that the raw mill 1 & 2 follow the calciner with 71% and high-pressure grinding roll presses instead of tumble mills or by
68% of unavoidable exergy destruction. Therefore, much can be combining the roller press with the ball mill [61]. The mixing
made to lessen the irreversibilities for the calciner and the raw mills temperatures of the materials, which constitute farine and gas
system, e.g. elimination of approximately 6 MW of avoidable exergy coming from the preheater cyclones and being the energy source of
destruction in the calciner the greatest improvement in the effi- the raw mills, should be reevaluated [16]. Additionally, 12.38% of
ciency of the overall system can be achieved. the exergy is wasted to the environment in the clinker cooler. Im-
Since this work aims also to provide practical improvement provements in the exergetic efficiency of this unit can be obtained
suggestions based on the findings, they are considered further in through a waste heat recovery steam generator. Using heat recov-
the next section. ery from the exhaust air, energy and exergy recovery efficiencies of
the cooling system found to be increased by 21.5% and 9.4%,
4.2. System performance enhancement respectively [62]. The electricity generated would offset a portion of
the purchased electricity, thereby reducing the electricity demand
After identifying the amounts and true locations of irrevers- [63].
ibilities within the system, here are suggestions that may reduce The near-term energy and emission-reduction opportunities
exergy destruction. Based on the results presented in the exergetic will mainly come from better energy management practices,
ternary diagram Fig. 2 and the advanced exergy analysis, the changes to greener fuels, and, to a smaller degree, changes in
improvement can start by decreasing the exergy destruction, which product formulation. Morocco is a country where the use of solar
is large in comminution operations and optimizing the calcination thermal energy should be strongly encouraged since solar radiation
process. is strong and reliable. Heat generated by solar concentrators could
The chemical reaction of calcination is a significant source of preheat the air supply for the plant, preheat the raw mill or
thermodynamic inefficiency. Advanced exergy analysis gives us generate additional heat to increase the electricity output of the
information that 15% of the exergy destruction within the calciner waste heat recovery during daytime. Also, in the longer term, the
unit can be avoided. Therefore, the general suggestion is to work to introduction of innovations such as novel quarrying methods, en-
reduce the destruction of exergy during combustion [54] through ergy efficiency improvements, environmental controls, and new
the employment of systems performing combustion in better cement products not only will result in reduction in specific energy
conditions (high internal energy) can meet this challenge. Also, consumption norms but also reduce the impact of environmental
there are ways to decrease the exergy destruction or entropy pro- degradation.
duction related to combustion by increasing the temperature of However, all the aforementioned improvement suggestions
reactants and increasing the temperature of combustion products need to be deeply analyzed from economical viewpoint.
(i.e. increasing the adiabatic flame temperature), by adopting
stoichiometric ratio between oxidizer and fuel and by utilizing the
fuels having simple molecular structure [55]. This is because lesser 5. Conclusions
entropy will be generated during combustion when simple mo-
lecular fuel species transform into complex molecular species of As a conclusion, the exergy analysis contributes to providing a
combustion products. The exergy destruction in the calciner unit quantitative structure for assessing cement industry, mapping the
under consideration can also be reduced by minimizing the use of irreversibility and material flows which should be valued. In this
excess air and by preheating the reactants [53e55]. Moreover, fuel paper, the exergy balances for the whole system and each unit are
substitution can be considered as an alternative option to reduce calculated and presented. The outcomes give important data con-
environmental pollution. In order to assess the exergy efficiency of cerning exergetic performance of the overall facility and its sections
the studied baking line; waste heat can be captured from com- through exergy destructions and second law efficiencies. The major
bustion exhaust gases, heated products, or heat losses from sys- findings can be stated as follows:
tems. It can improve the energy and exergy efficiency values to 84%
and 48%, respectively [18]. Furthermore, seals are used at the kiln Based on the results presented on the ternary diagram, we
inlet and outlet to reduce false air penetration, as well as heat losses pointed out that the Preheater/Calciner and the raw meal de-
[56]. Up of 23 MW could be saved just in the preheater cyclone partments are highly irreversible and have lower second-law
units. Hence, designing the pyroprocessing tower with refractories efficiency.
and insulation materials with better thermal properties will lead to Pyroprocessing found to be representing a major share of irre-
an increase in the exergetic efficiency values and decrease the versibility, it has been found to be about 79%. That is, those
198 S. Fellaou, T. Bounahmidi / Energy 154 (2018) 190e200
processes represent a big potential for increasing the exergy support to undertake the above work.
efficiency.
The examination of exergy efficiency of the overall system
shows that 1429.75 kJ/kg clinker of the exergy is a useful exergy Appendix A. Chemical composition
to the kiln system with the remaining 676.46 kJ/kg clinker being
exergy destroyed.
Among the different sections, raw meal grinding is responsible
Table A.1
for over 72% of the destroyed exergy, which are the irrevers- Chemical composition of principal streams
ibilities associated with heat transfer and friction. The exergy
efficiency values for the raw mill 1 & 2 respectively are obtained Composition (%) Stream 8 Stream 24 Stream 37 Stream 73 Stream 89
to be 20.97% and 19.69% which are even worse than energy LOI 34.34 34.40 35.01 0.13 1.35
utilization. SiO2 13.4 13.52 13.65 20.55 21.57
Al2O3 3.15 3.18 3.30 5.04 5.74
It has been identified that sizeable amounts of exergy are wasted
Fe2O3 2.06 2.11 2.45 3.24 3.58
and destroyed from the clinker cooler system 12.38% and 39.44% CaO 43.05 42.86 43.14 65.40 59.41
respectively. Thus, capturing the waste heat from the hot exit MgO 0.76 0.86 1.19 1.30 2.07
gases in the system can be considered as a potential option to SO3 0.25 0.28 0.35 1.53 2.46
improve exergy efficiency in the unit. K2O 0.43 0.48 0.57 0.90 0.90
TiO2 0.18 0.20 0.25 0.10 0.002
Values for IP ratio indicate that the Preheater/Calciner unit has MnO 0.05 0.05 0.07 0.00 0.06
most impact on exergy improvement potential of the overall P2O5 0.12 0.18 0.15 0.21 0.32
system. Na2O 0.00 0.00 0.17 0.15 0.02
A significant part (33.10 MW) of the exergy destruction within Cl- e e 0.01 0.01 0.001
CaOl e e e 1.7 1.58
the calciner unit is unavoidable. The irreversibility due to
Total 100 100 100 100 100
combustion cannot be avoided completely. However, irrevers- H2O 2.21 2.30 0.13 e e
ibility due to combustion can be reduced to a minimum value,
working with the suitable excess air coefficient (near stoichio-
metric condition) and using the better fuel.
Table A.2
The raw grinding process has an unavoidable exergy destruction
Chemical composition and lower heating value of Petroleum coke.
of about 7.64 MW. Therefore, improvements can be made in this
section such as optimizing the type of comminution equipment Composition Petroleum coke (%)
used, the operating parameters, particle size distribution of the C 83.7
feed and ore hardness could result in the saving of considerable S 4.61
N 1.40
amounts of energy.
H 3.60
O 3.13
The calciner system presenting the large share of the unavoid- Aches 0.20
able exergy destruction. Owing to this reason, the future work in- H2O 3.40
volves the improvement of the unit exergy efficiency which will be Total 100%
(LHV) (Kcal/Kg) 8096
performed using statistical modeling.
Acknowledgements
Appendix B. Exergetic analysis results
The authors gratefully acknowledge the support of engineers of
the selected cement factory for providing the necessary facilities
Table B.1
Exergy balance analysis over the total production system. T0 ¼ 298.15K
Equipment Input streams M (kg/ Cp (kJ/ T (K) DH (kJ/ DS (kJ/ E x (kJ/ Output streams M (kg/ Cp (kJ/ T (K) DH (kJ/ DS (kJ/ Ex (kJ/
kgcl) kg K) kgcl) kgcl) kgcl) kgcl) kg K) kgcl) kgcl) kgcl)
Raw Mill 8. Raw Material 1.15 0.86 300.15 1.97 0.007 0.007 16. Farine 1.115 0.92 348.15 51.31 0.159 3.875
1 department 3. Gaz from kiln 0.56 1 630.15 188.21 0.424 61.72 17.Gaz 1.101 1.24 434.15 185.71 0.513 32.714
7. Gaz from kiln 0.49 1 632.15 165.88 0.373 54.60 10’. Steam 0.035 1.96 354.15 3.829 0.012 0.320
4. False air 0.12 1.01 303.15 0.60 0.002 0.005 Dust 0.083 0.2097 394.15 1.669 0.005 0.222
Shaft work … … … 103.45 … 103.45 Heat losses … … … 137.03 … 17.630
Total 2.33 … … 460.14 … 219.78 Exergy of … … … 80.59 … 9.282
comminution
Irreversibility … … … … … 155.74
Total 2.33 … … 460.14 … 219.78
Raw Mill 24. Raw Material 0.573 0.876 300.15 1.004 0.003 0.003 32. Farine 0.551 0.939 350.15 26.888 0.083 2.103
2 department 22. Gaz from kiln 0.747 0.996 537.15 177.74 0.438 47.214 33. Gaz 0.808 1.18 398.15 95.345 0.276 13.125
23. False air 0.084 1.009 300.15 0.170 0.001 0.001 26’.Steam 0.022 1.89 345.15 1.992 0.006 0.142
Shaft work … … … 53.686 … 53.686 Dust 0.023 0.2088 388.15 0.429 0.001 0.054
Total 1.40 … … 232.60 … 100.90 Heat losses … … … 64.419 … 8.123
Exergy of … … … 43.533 … 4.582
comminution
Irreversibility … … … … … 72.774
Total 1.40 … … 232.60 … 100.90
37. Farine 1.666 0.861 357.15 84.637 7453.35 7.41 39. Hot Gaz 1.912 1.082 542.15 417.679 1.237 48.777
S. Fellaou, T. Bounahmidi / Energy 154 (2018) 190e200 199
Equipment Input streams M (kg/ Cp (kJ/ T (K) DH (kJ/ DS (kJ/ Ex (kJ/ Output streams M (kg/ Cp (kJ/ T (K) DH (kJ/ DS (kJ/ E x (kJ/
kgcl) kg K) kgcl) kgcl) kgcl) kgcl) kg K) kgcl) kgcl) kgcl)
Preheater- 47.Hot Gaz 0.880 1.106 1700.15 1364.93 48770.46 859.61 45.Raw meal 0.149 0.971 1123.15 119.097 0.191 62.012
Calciner 38’. False air 0.028 1.006 350.15 1.470 130.76 0.115 37’.Steam 0.003 2.047 650.15 2.041 0.005 0.693
system 39’. False air 0.058 1.006 350.15 3.011 267.91 0.236 50. Gaz 0.384 1.08 450.15 51.674 0.171 0.788
41’. False air 0.187 1.006 350.15 9.773 869.43 0.765 46.Calcined raw 0.903 0.942 1103.15 684.494 1.112 352.810
meal
43’. False air 0.033 1.006 350.15 1.867 153.26 0.279 Reaction Exergy … … … 1658.402 … 1188.115
48. Air 0.024 1.015 314.15 0.391 36.80 0.010 Heat losses … … … 481.865 … 96.890
49.Primary air 0.026 1.014 322.15 0.628 58.310 0.024 Irreversibility … … … … … 883.135
51. Tertiary air 0.404 1.0625 1168.15 373.636 16876.00 198.781 Total 3.35 … … 3415.25 … 2633.22
63.Coke 0.044 1.866 444.15 12.060 947.41 12.738
Shaft work … … … 63.246 … 63.246
Combustion … … … 1499.59 925.90 1489.999
Total 3.35 … … 3415.25 … 2633.22
Rotary 45. Calcined raw 0.149 0.971 1123.15 119.09 0.191 62.012 47.Hot Gaz 0.880 1.106 1700.15 1364.93 1.695 859.61
Kiln meal
46. Raw meal 0.903 0.942 1103.15 684.49 1.112 352.810 68.Raw meal 1.000 1.042 1280.15 1022.83 1.518 570.14
64.Coke 0.044 1.103 314.15 0.770 0.003 0.828 Leakages 0.051 1.02 610.15 16.335 0.037 5.157
Combustion … … … 1490.98 0.042 1478.340 Reaction Exergy … … … 133.90 … 80.45
65. Air 0.026 1.01 313.15 0.394 0.001 0.010 Heat losses … … … 418.57 … 154.86
66. Primary air 0.058 1.01 324.15 1.518 0.005 0.063 Irreversibility … … … … … 596.009
67.Secondary air 0.753 1.04 1020.15 566.96 0.963 279.818 Total 1.93 … … 2956.58 … 2266.24
Shaft work … … … 92.362 … 92.362
Total 1.93 … … 2956.58 … 2266.24
Cooler 68. Raw meal 1.000 1.042 1280.15 1022.834 1.518 570.143 70. Hot air from 2.062 0.9442 412.15 26.970 0.631 161.020
cooler
69. Coolant air 3.261 1.014 330.15 105.310 0.337 4.806 52. Hot air from 0.041 1.0104 807.15 21.279 0.042 8.865
cooler
Shaft work … … … 55.298 … 55.298 51. Tertiary air 0.404 1.0625 1168.15 373.636 0.586 198.781
Total 4.26 … … 1183.44 … 630.24 67. Hot air from 0.753 1.0431 1020.15 566.965 0.966 278.962
cooler
73.Clinker 1.000 0.77 330.15 1.423 0.079 21.982
Heat losses … … … 193.168 … 78.040
Irreversibility … … … … … 248.600
Total 4.26 … … 1183.44 … 630.24
Pet-coke 56. Raw coke 0.091 1.896 330.15 5.508 0.018 0.276 61.Exit Air 0.028 1.114 366.15 2.136 0.006 0.212
Mill 55. Hot air from 0.028 1.19 706.15 13.691 0.029 5.064 62.Coke 0.088 1.848 350.15 8.444 0.026 0.661
department cooler
Shaft work … … … 47.213 … 47.213 56’.Steam 0.003 1.861 345.15 0.254 0.001 0.018
Total 0.12 … … 66.41 … 52.55 Heat losses … … … 30.743 … 3.638
Exergy of … … … 24.834 … 30.442
comminution
Irreversibility … … … … … 17.582
Total 0.12 … … 66.41 … 52.55
Cement 80.Air 0.121 1.064 330.15 4.103 0.013 0.206 89.Cement 1.377 0.86 330.15 37.895 0.121 1.899
Mill 79.False air 0.168 1.014 300.15 0.341 0.001 0.001 78’.Steam 0.0001 1.88 350.15 0.008 0.000 0.001
department 78. Cement mill 1.355 0.859 378.15 93.149 0.277 10.632 90. Exit Air 0.288 0.965 360.15 17.255 0.053 1.579
feed
85.Ashes 0.022 0.795 310.15 0.205 0.001 0.004 Heat losses … … … 94.729 … 7.332
Shaft work … … … 86.322 … 86.322 Exergy of … … … 34.233 … 56.905
comminution
Total 1.66 … … 184.12 … 97.16 Irreversibility … … … … … 29.450
Total 1.66 … … 184.12 … 97.16
References [8] de Oliveira Junior Silvio. Exergy: production, cost and renewability. 2013.
https://doi.org/10.1007/978-1-4471-4165-5.
[9] Dincer Ibrahim, Midilli Adnan, Kucuk Haydar. Progress in exergy, energy, and
[1] Atmaca A, Kanoglu M, Gadalla M. Thermodynamic analysis of a pyropro-
the environment. 2014. https://doi.org/10.1007/978-3-319-04681-5.
cessing unit of a cement plant: a case study. Int J Exergy 2012;11:152e72.
[10] Bejan Adrian, Jones JA. Exergy analysis - advanced engineering thermody-
[2] Fellaou S, Bounahmidi T. Evaluation of energy efficiency opportunities of a
namics. 2016. https://doi.org/10.1002/9781119245964.ch5.
typical Moroccan cement plant: Part I. Energy analysis. Appl Therm Eng 2017.
[11] Dincer I. Refrigeration systems and applications. John Wiley & Sons; 2017.
https://doi.org/10.1016/j.applthermaleng.2017.01.010.
[12] Rashad A, El Maihy A. Energy and exergy analysis of a steam power plant in
[3] J. Kline, C. Kline. Assessing cement plant thermal performance. DOI 10.1109/
Egypt. In: Proceedings of the 13th international conference on aerospace
TIA.2017.2649458, IEEE Transactions on Industry Applications.
sciences and aviation technology, ASAT- 13, May 26 e 28; 2009.
[4] Boyd G, Zhang G. Energy Eff 2013;6:105. https://doi.org/10.1007/s12053-012-
[13] Bühler F, Nguyen T-V, Elmegaard B. Energy and exergy analysis of the Danish
9160-z.
industry sector. In: Proceedings of the 10th conference on sustainable
[5] Al-Ghandoor A, Phelan PE, Villalobos R, Jaber JO. Energy and exergy utiliza-
development of energy, water and environment systems. International centre
tions of the U.S. manufacturing sector. Energy 2010;35. https://doi.org/
for sustainable development of energy, water and environment systems;
10.1016/j.energy.2010.03.046.
2015.
[6] Atmaca A, Yumrutaş R. Thermodynamic and exergoeconomic analysis of a
[14] Bühler F, Nguyen T-V, Jensen JK, Elmegaard B. Energy, exergy and advanced
cement plant: Part II - Application. Energy Convers Manag 2014;79:799e808.
exergy analysis of a milk processing factory. In: Proceedings of ECOS 2016:
[7] Querol Enrique, Gonzalez-Regueral Borja, Perez-Benedito Jose Luis. Practical
29th international conference on efficiency, cost, optimization, simulation and
Approach to exergy and thermoeconomic analyses of industrial processes.
environmental impact of energy systems; 2016.
2013. https://doi.org/10.1007/978-1-4471-4622-3.
200 S. Fellaou, T. Bounahmidi / Energy 154 (2018) 190e200
[15] Camdali U, Erisen A, Celen F. Energy and exergy analyses in a rotary burner [40] Ramesh A. Thesis, Assessment of energy conservation in Indian cement in-
with pre-calcinations in cement production. Energy Convers Manag dustry and forecasting of CO2 emissions. October 2012. Reg. No. 3191.
2004;45(18e19):3017e31. [41] Farag M. Energy and exergy analyses of Egyptian cement kiln plant with
[16] Utlu Zafer, Sogut Ziya, Hepbasli Arif, Oktay Zuhal. Energy and exergy analyses complete kiln gas diversion through by Pass. Int J Adv Appl Sci 2012;1(1).
of a raw mill in a cement production, Turkey. Appl Therm Eng 2006;26: https://doi.org/10.11591/ijaas.v1i1.757.
2479e89. [42] Wang Jiangfeng, Dai Yiping, Gao Lin. Exergy analyses and parametric opti-
[17] Atmaca A, Kanoglu M. Reducing energy consumption of a raw mill in cement mizations for different cogeneration power plants in cement industry. Appl
industry. Energy 2012;42:261e9. Energy 2009;86:941e8.
[18] Sogut Z, Oktay Z, Hepbasli A. Energetic and exergetic assessment of a trass [43] Oliveira Silvio de. Chapter 2, exergy, exergy costing, and renewability analysis
mill process in a cement plant. Energy Convers Manag 2009;50:2316e23. of energy conversion processes. Exergy Green Energy Technol November
€g
[19] So üt Z, Oktay Z, Karakoc H, Hepbasli A. Investigation of environmental and 2012. https://doi.org/10.1007/978-1-4471-4165-5_2.
exergetic performance for coal-preparation units in cement production pro- [44] Baba A, Bundschuh J, Chandrasekharam D. Geothermal systems and energy
cesses. Energy October 2012;46(Issue 1):72e7. resources: Turkey and Greece. 2014. ISBN 9781138001091.
[20] Madlool NA, Saidur R, Rahim NA, Islam MR, Hossian MS. An exergy analysis [45] Bejan A, Mamut E. Thermodynamic optimization of complex energy systems.
for cement industries : an overview. Renew Sustain Energy Rev 2012;16(no. 1999. ISBN 978-94-011-4685-2.
1):921e32. [46] Hammond Geoffrey P. Engineering sustainability: thermodynamics, energy
[21] Sava&scedil AF, Kolip A. Comparative energy and exergy analyses of a serial systems, and the environment. Int J Energy Res 2004;28:613e39. https://
and parallel flow four-stage cyclone pre-calciner cement plant. Int J Exergy doi.org/10.1002/er.988.
2015;17(4):492. https://doi.org/10.1504/ijex.2015.071562. [47] Petrakopoulou F, Tsatsaronis G, Morosuk T, Carassai A. Conventional and
[22] Bühler Fabian, Nguyen Tuong-Van, Elmegaard Brian. Energy and exergy an- advanced exergetic analyses applied to a combined cycle power plant. Energy
alyses of the Danish industry sector. Appl Energy 15 December 2016;184: 2012;41:146e52.
1447e59. [48] Petrakopoulou F. Comparative evaluation of power plants with CO2 capture:
[23] Koroneos C, Roumbas G, Moussiopoulos N. Exergy analysis of cement pro- thermodynamic, economic and environmental performance. Ph.D. disserta-
duction. Int J Exergy 2005;2:55e68. tion. Technische Universit€ at Berlin; 2011.
[24] Ahamed JU, Madlool NA, Saidur R, Shahinuddin MI, Kamyar A, Masjuki HH. [49] Gourmelon S, Hetreux R, Floquet P. A new graphical representation of the
Assessment of energy and exergy efficiencies of a grate clinker cooling system exergy balance. Chem Eng Trans 2015;43:1285e90. https://doi.org/10.3303/
through the optimization of its operational parameters. Energy 2012;46(1): CET1543215.
664e74. https://doi.org/10.1016/j.energy.2012.06.074. [50] Gourmelon S, He treux R, Floquet P. PiXAR ;: pinch and eXergy for the Analysis
[25] Atmaca A, Yumrutaş R. The effects of grate clinker cooler on specific energy and Retrofit design of industrial processes. In: 26th European symposium on
consumption and emissions of a rotary kiln in cement industry. Int J of Exergy computer aided process engineering; 2016. p. 1941e6. https://doi.org/
2015;18(3):367e86. 10.1016/b978-0-444-63428-3.50328-3.
[26] Atmaca A, Yumrutaş R. Analysis of the parameters affecting energy con- [51] Tsatsaronis G. Strengths and limitations of exergy analysis. In: Thermody-
sumption of a rotary kiln in cement industry. Appl Therm Eng 2014;66: namic Optimization of Complex Energy Systems; 1999. p. 93e100. https://
434e44. doi.org/10.1007/978-94-011-4685-2_6.
[27] Erbay Z, Hepbasli A. Application of conventional and advanced exergy ana- [52] Parikh D. Handbook of pharmaceutical granulation technology. third ed.
lyses to evaluate the performance of a ground-source heat pump (GSHP) dryer Drugs and the Pharmaceutical Sciences; 2005. https://doi.org/10.1201/
used in food drying. Energy Convers Manag 2014;78:499e507. 9780849354953.
[28] Satsaronis G, Park MH. On avoidable and unavoidable exergy destructions and [53] Kreith Frank, Goswami Yogi. The CRC handbook of mechanical engineering.
investment costs in thermal systems. Energy Convers Manag 2002;43: second ed. 2005. ISBN 0-8493-0866-6.
1259e70. [54] Luis P, Van der Bruggen B. Exergy analysis of energy-intensive production
[29] Morosuk T, Tsatsaronis G, Schult M. Conventional and advanced exergetic processes: advancing towards a sustainable chemical industry. J Chem Tech-
analyses: theory and application. Arabian J Sci Eng 2013;38:395e404. nol Biotechnol 2014;89(9):1288e303. https://doi.org/10.1002/jctb.4422.
[30] Gungor Aysegul, Hepbasli Arif, Gunerhan Huseyin. Enhanced exergy analyses [55] Wang L, Yang Y, Morosuk T, Tsatsaronis G. Advanced thermodynamic analysis
of a gas engine heat pump (GEHP) dryer for medicinal and aromatic plants. and evaluation of a supercritical power plant. Energies 2012;5:1850e63.
International Journal of Exergy; Jan 2015. https://doi.org/10.3390/en5061850.
[31] Temmerman M. Energie cessaire au broyage de la biomasse et des produits
ne [56] Radwan AM. Different possible ways for saving energy in the cement pro-
densifies. Biotechnol Agron Soc 2011;15(2):349e60. duction. Adv Appl Sci Res 2012;3(2):1162e74. ISSN: 0976-8610 CODEN
[32] Fidaros DK, Baxevanou CA, Dritselis CD, Vlachos NS. Numerical modelling of (USA): AASRFC.
flow and transport processes in a calciner for cement production. Powder [57] Atmaca A, Yumrutas R. Reducing energy consumption and emissions of a
Technol 2007;171:81e95. rotary kiln in cement industry. In: The 2013 clute institute international ac-
[33] Voldsund M, Nguyen T-V, Elmegaard B, Ertesvåg IS, Kjelstrup S. Thermody- ademic conference, Paris June 9e21; 2013.
namic performance indicators for offshore oil and gas processing: application [58] Worrell Ernst, Galitsky Christina. Energy efficiency improvement and cost
to four north sea facilities. Oil and Gas Facilities 2014;3(06):051e63. https:// saving opportunities for cement making. An ENERGY STAR® guide for energy
doi.org/10.2118/171565-pa. and plant managers. 2008. LBNL-54036-Revision.
[34] Rosen Marc A. Exergy analysis of energy systems. Encycl Energy 2004: [59] Energy efficiency opportunities. Energy-mass balance : mining, version 1.0,
607e21. https://doi.org/10.1016/b0-12-176480-x/00129-7. Australia. 2010. ISBN 978-1-921516-85-6.
[35] Fellaou S, Bounahmidi T. Mass balance reconciliation for bilinear systems: a [60] Murray Matt. SEW eurodrive, total system efficiency, power transmission
case study of a raw mill separator in a typical Moroccan cement plant. Eng engineering. 2010.
Technol Appl Sci Res 2016;6(3):1006e9. [61] Saramak D, Tumidajski T, Broek M, Gawenda T, Naziemiec Z. Aspects of
[36] Atmaca A, Yumrutaş R. Thermodynamic and exergoeconomic analysis of a comminution flowsheets design in processing of mineral raw materials,
cement plant: Part I - Methodology. Energy Convers Manag 2014;79:790e8. Gozpodarka surrowcami mineralnymi, Gospodarka surowcami mineralnymi -
[37] Valero A, Valero A, Cortes C. Exergy of comminution and the crepuscular mineral resources management. Tom 2010;26.
planet. In: Proceeding of the 6th Dubrovnik conference on sustainable [62] Ahamed JU, Madlool NA, Saidur R, Shahinuddin MI, Kamyar A, Masjuki HH.
development of energy water and envorinmental systems, Dubrovnik, Assessment of energy and exergy efficiencies of a grate clinker cooling system
Croatia; September 25-29 2011. through the optimization of its operational parameters. Energy 2012;46.
[38] Dincer I, Rosen M. Exergy, energy, environment and sustainable development. 664e674, https://doi.org/10.1016/j.energy.2012.06.074.
Elsevier; 2007. [63] Naranjo Mauricio, Brownlow Darrell T, Garza Adolfo. CO2 capture and
[39] Koroneos C, Spachos T, Moussiopoulos N. Exergy analysis of renewable energy sequestration in the cement industry. Energy Proced 2011;4:2716e23.
sources. J Renew Energy 2003;28:295e310.